linac 4 project l4t/l4z design status j.humbert / b.riffaud on behalf of en-mme design team 1 st...
TRANSCRIPT
LINAC 4 ProjectL4T/L4Z Design Status
J.Humbert / B.Riffaudon behalf of EN-MME design team
1st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud
Design input data – LayoutEquipment Names Used name
DCUM L4T Integrated (Benoit,Jerome,Jean-Pierre)
Comments Equipment Names Used nameDCUM L4Z Integrated
(Benoit,Jerome,Jean-Pierre)Comments
L4T.VVGS.0101 Sector Valve 155.00 ↔ L4T.VVGS.0101 Sector Valve 155.00
L4T.BCT.0103 Transformer 725.00 ↔ L4T.BCT.0103 Transformer 725.00
L4T.MCHV.0105 Steerer ↔ L4T.MCHV.0105 Steerer
L4T.MQD.0110 1100.00 ↔ L4T.MQD.0110 1100.00
L4T.MCHV.0115 Steerer 2100.00 ↔ L4T.MCHV.0115 Steerer 2100.00
L4T.MCHV.0135 Steerer 3100.00 ↔ L4T.MCHV.0135 Steerer 3100.00
L4T.MQF.0210 4100.00 ↔ L4T.MQF.0210 4100.00
L4T.BSGHV.0223 SEM Grid 4320.00 ↔ L4T.BSGHV.0223 SEM Grid 4320.00
L4T.BPM.0227 Pick-up 4800.00 ↔ L4T.BPM.0227 Pick-up 4800.00
L4T.BPLFS.0233 Feshenko 5550.00 ↔ L4T.BPLFS.0233 Feshenko 5550.00
L4T.BPM.0237 Pick-up 6300.00 ↔ L4T.BPM.0237 Pick-up 6300.00
L4T.BSGHV.0243 SEM Grid 6630.00 ↔ L4T.BSGHV.0243 SEM Grid 6630.00
L4T.MBH.0250 7475.52 Distances relatives / L4T.MBH.0250 ↔ L4T.MBH.0250 7475.52
L4T.MQD.0310 8975.52 1500.00 L4Z.BSGHV.0273 SEM Grid 8340.00
L4T.MCHV.0315 Steerer 9525.52 2050.00 L4Z.VPI.0280 Ion Pump 9060.00
L4T.MQF.0410 10075.52 2600.00 L4Z.VGP.0280 Penning Gauge 9060.00
L4T.MBH.0450 11575.52 Distances relatives / L4T.MBH.0450 L4Z.VGR.0280 Pirani Gauge 9060.00
L4T.MQF.0510 13075.52 1500.00 L4Z.BSGHV.0293 SEM Grid 9780.00
L4T.BSGHV.0523 SEM Grid 13625.52 2050.00 L4Z.TDE.0295 Dump (start) 13442.00 Dump Start = 11942.00
L4T.MQD.0610 14175.52 2600.00 Dump End = 14942.00
L4T.MBH.0650 15675.52 Distances relatives / L4T.MBH.0650
L4T.BCT.0673 Transformer 17065.52 1390.00
L4T.MQF.0710 17675.52 2000.00
L4T.MCHV.0715 Steerer 18375.52 2700.00
L4T.MCHV.0735 Steerer 19375.52 3700.00
L4T.VPI.0740 Ion Pump 22062.52 6387.00
L4T.TDISA.0760 Beam Stopper
L4T.MQD.0810 22975.52 7300.00 QuadrupolesL4T.BPM.0827 Pick-up 25675.52 10000.00
L4T.BPM.0837 Pick-up 27175.52 11500.00 DipolesL4T.MQF.0910 28275.52 12600.00
L4T.MCHV.0915 Steerer 28975.52 13300.00 Vac elementsL4T.MCHV.0935 Steerer 29975.52 14300.00
L4T.MQD.1010 33575.52 17900.00
L4T.VPI.1020 Ion Pump 34494.52 18819.00
L4T.BPM.1027 Pick-up 36575.52 20900.00
L4T.BPM.1037 Pick-up 38075.52 22400.00
L4T.BCT.1043 Transformer 40405.52 24730.00
L4T.ACDB.1075 41575.52 25900.00
L4T.VPI.1075 Ion Pump 41575.52 25900.00
L4T.MCHV.1085 Steerer 43575.52 27900.00
L4T.MCHV.1095 Steerer 44575.52 28900.00
L4T.MQD.1110 45275.52 29600.00
L4T.MQF.1210 46525.72 30850.20
L4T.BPM.1227 Pick-up 47175.52 31500.00
L4T.VPI.1240 Ion Pump 47864.12 32188.60
L4T.VGP.1240 Penning Gauge 47864.12 32188.60
L4T.VGR.1240 Pirani Gauge 47864.12 32188.60
L4T.VPGF.1240 Fix Pump Group 47864.12 32188.60
L4T.BCT.1263 Transformer 48335.52 32660.00
L4T.BPM.1237 Pick-up 48675.52 33000.00
L4T.BSGHV.1243 SEM Grid 49280.52 33605.00
L4T.MBV.1250 50525.52 Distances relatives / MBV
L4T.MQD.1310 53025.52 2500.00
L4T.MCHV.1315 Steerer 54275.52 3750.00
L4T.MQF.1410 55525.52 5000.00
L4T.MCHV.1415 Steerer 56775.52 6250.00
L4T.MQD.1510 58025.52 7500.00
L4T.VPI.1520 Ion Pump 59289.52 8764.00
L4T.MBV.1550 60525.52 Distances relatives / MBV
L4T.BCT.1513 Transformer 61675.52 1150.00
L4T.BPM.1527 Pick-up 62075.52 1550.00
L4T.MQD.1610 62725.52 2200.00
L4T.BPM.1627 Pick-up 63075.52 2550.00
L4T.MCHV.1635 Steerer 63350.52 2825.00
L4T.MQF.1710 63975.52 3450.00
L4T.VVGS.1751 Sector Valve 64495.52 3970.00
LTBHZ20 70936.52 10411.00
Transfer Line - L4T Dump Line - L4Z
Layout & naming frozen by C.Carli & S.Weisz
24/08/2011
1st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud
Zone
1
Preliminary design – Configuration
Zone 3
Zone 4Zone 5
L4Z
Zone 2
1st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud
Machine integration inputs: Jean-Pierre Corso
Preliminary design – Layout Zone 1 + L4Z to dump
1st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud
MBH.0250
Dump
Beam pipe support
Modular support
Steerer
Feshenko
SEM grid
Pick-up
BCT
Pumping unit
Alignment jack
EMQ
Sector valve
Preliminary design – Layout Zone 2
1st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud
MBH.0250
Bellow
Support table
Steerer SEM grid
Quadrupole
Alignment jack
MBH.0450MBH.0650
Beam pipe
Preliminary design – Layout Zone 3
1st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud
MBH.0650
Beam pipe support
Modular support
Steerer
Beam stopper
Pick-up
BCT
Pumping unit
Alignment jack
MBV.1250
Debuncher cavity
Beam pipe support
Quadrupole
Bellow
Steerer
MBV.1550Quadrupole
Bellow
Pick-upBCT
Sector valve
LT.BHZ20
Preliminary design – Layout Zone 4 & 5
1st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud
MBV.1550
Support structure
Steerer Pumping unit
Alignment jack
QuadrupoleMBV.1250
Bellow
Preliminary design – Supports
1st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud
Detailed design of the support system to be finalized once the interface with bending magnets will be frozen (contact between EN-MME & T.Zickler).
LINAC4 support jack type 2.5 tons(pre-series manufacturing process ongoing)
MBH support configuration
LINAC4 jacks 2.5 tons have been selected for support & alignment of MBH and MBV magnets.
MBV support configuration
Preliminary design – Supports
1st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud
Detailed design of these supports to be finalized once the interfaces with components will be frozen (beam pipes, magnets, beam instrumentation - Contact between EN-MME & equipments responsible).
Alignment targets centers to be positioned in the beam vertical plane (requirement from BE/ABP).
Supports for beam pipes(preliminary design accepted by TE/VSC)
Supports for quadrupoles/steerers/instrumention(alignment principle accepted by BE/ABP)
Type LINAC4 intertank Type LINAC4 LEBT
Preliminary design – Vacuum devices
1st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud
Detailed design of these components ongoing
Pumping moduleTube Ø100/103 or Ø50/53
(preliminary design accepted by TE/VSC)
Bellow module 10 wavesTube Ø100/103 or Ø50/53
(preliminary design accepted by TE/VSC)(compatibility with alignment tolerances to be validated)
Support for beam pipes
Vacuum gauges port
Ion pump
Pumping unit port
Valve
Beam pipes detailed design – Requirements
1st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud
Magnets aperture (data fromT.Zickler)• EMQ : Ø54 ±0.05 mm• MQF/MQD : Ø100 ±0.05mm• MBH/MBV : Aperture height 56 ±0.05mm• Steerers : Ø101 ±0.1mm
Beam clearance : “as big as possible, not less than Ø95”. (to be urgently confirmed)
Main consequences on mechanical design:• Very tight gap between the magnets apertures and the beam pipes.• Very tight gap between the beam clearance and beam pipes internal diameter.• Precise alignment required Beam pipes need to be fixed on magnets. (this is not possible for steerers)
Insulation layer between beam pipes and pulsed magnets.
Beam pipes detailed design – Configurations
1st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud
Manufacturing tolerances values validated by CERN Main Workshop.
Magnet aperture tolerance
Pipe alignment tolerance wrt. magnet
Pipe insulation thickness
Pipe thickness + manufacturing tolerances
Beam clearance
1st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud
Pipe deformation due to vacuum
Beam pipes detailed design – Beam clearance
Configuration for bendings & quadrupoles(beam pipes fixed on magnets)
Beam pipe
Magnet
Beam axis
Beam pipes detailed design – Alignment tolerances Alignment Precision Position Determination
X,Y (Radial)
Z (Long.)
Roll Pitch and yaw
X,Y (Radial)
Z (Long.)
Roll Pitch and yaw
(1 sigma) (1 sigma) (1 sigma) (1 sigma) (1 sigma) (1 sigma) (1 sigma) (1 sigma)
Chopper line quadrupoles, bunchers, inline dump and chopper plates.
±0.1 mm ±1 mrad 2mrad (probably even more)
Chopper plates are very critical the rest is more forgiving.
±0.1 mm ±1 mrad 2mrad (probably even more)
Linac quadrupoles(DTL,CCDTL,PIMS)Transfer lines quadrupoles
±0.2 mm ±2 mrad 2mrad (probably even more)
±0.2 mm ±2 mrad 2mrad (probably even more)
Steeres and dipoles ±0.5 mm ±2 mrad 2mrad (probably even more)
±0.5 mm ±2 mrad 2mrad (probably even more)
Diagnostics ±0.5 mm Not relevant
Not relevant
For any passive element it is important to know the position but not necessarily to align, provided of course it doesn’t influence the acceptance of the lines.Transformers and BLMs ±0.5 mm Not
relevantNot relevant
PickUps ±0.3 mm ±0.3 mm Not relevant
Not relevant
SemGrid, Emmitance Meter, & Wire Scanners
±0.3 mm 3-5 degrees
3-5 degrees
Feschenko Beam Shape Monitor
±0.5 mm Not relevant
Not relevant
L4 Element Comments
±0.1 mm ±1 mrad 2mrad (probably
Critical for beam quality. We have 1 corrector / 40
±0.1 mm ±1 mrad 2mrad (probably
Table given by A.Lombardi• Alignment tolerances : 3 sigma
1st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud
1st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud
Beam pipes detailed design – Beam clearance
EMQ(mm)
MQF/MQD(mm)
MBH/MBV(mm)
Magnet aperture Ø54 Ø100 56
Magnet aperture tolerance 0.05 0.05 0.05
Pipe alignment tolerance wrt. magnet 0.25 0.25 0.25
Pipe insulation thickness 1 1 1
Pipe thickness 3 3 4
Pipe manufacturing tolerances 0.6 1.2 2.4
Deformation due to vacuum 0 0 2
Alignment tolerance (3 sigma) 1.2 1.2 3
Beam Clearance Ø47.9 Ø93.3 43.3
1st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud
Beam pipes detailed design – Pipes dimensionsEMQ(mm)
MQF/MQD(mm)
MBH/MBV(mm)
Beam pipe external size (nominal) Ø52.4 Ø98.1 53.5
Beam pipe internal size (nominal) Ø49.4 Ø95.1 49.5
Beam pipe length 205 750 1780
Manufacturing tolerance (t) 0.6 1.2 2.4
Special size manufacturing yes yes yes
Important
No standard size for beam pipes : Cost x10
Some sectors of the line (~30 meters, including pumping units and bellows) could be installed with standard beam pipes (Ø100/103).
±0.6
±0.6
±1.5±1.5
1st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud
Beam pipes detailed design – Beam clearance
Beam clearance reduction due to steerers misalignment (1÷3 sigma)
(accepted alignment tolerance : 3 sigma)
Steerer
Quadrupole
Bellow
Beam pipeBeam clearance inside MQ (Ø93 mm)
1st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud
Conclusions
•L4T/L4Z layout frozen.
• Very tight margin between required beam clearance and magnet apertures important consequences on mechanical design:
• Beam pipes fixed on magnets.• Bendings and steerers to be aligned at 1 sigma to avoid a decrease of the beam clearance?• Beam pipes to be aligned ? (to be checked)• Special size for beam pipes (cost x10).
• Beam instrumentation interfaces to be frozen as soon as possible.
Deadline for L4T/L4Z supports and beam pipes drawings : End 2011