Littoral Combat Ship Sustainment
LCS Planning Yard Recompete
Industry Day (7 Dec 2017) Robert Warren PMS 505AP - Abbey Scholl SEA 024
DISTRIBUTION STATEMENT A: Approved for public release. Distribution is unlimited.
2
• FAR 15.201
- Exchanging of information to improve the
understanding of Government requirements and
industry capabilities.
DISTRIBUTION STATEMENT A: Approved for public release. Distribution is unlimited.
Industry Day Intent
Questions
• NAVSEA will post this Industry Day presentation and Q&A sheets on the
FBO.gov website.
• Industry is invited to provide the Navy comments, concerns or questions. All
inquiries shall be directed to David Hector, Contracting Officer, and Abbey
Scholl, Contract Specialist, at [email protected] and
• Questions will be treated as “Bidder’s Questions” and all answers will be
made publicly available via www.fbo.gov.
• To ensure the Navy is able to adequately consider Industry’s feedback in the
upcoming solicitation, it is requested they be submitted no later than 1400
EST on 18 December 2017.
3 DISTRIBUTION STATEMENT A: Approved for public release. Distribution is unlimited.
4
Agenda
• Introductions
• PMS 505 Fleet Introduction and Sustainment
Program Office
• SEA 02 Contracts - NAVSEA Contracting
Process
• One on One Sessions (by confirmed request only)
DISTRIBUTION STATEMENT A: Approved for public release. Distribution is unlimited.
PMS 505 LCS
Fleet Introduction & Sustainment
5
DISTRIBUTION STATEMENT A: Approved for public release. Distribution is unlimited.
6
PEO LCS Products
DISTRIBUTION STATEMENT A: Approved for public release. Distribution is unlimited.
7
PMS 505:
Fleet Introduction and Sustainment
• Provides a single point of entry for the Fleet, Type Commander (TYCOM), and the Maintenance and Sustainment communities
• PMS 505 integrates ship and mission package fleet introduction, logistics, training, and maintenance strategies to deliver and sustain LCS combat capability for the Fleet
• PMS 505 provides:
- Technical oversight, management, and direct Fleet support for the LCS Class and its systems;
- Intermediate maintenance and depot level support of mission package systems and components, as well as the Command and Control Software; and
- Crew training until the Navy training pipeline is established.
DISTRIBUTION STATEMENT A: Approved for public release. Distribution is unlimited.
8
Overview of LCS Class Ships
• Two different ship variants meeting the same
design requirements: Monohull (Freedom
Variant) and Trimaran (Independence
Variant)
- Small crew focused on mission
execution
- 18 months forward deployed
• Targeted at critical capability: mines, small
fast surface craft, and diesel submarines
• Notional 42 ships planned (Mixture of LCSs
and Frigates)
• Modular Mission Packages
- MCM, ASW, and SUW
DISTRIBUTION STATEMENT A: Approved for public release. Distribution is unlimited.
San Diego LCS 1 – Freedom
LCS 2 – Independence
LCS 3 – Fort Worth
LCS 4 – Coronado
LCS 6 – Jackson
LCS 8 – Montgomery
LCS 10 – Gabrielle Giffords
LCS 12 – Omaha
LCS 14 – Manchester
LCS 16 – Tulsa
LCS 18 – Charleston
LCS 20 – Cincinnati
LCS 22 – Kansas City
LCS 24 – Oakland
LCS 26 – Mobile
LCS 28 – TBD
Mayport
LCS 5 – Milwaukee
LCS 7 – Detroit
LCS 9 – Little Rock
LCS 11 – Sioux City
LCS 13 – Wichita
LCS 15 – Billings
LCS 17 – Indianapolis
LCS 19 – St. Louis
LCS 21 – Minneapolis/St. Paul
LCS 23 – Cooperstown
LCS 25 – Marinette
LCS 27 – TBD
9
LCS Homeport Layout
Planning Yard supports both homeports and LCS variants
DISTRIBUTION STATEMENT A: Approved for public release. Distribution is unlimited.
10
• Selected Restricted Availability (SRA)
- 17 weeks every 64 months (LCS 1 variant only)
- Performed in the ship’s homeport
- Includes Continuous Maintenance/ Emergent Maintenance (CM/EM) performed during SRA
periods
• Dry-docking SRA (DSRA)
- 25 weeks every other 64 months (LCS 1 variant)
- 25 weeks every 32 months (LCS 2 variant)
- Performed in the ship’s homeport
- Includes CM/EM performed during DSRA periods
• Continuous Maintenance Availability (CMAV)
- Quarterly availabilities (2 weeks in duration) includes corrective/emergent maintenance
- Performed CONUS and OCONUS
• Preventative/Planned Maintenance Availability (PMAV)
- Monthly availabilities (5 days in duration)
- PMS tasked to a mixture by contractor(s) and ship’s force
- Performed CONUS and OCONUS
Notional Availability and
Periodicity
DISTRIBUTION STATEMENT A: Approved for public release. Distribution is unlimited.
11
• Support Ship Change Document (SCD) development
• Create Ships Installation Drawings (SIDs) to support modernization
- Often requires shipchecks to verify “as is” condition of the ship
• Procure and kit Long Lead Time Material (LLTM) especially in support of Firm
Fixed Price contracting via Provisioning Item Order (PIO) CLIN
• Create Availability Analysis Books in support of CNO Availabilities
• Keepers/Maintainers of the Configuration of the LCS Class
- ILS Product Development
- Configuration Data Management
- Provisioning Technical Documentation
- Ship Selected Record Documents
• Coordination includes, but not limited to: the Program Offices, RMCs, Executing
Contractors under Sustainment Execution Contract – East and West Coast (SEC
East/West), Execution Planning Contractor, Fleet/TYCOM, and Warfare Centers
Typical Planning Yard Efforts
DISTRIBUTION STATEMENT A: Approved for public release. Distribution is unlimited.
NAVSEA 02
Contracting Process
12
DISTRIBUTION STATEMENT A: Approved for public release. Distribution is unlimited.
13
Objective
• High level overview of the contracting strategy.
• Information presented is representative of the “planned”
acquisition.
• Released solicitation will govern the terms and conditions of the
competitive process.
DISTRIBUTION STATEMENT A: Approved for public release. Distribution is unlimited.
Planning Yard Contract Assumptions
• Full and Open Competition
- Cost Reimbursement Contract Type
Level of Effort CLINs-Cost Plus Award Fee (CPAF)
PIO CLIN for Material purchases-Cost Plus Fixed Fee (CPFF)
Travel CLIN-Cost Only
- Base year with four option years
• Evaluated using Best Value Trade-Off Source Selection
- This process permits tradeoffs among cost and non-cost factors
and allows the Government to accept other than the lowest priced
proposal.
- Technical is more important than Cost.
The importance of cost as an evaluation factor will increase as the
difference in overall technical merit among proposals narrows.
14
DISTRIBUTION STATEMENT A: Approved for public release. Distribution is unlimited.
CLIN Structure
15
CLIN Title Applicability
0001 Program Management LCS Class
0002 Planned Maintenance Management LCS Class
0003 Corrective and Continuous Maintenance LCS 1 Variant
0004 Corrective and Continuous Maintenance LCS 2 Variant
0005 Ship/Availability Product Work LCS 1 Variant
0006 Ship/Availability Product Work LCS 2 Variant
0007 Ship Alteration Work LCS Class
0008 In Service Engineering Activity (ISEA) LCS Class
0009 Emergent Installation and Repair Support LCS 1 Variant
0010 Emergent Installation and Repair Support LCS 2 Variant
0011 Logistics Management (CM/DMSMS) LCS Class
0012 PIO and Other Material (Warehouse) LCS Class
0013 Data
0014 Travel LCS Class
DISTRIBUTION STATEMENT A: Approved for public release. Distribution is unlimited.
Technical & Cost Proposal
• Technical Proposal will be evaluated to determine Technical Capability
and Management Approach as it pertains to the requirements of the
Statement of Work.
- The Navy is assessing how we will evaluate a transition plan.
• Cost Proposal will be evaluated to determine Cost Realism in
accordance with FAR 15.404-1(d) to derive a total projected cost to the
Government.
- While cost is the least important factor, it is still an important consideration.
- Failure to provide the required cost information may render the proposal
non-responsive.
16 DISTRIBUTION STATEMENT A: Approved for public release. Distribution is unlimited.
Proposal Quality
• Proposals should be organized in accordance with solicitation
requirements.
• Technical Proposal should stand on its own merits.
- Do not assume evaluation team possesses any pre-existing knowledge about
your company or its unique business practices.
• Cost Proposal should be free of mathematical and formula errors.
- To the greatest extent possible, do not include hard entered data with no
traceability to formulas.
• Ensure consistency between the Cost and Technical proposals.
- Cost proposal needs to represent the technical solution provided in the
Offeror’s Technical proposal.
- Inconsistency between the Cost and Technical Volumes will result in an
adjustment to the Offeror’s proposed cost.
17 DISTRIBUTION STATEMENT A: Approved for public release. Distribution is unlimited.
Notional Dates
• Pre-Solicitation Synopsis……………………………… Jan 2018
• Release RFP…………….…………............................... Feb 2018
• Proposal Due Date…………………………………… April 2018
• Award ………………………………………….......October 2018
18 DISTRIBUTION STATEMENT A: Approved for public release. Distribution is unlimited.
Comments ?
19 DISTRIBUTION STATEMENT A: Approved for public release. Distribution is unlimited.
Back Up
20
DISTRIBUTION STATEMENT A: Approved for public release. Distribution is unlimited.
PMS 505/NAVSEA HQ
• Establishes the Letter Of
Authorization for CNO Avails
• Program Office funded SCDs
• Program Office funded SIDs
• Manages overall PY work plan
• Provides New Construction Dwgs
from PMS 501
ISEA, Software Support,
and Warfare Centers –
NSWC Philly (HM&E), PHD
(CS)
• ILS Certs
• SCD Development
Execution Planning/aka 3PP
• 4e Work Specs to support CNO
avails, CMAVs, EM
• LLTM and Kitting
• Work Packages
• Turnover Books
• Warehousing
Supervisor of Shipbuilding
• Manage all funding except
PMS 505 (NAVAIR,
SPAWAR, ETC.) as ACO
• Manage all contract mods
except PMS 505 as ACO
• Manages the LLTM process
including LLTM ROMs
Executing Contractors (SEC East/West)
• Perform and manage CNO Avails
and CM/EM
• Maintain Integrated Master
Schedule (IMS)
• Perform PMS checks, FM, CC
• electronic Liaison Action Records
(eLARs)
• Redline Dwgs
Different Commands
(SPAWAR, NAVAIR)
• Provide Funding
• Provide design direction
Regional Maintenance
Centers/LCSRON
• Manage CNO Avails, CM/EM, PM,
FM, Corrosion Control as NSA
Fleet/TYCOM
• Requirements
• Funding
• Fleet funded SCDs
• Fleet funded SIDs
• Fleet funded LLTM
21
Planning Yard Interfaces
Planning Yard/Advance Planning
• CNO Avail
• CM/EM
• PM (Planning assistance & Part
Mgmt)
• Ship Change Documents (SCD)
• Ship Installation Dwgs (SIDS)
• LLTM, Kitting, Warehousing
• Avail Analysis Books
• ILS Product Development
DISTRIBUTION STATEMENT A: Approved for public release. Distribution is unlimited.