local government energy audit program energy … · 28/01/2011  · this audit is performed in...

69
LOCAL GOVERNMENT ENERGY AUDIT PROGRAM: ENERGY AUDIT REPORT PREPARED FOR: ATLANTIC COUNTY UTILITIES AUTHORITY: OPERATIONS B BUILDING 1801 ABSECON BLVD. ATLANTIC CITY, NJ 08401 ATTN: MR. MATTHEW VON DER HAYDEN PROJECT ANALYST PREPARED BY: CONCORD ENGINEERING GROUP 520 S. BURNT MILL ROAD VOORHEES, NJ 08043 TELEPHONE: (856) 427-0200 FACSIMILE: (856) 427-6529 WWW.CEG-INC.NET CEG CONTACT: SAM DORIA MANAGER, CX AND ENERGY AUDITS EMAIL: SDORIA@CEG-INC.NET REPORT ISSUANCE: FINAL, JANUARY 28, 2011 PROJECT NO: 9C10051

Upload: others

Post on 17-Mar-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

LOCAL GOVERNMENT ENERGY AUDIT PROGRAM: ENERGY AUDIT REPORT

PREPARED FOR: ATLANTIC COUNTY UTILITIES AUTHORITY: OPERATIONS B BUILDING 1801 ABSECON BLVD. ATLANTIC CITY, NJ 08401 ATTN: MR. MATTHEW VON DER HAYDEN PROJECT ANALYST

PREPARED BY: CONCORD ENGINEERING GROUP

520 S. BURNT MILL ROAD VOORHEES, NJ 08043 TELEPHONE: (856) 427-0200 FACSIMILE: (856) 427-6529 WWW.CEG-INC.NET

CEG CONTACT: SAM DORIA

MANAGER, CX AND ENERGY AUDITS EMAIL: [email protected]

REPORT ISSUANCE: FINAL, JANUARY 28, 2011

PROJECT NO: 9C10051

Page 2: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 1 of 45

TABLE OF CONTENTS

I.  EXECUTIVE SUMMARY ................................................................................................. 3 

II.  INTRODUCTION ............................................................................................................... 7 

III.  METHOD OF ANALYSIS.................................................................................................. 9 

IV.  HISTORIC ENERGY CONSUMPTION/COST ............................................................... 11 

A.  ENERGY USAGE / TARIFFS .................................................................................................................................... 11 B.  ENERGY USE INDEX (EUI)..................................................................................................................................... 18 C.  EPA ENERGY BENCHMARKING SYSTEM ................................................................................................................... 20 

V.  FACILITY DESCRIPTION .............................................................................................. 21 

VI.  MAJOR EQUIPMENT LIST ............................................................................................ 23 

VII.  ENERGY CONSERVATION MEASURES ..................................................................... 24 

VIII.  RENEWABLE/DISTRIBUTED ENERGY MEASURES ................................................ 40 

IX.  ENERGY PURCHASING AND PROCUREMENT STRATEGY .................................. 41 

X.  INSTALLATION FUNDING OPTIONS.......................................................................... 42 

XI.  ADDITIONAL RECOMMENDATIONS ......................................................................... 44 

XII.  ENERGY AUDIT ASSUMPTIONS ................................................................................. 45 

Appendix A – ECM Cost & Savings Breakdown

Appendix B – New Jersey Smart Start® Program Incentives

Appendix C - Portfolio Manager “Statement of Energy Performance”

Appendix D – Major Equipment List

Appendix E – Investment Grade Lighting Audit

Appendix F – Novathermal Energy Calculation

Page 3: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 2 of 45

REPORT DISCLAIMER

The information contained within this report, including any attachment(s), is intended solely for use by the named addressee(s). If you are not the intended recipient, or a person designated as responsible for delivering such messages to the intended recipient, you are not authorized to disclose, copy, distribute or retain this report, in whole or in part, without written authorization from Concord Engineering Group, Inc., 520 S. Burnt Mill Road, Voorhees, NJ 08043.

This report may contain proprietary, confidential or privileged information. If you have received this report in error, please notify the sender immediately. Thank you for your anticipated cooperation.

Page 4: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 3 of 45

I. EXECUTIVE SUMMARY

This report presents the findings of the energy audit conducted for:

Atlantic County Utilities Authority Operations B Building 1801 Absecon Blvd. ACUA Contact Person: Matthew von der Hayden

Facility Contact Person: Robert Carlson This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program. The energy audit is conducted to promote the mission of the office of Clean Energy, which is to use innovation and technology to solve energy and environmental problems in a way that improves the State’s economy. This can be achieved through the wiser and more efficient use of energy. The annual energy costs estimated for the B Building are as follows: This wastewater facility is unique in that it generates its own power via the first commercial wind project in New Jersey and the nation’s first coastal and urban wind farm. The rate is set by the Power Purchase Agreement at 8¢ per kWh. In addition, the site contains a 500-kilowatt photovoltaic solar array consisting of ground-mounted, roof-mounted and parking area canopy systems. Note: Electricity is delivered to the Operations B Building from the solar arrays or the local utility. When purchased from the local utility, the average blended rate is approximately 12¢ per kWh. When the electricity is supplied by the wind farm or solar arrays, the internally calculated rate is 8¢ per kWh. The actual usage split cannot be determined since the building is not sub-metered for usage from the local utility versus the wind or solar generated power. By reducing the usage of electricity at the Operations B Building, the facility will be using less power from the utility company and more of the wind generated power. Conservatively, CEG has used the 8¢ per kWh blended rate for all of the energy calculations in this report. The potential annual energy cost savings for each energy conservation measure (ECM) and renewable energy measure (REM) are shown below in Table 1. Be aware that the ECM’s and REM’s are not additive because of the interrelation of some of the measures. This audit is consistent with an ASHRAE level 2 audit. The cost and savings for each measure is ± 20%. The

Electricity $114,223 #2 Fuel Oil Natural Gas

$11,343 $17,097

Total $142,663

Page 5: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 4 of 45

evaluations are based on engineering estimations and industry standard calculation methods. More detailed analyses would require engineering simulation models, hard equipment specifications, and contractor bid pricing.

Table 1 Financial Summary Table

ENERGY CONSERVATION MEASURES (ECM's)

ECM #1 Lighting Upgrade $41,785 $9,337 4.5 235.2%

ECM #2 Lighting Controls $9,300 $2,216 4.2 257.4%

ECM #3 Steam Boiler Replacement $82,000 $7,039 11.6 157.5%

ECM #4 Computer Monitor Replacement

$800 $215 3.7 303.1%

ECM #5 Water Conservation Opportunities

$240 $179 1.3 645.8%

$134,125 $18,986 5.1 319.8%

Notes:

ECM NO.

ECM NO. DESCRIPTION

SIMPLE PAYBACK

(Yrs)

SIMPLE LIFETIME

ROI

NET INSTALLATION

COSTA

A. Cost takes into consideration applicable NJ Smart StartTM incentives.B. Savings takes into consideration applicable maintenance savings.

ANNUAL SAVINGSB

Totals

The estimated demand and energy savings for each ECM and REM is shown below in Table 2. The descriptions in this table correspond to the ECM’s and REM’s listed in Table 1.

Table 2 Further Considerations

FURTHER CONSIDERATIONS - ENERGY CONSERVATION MEASURES (ECM's)

ECM #6 Waste Heat Geothermal Technology

$121,000 $10,709 11.3 32.8%

ECM NO. DESCRIPTION

NET INSTALLATION

COSTA

ANNUAL SAVINGSB

SIMPLE PAYBACK

(Yrs)

SIMPLE LIFETIME

ROI

Page 6: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 5 of 45

Table 3 Estimated Energy Savings Summary Table

ECM #1 Lighting Upgrade 15.1 116,706 0 0

ECM #2 Lighting Controls 4.3 27,706 0 0

ECM #3 Steam Boiler Replacement 0 0 -5,878 6,293

ECM #4 Computer Monitor Replacement

0.0 2,688 0 0

ECM #5 Water Conservation Opportunities

0.0 0 76 0

19.4 280967.0 -5801.8 6293.0

ELECTRIC DEMAND

(KW)

ELECTRIC CONSUMPTION

(KWH)

NATURAL GAS (THERMS)

ECM NO. DESCRIPTION

Totals

#2 FUEL OIL (GALLONS)

ENERGY CONSERVATION MEASURES (ECM's)ANNUAL UTILITY REDUCTION

Table 4

Further Considerations - Summary Table

ECM #6 Waste Heat Geothermal Technology

0.0 89,242 0 0

FUTHER CONSIDERATIONS - ENERGY CONSERVATION MEASURES (ECM's)

ECM NO. DESCRIPTION

ANNUAL UTILITY REDUCTION

ELECTRIC DEMAND

(KW)

ELECTRIC CONSUMPTION

(KWH)

NATURAL GAS (THERMS)

#2 FUEL OIL (GALLONS)

Page 7: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 6 of 45

Concord Engineering Group (CEG) recommends proceeding with the implementation of all ECM’s that provide a calculated simple payback at or under ten (10) years. The following Energy Conservation Measures are recommended for the facility:

• ECM #1: Lighting Upgrade

• ECM #2: Lighting Controls

• ECM #3: Steam Boiler Replacement

• ECM #4: Computer Monitor Replacement

• ECM #5: Water Conservation Opportunities

The ECM for the steam boiler replacement has a simple payback of over 10 years but due to the age of the boiler and that it is seriously oversized for the control room/office/lab heating load it is strongly recommended that it be replaced. In addition, a small increase in fuel oil pricing would change the simple payback to less than 10 years (for example, from $1.80 to $2.20 per gallon).

In addition to the ECMs, there are maintenance and operational measures that can provide significant energy savings and provide immediate benefit. The ECMs listed above represent investments that can be made to the facility which are justified by the savings seen overtime. However, the maintenance items and small operational improvements below are typically achievable with on site staff or maintenance contractors and in turn have the potential to provide substantial operational savings compared to the costs associated. The following are recommendations which should be considered a priority in achieving an energy efficient building: 1. Chemically clean the condenser and evaporator coils periodically to optimize efficiency.

Poorly maintained heat transfer surfaces can reduce efficiency 5-10%. 2. Maintain all weather stripping on entrance doors. 3. Clean all light fixtures to maximize light output. 4. Provide more frequent air filter changes to decrease overall system power usage and maintain

better IAQ.

Page 8: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 7 of 45

II. INTRODUCTION

This comprehensive energy audit covers the 19,150 SF Operations B Building which consists of the Control Room, Water/Wastewater Environmental Testing Laboratory, Administration Offices, Conference Room, Shops, Receiving, Storage and Restroom/Lockers. No. 2 fuel oil and natural gas utility information was collected and analyzed for one full year’s energy use for the B Building. No. 2 fuel oil is used for the steam boiler to produce heating hot water through a steam converter and the natural gas is used for the infrared heating units in the shops, receiving, storage, etc. Electrical usage for the entire facility (single electric meter for the entire facility) was obtained in order to calculate a blended kWh rate for the energy savings calculations. The utility information allows for analysis of the building’s operational characteristics; calculate energy benchmarks for comparison to industry averages, estimated savings potential, and baseline usage/cost to monitor the effectiveness of implemented measures. The Energy Use Index (EUI) is established for the building. Energy Use Index (EUI) is expressed in British Thermal Units/square foot/year (BTU/ft2/yr), which is used to compare energy consumption to similar building types or to track consumption from year to year in the same building. The EUI is calculated by converting the annual consumption of all energy sources to BTU’s and dividing by the area (gross square footage) of the building. Blueprints (where available) are utilized to verify the gross area of the facility. The EUI is a good indicator of the relative potential for energy savings. A low EUI indicates less potential for energy savings, while a high EUI indicates poor building performance therefore a high potential for energy savings. Existing building architectural and engineering drawings (where available) are utilized for additional background information. The building envelope, lighting systems, HVAC equipment, and controls information gathered from building drawings allow for a more accurate and detailed review of the building. The information is compared to the energy usage profiles developed from utility data. Through the review of the architectural and engineering drawings a building profile can be defined that documents building age, type, usage, major energy consuming equipment or systems, etc. The preliminary audit information is gathered in preparation for the site survey. The site survey provides critical information in deciphering where energy is spent and opportunities exist within a facility. The entire site is surveyed to inventory the following to gain an understanding of how each facility operates:

• Building envelope (roof, windows, etc.) • Heating, ventilation, and air conditioning equipment (HVAC) • Lighting systems and controls

Page 9: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 8 of 45

The building site visit is performed to survey all major building components and systems. The site visit includes detailed inspection of energy consuming components. Summary of building occupancy schedules, operating and maintenance practices, and energy management programs provided by the building manager are collected along with the system and components to determine a more accurate impact on energy consumption.

Page 10: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 9 of 45

III. METHOD OF ANALYSIS

Post site visit work includes evaluation of the information gathered, researching possible conservation opportunities, organizing the audit into a comprehensive report, and making recommendations on HVAC, lighting and building envelope improvements. Data collected is processed using energy engineering calculations to anticipate energy usage for each of the proposed energy conservation measures (ECMs). The actual building’s energy usage is entered directly from the utility bills provided by the owner. The anticipated energy usage is compared to the historical data to determine energy savings for the proposed ECMs. It is pertinent to note, that the savings noted in this report are not additive. The savings for each recommendation is calculated as standalone energy conservation measures. Implementation of more than one ECM may in some cases affect the savings of each ECM. The savings may in some cases be relatively higher if an individual ECM is implemented in lieu of multiple recommended ECMs. For example implementing reduced operating schedules for inefficient lighting will result in a greater relative savings. Implementing reduced operating schedules for newly installed efficient lighting will result in a lower relative savings, because there is less energy to be saved. If multiple ECM’s are recommended to be implemented, the combined savings is calculated and identified appropriately. ECMs are determined by identifying the building’s unique properties and deciphering the most beneficial energy saving measures available that meet the specific needs of the facility. The building construction type, function, operational schedule, existing conditions, and foreseen future plans are critical in the evaluation and final recommendations. Energy savings are calculated base on industry standard methods and engineering estimations. Energy consumption is calculated based on manufacturer’s cataloged information when new equipment is proposed. Cost savings are calculated based on the actual historical energy costs for the facility. Installation costs include labor and equipment costs to estimate the full up-front investment required to implement a change. Costs are derived from Means Cost Data, industry publications, and local contractors and equipment suppliers. The NJ Smart Start Building® program incentives savings (where applicable) are included for the appropriate ECM’s and subtracted from the installed cost. Maintenance savings are calculated where applicable and added to the energy savings for each ECM. The life-time for each ECM is estimated based on the typical life of the equipment being replaced or altered. The costs and savings are applied and a simple payback, simple lifetime savings, and simple return on investment are calculated. See below for calculation methods:

Page 11: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 10 of 45

ECM Calculation Equations:

⎟⎟⎠

⎞⎜⎜⎝

⎛=

SavingsYearlyCostNetPaybackSimple

( )LifetimeECMSavingsYearlySavingsLifetimeSimple ×=

CostNetCostNetSavingsLifetimeSimpleROILifetimeSimple )( −

=

( )LifetimeECMSavingsenanceMaYearlySavingsenanceMaLifetime ×= intint

( )∑=

⎟⎟⎠

⎞⎜⎜⎝

⎛+

=N

nnIRRPeriodofFlowCashturnofRateInternal

0 1Re

( )∑=

⎟⎟⎠

⎞⎜⎜⎝

⎛+

=N

nnDRPeriodofFlowCashValueesentNet

0 1Pr

Net Present Value calculations based on Interest Rate of 3%.

Page 12: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 11 of 45

IV. HISTORIC ENERGY CONSUMPTION/COST A. Energy Usage / Tariffs The energy usage for the facility has been tabulated and plotted in graph form as depicted within this section. Each energy source has been identified and monthly consumption and cost noted per the information provided by the Owner. This wastewater facility is unique in that it generates its own power via the first commercial wind project in New Jersey and the nation’s first coastal and urban wind farm. In addition, the site contains a 500-kilowatt photovoltaic solar array consisting of ground-mounted, roof-mounted and parking area canopy systems. The Operations B Building was sub-metered for an 8-month period when Rowan University was performing an energy audit of this building. This electric usage profile represents the estimated electrical usage for the Operations B Building. Note: Electricity is delivered to the Operations B Building from the solar arrays or the local utility. When purchased from the local utility, the average blended rate is approximately 12¢ per kWh. When the electricity is supplied by the wind farm or solar arrays, the internally calculated rate is 8¢ per kWh. The actual usage split cannot be determined since the building is not sub-metered for usage from the local utility versus the wind or solar generated power. By reducing the usage of electricity at the Operations B Building, the facility will be using less power from the utility company and more of the wind generated power. Conservatively, CEG has used the 8¢ per kWh blended rate for all of the energy calculations in this report. The gas usage profile shows the actual natural gas energy usage for the B Building. South Jersey Gas provides natural gas to the facility. The gas utility measures consumption in cubic feet x 100 (CCF), and converts the quantity into Therms of energy. One Therm is equivalent to 100,000 BTUs of energy. The oil usage profile shows the actual oil consumption for the facility. Oil is provided by Major Petroleum Industries to the facility. The oil provider measures consumption in gallons. One gallon of #2 fuel oil is equivalent to 140,000 BTUs of energy. The overall cost for utilities is calculated by dividing the total cost by the total usage. Based on the utility history provided, the average estimated cost for utilities at the B Building is as follows: Description Average

Electricity 8¢ per kWh Natural Gas $1.20 / Therm #2 Fuel Oil $1.80 /Gallon

Page 13: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 12 of 45

Table 5 Electric Billing Data

Utility Provider: Atlantic City Electric

MONTH OF USE CONSUMPTION KWH TOTAL BILL

Jan-10 123,634 $9,891 Feb-10 107,275 $8,582 Mar-10 142,538 $11,403 Apr-10 94,462 $7,557 May-10 102,580 $8,206 Jun-10 120,185 $9,615 Jul-10 127,756 $10,220

Aug-10 117,413 $9,393 Sep-10 131,833 $10,547 Oct-10 124,623 $9,970 Nov-10 120,039 $9,603 Dec-10 115,455 $9,236 Totals 1,427,792 $114,223

AVERAGE RATE $0.080 $/kWh

ELECTRIC USAGE SUMMARY

*Note: The months of October, November and December of 2010 are estimated values based on averages of surrounding months. Values are estimated due to lack of current billing information.

Page 14: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 13 of 45

Figure 1 Electric Usage Profile

Page 15: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 14 of 45

Table 6 Natural Gas Billing Data

Utility Provider: South Jersey Gas

MONTH OF USE CONSUMPTION (THERMS) TOTAL BILL

Jan-09 4,294.20 $5,847.78Feb-09 3,465.40 $4,469.65Mar-09 2,784.30 $3,018.24Apr-09 624.80 $621.15May-09 297.50 $300.39Jun-09 113.90 $125.59Jul-09 60.00 $78.69

Aug-09 54.70 $69.58Sep-09 52.30 $63.98Oct-09 378.90 $364.22Nov-09 583.20 $592.00Dec-09 1,496.30 $1,545.66

TOTALS 14,205.50 $17,096.93

AVERAGE RATE: $1.20 $/THERM

NATURAL GAS USAGE SUMMARY

Page 16: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 15 of 45

Figure 2 Natural Gas Usage Profile

Page 17: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 16 of 45

Table 7 Oil Billing Data

Utility Provider: Major Petrolium Industries

MONTH OF USE CONSUMPTION (GALLONS) TOTAL BILL

Jan-09 1,302.70 $2,269.95Feb-09 982.80 $1,611.79Mar-09 1,139.60 $1,660.91Apr-09 634.90 $925.34May-09 0.00 $0.00Jun-09 0.00 $0.00Jul-09 0.00 $0.00

Aug-09 0.00 $0.00Sep-09 0.00 $0.00Oct-09 128.80 $277.07Nov-09 843.50 $1,814.54Dec-09 1,260.70 $2,783.00

TOTALS 6,293.00 $11,342.60

AVERAGE RATE: $1.80 $/GALLON

OIL USAGE SUMMARY

Page 18: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 17 of 45

Figure 3 Oil Usage Profile

Page 19: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 18 of 45

B. Energy Use Index (EUI) Energy Use Index (EUI) is a measure of a building’s annual energy utilization per square foot of building. This calculation is completed by converting all utility usage consumed by a building for one year, to British Thermal Units (BTU) and dividing this number by the building square footage. EUI is a good measure of a building’s energy use and is utilized regularly for comparison of energy performance for similar building types. The Oak Ridge National Laboratory (ORNL) Buildings Technology Center under a contract with the U.S. Department of Energy maintains a Benchmarking Building Energy Performance Program. The ORNL website determines how a building’s energy use compares with similar facilities throughout the U.S. and in a specific region or state. Source use differs from site usage when comparing a building’s energy consumption with the national average. Site energy use is the energy consumed by the building at the building site only. Source energy use includes the site energy use as well as all of the losses to create and distribute the energy to the building. Source energy represents the total amount of raw fuel that is required to operate the building. It incorporates all transmission, delivery, and production losses, which allows for a complete assessment of energy efficiency in a building. The type of utility purchased has a substantial impact on the source energy use of a building. The EPA has determined that source energy is the most comparable unit for evaluation purposes and overall global impact. Both the site and source EUI ratings for the building are provided to understand and compare the differences in energy use. The site and source EUI for this facility is calculated as follows:

FootageSquareBuildingkBtuinUsageGaskBtuinUsageElectricEUISiteBuilding )( +

=

FootageSquareBuildingRatioSSXkBtuinUsageGasRatioSSXkBtuinUsageElectricEUISourceBuilding )( +

=

Page 20: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 19 of 45

Table 8

Facility Energy Use Index (EUI) Calculation

kWh Therms Gallons kBtu kBtu

ELECTRIC 1,427,792.3 4,874,483 3.340 16,280,772

NATURAL GAS 14,205.5 1,420,550 1.047 1,487,316

FUEL OIL 6,293.0 874,727 1.010 883,474

PROPANE 0.0 0 1.010 0

TOTAL 7,169,760 18,651,562

BUILDING AREA 19,150 SQUARE FEETBUILDING SITE EUI 374.40 kBtu/SF/YRBUILDING SOURCE EUI 973.97 kBtu/SF/YR

ENERGY USE INTENSITY CALCULATION

ENERGY TYPESITE-

SOURCE RATIO

BUILDING USE SITE ENERGY SOURCE ENERGY

*Site - Source Ratio data is provided by the Energy Star Performance Rating Methodology for Incorporating Source Energy Use document issued Dec 2007.

Page 21: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 20 of 45

C. EPA Energy Benchmarking System The United States Environmental Protection Agency (EPA) in an effort to promote energy management has created a system for benchmarking energy use amongst various end users. The benchmarking tool utilized for this analysis is entitled Portfolio Manager. The Portfolio Manager tool allows tracking and assessment of energy consumption via the template forms located on the ENERGY STAR website (www.energystar.gov). The importance of benchmarking for local government municipalities is becoming more important as utility costs continue to increase and emphasis is being placed on carbon reduction, greenhouse gas emissions and other environmental impacts. Based on information gathered from the ENERGY STAR website, Government agencies spend more than $10 billion a year on energy to provide public services and meet constituent needs. Furthermore, energy use in commercial buildings and industrial facilities is responsible for more than 50 percent of U.S. carbon dioxide emissions. It is vital that local government municipalities assess facility energy usage, benchmark energy usage utilizing Portfolio Manager, set priorities and goals to lessen energy usage and move forward with priorities and goals. In accordance with the Local Government Energy Audit Program, CEG has created an ENERGY STAR account for the municipality to access and monitoring the facility’s yearly energy usage as it compares to facilities of similar type. The login page for the account can be accessed at the following web address; the username and password are also listed below:

https://www.energystar.gov/istar/pmpam/index.cfm?fuseaction=login.login User Name: ACutilities Password: lgeaceg2010 Security Question: What city were you born in? Security Answer: “atlantic county” The utility bills and other information gathered during the energy audit process are entered into the Portfolio Manager. The following is a summary of the results for the facility:

Table 9 ENERGY STAR Performance Rating

ENERGY STAR PERFORMANCE RATING

FACILITY DESCRIPTION

ENERGY PERFORMANCE

RATING

NATIONAL AVERAGE

Atlantic County Utilities Authority N/A 50

The Atlantic County Utilities Authority falls under the “other” category which is not applicable for Energy Performance Rating. See the Statement of Energy Performance Appendix for the detailed energy summary.

Page 22: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 21 of 45

V. FACILITY DESCRIPTION

The 19,151SF Operations B Building is a two-story with basement facility comprised of administration offices, control room, conference room, IT office, electronics shop, environmental labs, 4-bay garage, maintenance/repair shop, storage and a shipping/receiving area. The basement and second floor are no longer occupied and are kept at approximately 50°F during the winter months.

HVAC Systems

The facility is heated by a Cleaver Brooks oil-fired, sectional steam boiler with a rated capacity of 4,000 MBH input and 3,200 MBH output. A large portion of the steam feeds a steam-to-hot water convertor and the hot water is circulated to duct-mounted hot water coils, unit heaters, cabinet heaters and baseboard heaters via two (2) 1.5 HP pumps delivering 90 GPM at 30 feet TDH. The balance of the steam feeds several steam unit heaters. The basement and second floor of the original building are no longer used. The repair shops, storage and receiving areas have been converted to infra-red gas-fired heating. The domestic hot water that was produced by another steam-to-hot water convertor has been replaced by two (2) electric domestic hot water heaters. Therefore the estimated thermal efficiency for this boiler that is partially loaded, even in the coldest weeks of the winter, is approximately 50%.

The office, control room, and lab spaces are cooled by seven (7) rooftop units (cooling only) that range in size from 4 to 10 tons [two (2) of the units are heat pumps]. A 1.5 ton split unit serves the data room.

Exhaust System

Air is exhausted from the toilet rooms, locker rooms, and hallways through roof exhausters.

HVAC System Controls

The HVAC systems within the facility are controlled via a Honeywell which controls the hot water convertor, unit heaters, duct-mounted coils, and several exhaust fans. All of the rooftop units are controlled by thermostats located in various offices, the control room, conference room and labs.

Domestic Hot Water

Domestic hot water for the office restrooms and locker rooms is provided by a 120-gallon A. O. Smith electric hot water heater with two (2) electric elements rated at 3,375 watts each. The domestic hot water is circulated throughout the building by a hot water re-circ pump. The circulation pump is controlled by an aqua stat. The domestic hot water piping insulation appeared to be in good condition. The shops/receiving area restroom is serviced by an A. O. Smith domestic hot water heater with a 40-gallon capacity and two (2) electric elements rated at 3,375 watts each.

Page 23: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 22 of 45

Lighting Typical lighting throughout the office/lab portion of the building is fluorescent tube lay-in fixtures with T-8 lamps and electronic ballasts. Some of the offices, corridors, storage spaces, utility closets and bathrooms in the buildings still have a variety of older fixtures with T12 lamps with magnetic ballasts. In addition, some of the existing exit signs have 7-Watt Compact Fluorescent Lamps (CFLs) or incandescent bulbs.

Page 24: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 23 of 45

VI. MAJOR EQUIPMENT LIST

The equipment list contains major energy consuming equipment that through implementation of energy conservation measures could yield substantial energy savings. The list shows the major equipment in the facility and all pertinent information utilized in energy savings calculations. An approximate age was assigned to the equipment in some cases if a manufactures date was not shown on the equipment’s nameplate. The ASHRAE service life for the equipment along with the remaining useful life is also shown in the Appendix.

Refer to the Major Equipment List Appendix for this facility.

Page 25: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 24 of 45

VII. ENERGY CONSERVATION MEASURES

ECM #1: Lighting Upgrade Description: The majority of the lighting throughout the Atlantic County Utilities Authority is provided with modern fixtures with T8 lamps and electronic ballasts. However, some of the offices, corridors, storage spaces, utility closets and bathrooms in the buildings still have a variety of older fixtures with T12 lamps with magnetic ballasts. It is recommended to replace all of the T12 fixtures in these areas with higher efficiency fluorescent T8 fixtures with electronic ballasts. This ECM includes retrofit of all T12 fixtures with Super T8 fixtures with electronic ballasts in the building. The new, energy efficient Super T8 fixtures will provide adequate lighting and will save on electrical costs due to better performance of the lamp and ballasts. Therefore, ACUA should not wait until the fixtures have reached their life expectancy since these electrical savings would be lost. This ECM also includes maintenance savings through the reduced number of lamps replaced per year. The expected lamp life of a Super T8 lamp is approximately 30,000 burn-hours, in comparison to the existing T12 lamps which is approximately 20,000 burn-hours. The facility will need approximately 33% less lamps replaced per year for each one for one fixture replaced. The last part of this ECM involves replacing some of the existing exit signs that have 7-Watt Compact Fluorescent Lamps (CFLs) or incandescent bulbs with the newer LED technology units. Energy Savings Calculations: The Investment Grade Lighting Audit Appendix outlines the hours of operation, proposed retrofits, costs, savings, and payback periods for each set of fixtures in the each building. From the Smart Start Incentive Appendix, the following incentives are warranted: For the LED Exit Sign: $20/LED Exit sign (≤75kW facility connected load) and $10/LED Exit sign (≥75kW facility connected load). Smart Start ® Incentive = (# of LED Exit fixtures x $10 per fixture) Smart Start ® Incentive = 5 fixtures x $10 per fixture = $50. For replacement of T12 to Super T8 with electronic ballast is $10 per fixture. Smart Start ® Incentive = (# of T8w/EB fixtures x $10 per fixture) Smart Start ® Incentive = 266 fixtures x $10 per fixture = $2,660.

Page 26: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 25 of 45

Energy Savings Summary:

Installation Cost ($): $44,445

NJ Smart Start Equipment Incentive ($): $2,660

Net Installation Cost ($): $41,785

Maintenance Savings ($/Yr): $0

Energy Savings ($/Yr): $9,337

Total Yearly Savings ($/Yr): $9,337

Estimated ECM Lifetime (Yr): 15

Simple Payback 4.5

Simple Lifetime ROI 235.2%

Simple Lifetime Maintenance Savings $0

Simple Lifetime Savings $140,055Internal Rate of Return (IRR) 21%Net Present Value (NPV) $69,679.50

ECM #1 - ENERGY SAVINGS SUMMARY

Page 27: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 26 of 45

ECM #2: Lighting Occupancy Sensors / Daylight Sensors Description: In some areas the lighting is left on unnecessarily. In many cases the lights are left on because of the inconvenience to manually switch lights off when a room is left or on when a room is first occupied. This is common in rooms that are occupied for only short periods and only a few times per day. In some instances lights are left on due to the misconception that it is better to keep the lights on rather than to continuously switch lights on and off. Although increased switching reduces lamp life, the energy savings outweigh the lamp replacement costs. The payback timeframe for when to turn the lights off is approximately two minutes. If the lights are expected to be off for at least a two minute interval, then it pays to shut them off.

Lighting controls come in many forms. Sometimes an additional switch is adequate to provide reduced lighting levels when full light output is not needed. Occupancy sensors detect motion and will switch the lights on when the room is occupied. Occupancy sensors can either be mounted in place of a current wall switch, or on the ceiling to cover large areas. Photocell control senses light levels and turn off or reduce lights when there is adequate daylight. Photocells are mostly used outside, but are becoming more popular in energy-efficient interior lighting designs as well. The U.S. Department of Energy sponsored a study to analyze energy savings achieved through various types of building system controls. The referenced savings is based on the “Advanced Sensors and Controls for Building Applications: Market Assessment and Potential R&D Pathways,” document posted for public use April 2005. The study has found that commercial buildings have the potential to achieve significant energy savings through the use of building controls. The average energy savings are as follows based on the report:

• Occupancy Sensors for Lighting Control 20% - 28% energy savings.

Savings resulting from the implementation of this ECM for energy management controls are estimated to be 10% of the total light energy controlled by occupancy sensors and 25% for daylight sensors (The majority of the savings is expected to be after school hours when rooms are left with lights on) This ECM includes installation of wall-mounted and ceiling type sensors for individual offices, conference rooms, locker rooms, small repair shops, restrooms, etc. Sensors shall be manufactured by Sensorswitch, Watt Stopper or equivalent. The Investment Grade Lighting Audit Appendix of this report includes the summary of lighting controls implemented in this ECM and outlines the proposed controls, costs, savings, and payback periods. The calculations adjust the lighting power usage by the applicable percent savings for each area that includes lighting controls.

Page 28: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 27 of 45

Energy Savings Calculations:

( )( )kWh/YrEnergyLightControlledSavings%SavingsEnergy ×=

( ) ⎟⎠⎞

⎜⎝⎛×=

kWh$CostElecAvekWhSavingsEnergySavings.

Installation cost per dual-technology sensors (Basis: Sensor switch or equivalent) are as follows:

Dual Technology Occupancy Sensor (Switch Mount) $75 per installation Dual Technology Occupancy Sensor (Remote Mount) $160 per installation Spring Wound Timer Switch $125 per installation Dual Tech. Occupancy Sensor w/2 Pole Power Pack $225 per installation Dual Technology Occupancy Sensor & Day Light Sensor $360 per installation

Cost includes material/labor and additional wiring where there are dual circuits and three-way switches.

See the Investment Grade Lighting Audit Appendix for details. From the NJ Smart Start® Program Incentives Appendix, the installation of a lighting control device warrants the following incentive: Occupancy Sensor Wall Mounted (existing facility only) = $20 per sensor. Occupancy Sensor Remote Mounted (existing facility only) = $35 per sensor

( )( ) $440 35)$(420$15IncentiveStartSmart

35)mountceilingof(#20$mountwallof#IncentiveStartSmart =×+×=®

×+×=®

For safety reasons, some areas of the building will not be completely without light so that some re-wiring of fixtures and added relays will be installed to maintain some lighting in these areas. These areas would need to be addressed during the engineering and specification phase of implementing this ECM.

Page 29: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 28 of 45

Energy Savings Summary:

Installation Cost ($): $9,740

NJ Smart Start Equipment Incentive ($): $440

Net Installation Cost ($): $9,300

Maintenance Savings ($/Yr): $0

Energy Savings ($/Yr): $2,216

Total Yearly Savings ($/Yr): $2,216

Estimated ECM Lifetime (Yr): 15

Simple Payback 4.2

Simple Lifetime ROI 257.4%

Simple Lifetime Maintenance Savings $0

Simple Lifetime Savings $33,240Internal Rate of Return (IRR) 23%Net Present Value (NPV) $17,154.46

ECM #2 - ENERGY SAVINGS SUMMARY

Page 30: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 29 of 45

ECM #3: Heating System Upgrade Description:

The heating for the offices, control room, conference room, locker rooms, etc. is provided via an oil-fired 4,000 MBH, water-tube, Model 4, Series 100, low pressure steam boiler made by Cleaver Brooks. The boiler is approximately 24 years old and is near the end of its expected useful service life, which is thirty (30) years per ASHRAE. The boiler provides steam to a hot water converter. Generated heating hot water is circulated through the duct heaters, baseboard heaters and cabinet heaters in the building via a set of older hot water pumps.

Steam heating is an inherently inefficient process due to higher operating temperature of the system. An alternative to reduce the heating energy consumption of the building is to convert the entire heating system into hot water. In addition, the boiler is oversized for the current heating load since most of the heating and all of the domestic hot water load was taken off the boiler. Because of this, the boiler runs at part load conditions year round. Current average combustion efficiency of the boiler is estimated to be 55% due to part load conditions, limited turndown ratio or cycling losses, age of the equipment, rusting and sediment build-up on the heat transfer surfaces, deteriorating or missing insulation, outdated design and controls.

CEG recommends replacing the original 4,000 MBH oil-fired steam boiler with a smaller, gas-fired, high-efficiency, condensing, modular, hot water boiler to carry the load during the entire heating season. The efficiency of a condensing, hot water boiler can reach as high as 90% when the return water temperature is lowered. It is also recommended to install two (2) new hot water pumps to replace the existing hot water pumps, which are oversized for the current heating load.

Calculations are based on one (1) Aerco Benchmark 1.5 high efficiency, gas-fired, modular, condensing hot water boiler rated at 1,500 MBH input and a maximum output of between 1290 MBH and 1409 MBH output depending on return water temperature. The calculation results can be used for comparative purposes between existing and new system and can be used as a basis for overall heating energy use or operating cost. The Owner should retain a professional engineer to verify heating loads as well as the flow requirements prior to moving forward with this ECM. Energy Savings Calculations: Fuel consumption of the steam boiler plant is gathered in order to calculate the estimated annual steam production of the boiler plant. Then, the steam production info is used in a reverse calculation to obtain proposed annual fuel consumption based on improved efficiency.

Net Heat Production, MMBTUOil Cons Gallons

1 Gallon 0.14 MMBTU

Boiler Eff.

Total annual energy consumption of the boiler is obtained from the energy billing data, which is summarized in the table below.

Page 31: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 30 of 45

MONTH OF USE

OIL CONSUMPTION

(GALLONS)

TOTAL ENERGY

INPUT (MMBTU)

TOTAL HEAT ENERGY OUTPUT

(MMBTU)Jan-09 1,303 182 109Feb-09 983 138 83Mar-09 1,140 160 96Apr-09 635 89 53May-09 0 0 0Jun-09 0 0 0Jul-09 0 0 0

Aug-09 0 0 0Sep-09 0 0 0Oct-09 129 18 11Nov-09 844 118 71Dec-09 1,261 176 106

TOTALS 6,293 881 529

HEATING ENERGY USAGE SUMMARY

The equation below is used to calculate the energy consumption of the proposed boiler.

New Gas Consumption, ThermsNet Heat Production, MMBTU 1 Therm

0.1 MMBTUNew Boiler Efficiency

Results of the energy savings calculations are summarized in the following table.

Page 32: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 31 of 45

ECM INPUTS EXISTING PROPOSED SAVINGS

Equipment Existing Steam Heating System

Hot Water Heating System

Nat Gas Usage (Therms) 0 - -Oil Usage (Gallons) 6,293 - -Boiler Efficiency (%) 55% 90.0% 35%Gas Cost ($/Therm) $1.20 $1.20 -Oil Cost ($/Gallon) $1.80 $1.80 -Nat Gas Heat Value (BTU/Therm) 100,000 100,000 -Oil Value (BTU/Gallon) 140,000 140,000 -

ECM RESULTS EXISTING PROPOSED SAVINGSNet Heat with Oil (MMBTU) 485 - -Net Heat with Gas (MMBTU) - 529 -Total Net Heat (MMBTUs) 485 485 0Natural Gas Usage (Therms) - 5,878 (5,878)Oil Usage (Gallons) 6,293 - 6,293 Natural Gas Cost ($) - $7,053 ($7,053)Oil Cost ($) $11,343 - $11,343 Heating Energy Cost ($) $11,343 $7,053 $4,289 COMMENTS:

HOT WATER BOILER CALCULATIONS

ENERGY SAVINGS CALCULATIONS

Annual oil usage estimated based on previous years usage.

Project Cost, Incentives and Maintenance Savings Estimated cost for removing the existing steam boiler and the hot water converter and installing new hot water boiler and a set of two (2) hot water pumps connecting to the existing hot water loop is $85,000. The cost does not include any asbestos abatement requirements. From the New Jersey Smart Start® Program Incentives Appendix, installation of a high efficiency hot water boiler falls under the category “Gas Heating” and warrants an incentive based on efficiency at or above 84% for this type of equipment. The program incentives are calculated as follows:

Page 33: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 32 of 45

>1500 - ≤ 4000 MBH 84% AFUE for Hot Water boilers

$1 $1 1500 $3,000

TOTAL 1500 $3,000

GAS FIRED BOILER REBATE SUMMARY - ALT 2

UNIT DESCRIPTION UNIT EFFICIENCY

REBATE $/MBH

PROPOSED CAPACITY,

MBH

TOTAL REBATE

$

South Jersey Gas Rebate

Match $/ MBH

Estimated maintenance savings achieved with this ECM is $2,750/Year. Energy Savings Summary:

Installation Cost ($): $85,000

NJ Smart Start Equipment Incentive ($): $3,000

Net Installation Cost ($): $82,000

Maintenance Savings ($/Yr): $2,750

Energy Savings ($/Yr): $4,289

Total Yearly Savings ($/Yr): $7,039

Estimated ECM Lifetime (Yr): 30

Simple Payback 11.6

Simple Lifetime ROI 157.5%

Simple Lifetime Maintenance Savings $82,500

Simple Lifetime Savings $211,178Internal Rate of Return (IRR) 8%Net Present Value (NPV) $55,972.73

ECM #3 - ENERGY SAVINGS SUMMARY

Page 34: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 33 of 45

ECM #4: Computer Monitor Replacement Description: The computers throughout the Atlantic County Utility Authority utilize CRT computer monitors. These computer monitors are used at almost every computer work station including the offices, computer labs, lounges, conference rooms, etc. These computer monitors are outdated and have several disadvantages such as; significantly increased higher energy consumption, uses large amount of desk space, poor picture quality, distortions and flickering image, secular glare problems, and high weight, and electromagnetic emissions. Many of the drawbacks are difficult to quantify except for the energy use. CRT monitors use considerably more energy than an alternative flat panel LCD monitor. Replacement of the existing CRT monitors with LCD monitors saves considerable energy as well as provides other ergonomic benefits as well. Based on the site survey it was noted that a large number of the computers were left on and allowed to run 24 / 7. The majority of the monitors were left in screen saver mode, which is deceiving since this mode only saves the computer screen from image burn in, however it does not save on energy consumption. The average operating hours for all computers and monitors is estimated based on the site survey observations. Energy consumption of computer monitors are based on manufacture’s specifications. This ECM includes replacement of all existing CRT monitors with LCD flat panel monitors throughout the administration offices / control room. Installation costs were neglected for this ECM with the intention that this ECM would be replaced by the ACUA employees. The calculations are based on the following operating assumptions: Energy Savings Calculations: No. of Computers: 8 Run Time %: 100% Weeks per Yr: 52 Hrs per Week: 168

( ) ( )

⎟⎠⎞

⎜⎝⎛

×××=

KWW

HrsOperationWPowerMonitorTimeRunComputersofUsageElectric

1000

%#

( ) ⎟⎠⎞

⎜⎝⎛×=

kWhCostElecAvekWhUsageElectricCostEnergy $

Page 35: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 34 of 45

ECM INPUTS EXISTING PROPOSED SAVINGSECM INPUTS CRT Monitors LCD Monitor

# of Computers 8 8

Monitor Power Cons. (W) 75 25

Run Time % 100% 100%

Operating Hrs per Week 168 168

Operating Weeks per Yr 40 40

Elec Cost ($/kWh) 0.080 0.080

ECM RESULTS EXISTING PROPOSED SAVINGS

Electric Usage (kWh) 4,032 1,344 2,688

Energy Cost ($) $323 $108 $215

COMMENTS:

COMPUTER MONITOR CALCULATIONS

ENERGY SAVINGS CALCULATIONS

Installation cost of new monitors is estimated based on current pricing for a 17” LCD monitor on the market today. No labor costs were included for replacing the existing monitors with the new monitors. No incentives are available for installation of computer monitors. Net cost per monitor was estimated to be $100. Installation Costs: # Monitors X Cost per Monitor

8 Monitors X $100 per Monitor = $800 Energy Savings Summary:

Page 36: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 35 of 45

Installation Cost ($): $800

NJ Smart Start Equipment Incentive ($): $0

Net Installation Cost ($): $800

Maintenance Savings ($/Yr): $0

Energy Savings ($/Yr): $215

Total Yearly Savings ($/Yr): $215

Estimated ECM Lifetime (Yr): 15

Simple Payback 3.7

Simple Lifetime ROI 303.1%

Simple Lifetime Maintenance Savings $0

Simple Lifetime Savings $3,225Internal Rate of Return (IRR) 26%Net Present Value (NPV) $1,766.66

ECM #4 - ENERGY SAVINGS SUMMARY

Page 37: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 36 of 45

ECM #5: Water Conservation Opportunities Description: Water conservation is defined as any action that reduces the amount of water withdrawn from water supply sources, reduces consumptive use, reduces the loss or waste of water, improves the efficiency of water use, increases recycling and reuse of water, or prevents the pollution of water. Conversely, water waste is the excessive use of potable water that is unproductive or does not reasonably sustain economic benefits or life forms, particularly where there is a shortage of potable water. Faucets for restrooms, kitchen, and workroom sinks vary in flow rates. Restroom sinks need no more than 1.5 gallons per minute and kitchen sinks need about 2.5 gallons per minute while workroom sinks may include automated controls and pre-mixed temperatures. Toilets and urinals account for almost half of a typical building’s water consumption. According to the Plumbing Foundation, replacing all existing toilets with 1.6 gallons per flush, ultra-low flow models and urinals with 1.0 gallons per flush models would save almost 5,000 gallons of water per person each year. A conventional showerhead is rated to use 3 to 5 gallons per minute at normal water pressure, about 60 psi. A 5-minute shower with a conventional showerhead typically consumes 15 to 25 gallons of water. High quality replacement showerheads that deliver 1 to 2.5 gallons per minute can save many gallons per shower. Products vary in price from $10 to $50. This ECM would install low flow high performance sink aerators and high performance shower heads with ultra low flow. Water Savings Calculations: The water savings for the faucet aerators and showerheads were calculated by using the U. S. Department of Energy Federal Energy Management Program (FEMP) energy cost calculators for faucets, showerheads and urinals. Additional information on the referenced calculators can be found at www1.eere.energy.gov/femp/technologies. Water and sewer rates obtained from Atlantic County are as follows: Water: $3.10/1,000 gallons + Sewer: $2.80/1,000 gallons = Total: $5.90/1,000 gallons Summary of the water savings for this facility are as follows: Plumbing Fixture # of Units Water/Sewer Savings Material $ Payback(Yrs.) Faucet Aerators 4 $45 $80 1.7 Showerheads 4 $43 $160 3.7

Page 38: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 37 of 45

The basis of calculation for the low flow high performance sink aerator and high performance shower heads with ultra low flow is the UtilitySavers™ high performance Spray Stream. It is also assumed that the facility operators will install the new faucet aerators and showerheads. Cost Savings Summary:

Installation Cost ($): $240

NJ Smart Start Equipment Incentive ($): $0

Net Installation Cost ($): $240

Maintenance Savings ($/Yr): $0

Energy Savings ($/Yr): $179

Total Yearly Savings ($/Yr): $179

Estimated ECM Lifetime (Yr): 10

Simple Payback 1.3

Simple Lifetime ROI 645.8%

Simple Lifetime Maintenance Savings $0

Simple Lifetime Savings $1,790Internal Rate of Return (IRR) 74%Net Present Value (NPV) $1,286.91

ECM #5 - ENERGY SAVINGS SUMMARY

Page 39: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 38 of 45

Further Considerations Waste Heat Geothermal Technology Description: The Operations B Building is presently heated by a steam boiler that feeds a steam-to-hot water converter and cooled by rooftop units. This ECM would replace this heating/cooling system with a technology that incorporates heat pumps. Heat pumps move heat from one location to another, drawing heat from air or groundwater sources and transferring that heat into buildings. Wastewater follows a highly predictable temperature curve relative to outside air, and is warm in the winter and cool in the summer. NovaThermal Energy combines a geothermal heat pump with a patented anti-block filtration device to transfer heat energy directly from wastewater for commercial HVAC applications. In the heating cycle, warm wastewater is transported to the NovaThermal heat pump which absorbs this heat. The heat pump then transfers heat to the building’s clean water circulation loop, heating the building. The wastewater is then returned to the treatment plant, whereupon the 8-15°F temperature differential is dissipated. This ECM would install a NovaThermal Energy anti-block filtration unit and heat pump skid in the existing boiler room, pipe into the existing hot water circulation system, and provide the controls for the system. The cost does not include piping to/from the wastewater feed line, chilled water piping to the rooftop air handling units nor the installation of chilled water coils into the rooftop units and associated controls. These costs will need to be estimated once the preliminary engineering is completed. Energy Savings Calculations: See the Novathermal Energy Appendix for a detailed energy savings and capital cost study performed by NovaThermal Energy. This system uses intellectual property developed by NovaThermal Energy and this study/analysis should be considered proprietary information.

Page 40: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 39 of 45

Cost Savings Summary:

Installation Cost ($): $121,000

NJ Smart Start Equipment Incentive ($): $0

Net Installation Cost ($): $121,000

Maintenance Savings ($/Yr): $0

Energy Savings ($/Yr): $10,709

Total Yearly Savings ($/Yr): $10,709

Estimated ECM Lifetime (Yr): 15

Simple Payback 11.3

Simple Lifetime ROI 32.8%

Simple Lifetime Maintenance Savings 0

Simple Lifetime Savings $160,635Internal Rate of Return (IRR) 4%Net Present Value (NPV) $6,843.35

ENERGY SAVINGS SUMMARY

Page 41: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 40 of 45

VIII. RENEWABLE/DISTRIBUTED ENERGY MEASURES This wastewater facility is unique in that it generates its own power via the first commercial wind project in New Jersey and the nation’s first coastal and urban wind farm. In addition, the site contains a 500-kilowatt photovoltaic solar array consisting of ground-mounted, roof-mounted and parking area canopy systems. Therefore renewable energy measures were not analyzed.

Page 42: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 41 of 45

IX. ENERGY PURCHASING AND PROCUREMENT STRATEGY This wastewater facility is unique in that it generates its own power via the first commercial wind project in New Jersey and the nation’s first coastal and urban wind farm which contains five 1.5 MW wind turbines. This wind farm was installed under a Power Purchase Agreement. In addition, the site contains a 500-kilowatt photovoltaic solar array consisting of ground-mounted, roof-mounted and parking area canopy systems. Note: Electricity is delivered to the Operations B Building from the solar arrays or the local utility. When purchased from the local utility, the average blended rate is approximately 12¢ per kWh. When the electricity is supplied by the wind farm or solar arrays, the internally calculated rate is 8¢ per kWh. The actual usage split cannot be determined since the building is not sub-metered for usage from the local utility versus the wind or solar generated power. By reducing the usage of electricity at the Operations B Building, the facility will be using less power from the utility company and more of the solar and wind generated power. Conservatively, CEG has used the 8¢ per kWh blended rate for all of the energy calculations in this report. The ACUA is representative of a trend-setter within the state of New Jersey. The ACUA’s executive management and engineering staff are ahead of the majority of end users when it comes to both procuring energy and creating their own energy via renewable energy systems. Therefore, recommendations that would typically be made for an entity are not valid due to the ACUA’s forward thinking.

Page 43: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 42 of 45

X. INSTALLATION FUNDING OPTIONS CEG has reviewed various funding options for the facility owner to utilize in subsidizing the costs for installing the energy conservation measures noted within this report. Below are a few alternative funding methods:

i. Energy Savings Improvement Program (ESIP) – Public Law 2009, Chapter 4

authorizes government entities to make energy related improvements to their facilities and pay for the costs using the value of energy savings that result from the improvements. The “Energy Savings Improvement Program (ESIP)” law provides a flexible approach that can allow all government agencies in New Jersey to improve and reduce energy usage with minimal expenditure of new financial resources.

ii. New Jersey Environmental Infrastructure Trust – The loan program functions as

a trust that allows environmental assistance to projects involving wastewater, drinking water, storm water, landfills, brown fields, open space acquisition, and several others. The program abides by the N.J.A.C. 7:22 - Financial Assistance Programs for Environmental Infrastructure Facilities. For further information regarding the loan process please refer to the following website: www.njeit.org.

iii. Power Purchase Agreement – Public Law 2008, Chapter 3 authorizes contractor

of up to fifteen (15) years for contracts commonly known as “power purchase agreements.” These are programs where the contracting unit (Owner) procures a contract for, in most cases, a third party to install, maintain, and own a renewable energy system. These renewable energy systems are typically solar panels, windmills or other systems that create renewable energy. In exchange for the third party’s work of installing, maintaining and owning the renewable energy system, the contracting unit (Owner) agrees to purchase the power generated by the renewable energy system from the third party at agreed upon energy rates.

iv. Pay For Performance – The New Jersey Smart Start Pay for Performance

program includes incentives based on savings resulted from implemented ECMs. The program is available for all buildings that were audited as part of the NJ Clean Energy’s Local Government Energy Audit Program. The facility’s participation in the program is assisted by an approved program partner. An “Energy Reduction Plan” is created with the facility and approved partner to shown at least 15% reduction in the building’s current energy use. Multiple energy conservation measures implemented together are applicable toward the total savings of at least 15%. No more than 50% of the total energy savings can result from lighting upgrades / changes.

Total incentive is capped at 50% of the project cost. The program savings is broken down into three benchmarks; Energy Reduction Plan, Project Implementation, and Measurement and Verification. Each step provides

Page 44: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 43 of 45

additional incentives as the energy reduction project continues. The benchmark incentives are as follows:

1. Energy Reduction Plan – Upon completion of an energy reduction plan by

an approved program partner, the incentive will grant $0.10 per square foot between $5,000 and $50,000, and not to exceed 50% of the facility’s annual energy expense. (Benchmark #1 is not provided in addition to the local government energy audit program incentive.)

2. Project Implementation – Upon installation of the recommended measures

along with the “Substantial Completion Construction Report,” the incentive will grant savings per KWH or Therm based on the program’s rates. Minimum saving must be 15%. (Example $0.11 / kWh for 15% savings, $0.12/ kWh for 17% savings, … and $1.10 / Therm for 15% savings, $1.20 / Therm for 17% saving, …) Increased incentives result from projected savings above 15%.

3. Measurement and Verification – Upon verification 12 months after

implementation of all recommended measures, that actual savings have been achieved, based on a completed verification report, the incentive will grant additional savings per kWh or Therm based on the program’s rates. Minimum savings must be 15%. (Example $0.07 / kWh for 15% savings, $0.08/ kWh for 17% savings, … and $0.70 / Therm for 15% savings, $0.80 / Therm for 17% saving, …) Increased incentives result from verified savings above 15%.

CEG recommends the Owner review the use of the above-listed funding options in addition to utilizing their standard method of financing for facilities upgrades in order to fund the proposed energy conservation measures.

Page 45: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 44 of 45

XI. ADDITIONAL RECOMMENDATIONS The following general recommendations include no cost/low cost measures, Operation & Maintenance (O&M) items, and water conservation measures with attractive paybacks. These measures are not eligible for the Smart Start Buildings incentives from the Office of Clean Energy but save energy none the less. A. Chemically clean the condenser and evaporator coils periodically to optimize efficiency.

Poorly maintained heat transfer surfaces can reduce efficiency 5-10%.

B. Maintain all weather stripping on windows and doors.

C. Use cog-belts instead of v-belts on all belt-driven fans, etc. These can reduce electrical consumption of the motor by 2-5%.

D. Reduce lighting in specified areas where the foot candle levels are above 70 in private offices and above 30 in corridor, lobbies, etc.

E. Provide more frequent air filter changes to decrease overall fan horsepower requirements and maintain better IAQ.

F. Recalibrate existing sensors serving the office spaces

G. Install a Vending Miser system to turn off the vending machines when not in use.

H. Clean all light fixtures to maximize light output.

I. Confirm that outside air economizers on the rooftop units are functioning properly to take advantage of free cooling.

Page 46: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

ACUA – Operations B Building Energy Audit

Concord Engineering Group, Inc. 9C10051 January 28, 2011 – FINAL Page 45 of 45

XII. ENERGY AUDIT ASSUMPTIONS The assumptions utilized in this energy audit include but are not limited to following:

A. Cost Estimates noted within this report are based on industry accepted costing data such as RS MeansTM Cost Data, contractor pricing and engineering estimates. All cost estimates for this level of auditing are +/- 20%. Prevailing wage rates for the specified region has been utilized to calculate installation costs. The cost estimates indicated within this audit should be utilized by the owner for prioritizing further project development post the energy audit. Project development would include investment grade auditing and detailed engineering.

B. Energy savings noted within this audit are calculated utilizing industry standard procedures and accepted engineering assumptions. For this level of auditing, energy savings are not guaranteed.

C. Information gathering for each facility is strongly based on interviews with operations personnel. Information dependent on verbal feedback is used for calculation assumptions including but not limited to the following:

a. operating hours b. equipment type c. control strategies d. scheduling

D. Information contained within the major equipment list is based on the existing owner documentation where available (drawings, O&M manuals, etc.). If existing owner documentation is not available, catalog information is utilized to populate the required information.

E. Equipment incentives and energy credits are based on current pricing and status of rebate programs. Rebate availability is dependent on the individual program funding and applicability.

F. Equipment (HVAC, Plumbing, Electrical, & Lighting) noted within an ECM recommendation is strictly noted as a basis for calculation of energy savings. The owner should use this equipment information as a benchmark when pursuing further investment grade project development and detailed engineering for specific energy conservation measures.

Utility bill annual averages are utilized for calculation of all energy costs unless otherwise noted. Accuracy of the utility energy usage and costs are based on the information provided. Utility information including usage and costs is estimated where incomplete data is provided.

Page 47: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

APPENDIX A1 of 1

LIFETIME ENERGY SAVINGS

LIFETIME MAINTENANCE

SAVINGSLIFETIME ROI SIMPLE PAYBACK INTERNAL RATE OF

RETURN (IRR)NET PRESENT VALUE

(NPV)

MATERIAL LABOR REBATES, INCENTIVES

NET INSTALLATION

COSTENERGY MAINT. / SREC TOTAL (Yearly Saving * ECM Lifetime)

(Yearly Maint Svaing * ECM Lifetime)

(Lifetime Savings - Net Cost) / (Net Cost) (Net cost / Yearly Savings)

($) ($) ($) ($) ($/Yr) ($/Yr) ($/Yr) (Yr) ($) ($) (%) (Yr) ($) ($)

ECM #1 Lighting Upgrade $35,556 $8,889 $2,660 $41,785 $9,337 $0 $9,337 15 $140,055 $0 235.2% 4.5 21.08% $69,679.50

ECM #2 Lighting Controls $7,792 $1,948 $440 $9,300 $2,216 $0 $2,216 15 $33,240 $0 257.4% 4.2 22.72% $17,154.46

ECM #3 Steam Boiler Replacement $85,000 $0 $3,000 $82,000 $4,289 $2,750 $7,039 30 $211,178 $82,500 157.5% 11.6 7.64% $55,972.73

ECM #4 Computer Monitor Replacement $800 $0 $0 $800 $215 $0 $215 15 $3,225 $0 303.1% 3.7 26.04% $1,766.66

ECM #5 Water Conservation Opportunities $240 $0 $0 $240 $179 $0 $179 10 $1,790 $0 645.8% 1.3 74.30% $1,286.91

ECM #6 Waste Heat Geothermal Technology $121,000 $0 $0 $121,000 $10,709 $0 $10,709 15 $160,635 $0 32.8% 11.3 3.77% $6,843.35

Notes: 1) The variable Cn in the formulas for Internal Rate of Return and Net Present Value stands for the cash flow during each period.2) The variable DR in the NPV equation stands for Discount Rate3) For NPV and IRR calculations: From n=0 to N periods where N is the lifetime of ECM and Cn is the cash flow during each period .

ECM COST & SAVINGS BREAKDOWNCONCORD ENGINEERING GROUP

Atlantic County Utilities Authority

INSTALLATION COST YEARLY SAVINGSECM

LIFETIMEDESCRIPTIONECM NO.

ECM ENERGY AND FINANCIAL COSTS AND SAVINGS SUMMARY

Page 48: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

Appendix B Page 1 of 3

Concord Engineering Group, Inc. 520 BURNT MILL ROAD VOORHEES, NEW JERSEY 08043 PHONE: (856) 427-0200 FAX: (856) 427-6508

SmartStart Building Incentives The NJ SmartStart Buildings Program offers financial incentives on a wide variety of building system equipment. The incentives were developed to help offset the initial cost of energy-efficient equipment. The following tables show the current available incentives as of February, 2010:

Electric Chillers Water-Cooled Chillers $12 - $170 per ton

Air-Cooled Chillers $8 - $52 per ton Energy Efficiency must comply with ASHRAE 90.1-2004

Gas Cooling Gas Absorption Chillers $185 - $400 per ton

Gas Engine-Driven Chillers Calculated through custom measure path)

Desiccant Systems $1.00 per cfm – gas or electric

Electric Unitary HVAC Unitary AC and Split Systems $73 - $93 per ton

Air-to-Air Heat Pumps $73 - $92 per ton Water-Source Heat Pumps $81 per ton

Packaged Terminal AC & HP $65 per ton Central DX AC Systems $40- $72 per ton

Dual Enthalpy Economizer Controls $250 Occupancy Controlled Thermostat

(Hospitality & Institutional Facility) $75 per thermostat

Energy Efficiency must comply with ASHRAE 90.1-2004

Ground Source Heat Pumps

Closed Loop & Open Loop $450 per ton, EER ≥ 16 $600 per ton, EER ≥ 18 $750 per ton, EER ≥ 20

Energy Efficiency must comply with ASHRAE 90.1-2004

Page 49: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

Appendix B Page 2 of 3

Gas Heating Gas Fired Boilers < 300 MBH $300 per unit

Gas Fired Boilers ≥ 300 - 1500 MBH $1.75 per MBH

Gas Fired Boilers ≥1500 - ≤ 4000 MBH $1.00 per MBH

Gas Fired Boilers > 4000 MBH (Calculated through Custom Measure Path)

Gas Furnaces $300 - $400 per unit, AFUE ≥ 92%

Variable Frequency Drives

Variable Air Volume $65 - $155 per hp Chilled-Water Pumps $60 per hp

Compressors $5,250 to $12,500 per drive

Natural Gas Water Heating Gas Water Heaters ≤ 50 gallons $50 per unit

Gas-Fired Water Heaters > 50 gallons $1.00 - $2.00 per MBH Gas-Fired Booster Water Heaters $17 - $35 per MBH Gas Fired Tankless Water Heaters $300 per unit

Prescriptive Lighting Retro fit of T12 to T-5 or T-8 Lamps

w/Electronic Ballast in Existing Facilities

$10 per fixture (1-4 lamps)

Replacement of T12 with new T-5 or T-8 Lamps w/Electronic Ballast in

Existing Facilities

$25 per fixture (1-2 lamps) $30 per fixture (3-4 lamps)

Replacement of incandescent with screw-in PAR 38 or PAR 30 (CFL)

bulb $7 per bulb

T-8 reduced Wattage (28w/25w 4’, 1-4 lamps)

Lamp & ballast replacement $10 per fixture

Hard-Wired Compact Fluorescent $25 - $30 per fixture

Metal Halide w/Pulse Start $25 per fixture LED Exit Signs $10 - $20 per fixture

T-5 and T-8 High Bay Fixtures $16 - $284 per fixture

HID ≥ 100w Retrofit with induction lamp, power coupler and generator

(must be 30% less watts/fixture than HID system)

$50 per fixture

HID ≥ 100w Replacement with new HID ≥ 100w $70 per fixture

LED Refrigerator/Freezer case lighting replacement of fluorescent in medium

and low temperature display case

$42 per 5 foot $65 per 6 foot

Page 50: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

Appendix B Page 3 of 3

Lighting Controls – Occupancy Sensors Wall Mounted $20 per control

Remote Mounted $35 per control Daylight Dimmers $25 per fixture

Occupancy Controlled hi-low Fluorescent Controls $25 per fixture controlled

Lighting Controls – HID or Fluorescent Hi-Bay Controls Occupancy hi-low $75 per fixture controlled Daylight Dimming $75 per fixture controlled

Daylight Dimming - office $50 per fixture controlled

Premium Motors Three-Phase Motors $45 - $700 per motor

Fractional HP Motors Electronic Communicated Motors (replacing shaded pole motors in

refrigerator/freezer cases)

$40 per electronic communicated motor

Other Equipment Incentives

Performance Lighting

$1.00 per watt per SF below program incentive threshold, currently 5% more energy efficient than ASHRAE 90.1-

2004 for New Construction and Complete Renovation

Custom Electric and Gas Equipment Incentives not prescriptive

Custom Measures

$0.16 KWh and $1.60/Therm of 1st year savings, or a buy down to a 1 year

payback on estimated savings. Minimum required savings of 75,000

KWh or 1,500 Therms and a IRR of at least 10%.

Multi Measures Bonus 15%

Page 51: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

OMB No. 2060-0347

STATEMENT OF ENERGY PERFORMANCEBuilding B

Building ID: 2560288 For 12-month Period Ending: December 31, 20101

Date SEP becomes ineligible: N/A Date SEP Generated: January 24, 2011

FacilityBuilding B1801 Absecon Blvd.Atlantic City, NJ 08401

Facility OwnerAtlantic County Utilities Authority1801 Absecon Blvd atlantic city, NJ 08401

Primary Contact for this FacilityRobert Carlson1801 Absecon Blvd atlantic city, NJ 08401

Year Built: 1978Gross Floor Area (ft2): 19,151

Energy Performance Rating2 (1-100) N/A

Site Energy Use Summary3

Electricity - Grid Purchase(kBtu) 4,871,630 Natural Gas - (kBtu)4 0 Total Energy (kBtu) 4,871,630

Energy Intensity5 Site (kBtu/ft2/yr) 254 Source (kBtu/ft2/yr) 850 Emissions (based on site energy use) Greenhouse Gas Emissions (MtCO2e/year) 742 Electric Distribution Utility Pepco - Atlantic City Electric Co National Average Comparison National Average Site EUI 104 National Average Source EUI 213 % Difference from National Average Source EUI 299% Building Type Other

Stamp of Certifying Professional

Based on the conditions observed at thetime of my visit to this building, I certify that

the information contained within thisstatement is accurate.

Meets Industry Standards6 for Indoor EnvironmentalConditions:Ventilation for Acceptable Indoor Air Quality N/A Acceptable Thermal Environmental Conditions N/A Adequate Illumination N/A

Certifying ProfessionalMichael Fischette520 south burnt mill road voorhees, NJ 08043

Notes: 1. Application for the ENERGY STAR must be submitted to EPA within 4 months of the Period Ending date. Award of the ENERGY STAR is not final until approval is received from EPA.2. The EPA Energy Performance Rating is based on total source energy. A rating of 75 is the minimum to be eligible for the ENERGY STAR.3. Values represent energy consumption, annualized to a 12-month period.4. Natural Gas values in units of volume (e.g. cubic feet) are converted to kBtu with adjustments made for elevation based on Facility zip code.5. Values represent energy intensity, annualized to a 12-month period.6. Based on Meeting ASHRAE Standard 62 for ventilation for acceptable indoor air quality, ASHRAE Standard 55 for thermal comfort, and IESNA Lighting Handbook for lighting quality.

The government estimates the average time needed to fill out this form is 6 hours (includes the time for entering energy data, Licensed Professional facility inspection, and notarizing the SEP) andwelcomes suggestions for reducing this level of effort. Send comments (referencing OMB control number) to the Director, Collection Strategies Division, U.S., EPA (2822T), 1200 Pennsylvania Ave.,NW, Washington, D.C. 20460.

EPA Form 5900-16

Appendix CPage 1 of 1

Page 52: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

Appendix DPage 1 of 7

Steam BoilerTag B -1 Steam/HW ConvertorType Shell & TubeLocation Boiler Room Boiler RoomArea Served B BuildingManufacturer Cleaver BrooksQty. 1Model # M4S-4000 Series 100Serial # 4G016886MBH Input 4,000MBH Output 3,200Lbs of Steam/Hr 3,200 940EWT 180°FLWT 200°FGPM 90Estimated Thermal Eff ** 60% **#2 Oil Usage (Full Load) 28.8 GPHApprox. Age 24 24ASHRAE Service Life 30Remaining Life 6

Notes **Boiler usgae is only 7 gal/hr (partial load)

MAJOR EQUIPMENT LISTConcord Engineering Group

ACUA "B" BUILDING/LABS

Model 4 Packaged Boiler

Page 53: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

Appendix DPage 2 of 7

Rooftop UnitsTag RTU - 1 RTU - 2 RTU-3Location Roof Roof RoofArea Served Control Room New Lab VOC RoomManufacturer Trane Trane TraneQty 1 1 1Model # TSC120A4R0A2N TSC120A4R0A2N TSC060A4R0A11FSerial # 926101943L N/A N/ADX Coil Yes Yes Yes

Cooling Capacity 10-Tons 10-Tons 5-Tons

Supply Flow, CFM 3,200 3,200 2,000

Heating Type Cooling Only Cooling Only CInput (MBh) - - -Output (MBh) - - -Heating Eff. (%) - - -

Ecomonizer N/A N/A 0%-100% O/A

Supply Motor HP 3 HP 3 HP 2HP

Supply Motor Efficiency Premium Premium Premium

Unit Eff. 10.4 EER 10.4 EER 11.3 SEERApprox. Age 2 2 2

ASHRAE Service Life 15 15 15

Remaining Life 13 13 13 Notes

Maintains 67°F in VOC Room

MAJOR EQUIPMENT LISTConcord Engineering Group

ACUA "B" BUILDING/LABS

Page 54: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

Appendix DPage 3 of 7

Rooftop UnitsTag RTU - 4 RTU - 5 RTU-6Location Roof Roof Roof

Area Served Part of Lobby/Lockers/Supt Ofice Original Offices Greenhouse Offices

Manufacturer Trane Trane TraneQty 1 1 1Model # THC063A4E0A17 TSC102A4R0A23 TSC102A4R0A23Serial # 832102378L 621102107L N/ADX Coil Heat Pump Yes YesCooling Capacity 5-Ton 8.5 Tons 8.5 TonsSupply Flow, CFM 2,000 3,000 3,000Heating Type Heat Pump Cooling Only Cooling OnlyInput (MBh) - - -Output (MBh) - - -Heating Eff. (%) - - -Ecomonizer N/A N/A N/ASupply Motor HP 1 HP 2 HP 2 HPSupply Motor Efficiency Premium Premium Premium

Unit Eff. 12 SEER 10.3 EER 10.3 EERApprox. Age 2 4 1

ASHRAE Service Life 15 15 15

Remaining Life 13 11 14 Notes

MAJOR EQUIPMENT LISTConcord Engineering Group

ACUA "B" BUILDING/LABS

Page 55: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

Appendix DPage 4 of 7

Rooftop UnitsTag RTU - 7Location RoofArea ServedManufacturer TraneQty 1Model # THC048A4R0A11F0CSerial # N/ADX Coil Heat PumpCooling Capacity 4-TonsSupply Flow, CFM 1,600Heating Type Heat PumpInput (MBh)Output (MBh)Heating Eff. (%)Ecomonizer N/ASupply Motor HP 0.60 HPSupply Motor Efficiency Premium

Unit Eff. SEER=12.0Approx. Age 7

ASHRAE Service Life 15

Remaining Life 8Notes

MAJOR EQUIPMENT LISTConcord Engineering Group

ACUA "B" BUILDING/LABS

Page 56: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

Appendix DPage 5 of 7

Split A/C SystemsAir Handling UnitTag AHU-1Location Data CenterArea Served Data CenterManufacturerQty 1Model #Serial #Cooling Coil DXCooling Capacity 18,000 BTUHSupply Flow, CFMHeating Type Cooling OnlyInput (MBh) N/AEcomonizer N/ASupply Motor HPSupply Motor Efficiency

Approx. Age 2ASHRAE Service Life 15Remaining Life 13 NotesCondensing Units CU-1Qty 1Location RoofManufacturer Trane X13Model # 2TTB3018A1000AASerial # 8323LF23FCooling Capacity, MBH 18,000 BTUHCooling Eff., SEER 13.0Refrigerant

Approx Age 2ASHRAE Service Life 15Remaining Life 13 Comments

MAJOR EQUIPMENT LISTConcord Engineering Group

ACUA "B" BUILDING/LABS

Page 57: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

Appendix DPage 6 of 7

HW PumpsTag Heating HW Pump Heating HW PumpLocation Boiler Room Boiler RoomArea Served B Building/Labs B Building/LabsManufacturer N/A N/AQty. 1 1Model # N/A N/ASerial # N/A N/AHP 1.5 1.5RPM 1,745 1,730GPM 90 90PUMP EFF 55% 55%Ft. Hd 30 TDH 30 TDHMotor Frame Size N/A N/AMotor Efficiency 78.5% 78.5%Volts / PhaseApprox. Age N/A N/AASHRAE Service Life 18 18Remaining LifeNotes

MAJOR EQUIPMENT LISTConcord Engineering Group

ACUA "B" BUILDING/LABS

Page 58: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

Appendix DPage 7 of 7

Domestic Hot WaterTag

Unit Type DHW Heater DHW Heater

Qty 1 1

Location Locker Room Receiving

Area Served Lockers/Restrooms Receiving Rest Room/Sinks

Manufacturer A O Smith A O Smith

Model # PEC 120 914 EES 40 913

Serial # MD93-0067271-914 MG96-0026915-913

Recovery (Gallons/Hour) N/A N/A

Size (Gallons) 120 40

Input Capacity (Watts) (2) elements @ 3,375 Watts (2) elements @ 3,375 Watts

Fuel Electric Electric

Approx Age 9 9

Ashrae Service Life 20 20

Remaining Life 11 11Comments

MAJOR EQUIPMENT LISTConcord Engineering Group

ACUA "B" BUILDING/LABS

Page 59: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

Investment Grade Lighting Audit APPENDIX E1 of 8

CEG Job #: 9C10051

Project: ACUA KWH COST: $0.080

Bldg. Sq. Ft.

ECM #1: Lighting Upgrade - GeneralEXISTING LIGHTING PROPOSED LIGHTING SAVINGS

CEG Fixture Yearly No. No. Fixture Fixt Total kWh/Yr Yearly No. No. Retro-Unit Watts Total kWh/Yr Yearly Unit Cost Total kW kWh/Yr Yearly Yearly SimpleType Location Usage Fixts Lamps Type Watts kW Fixtures $ Cost Fixts Lamps Description Used kW Fixtures $ Cost (INSTALLED) Cost Savings Savings $ Savings Payback

122.21 2600 25 21x4, 2-Lamp, 40w T12, Mag.

Ballast, Recessed Mnt., Prismatic Lens

88 2.20 5,720.0 $457.60 25 22 Lamp, 28w T8, Elect.

Ballast, w/Specular Reflector; retrofit

50 1.25 3250 $260.00 $160.00 $4,000.00 0.95 2470 $197.60 20.24

602 8760 2 2 Incandescent Exit Sign 20 0.04 350.4 $28.03 2 1 LED Exit Sign 2 0.00 35.04 $2.80 $65.00 $130.00 0.04 315.36 $25.23 5.15

122.21 VOC Room 2600 6 21x4, 2-Lamp, 40w T12, Mag.

Ballast, Recessed Mnt., Prismatic Lens

88 0.53 1,372.8 $109.82 6 22 Lamp, 28w T8, Elect.

Ballast, w/Specular Reflector; retrofit

50 0.30 780 $62.40 $160.00 $960.00 0.23 592.8 $47.42 20.24

122.21 AA Room 2600 4 21x4, 2-Lamp, 40w T12, Mag.

Ballast, Recessed Mnt., Prismatic Lens

88 0.35 915.2 $73.22 4 22 Lamp, 28w T8, Elect.

Ballast, w/Specular Reflector; retrofit

50 0.20 520 $41.60 $160.00 $640.00 0.15 395.2 $31.62 20.24

563 Office - Lab Director 2600 6 2 Recessed Down Light, (2)

26w Quad PL Lamp 54 0.32 842.4 $67.39 6 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

122.21 Flume Room #1 2600 2 21x4, 2-Lamp, 40w T12, Mag.

Ballast, Recessed Mnt., Prismatic Lens

88 0.18 457.6 $36.61 2 22 Lamp, 28w T8, Elect.

Ballast, w/Specular Reflector; retrofit

50 0.10 260 $20.80 $160.00 $320.00 0.08 197.6 $15.81 20.24

122.21 Flume Room #2 2600 2 21x4, 2-Lamp, 40w T12, Mag.

Ballast, Recessed Mnt., Prismatic Lens

88 0.18 457.6 $36.61 2 22 Lamp, 28w T8, Elect.

Ballast, w/Specular Reflector; retrofit

50 0.10 260 $20.80 $160.00 $320.00 0.08 197.6 $15.81 20.24

121.34 Electrical/ Storage Room 800 2 2

1x4, 2-Lamp, 34w T12, Mag. Ballast, Pendant Mnt., No

Lens78 0.16 124.8 $9.98 2 2 2 Lamp, 28w T8, Elect.

Ballast; retrofit 50 0.10 80 $6.40 $160.00 $320.00 0.06 44.8 $3.58 89.29

127.21 Analyst Work Room 2600 8 2

2x2, 2 Lamp, 34w T12, Mag. Ballast, Recessed Mnt.,

Prismatic Lens78 0.62 1,622.4 $129.79 8 3 3 Lamp, 17w T8, Elect.

Ballast; retrofit 47 0.38 977.6 $78.21 $160.00 $1,280.00 0.25 644.8 $51.58 24.81

122.21 Sample Room 2600 2 21x4, 2-Lamp, 40w T12, Mag.

Ballast, Recessed Mnt., Prismatic Lens

88 0.18 457.6 $36.61 2 22 Lamp, 28w T8, Elect.

Ballast, w/Specular Reflector; retrofit

50 0.10 260 $20.80 $160.00 $320.00 0.08 197.6 $15.81 20.24

142.21 Women's Locker Room 2600 1 4

2x4, 4 Lamp, 34w T12, Mag. Ballast, Recessed Mnt.,

Prismatic Lens156 0.16 405.6 $32.45 1 3

3 Lamp , 28w T8, Elect. Ballast, Specular Reflector; retrofit

72 0.07 187.2 $14.98 $180.00 $180.00 0.08 218.4 $17.47 10.30

121.41 Women's Restroom 2600 1 2

1x4, 2-Lamp, 34w T12, Mag. Ballast, Wall Mnt., Prismatic

Lens78 0.08 202.8 $16.22 1 2 2 Lamp, 28w T8, Elect.

Ballast; retrofit 50 0.05 130 $10.40 $160.00 $160.00 0.03 72.8 $5.82 27.47

142.21 Men's Locker Room 2600 1 4

2x4, 4 Lamp, 34w T12, Mag. Ballast, Recessed Mnt.,

Prismatic Lens156 0.16 405.6 $32.45 1 3

3 Lamp , 28w T8, Elect. Ballast, Specular Reflector; retrofit

72 0.07 187.2 $14.98 $180.00 $180.00 0.08 218.4 $17.47 10.30

Operations Building and Lab

Lab

Page 60: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

Investment Grade Lighting Audit APPENDIX E2 of 8

121.41 Men's Restroom 2600 1 21x4, 2-Lamp, 34w T12, Mag. Ballast, Wall Mnt., Prismatic

Lens78 0.08 202.8 $16.22 1 2 2 Lamp, 28w T8, Elect.

Ballast; retrofit 50 0.05 130 $10.40 $160.00 $160.00 0.03 72.8 $5.82 27.47

221.42 8760 4 2 1x4, 2 Lamp, 32w T8, Elect. Ballast, Wall Mnt., Prismatic 58 0.23 2,032.3 $162.59 4 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

602 8760 1 2 Incandescent Exit Sign 20 0.02 175.2 $14.02 1 1 LED Exit Sign 2 0.00 17.52 $1.40 $65.00 $65.00 0.02 157.68 $12.61 5.15

651 8760 2 1 Wallpack, (1) 13w PL Quad Lamp 13 0.03 227.8 $18.22 2 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

221.42 8760 2 2 1x4, 2 Lamp, 32w T8, Elect. Ballast, Wall Mnt., Prismatic 58 0.12 1,016.2 $81.29 2 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

651 8760 1 1 Wallpack, (1) 13w PL Quad Lamp 13 0.01 113.9 $9.11 1 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

121.14 Electrical Room 8760 30 21x4, 2-Lamp, 34w T12, Mag.

Ballast, Surface Mnt., No Lens

78 2.34 20,498.4 $1,639.87 30 2 2 Lamp, 28w T8, Elect. Ballast; retrofit 50 1.50 13140 $1,051.20 $160.00 $4,800.00 0.84 7358.4 $588.67 8.15

560 8760 14 1 Recessed Down Light, 38w CFL Lamp 38 0.53 4,660.3 $372.83 14 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

561 8760 12 1 Recessed Eyeball, 18w CFL Lamp 18 0.22 1,892.2 $151.37 12 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

564 8760 11 1 Recessed Down Light, (1) 18w R30 CFL Lamp 18 0.20 1,734.5 $138.76 11 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

660 8760 11 1 Track Head, 18w R30 CFL Lamp 18 0.20 1,734.5 $138.76 11 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

227.22 Office - Shift Supervisor 8760 4 2

2x2, 2 Lamp, 32w T8, Elect. Ballast, Recessed Mnt.,

Parabolic Lens58 0.23 2,032.3 $162.59 4 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

232.22 Offices - "Greenhouse" 2600 30 3

2x4, 3 Lamp, 32w T8, Elect. Ballast, Recessed Mnt.,

Parabolic Lens86 2.58 6,708.0 $536.64 30 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

121.11 Men's Locker Room 8760 12 2

1x4, 2-Lamp, 34w T12, Mag. Ballast, Surface Mnt.,

Prismatic Lens78 0.94 8,199.4 $655.95 12 2 2 Lamp, 28w T8, Elect.

Ballast; retrofit 50 0.60 5256 $420.48 $160.00 $1,920.00 0.34 2943.36 $235.47 8.15

232.21 Lunch Room 8760 6 32x4, 3 Lamp, 32w T8, Elect.

Ballast, Recessed Mnt., Prismatic Lens

86 0.52 4,520.2 $361.61 6 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

232.21 Vending 8760 6 32x4, 3 Lamp, 32w T8, Elect.

Ballast, Recessed Mnt., Prismatic Lens

86 0.52 4,520.2 $361.61 6 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

121.11 8760 3 21x4, 2-Lamp, 34w T12, Mag.

Ballast, Surface Mnt., Prismatic Lens

78 0.23 2,049.8 $163.99 3 2 2 Lamp, 28w T8, Elect. Ballast; retrofit 50 0.15 1314 $105.12 $160.00 $480.00 0.08 735.84 $58.87 8.15

Walkway

Atrium

Control Room

Lobby

Men's Restroom

Page 61: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

Investment Grade Lighting Audit APPENDIX E3 of 8

121.41 8760 2 21x4, 2-Lamp, 34w T12, Mag. Ballast, Wall Mnt., Prismatic

Lens78 0.16 1,366.6 $109.32 2 2 2 Lamp, 28w T8, Elect.

Ballast; retrofit 50 0.10 876 $70.08 $160.00 $320.00 0.06 490.56 $39.24 8.15

121.14 8760 86 21x4, 2-Lamp, 34w T12, Mag.

Ballast, Surface Mnt., No Lens

78 6.71 58,762.1 $4,700.97 86 2 2 Lamp, 28w T8, Elect. Ballast; retrofit 50 4.30 37668 $3,013.44 $160.00 $13,760.00 2.41 21094.08 $1,687.53 8.15

128.14 8760 6 28' Channel, 2 Lamp, 75w

T12, Mag. Ballast, Surface Mnt., No Lens

142 0.85 7,463.5 $597.08 6 4(2) 8' Lamps to (4) 4'

Lamps - 28w T8, Elect Ballast; retrofit

98 0.59 5150.88 $412.07 $180.00 $1,080.00 0.26 2312.64 $185.01 5.84

128.14 2600 8 28' Channel, 2 Lamp, 75w

T12, Mag. Ballast, Surface Mnt., No Lens

142 1.14 2,953.6 $236.29 8 4(2) 8' Lamps to (4) 4'

Lamps - 28w T8, Elect Ballast; retrofit

98 0.78 2038.4 $163.07 $180.00 $1,440.00 0.35 915.2 $73.22 19.67

121.14 2600 5 21x4, 2-Lamp, 34w T12, Mag.

Ballast, Surface Mnt., No Lens

78 0.39 1,014.0 $81.12 5 2 2 Lamp, 28w T8, Elect. Ballast; retrofit 50 0.25 650 $52.00 $160.00 $800.00 0.14 364 $29.12 27.47

221.14 Mezzanine Storage 2600 16 2

1x4, 2 Lamp, 32w T8, Elect. Ballast, Surface Mnt., No

Lens58 0.93 2,412.8 $193.02 16 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

738 Garage Bay 8760 3 1 175w MH Low Bay 210 0.63 5,518.8 $441.50 3 3 1x4, 3 Lamp, 54w T5HO Fixture 177 0.53 4651.56 $372.12 $200.00 $600.00 0.10 867.24 $69.38 8.65

242.22 CEMS Room 2600 4 42x4, 4 Lamp, 32w T8, Elect.

Ballast, Recessed Mnt., Parabolic Lens

104 0.42 1,081.6 $86.53 4 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

565 Hall 8760 3 1 1x1 Recessed, Glass Lens, (1) 13w CFL Lamp 13 0.04 341.6 $27.33 3 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

625 Basement 8760 56 1 Pendant Mnt., Prismatic Globe, 200w A Lamp 200 11.20 98,112.0 $7,848.96 56 2

1x4, 2 lamp, 28w T8 Vapor Tight Fixture,

Prismatic Lens50 2.80 24528 $1,962.24 $180.00 $10,080.00 8.40 73584 $5,886.72 1.71

242.22 Map Room 2600 2 42x4, 4 Lamp, 32w T8, Elect.

Ballast, Recessed Mnt., Parabolic Lens

104 0.21 540.8 $43.26 2 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

242.22 IT Room 2600 2 42x4, 4 Lamp, 32w T8, Elect.

Ballast, Recessed Mnt., Parabolic Lens

104 0.21 540.8 $43.26 2 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

232.22 Conference Room 2600 6 3

2x4, 3 Lamp, 32w T8, Elect. Ballast, Recessed Mnt.,

Parabolic Lens86 0.52 1,341.6 $107.33 6 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

242.22 Glass Room 2600 2 42x4, 4 Lamp, 32w T8, Elect.

Ballast, Recessed Mnt., Parabolic Lens

104 0.21 540.8 $43.26 2 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

222.22 2600 8 22x4, 2 Lamp, 32w T8, Elect.

Ballast, Recessed Mnt., Parabolic Lens

58 0.46 1,206.4 $96.51 8 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

601 8760 2 2 (2) 7w CFL Exit Sign 16 0.03 280.3 $22.43 2 1 LED Exit Sign 2 0.00 35.04 $2.80 $65.00 $130.00 0.03 245.28 $19.62 6.63

242.22 Insturmentation Room 2600 7 4

2x4, 4 Lamp, 32w T8, Elect. Ballast, Recessed Mnt.,

Parabolic Lens104 0.73 1,892.8 $151.42 7 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

Men s Restroom

Machine Shop

Parts Storage

Hall

Page 62: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

Investment Grade Lighting Audit APPENDIX E4 of 8

Totals 430 103 38.94 261,023 $20,882 430 55 14.4 102,382 $8,191 $44,445 15.1 116,706 $9,337 4.76

Page 63: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

Investment Grade Lighting Audit APPENDIX E5 of 8

CEG Job #: 9C10051

Project: ACUA 0.08 $0.080

ECM #2: Lighting Controls

EXISTING LIGHTING PROPOSED LIGHTING CONTROLS SAVINGSCEG Fixture Yearly No. No. Fixture Fixt Total kWh/Yr Yearly No. No. Controls Watts Total Reduction kWh/Yr Yearly Unit Cost Total kW kWh/Yr Yearly Yearly SimpleType Location Usage Fixts Lamps Type Watts kW Fixtures $ Cost Fixts Cont. Description Used kW (%) Fixtures $ Cost (INSTALLED) Cost Savings Savings $ Savings Payback

122.21 2600 25 21x4, 2-Lamp, 40w T12, Mag. Ballast, Recessed Mnt., Prismatic Lens

88 2.2 5720 $457.60 25 2Dual Technology

Occupancy Sensor - Remote Mnt.

88 1.98 10% 5148 $411.84 $300.00 $600.00 0.22 572 $45.76 13.11

602 8760 2 2 Incandescent Exit Sign 20 0.04 350.4 $28.03 2 0 No Change 20 0.04 0% 350.4 $28.03 $0.00 $0.00 0.00 0 $0.00 0.00

122.21 VOC Room 2600 6 21x4, 2-Lamp, 40w T12, Mag. Ballast, Recessed Mnt., Prismatic Lens

88 0.528 1372.8 $109.82 6 1Dual Technology

Occupancy Sensor - Switch Mnt.

88 0.48 10% 1235.52 $98.84 $150.00 $150.00 0.05 137.28 $10.98 13.66

122.21 AA Room 2600 4 21x4, 2-Lamp, 40w T12, Mag. Ballast, Recessed Mnt., Prismatic Lens

88 0.352 915.2 $73.22 4 1Dual Technology

Occupancy Sensor - Switch Mnt.

88 0.32 10% 823.68 $65.89 $150.00 $150.00 0.04 91.52 $7.32 20.49

563 Office - Lab Director 2600 6 2 Recessed Down Light, (2)

26w Quad PL Lamp 54 0.324 842.4 $67.39 6 1Dual Technology

Occupancy Sensor - Switch Mnt.

54 0.29 10% 758.16 $60.65 $150.00 $150.00 0.03 84.24 $6.74 22.26

122.21 Flume Room #1 2600 2 21x4, 2-Lamp, 40w T12, Mag. Ballast, Recessed Mnt., Prismatic Lens

88 0.176 457.6 $36.61 2 1Dual Technology

Occupancy Sensor - Switch Mnt.

88 0.16 10% 411.84 $32.95 $150.00 $150.00 0.02 45.76 $3.66 40.97

122.21 Flume Room #2 2600 2 21x4, 2-Lamp, 40w T12, Mag. Ballast, Recessed Mnt., Prismatic Lens

88 0.176 457.6 $36.61 2 1Dual Technology

Occupancy Sensor - Switch Mnt.

88 0.16 10% 411.84 $32.95 $150.00 $150.00 0.02 45.76 $3.66 40.97

121.34 Electrical/ Storage Room 800 2 2

1x4, 2-Lamp, 34w T12, Mag. Ballast, Pendant

Mnt., No Lens78 0.156 124.8 $9.98 2 0 No Change 78 0.16 0% 124.8 $9.98 $0.00 $0.00 0.00 0 $0.00 0.00

127.21 Analyst Work Room 2600 8 2

2x2, 2 Lamp, 34w T12, Mag. Ballast, Recessed Mnt., Prismatic Lens

78 0.624 1622.4 $129.79 8 1Dual Technology

Occupancy Sensor - Switch Mnt.

78 0.56 10% 1460.16 $116.81 $150.00 $150.00 0.06 162.24 $12.98 11.56

122.21 Sample Room 2600 2 21x4, 2-Lamp, 40w T12, Mag. Ballast, Recessed Mnt., Prismatic Lens

88 0.176 457.6 $36.61 2 1Dual Technology

Occupancy Sensor - Switch Mnt.

88 0.16 10% 411.84 $32.95 $150.00 $150.00 0.02 45.76 $3.66 40.97

142.21 Women's Locker Room 2600 1 4

2x4, 4 Lamp, 34w T12, Mag. Ballast, Recessed Mnt., Prismatic Lens

156 0.156 405.6 $32.45 1 1Dual Technology

Occupancy Sensor - Switch Mnt.

156 0.14 10% 365.04 $29.20 $150.00 $150.00 0.02 40.56 $3.24 46.23

121.41 Women's Restroom 2600 1 2

1x4, 2-Lamp, 34w T12, Mag. Ballast, Wall Mnt.,

Prismatic Lens78 0.078 202.8 $16.22 1 0 No Change 78 0.08 0% 202.8 $16.22 $0.00 $0.00 0.00 0 $0.00 0.00

142.21 Men's Locker Room 2600 1 4

2x4, 4 Lamp, 34w T12, Mag. Ballast, Recessed Mnt., Prismatic Lens

156 0.156 405.6 $32.45 1 1Dual Technology

Occupancy Sensor - Switch Mnt.

156 0.14 10% 365.04 $29.20 $150.00 $150.00 0.02 40.56 $3.24 46.23

Operations Building and Lab

Lab

Page 64: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

Investment Grade Lighting Audit APPENDIX E6 of 8

121.41 Men's Restroom 2600 1 21x4, 2-Lamp, 34w T12, Mag. Ballast, Wall Mnt.,

Prismatic Lens78 0.078 202.8 $16.22 1 0 No Change 78 0.08 0% 202.8 $16.22 $0.00 $0.00 0.00 0 $0.00 0.00

221.42 8760 4 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Wall Mnt., Prismatic

58 0.232 2032.32 $162.59 4 1Daylight Sensor

(Sensorswitch PP-20 & CM-PC or equal)

58 0.17 25% 1524.24 $121.94 $300.00 $300.00 0.06 508.08 $40.65 7.38

602 8760 1 2 Incandescent Exit Sign 20 0.02 175.2 $14.02 1 0 No Change 20 0.02 0% 175.2 $14.02 $0.00 $0.00 0.00 0 $0.00 0.00

651 8760 2 1 Wallpack, (1) 13w PL Quad Lamp 13 0.026 227.76 $18.22 2 0 No Change 13 0.03 0% 227.76 $18.22 $0.00 $0.00 0.00 0 $0.00 0.00

221.42 8760 2 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Wall Mnt., Prismatic

58 0.116 1016.16 $81.29 2 1Daylight Sensor

(Sensorswitch PP-20 & CM-PC or equal)

58 0.09 25% 762.12 $60.97 $300.00 $300.00 0.03 254.04 $20.32 14.76

651 8760 1 1 Wallpack, (1) 13w PL Quad Lamp 13 0.013 113.88 $9.11 1 0 No Change 13 0.01 0% 113.88 $9.11 $0.00 $0.00 0.00 0 $0.00 0.00

121.14 Electrical Room 8760 30 21x4, 2-Lamp, 34w T12,

Mag. Ballast, Surface Mnt., No Lens

78 2.34 20498.4 $1,639.87 30 2Dual Technology

Occupancy Sensor - Remote Mnt.

78 2.11 10% 18448.56 $1,475.88 $300.00 $600.00 0.23 2049.84 $163.99 3.66

560 8760 14 1 Recessed Down Light, 38w CFL Lamp 38 0.532 4660.32 $372.83 14 0 No Change 38 0.53 0% 4660.32 $372.83 $0.00 $0.00 0.00 0 $0.00 0.00

561 8760 12 1 Recessed Eyeball, 18w CFL Lamp 18 0.216 1892.16 $151.37 12 0 No Change 18 0.22 0% 1892.16 $151.37 $0.00 $0.00 0.00 0 $0.00 0.00

564 8760 11 1 Recessed Down Light, (1) 18w R30 CFL Lamp 18 0.198 1734.48 $138.76 11 0 No Change 18 0.20 0% 1734.48 $138.76 $0.00 $0.00 0.00 0 $0.00 0.00

660 8760 11 1 Track Head, 18w R30 CFL Lamp 18 0.198 1734.48 $138.76 11 0 No Change 18 0.20 0% 1734.48 $138.76 $0.00 $0.00 0.00 0 $0.00 0.00

227.22 Office - Shift Supervisor 8760 4 2

2x2, 2 Lamp, 32w T8, Elect. Ballast, Recessed

Mnt., Parabolic Lens58 0.232 2032.32 $162.59 4 1

Dual Technology Occupancy Sensor -

Switch Mnt.58 0.21 10% 1829.088 $146.33 $150.00 $150.00 0.02 203.232 $16.26 9.23

232.22 Offices - "Greenhouse" 2600 30 3

2x4, 3 Lamp, 32w T8, Elect. Ballast, Recessed

Mnt., Parabolic Lens86 2.58 6708 $536.64 30 1

Dual Technology Occupancy Sensor -

Switch Mnt.86 2.32 10% 6037.2 $482.98 $150.00 $150.00 0.26 670.8 $53.66 2.80

121.11 Men's Locker Room 8760 12 2

1x4, 2-Lamp, 34w T12, Mag. Ballast, Surface Mnt., Prismatic Lens

78 0.936 8199.36 $655.95 12 1Dual Technology

Occupancy Sensor - Switch Mnt.

78 0.84 10% 7379.424 $590.35 $150.00 $150.00 0.09 819.936 $65.59 2.29

232.21 Lunch Room 8760 6 32x4, 3 Lamp, 32w T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens86 0.516 4520.16 $361.61 6 1

Dual Technology Occupancy Sensor & Day

Light Sensor - (Sensor Switch CM-PC, PP-20,

CM-PDT)

86 0.39 25% 3390.12 $271.21 $520.00 $520.00 0.13 1130.04 $90.40 5.75

232.21 Vending 8760 6 32x4, 3 Lamp, 32w T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens86 0.516 4520.16 $361.61 6 1

Dual Technology Occupancy Sensor -

Remote Mnt.86 0.46 10% 4068.144 $325.45 $300.00 $300.00 0.05 452.016 $36.16 8.30

121.11 8760 3 21x4, 2-Lamp, 34w T12,

Mag. Ballast, Surface Mnt., Prismatic Lens

78 0.234 2049.84 $163.99 3 1Dual Technology

Occupancy Sensor - Switch Mnt.

78 0.21 10% 1844.856 $147.59 $150.00 $150.00 0.02 204.984 $16.40 9.15

121.41 8760 2 21x4, 2-Lamp, 34w T12, Mag. Ballast, Wall Mnt.,

Prismatic Lens78 0.156 1366.56 $109.32 2 1

Dual Technology Occupancy Sensor -

Switch Mnt.78 0.14 10% 1229.904 $98.39 $150.00 $150.00 0.02 136.656 $10.93 13.72

Walkway

Atrium

Control Room

Lobby

Men's Restroom

Page 65: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

Investment Grade Lighting Audit APPENDIX E7 of 8

121.14 8760 86 21x4, 2-Lamp, 34w T12,

Mag. Ballast, Surface Mnt., No Lens

78 6.708 58762.08 $4,700.97 86 3

Dual Tech. Occupancy Sensor w/2 Pole Power Pack(Sensorswitch or

equal)78 6.04 10% 52885.872 $4,230.87 $300.00 $900.00 0.67 5876.208 $470.10 1.91

128.14 8760 6 28' Channel, 2 Lamp, 75w

T12, Mag. Ballast, Surface Mnt., No Lens

142 0.852 7463.52 $597.08 6 1Dual Technology

Occupancy Sensor - Remote Mnt.

142 0.77 10% 6717.168 $537.37 $300.00 $300.00 0.09 746.352 $59.71 5.02

128.14 2600 8 28' Channel, 2 Lamp, 75w

T12, Mag. Ballast, Surface Mnt., No Lens

142 1.136 2953.6 $236.29 8 1Dual Technology

Occupancy Sensor - Remote Mnt.

142 1.02 10% 2658.24 $212.66 $300.00 $300.00 0.11 295.36 $23.63 12.70

121.14 2600 5 21x4, 2-Lamp, 34w T12,

Mag. Ballast, Surface Mnt., No Lens

78 0.39 1014 $81.12 5 1Dual Technology

Occupancy Sensor - Switch Mnt.

78 0.35 10% 912.6 $73.01 $150.00 $150.00 0.04 101.4 $8.11 18.49

221.14 Mezzanine Storage 2600 16 2

1x4, 2 Lamp, 32w T8, Elect. Ballast, Surface

Mnt., No Lens58 0.928 2412.8 $193.02 16 1 Spring Wound Timer

Switch 58 0.46 50% 1206.4 $96.51 $150.00 $150.00 0.46 1206.4 $96.51 1.55

738 Garage Bay 8760 3 1 175w MH Low Bay 210 0.63 5518.8 $441.50 3 1

Dual Technology Occupancy Sensor & Day

Light Sensor - (Sensor Switch CM-PC, PP-20,

CM-PDT)

210 0.47 25% 4139.1 $331.13 $520.00 $520.00 0.16 1379.7 $110.38 4.71

242.22 CEMS Room 2600 4 42x4, 4 Lamp, 32w T8, Elect. Ballast, Recessed

Mnt., Parabolic Lens104 0.416 1081.6 $86.53 4 1

Dual Technology Occupancy Sensor -

Switch Mnt.104 0.37 10% 973.44 $77.88 $150.00 $150.00 0.04 108.16 $8.65 17.34

565 Hall 8760 3 1 1x1 Recessed, Glass Lens, (1) 13w CFL Lamp 13 0.039 341.64 $27.33 3 0 No Change 13 0.04 0% 341.64 $27.33 $0.00 $0.00 0.00 0 $0.00 0.00

625 Basement 8760 56 1 Pendant Mnt., Prismatic Globe, 200w A Lamp 200 11.2 98112 $7,848.96 56 6

Dual Technology Occupancy Sensor -

Remote Mnt.200 10.08 10% 88300.8 $7,064.06 $300.00 $1,800.00 1.12 9811.2 $784.90 2.29

242.22 Map Room 2600 2 42x4, 4 Lamp, 32w T8, Elect. Ballast, Recessed

Mnt., Parabolic Lens104 0.208 540.8 $43.26 2 1

Dual Technology Occupancy Sensor -

Switch Mnt.104 0.19 10% 486.72 $38.94 $150.00 $150.00 0.02 54.08 $4.33 34.67

242.22 IT Room 2600 2 42x4, 4 Lamp, 32w T8, Elect. Ballast, Recessed

Mnt., Parabolic Lens104 0.208 540.8 $43.26 2 1

Dual Technology Occupancy Sensor -

Switch Mnt.104 0.19 10% 486.72 $38.94 $150.00 $150.00 0.02 54.08 $4.33 34.67

232.22 Conference Room 2600 6 3

2x4, 3 Lamp, 32w T8, Elect. Ballast, Recessed

Mnt., Parabolic Lens86 0.516 1341.6 $107.33 6 1

Dual Technology Occupancy Sensor -

Switch Mnt.86 0.46 10% 1207.44 $96.60 $150.00 $150.00 0.05 134.16 $10.73 13.98

242.22 Glass Room 2600 2 42x4, 4 Lamp, 32w T8, Elect. Ballast, Recessed

Mnt., Parabolic Lens104 0.208 540.8 $43.26 2 1

Dual Technology Occupancy Sensor -

Switch Mnt.104 0.19 10% 486.72 $38.94 $150.00 $150.00 0.02 54.08 $4.33 34.67

222.22 2600 8 22x4, 2 Lamp, 32w T8, Elect. Ballast, Recessed

Mnt., Parabolic Lens58 0.464 1206.4 $96.51 8 0 No Change 58 0.46 0% 1206.4 $96.51 $0.00 $0.00 0.00 0 $0.00 0.00

601 8760 2 2 (2) 7w CFL Exit Sign 16 0.032 280.32 $22.43 2 0 No Change 16 0.03 0% 280.32 $22.43 $0.00 $0.00 0.00 0 $0.00 0.00

242.22 Insturmentation Room 2600 7 4

2x4, 4 Lamp, 32w T8, Elect. Ballast, Recessed

Mnt., Parabolic Lens104 0.728 1892.8 $151.42 7 1

Dual Technology Occupancy Sensor -

Switch Mnt.104 0.66 10% 1703.52 $136.28 $150.00 $150.00 0.07 189.28 $15.14 9.91

Machine Shop

Parts Storage

Hall

Page 66: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

Investment Grade Lighting Audit APPENDIX E8 of 8

Totals 430 103 38.9 261,022.7 $20,882 430 42 34.7 233,317.0 $18,665.36 $9,740 4.28 27,706 $2,216 4.39

Page 67: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

 

2 Penn Center, Suite 200  1  phone: (215) 854‐6418 1500 JFK Boulevard     [email protected] Philadelphia, PA 19102      

HVAC Retrofit Project for ACUA Building B Basic Information Conditioned Area:  19,150 Sq ft Current Heating and Cooling:   Heating: Gas and Oil; heating load is approximately 2,000 MBH steam boiler is oversized (4,000 MBH)    Cooling: Air Source Heat Pump (Roof Unit); cooling load is approximately 45 Tons; 51 Tons installed   

                                  Steam Boiler 

Tag  B ‐1      Steam/HW Convertor 

Type  Model 4 Packaged Boiler  Shell & Tube 

Location  Boiler Room    Boiler Room 

Area Served  B Building      

Manufacturer  Cleaver  Brooks      

Qty.  1      

Model #  M4S‐4000  Series 100      

Serial #  4G016886      

MBH Input  4,000  (4000 KBTU/Hr )      

MBH Output  3,200  (3200 KBTU/Hr )      

Lbs of Steam/Hr  3,200  (3200 KBTU/Hr )    940  (1Lb = 1079 BTU/Hr) 

EWT       180°F 

LWT       200°F 

GPM       90 

Estimated Thermal Eff **  60% **      

#2 Oil Usage (Full Load)  28.8 GPH (1 Gal =140KBTU)      

Approx. Age  24    24 

ASHRAE Service Life  25      

Remaining Life  1      

          

Notes **Boiler usgae is only 7 gal/hr 

(partial load)     

           Total  Heat    3200  KBTU/Hr     1014 KBTU/Hr 

 Current Heating load:     3200 *0.6 + 1014 = 2934 KBTU/Hr = 2934 MBH         3200 x 0.6 = 1920KBTU/Hr    Heating and Cooling Delivery:    AHUs, heaters Current Heating Cost:    $24,622 /year   Current Heating Cost:    $12,946 /year   (No bill information) 

Estimation based on 51ton, 32btu/sq ft, COP=3.5,  Total Current HVAC Cost:  $37,568 /Year 

Appendix FPage 1 of 3

Page 68: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

 

2 Penn Center, Suite 200  2  phone: (215) 854‐6418 1500 JFK Boulevard     [email protected] Philadelphia, PA 19102      

NovaThermal Retrofit Main Equipment:   Sewage Anti‐Block Filtration Device   Sewage Source Heat Pump     Estimation:   COPheat :    3.96   COPcool:     5.35   Operation Parameter:   0.68   Electricity Price:    $0.08/KWH    Main Heating and Cooling Equipment Operation Schedule  

   Days  31  29  31  30  31  30  31  31  30  31  30  31 Item  Month  Jan  Feb  Mar Apr May Jun Jul  Aug Sep Oct  Nov  Dec

Cooling   Hours  0  0  0  0  16  20  24  20  16  8  0  0 Heating  Hours  24  20  16  8  0  0  0  0  0  0  16  20 

   Load     Heating Load:    546,683 BTU/Hr 

Cooling load:    51 ton      (45ton)   D. Hot Water:    2 ton/day 

   Consumption 

Heating Consumption:   85816 KWH Cooling Consumption:  70577 KWH    (63520KWH) 

    Other Consumption:  31279 KWH    (35102KWH) D.Hot Water Cnsption:   9901 KWH    (not included) Total Consumption:  187672KWH 

Cost Heating Cost:     $6,865       ($6,235) 

    Cooling Cost:    $5,646      ($5,082)     Other Cost:    $2,502      ($2,808)     D.Hot Water Cost:  $792 (no include in)     Total cost:    $15,805    ($14,125)   Saving     Current Cost:    $37,568 /Year    ($37,568 /Year)     NovaThermal:      $15,805    ($14,125)     Saving:      $10,031    ($10,709)     Saving Rate:    42 %      (37.6%)    

Equipment (without redundant)      Cost:      $121000    ($121,000)    

Payback      12 years    (11.3 years)    

Appendix FPage 2 of 3

Page 69: LOCAL GOVERNMENT ENERGY AUDIT PROGRAM ENERGY … · 28/01/2011  · This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program

 

2 Penn Center, Suite 200  3  phone: (215) 854‐6418 1500 JFK Boulevard     [email protected] Philadelphia, PA 19102      

Discussion • Total current heating load is 2934 KBTU/Hr (153BTU/Sq ft/Hr) 

 • NovaThermal heating load is 546.7 KBTU/Hr (29BTU/Sq ft/Hr), which is 20% of the heat that the current 

system is delivering to the building.  

• The current hot water for heating is approximately 180F.  We could provide hot water at a maximum temperature of 160F.  If the delivery device has enough heating capacity, this temperature will be sufficient.   We assume the delivery system will meet the NovaThermal requirements.    

• The cooling calculation utilizes two options:  51 tons and 45 tons.   The 45 ton cooling capacity should be sufficient.  

• Cooling uses a roof unit through refrigerant coil and AHU.  The building requires a new AHU system with a water coil so that hot water and chilled water can be circulated.   AHU will have extra cost.  

• With redundant settings, the project cost will be increased.      

Appendix FPage 3 of 3