local level participatory planning, an approach towards

28
Local Level Participatory Planning, an approach towards tenure security and development planning. Marcel Meijs, Claus-Peter Hager, Jericho Mulofwa Ministry of Lands and Resettlement, Namibia [email protected] Paper prepared for presentation at the “2014 WORLD BANK CONFERENCE ON LAND AND POVERTYThe World Bank - Washington DC, March 24-27, 2014 Copyright 2014 by author(s). All rights reserved. Readers may make verbatim copies of this document for non-commercial purposes by any means, provided that this copyright notice appears on all such copies.

Upload: others

Post on 08-Dec-2021

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Local Level Participatory Planning, an approach towards

Local Level Participatory Planning, an approach towards tenure security and development

planning.

Marcel Meijs, Claus-Peter Hager, Jericho Mulofwa

Ministry of Lands and Resettlement, Namibia

[email protected]

Paper prepared for presentation at the

“2014 WORLD BANK CONFERENCE ON LAND AND POVERTY”

The World Bank - Washington DC, March 24-27, 2014

Copyright 2014 by author(s). All rights reserved. Readers may make verbatim copies of this

document for non-commercial purposes by any means, provided that this copyright notice

appears on all such copies.

Page 2: Local Level Participatory Planning, an approach towards

Abstract

In Namibia access to grazing forms an essential source of livelihoods for the poor. Namibia is witnessing

an exacerbation of the proverbial ‘tragedy of the commons’ caused by ‘defensive’ fencing of communal

areas, predominantly by the well-connected and the rich.

Since 2006 the Ministry of Lands and Resettlement (MLR) is implementing a land reform program to

ensure that land rights are secured, Land Use Plans are established and that development of underutilized

land is supported by providing key infrastructure. As part of the implementation, the local level

participatory planning (LLPP) process was developed, tested and implemented in three underutilized

areas.

Through LLPP the MLR has effectively dealt with a host of challenges, including, a lack of congruence

between Traditional Authorities and the recently instituted Communal Land Boards as regards the

legitimacy of land rights; attempts of marginalisation of certain groups in programme areas; allaying

boundary disputes between Traditional Authorities, and the need to create mechanisms to negotiate and

secure land rights for groups of local residents.

The paper explores design features, institutional overviews, challenges encountered, emerging success

stories and possible lessons from a process-based land governance intervention aimed at informed and

secured land based investments in a prevailing climate of uncertainty and transition.

Key Words: Development, Investment, Local level, Namibia, Planning,

Page 3: Local Level Participatory Planning, an approach towards

1 Introduction

1.1 Namibia

The Republic of Namibia gained independence from South Africa on 21 March 1990. It is situated in

Southern Africa and is fully covered by desert, semi desert and savanna. It has a population of 2.1 million

on a total surface of 825,418 km2. General population density is low (second lowest in the world), with a

countrywide population density of 2.6 persons per km2. The density of the rural population is highest in

the north due to a more favourable agricultural climate and to past colonial and apartheid interference.

In Namibia, land is classified for administrative purposes as state land, commercial (freehold) land, or

communal land (Guide to the Communal Land Reform Act, Legal Assistance Centre, NNFU (2003)).

This paper focuses on experiences gained in designated areas within the communal lands which represent

around 40% of the country’s total surface area. The communal lands are the safety net for a large part of

the population. It is estimated that 50% of Namibia’s population lives in the rural parts of the communal

lands and at least 70% derives a significant part of their livelihood from them.

The climate in the northern regions, where most of the communal lands are situated, allows for the

cultivation of crops as millet, sorghum and maize. Most of the country is used for cattle, small livestock

or game farming or is unsuitable for any agricultural activities. About half of the population depends on

agriculture (largely subsistence agriculture) for its livelihood. Rainfall in the whole country is erratic and

droughts are occurring frequently.

Namibia’s economy consists primarily of mining (diamond and uranium), agriculture, and Tourism. In

terms of revenue, mining is the biggest contributor to Namibia's economy, accounting for 25% of the

country's income. Namibia’s economy is tied closely to South Africa which is the source of four-fifths of

Namibia’s imports.

1.2 Land Reform in Namibia

At Independence, the Namibian government inherited an asymmetrical system of land distribution along

racial lines. Land and land reform are a highly prominent political and social topic in Namibia, and are

considered decisive for the socio-economic development and social peace of Namibia. The Namibian

Government has therefore been implementing an ambitious land reform programme addressing the

skewed ownership of commercial (freehold) land primarily held by previously advantaged farmers, as

Page 4: Local Level Participatory Planning, an approach towards

well as reforming tenure rights and improving farming systems in the communal areas of Namibia. The

main aim of the land reform programme is to bring about more equitable land distribution and access to

land, to promote sustainable economic growth, to lower income inequalities and to reduce rural poverty.

Great emphasis is continuously placed on carrying out land reform within the rule of law.

To target both the commercial and communal areas, the government is implementing two land reform

programs each through its own act of parliament and regulations. In the commercial (freehold) areas the

skewness of land ownership is being addressed by acquiring and redistribution of land through a willing

buyer – willing seller program, in accordance to the commercial land reform act of 1995. In communal

areas land reform is guided by the Communal Land Reform Act No 5 of 2002 (CLRA) which is aiming at

securing land tenure, ensuring equitable access to commonages and prevention of land grabbing by the

regulation of fencing. In addition, the MLR is implementing the Programme for Communal Lands

Development which supports the objectives of the land reform action plan and also comprises support to

economic development by assisting the beneficiaries of the land reform programs with infrastructure and

post settlement support.

1.2.1 Communal Land Reform

Legal instruments and policies such as the CLRA, the Traditional Authority Act and the National Land

Policy empower statutory bodies to administer and allocate land rights on communal land. The State

assists in the process by putting systems in place to ensure that communal land is correctly administered

and managed. The CLRA legislates for this by incorporating the Traditional Authorities in the

administrative structure, and by creating CLBs.

The CLRA was passed with the aim of facilitating a proper and uniform land administration and

management, with secure land tenure for all, which will result in the minimization of land disputes on

communal land (Communal Land Reform Act, No 5 of 2002). This is the key reason why communal land

registration is being carried out in Namibia. Moreover, by having all land rights registered and surveyed,

the Ministry of Lands and Resettlement as well as the Traditional Authorities will be able to improve their

means of land administration and ensure that all people have equal access to land.

Before the enactment of the CLRA, Traditional Authorities used to allocate land rights in accordance with

their customary tenure systems (National Land Policy, 1998). These allocations were not documented

and were considered biased by some residents of communal land. Results included that some people

were allocated large land parcels whereas other received less; some people were allowed to fence around

their land parcels, whereas others were not; and there were cases of double allocation of land rights. This

biased land tenure system was characterized by many land related disputes, including boundary disputes,

Page 5: Local Level Participatory Planning, an approach towards

self-extensions and illegal fencing, and was operated in the absence of regulatory legislation. In these

tenure settings, widows and orphans in particular were often deprived of the rights to land.

Tenure insecurity and a period of transition between customary and modern land administration has led to

‘defensive’ fencing by some relatively well-off citizens, escalating after Independence. These fences

reduce the commonage in spite of growing population pressure and increasing livestock numbers, and

have led to a proliferation of land disputes.

Over the last decades, the country is witnessing the rapid erosion of the communal grazing areas due to a

multitude of factors. These factors include the overall lack of spatial planning, the expansion of villages

due to population growth, and the fencing in of large tracks of commonage by individuals. Besides the

reduction in grazing area, the remaining area is being overgrazed due to the increased number of

livestock, water that has become permanently available by drilling boreholes and the unrestricted access

to the commonage.

A lack of organized and well documented tenure security further manifests in limited private investment

in the land, a lag in the modernization of farming systems, and a quasi-absence of private sector provision

of inputs and services.

1.2.2 Stakeholders of Communal Land Reform

Communal Land Boards

The Communal Land Boards are established by the Minister of Lands and Resettlement in terms of the

Communal Land Reform Act (Act No.5 of 2002). The communal land boards consist of representatives of

relevant line Ministries, Traditional Authorities, as well as representations from the farmer communities

and four women with expertise relevant to the functions of the board.

The Act sets out the functions of Communal Land Boards as follows:

• Controlling the allocation and cancellation of customary land rights by Chiefs or Traditional

Authorities.

• Deciding on applications for rights of leasehold.

• Creating and maintaining registers for the allocation, transfer and cancellation of customary land

rights and rights of leasehold.

• Advising the Minister on regulations to be made to meet the objectives of the Act.

• Giving effect to the provision of this Act.

Page 6: Local Level Participatory Planning, an approach towards

The administrative tasks of the board are performed by the MLR through an appointed secretary to the

board. The CLBs perform their functions in monthly meetings as well as through appointed committees.

While the CLBs in general take their work very serious, they are often under capacitated to perform the

duties assigned to them by the act.

The Ministry supports the CLBs in the administration of their functions. In reality this means that most of

the vital tasks, such as the verification of land rights are actually done by MLR staff. Therefore, whatever

the CLBs decide depends on the performance of the MLR. The work of the MLR is guided by its

planning cycles, and its own management structure. Therefore, with the limited capacity of the CLBs,

Land Reform is factually implemented by the MLR.

For leaseholds above 50ha and for longer than 10 years, as well as for customary land rights above 20

hectares, the Ministry will have to give it prior approval before the CLBs can allocate such a land right.

Traditional Authorities

According to the Communal Land Reform Act, the Traditional Authority is given the responsibility of

land allocation and administration at community level. The Traditional Authority is further empowered

through the Traditional Authority Act to administer land and other natural resources within their areas of

jurisdiction, and to impose fees and fines in the process of allocating both access and user rights to those

resources.

The TAs in some areas maintain their traditional way of doing business and have improved little in

transparency and written record keeping. In the current reality of land allocation, both the TAs and the

CLBs are involved in the allocation of land parcels for customary rights and leaseholds. This situation of

dual legal empowerment in land administration often poses a great challenge. This becomes very

pertinent in cases where leaseholds are concerned, in particular in the determination of leasehold

conditions and fees as well as selection criteria for land allocation, leasehold conditions and co-funding

for economic investments.

Other line Ministries

There has been little coordination between Ministries in Namibia, with a tendency for each Ministry to

make and implement its own plans. The MLR, through the processes of Integrated Regional Land Use

Plans (IRLUP) and the LLPP methodology is aiming to improve coordination and promote a wider

analyses in planning processes.

Regional Councils, Councillors and Governors

Page 7: Local Level Participatory Planning, an approach towards

Regional councils comprise elected councillors from every constituency and in Namibia, there are on

average 10 constituencies per region each with an elected councillor. The Namibian Constitution allow

for the President to appoint a Governor for each region.

The regional leadership has often a powerful hand in local politics and most of the development plans are

initiated through the regional councillors and approved by the Regional Development Coordinating

Committee comprising all line ministries at regional level. The Chief Regional officer - who is the

regional chief administrator - is a member of the Communal Land Board.

Other Stakeholders

Farmers Associations represent farmers at constituency level and they form a cooperative at regional

level. The farmers associations coordinate activities related to input availability and distribution,

marketing and keeping of records of farmers in the district and they know which farmers have legitimate

land rights within the areas they occupy. The LLPP model often makes use of the farmer associations to

do preliminary verification of local rights as part of the regional consultation process, culminating into the

actual planning stage.

Conservancies, Community Forests and Cooperatives are community based organizations formed through

the relevant legal instruments such as the Forest Act (Act No 12 of 2001), the Nature Conservation

Amendment Act (Act No 5 of 1996) and Cooperative (Act No 23 of 1996) The Community Based

organizations are installed to foster good governance through a democratic process of managing common

land resources such as wildlife, water, forests and others. The land these institutions occupy is not legally

secured through lease as their registration is only for access and management.

In the land allocation process, there are areas designated for commercialized farming that overlap with

conservancies and community forests. In such areas with overlapping land use, the conservancy or

community forest involved give a consent indicating that the intended area for development does not

conflict with the zonation plan, regarding wildlife migration, breeding or trophy hunting.

1.3 Programme for Communal Land Development

Since 2006 the Ministry of Lands and Resettlement (MLR), with support of the German Government

through the KfW, is implementing a land reform program to ensure that land rights are secured, land use

plans are established and that economic development of underutilized land is supported by providing key

infrastructure. A set of clearly articulated core principles have been developed and guide the

Page 8: Local Level Participatory Planning, an approach towards

implementation of the Programme for Communal Lands Development (PCLD) across 7 regions and on 5

Million hectares.

Figure 1: Map of the PCLD intervention sites

The PCLD addresses some of the core developmental challenges of Namibia – a colonial legacy of

skewed access to land, tenure insecurity in the areas of the poorer populace, the absence of processes and

legal instruments for communities to lead local development, and limited means to manage and utilise

land as both a productive and market-oriented resource.

Page 9: Local Level Participatory Planning, an approach towards

The design concept of the PCLD can be summarized as follows: The registration of all legitimate rights in

a specific intervention area forms the secure basis for participatory planning and subsequent infrastructure

investments. Secure property rights generate and sustain a genuine interest and motivation, as well as the

necessary clout, to participate in community-level planning processes. Moreover, security of tenure is a

pre-requisite for private investments in securing and improving the productive capacity of the land itself.

The provision of (partially) publicly funded infrastructure in communities can be safeguarded when the

resulting benefits are tangible and provide the required utility for people to actually look after the given

infrastructure. Secure rights, jointly prepared plans and physical infrastructure alone however do not

ensure a commercially successful farmer, and as such targeted advisory services underpin the prior

investments.

Partners in this programme are the Government of the Republic of Namibia, the European Commission,

the Kredietanstalt fuer Wiederaufbau (KfW) and the Deutsche Gesellschaft für Internationale

Zusammenarbeit (GIZ).

1.3.1 Objectives and Expected Results

The PCLD provide the basis for improved land inventory and administration, informed and empowered

planning, private investments in the land, and – in the longer run – potentially unlocking the economic

value of land as collateral for communal farmers. The overall objective of the programme is to improve

rural communities’ land based livelihoods through the development of communal lands and a better

integration into the mainstream economy.

The following results are pursued in order to contribute meaningfully to the overall objective:

Result 1 (R1): Verified and mapped existing customary Land Rights and Leaseholds in communal

areas are registered, secured in the administration system for communal lands and issued to the

beneficiaries.

The PCLD’s efforts to conclude the registration of both customary land rights and commercial leaseholds

in communal areas is an important step in providing the tenure security enshrined in the Namibian

Constitution. Also, tenure security provides a platform for improved participation and ownership in

planning processes and stimulates private investments in land.

The PCLD is piloting efforts to make provisions for infrastructure, and more importantly land rights, to

be held in common and be legally defendable by groups. Close collaboration with civil society, and in

particular legal advice, is maintained in this regard.

Page 10: Local Level Participatory Planning, an approach towards

Sustainability, in terms of land tenure, is achieved through systematic verification and registration of

communal land rights in a central register at regional level, with an operational link to Deeds. The

existing registration system allows for the transfer and continuously update of rights. The existing legal

framework makes provision for the adjudication of disputing claims via a Tribunal and in the court of

law. As the programme is hosted by the MLR itself, working in close collaboration with local-level

institutions which primarily include the Traditional Authorities and Communal Land Boards, the land

register’s sustainability from a regulatory and institutional perspective is enhanced.

Result 2 (R2): Participatory Integrated Regional Land Use Plans (IRLUPs) and Local Level

Participatory Plans (LLPP) are developed in accordance with MLR standards.

Options for land based activities in rural communities have proliferated since Independence, as have

associated institutions and interest groups. The absence of integrated land use plans at the regional level,

in terms of coordinated public service provision, exacerbates a situation of overlapping and at times

conflicting land uses. The discipline of land use planning provides the platform for community members,

traditional authorities and communal land boards to actively influence and secure access rights, shape

rules of affiliation to selected land uses, to disentangle and streamline overlapping land uses, and

generally determine their own resource management plans and affiliated investments in the land.

The Local Level Participatory Planning process is discussed in more detail in Chapter 2.

Result 3 (R3): Core infrastructure investments identified through the participatory planning

processes (LLPP) have been implemented and improve the conditions for commercial land-based

development in designated areas.

The communal areas of Namibia continue to lack critical infrastructure in many farming areas. Farming

enterprises in semi-arid environments are built predominantly on a few base conditions: access to reliable

water, to land and a fodder base, and to husbandry infrastructure. As such, infrastructure support is

predominantly in the form of boreholes and water abstraction/ reticulation equipment, fences where

justified and needed for improved rangeland management practices, and marketing and husbandry

infrastructure where considered of strategic importance.

However, the MLR is committed to support a wider variety of intervention modalities in terms of

infrastructure development and importantly includes different ownership, management and land use

options to suit prevailing social practices and preferences by local residents. The rules governing access

to, and obligations associated with publicly provided infrastructure are based, as much as possible, on

Page 11: Local Level Participatory Planning, an approach towards

existing systems successfully employed in rural areas across Namibia (such as water point committees,

their associated structures and regulations) in consultation with communities via the LLPP process.

Result 4 (R4): Programme beneficiaries receive advisory services to tap into the improved physical

environment and successfully pursue more commercially driven modes of production and farm

productivity increases

In addition to the improved physical and regulatory means base provided by R1 through R3 above, the

skills to optimally utilise and manage the business of farming is paramount if sufficiently high rates of

return are to be realised from the investments in the programme. As such, the provision of 'mentorship' of

experienced commercial farmers is considered pivotal to the success of the proposed intervention –

infrastructure alone is no guarantee for improved production or for providing an impetus towards

commercialisation.

Result 5 (R5): The MLR has increased the capacity to assume its mandate for the management and

development of communal lands

The design, coordination and continued responsiveness to a participatory process not only require time

and dedication, but also a good understanding of the complexities of the process at hand. Equally, the

administrative and management capacity for such an endeavour, including sub-contracted components,

needs to be assured.

1.3.2 Method of Implementation

The PCLD supports the MLR in implementing the Land Reform Action Plan component addressing

tenure reform and land development in the communal areas of Namibia. The MLR takes full ownership

and responsibility, whilst donors and the most relevant national public institutions are members of the

Programme Steering Committee. The Namibian Government has a laudable and proven track record in

sensitively managing land reform within the existing legal framework, and regular communication with

the Namibian population, frequent partner dialogue and involvement with the programme steering

mechanisms, mitigate the risks of exposure. The role of the MLR at central level is predominantly

strategic, setting standards and executing oversight. The MLR regional offices are responsible for

programme implementation at the local level, and ensure close collaboration with the relevant parties at

intervention sites. Existing regulatory provisions and working practices ensure close collaboration with

Traditional Authorities and Communal Land Boards.

Page 12: Local Level Participatory Planning, an approach towards

The programme strengthens the Divisions responsible for Land Boards, Tenure and Advice (LBTA), for

Land Use Planning and Allocation (LUPA) as well as the Directorate for Regional Programme

Implementation (DRPI), in order to ensure effective programme execution and contributes to the capacity

development for land management nationally. Provision is made to promptly address policy or regulatory

issues, as identified in the PCLD and emanating from programme activities, in order to underpin lessons

in the medium-term by contributing to an improved land administration and land management framework

in Namibia.

Advisory services will be rendered by GIZ building on a Farmer Support Programme, extending the

current mentorship pool to cover the communal areas as well. It is foreseen that other service providers,

notably from the private sector, will be contracted to provide advisory services. The Advisory Services

will be closely coordinated with the other components of the action, in order to ensure timely, targeted

and relevant advisory services.

2 Local level Participatory Planning, a Decision Making Modality for Local

Level Development

To facilitate the creation of development plans for the designated areas, in 2012-2013 the Local Level

Participatory Planning process was developed, tested and implemented in three selected designated areas,

and hence formally adopted by the MLR.

The LLPP process is nestled in the participation of the prevailing Traditional Authorities (TA), the

modern-day Communal Land Boards (CLBs), local residents and local and regional based stakeholders.

The LLPP process is integrated with the mapping and registration of communal land rights, the Regional

planning activities as well as the development of physical infrastructure. LLPP makes extensive use of

visual aids, and facilitates a process which allows for the local adaptation of both programme objectives

and eligibility criteria.

LLPP comprises the essential elements in the approach that should lead to a state borrowing from the

concept of free prior informed consent (FPIC), in order to ensure transparency in decision-making and

local ownership of programme outputs. It refers to informed consent by all affected parties to land tenure

arrangements, infrastructure developments, resource use rules and other key livelihood decisions made.

LLPP provides a platform for all stakeholders to:

• Streamline overlapping landuses

• Adjudicate land tenure (depicting the location of both legal and illegal land occupants)

• Determine and secure access rights

Page 13: Local Level Participatory Planning, an approach towards

• Selection of the beneficiaries

• Shape use rules to selected infrastructure

• Define their own development plans in line with a given budget

The following general guidelines were designed to ensure that the Local Level Participatory Planning

process will have the desired results. Most of these guidelines are to ensure that all stakeholders will be

able to participate fully in the process:

• Ensure the allowance of sufficient time; time during workshops but also between workshops not

to force decisions and to allow for community internal process to ponder the trade-offs, impact

and expectations of decisions

• Allow for translation during workshops, and again, plan time for this.

• Involve respected local leaders in the work, but ensure that they will not bias the discussion

disproportionately.

• Where feasible, ensure that the Communal Land Board has an active role in the LLPP. Ideally

they should chair the LLPP workshops. They should take the lead in any issue related to land

administration.

• The MLR regional Deputy Director or a duly and capable designated member of staff, should be

actively involved in the LLPP process and all public consultations.

• The use of visual aids is to be considered wherever possible. However, ensure that appropriate

time and guidance is given to ensure that all participants are convenient with them.

• Do not shy away from repetition of content of previous workshops and be ready to answer

questions which have been answered before, be patient. Meetings are often one step back and two

steps forward.

• Be clear on what people can expect. Especially on the timeline of the process, the budget

available and the framework within which the LLPP has to stay.

• A site file, freely available in strategic places and with all relevant and up-to-date information,

should be developed and continuously updated.

2.1 LLPP Stages

The LLPP is process consists of four sequential stages. While stages have a fixed content, they are

implemented in a flexible way and adjusted to local circumstances. This means that where needed,

different methods can be used to reach the desired outcomes. Nevertheless, even these decisions on

varying the methodology will have to be taken and documented in the public domain.

Page 14: Local Level Participatory Planning, an approach towards

Figure 1: Illustration of core elements of the LLPP process

Figure 2 illustrates the steps in the LLPP implementation with major activities and outcomes at each

stage.

Stage 1: Selection of priority site(s) within the designated areas.

The LLPP process starts with a scoping visit to a selected designated area to ascertain the level of

readiness by the regional and local communities to proceed with the LLPP process and the

implementation of the PCLD. If the stakeholders are ready, an inception workshop is conducted to

introduce the PCLD and the LLPP process. During the inception workshop the institutional setup around

the LLPP is discussed which normally leads to the appointment of a LLPP organizing committee. The

inception workshop is followed by the mapping of the entire area. In most instances, initial mapping is

generic and captures the following elements.

• Registered land rights

• Villages

• Dwellings

• Fences and cattle handling facilities

Page 15: Local Level Participatory Planning, an approach towards

• Livestock numbers

• Major land use zonations (formal and informal)

• Water points and boreholes

• Roads, schools, clinics

• Conservancy and community forest boundaries

From the collected data a baseline map is produced and presented in the following workshop. With the

use of the base map, the actual areas in which infrastructure developments are focussed will be selected.

Stage 2: Selection and agreement of beneficiaries, designing of the scenario for desired future of

designated area, including infrastructure investments on a local level, agreement on the rules of

affiliation.

This stage is the core of the LLPP process and starts with site specific detailed mapping which includes a

survey to assess the socio-economic conditions of the local farmers. With all possible data available,

maps will be produced and used in the meetings to develop scenarios. These scenarios are often

developed during group work after which they will be discussed finally the meeting will have to come up

with one development scenario, indicating the type and locality of the desired infrastructure. This scenario

will, after the meeting, be digitized and evaluated by some technical experts on economic viability,

practicality ad budget availability. In the following meeting, the results of this internal validation are

brought back to the meeting for their finalization. What follows is the selection of beneficiaries which is

guided by the MLR/CLB in accordance to the CLRA.

Through the LLPP, not only individual leaseholds are being registered, but there is an increasing request

for the registration of leaseholds for groups of people. The formalisation of group rights over

commonage, over cattle posts or over any other designated land holding, holds significant promise for the

PCLD not only to be able to support farmers in more densely populated areas, but also to spread

investments across larger groups of beneficiaries and allow a more diverse socio-economic stratification

amongst beneficiaries. However, the pursuit of formalising group rights in communal areas is a largely

unchartered territory with a multitude of possible legal implications. Therefore the PCLD has engaged the

services of a reputable entity (the Legal Assistance Centre) to assist in this part of the LLPP process. They

have been given the specific task to safeguard the rights of local residents in the intervention sites, in

particular the rights of poorer segments of society. They assist groups of local residents in their

understanding, selection and design of appropriate legal entities to formalise group rights and associated

rules of affiliation over jointly held land rights and associated infrastructure.

Page 16: Local Level Participatory Planning, an approach towards

Besides, the LAC advises the MLR in an on-going fashion on the design of a suitable policy framework

for group rights over communal land and infrastructure through the synthesis of lessons learn in the

implementation of the programme.

Throughout the process, the implications of the selected tenure type and development scenario will have

to be explained. These include the leasehold conditions, lease fees in particular as well as requirements

regarding co-funding for economic investments.

Designated engineering services (further discussed in Stage 4 below) provide information needed to

estimate the costs of the selected development scenario, especially for the possible water supply options.

Stage two ends when a final local level development plan has been approved and beneficiaries of

leaseholds and investments are selected. Stage two can take as long as six months to be completed.

Stage 3: Validation of the local level development plan, investment plan and applications for

leaseholds

The third stage involves the finalization of the site file which describes the LLPP process so far and

includes all decisions made in all the workshops as well as the lists of people who participated. The

completed site file is circulated to key stakeholders such as the TA, RC, MLR, CLB and others for their

consideration and feedback. The leasehold applications are publicly displayed as well as advertised in the

newspapers and those with objections can lodge them in writing to the CLB which advertised the

leasehold application. The following diagram illustrates the process of validation.

Page 17: Local Level Participatory Planning, an approach towards

Figure 3: Validation process in Stage 3 of LLPP

Stage 4: Implementation of the LLPP results

Once the LLPP results are validated as described in stage three and no objections have been lodged/ all

have been amicably resolved, the CLB send a written confirmation letter to the MLR indicating that the

LLPP process has been completed successfully. With this confirmation, the Ministry will start the tender

for the works as per the development plan yielded from the LLPP process. At the same time the CLB will

further process the application(s) for leaseholds. The Regional MLR Deputy Director also submits a

confirmation letter to proceed with the LLPP implementation.

Thereafter, the Ministry through the program for Communal Land Development goes through the tender

process and supports the monitoring and supervision of construction process up to handing over. In the

areas completed with LLPP planning, advisory services commence to enable farmers make use of their

investments to commercialize production.

To ensure proper technical designs for the infrastructure to be developed, but also to complement other

areas of expertise, the PCLD includes a pool of experts from which it can draw on behest of the MLR.

Since the development of water infrastructure forms a substantial part of the investments – usually more

than 50% of the infrastructure provisions, the MLR has recruited a specialized consulting engineer in this

Page 18: Local Level Participatory Planning, an approach towards

field. This consulting engineer, from a purely technical point of view and building on LLPP results,

compiles a comprehensive needs assessment, detailed site surveys, designs, specifications, cost estimates

and the tender documents. The same consulting firm supervises all works and supply activities by

contractors during construction and the defects liability period on a continuous basis, including reporting

and certification of payment requests.

3 LLPP Results

As part of the overall Communal Land Reform process, in 2012-2013 the local level participatory

planning process has been developed, tested and implemented in three selected underutilized areas.

Figure 4: Map of the LLPP pilot areas

In the selected areas, the LLPP approach has proven to be an important tool for ensuring local grown

development plans which underpin all investment decisions. It has also played a vital role in the

adjudication and formalization of land rights in the selected areas.

Through LLPP the Communal Land Reform Programme has effectively dealt with a host of challenges,

including, a lack of congruence between TA and CLBs as regards the interpretation of the legitimacy of

Page 19: Local Level Participatory Planning, an approach towards

land rights; attempts of eviction of certain ethnicities in programme areas; allaying decade-old boundary

disputes between competing Traditional Authorities, and as a mechanism to negotiate and secure land

rights for groups of local residents to harness local ownership and decision-making. The LLPP has

yielded local level development plans that are adapted to the local needs and available budget, with a

focus on promoting the commercialization of land based economic activities. For three of the two sites,

infrastructure is presently being implemented

A number of challenges were encountered during the planning process; challenges at which the LLPP

methodology, and its embeddedness in the MLR, has proven to provide amicable solutions. These

include overlapping Traditional Authorities, overlapping land uses, the adjudication of fences, group

rights and a concerted effort to diminish the rights of certain groups. Each of these may well be worth a

paper in themselves, and are briefly alluded to in the following sections.

Namibia is witnessing the rapid erosion of one of its most valuable resources – the commonage. Set in an

ever-more marginal open access system local, often poor, residents are witnessing the dissolution of their

principle livelihood source, and the dwindling of a primary national safety net. Whilst ongoing efforts in

the registration of customary land rights are a positive development in post-Apartheid Namibia,

commonages remain largely a free-for-all. In reality, the open access regime is presently approached less

as a commodity “for-all”, but rather as “for-the-rich” as Namibia makes the transition from customary to

modern land administration systems. Namibia’s ill-fated history of colonization witnessed an

exacerbation of the proverbial ‘tragedy of the commons’; a lack of tenure security further manifested in

limited private investment in the land, a lag in the modernization of farming systems, and a quasi-absence

of private sector provision of inputs and services. Communal land allocations were mostly not

documented; transferred only orally with resulting boundary disputes, unauthorized extensions of

allocated land, and in unregulated - and at times illegal - fencing. Widows and orphans in particular were

often deprived of their land rights.

LLPP is nestled in the participation of local residents and locally based institutions, and plays an

important role in the adjudication process between these and the two primary land administration bodies

from separate eras, namely the prevailing Traditional Authorities (TA) and the modern-day Communal

Land Boards (CLBs). The tools and results of the LLPP process (inter alia residential, resource,

infrastructure and land use zonation maps; basic socio-economic assessments; land right scenarios

depicting settlement, commonage and commercialization sites; investment planning scenarios, list of

beneficiaries; rules of resource user rights and responsibilities; etc.), highlight the commonage

boundaries, potential conflict areas, numbers of households and livestock in an area and the proportion

Page 20: Local Level Participatory Planning, an approach towards

dependent on the commonage, fenced-off sections and other important planning elements. These generate

a solid platform for informed discussion about prevailing practices, as well as possible future decisions.

Such decisions may pertain as to the need for secured group rights; alignment to or negotiation with other

land uses; adjudication processes on fences and water infrastructure (both existing and planned);

regulations as to the use of jointly held infrastructure or, on the other hand, regulations for exclusive use.

The work with designated entities like the LAC (reference is made to section x.x) is advancing the

institutional and legal framework response to such needs, to the affect that under the PCLD the first legal

entities of designated groups are being issues land rights.

Tenure insecurity and a period of transition between customary and modern land administration has led to

‘defensive’ fencing by some relatively well-off citizens. These fences reduce the commonage in spite of

growing population pressure and increasing livestock numbers, and have led to a proliferation of land

disputes. LLPP has successfully brought together local residents, affected parties, CLBs, TA’s and

support institutions and amicably resolved such situations. Decisions were recorded to remove certain

fences entirely, reduce certain land holdings, regularize certain portions and issue formal leasehold

certificates – all of this with due respect to both local customs and national laws.

Areas on which multiple Traditional Authorities lay claim, where successions are disputed, or where

residents pay allegiance to different TA’s, are commonplace. The LLPP process, by virtue of its

structure, the time it is allowed to take and the efforts it takes in having an inclusive consultation, has

proven apt at not only bringing such conflicts to the fore but, more importantly, allowing for a multitude

of interventions to eventually overcome such conflicts in the interest of advancing development in a

certain area. TA’s have provided written consent to the State to conclude the process of planning and

investments.

In insoluble cases the MLR has been willing to postpone the intervention by 12 months or more for local

leadership structures to sort their issues out, before again engaging at the regional/ local level.

3.1 The Otjetjekua example

Otjetjekua designated area covers 47.000 hectare and is sparsely populated. The area receives on average

around 300mm of rain a year and is fully used for grazing of small stock and cattle. There are 2.800 heads

of cattle, which is the main source of income for the local population consisting of 133 households. The

area is situated within the multipurpose zone of the Ehirivopuka conservancy. There are no clearly

defined traditional authority boundaries and conflicts with neighbouring cattle farmers invading into the

Otjetjekua area are frequent, especially in dry years.

Page 21: Local Level Participatory Planning, an approach towards

Through the LLPP, the local residents have registered themselves as a cooperative and applied for a

leasehold over the larger Otjetjekua area. They have developed a basic business plan and have fully

constituted cooperative boards and bylaws, and prepared rules of affiliation for the shared infrastructure

which are being finalized.

Challenges in this area have been the insurance of the inclusion in the LLPP process of all the relevant

local residents as well as the definition of the boundaries for the leasehold without creating major

conflicts.

The final infrastructure agreed upon through the LLPP is a boundary fence and internal fences for better

grazing management as well as multipurpose kraals and auctioning facilities for better management and

marketing.

Figure 5: The Otjetjekua example

Page 22: Local Level Participatory Planning, an approach towards

3.2 The Okongo example

The Okongo designated area covers 60.000 hectares and receives on average around 550mm of rain a

year. The area is covered by dens savanna and is mainly used for grazing of small stock and cattle with

some small patches of crop land. Most of the land is occupied by around 24 individual farmers and three

villages on the Western site. The three villages comprise of around 150 households in total, where the

farms support around 100 households. The area is disputed between the Ndonga and Ukwanyama

Traditional Authorities, with both claiming primary jurisdiction over the area.

Of the 24 farms 15 are having consent from one of the two mentioned TAs and therefore were considered

eligible for Leaseholds and infrastructure support. These 15 farms support 80 households and have a total

of 3.200 heads of cattle. Leaseholds for the 15 farms have been approved and developments are being

implemented. The LLPP process for the three villages has started and is steering towards the registration

of a cooperative and a group right over the larger area, thus securing the commonage for the local

population.

Figure 6: The Okongo example

Page 23: Local Level Participatory Planning, an approach towards

The main challenges in this area were to adjudicate the existing farmers while there is a land conflict

between two TAs. The final infrastructure agreed upon through the LLPP is a boundary fence and internal

fences for better grazing management as well as multipurpose kraals and auctioning facilities for better

management and marketing. Also, water abstraction and reticulation will be augmented.

3.3 The Ongandjera East example

The Ongandjera East area was selected in the first stage of the LLPP through a zooming-in exercise. The

whole of the Ohgandjera area consists of more than 148.000 ha, and with the available resources only part

of the area can be developed. In the first stage of LLPP it was decided which areas would be developed;

one in the east and one in the west. Both areas were selected due to their lack of conflict as well as their

high potential (once water is made available). The Eastern area was selected to be handled within the

piloting phase while the Western site will be subject to LLPP in the 2014-2015 financial year.

The Ongandjera East area has 40.000 hectares with two permanent settlements occupied by the San

Community. The rest of the area is used as commonage for seasonal grazing for 120 cattle post owners,

predominantly from the Ovambo tribes. The area receives an average of 400mm of annual rainfall which

supports an open savanna vegetation. There are an estimated 3.400 heads of cattle grazing on the

commonage in the area

• The area has saline ground water and cattle owners harvest rainwater (floating on the salt water)

through hand dug wells. The area is fully covered by the Sheya Shuushona conservancy, but falls

outside the core areas.

• The area will be leased to a cooperative consisting of local residents. The larger area has been

zoned into three land use systems, which are:

Permanent village settlements mainly for San communities

Commonage areas for san communities as well as grazing of small herds of cattle.

Business area which will be sub leased for commercial cattle farming.

• The planned development mainly includes piping water from the main distribution network (40

km away), fencing of the business area, external fences as well as multipurpose kraals.

Page 24: Local Level Participatory Planning, an approach towards

Figure 7: The Ongandjera East example

4 Reflection, lessons learnt and potential for wider application

LLPP is the pivot of the implementation approach adopted by the MLR in the implementation of its

Programme for Communal Lands Development. LLPP provides the causal and procedural link between

baseline data (maps), local conditions, local aspirations, the design of required infrastructure, and finally

the spatial arrangement of the infrastructure with the aim to enable famers – primarily local residents – to

improve productivity and market linkages.

The programme disburses relatively large amounts of public funding, which presents a large

responsibility for the implementing agency (MLR), and also promotes rent-seeking by a wide variety of

stakeholders. As such, the processes’ integrity is paramount. LLPP derives its integrity from transparent

processes, conducted throughout in the public domain; from taking the time for (predominantly) rural

communities to make decisions about their own livelihoods; to fostering inclusive decision-making

which, in as far possible, limits rent-seeking by proportionately better connected individuals. Any trade-

off, by definition, will yield both winners and losers. When it comes to land rights in Namibia, care is

being taken to, in the very least, do-no-harm.

Page 25: Local Level Participatory Planning, an approach towards

Another core element for successful LLPP implementation is teamwork and open communication.

Teamwork between the main stakeholders – the regional and national MLR, Traditional Authorities,

Regional Councils, Communal Land Boards, resident (and absentee) farmers and designated LLPP

consultants – is paramount. Healthy teamwork requires that there is a common understanding of

challenges, opportunities, scope and promise, as well as a set of clearly defined roles and responsibilities.

Also, it requires open channels of communications.

LLPP furthermore requires a high degree of flexibility and situational intelligence from the relevant

decision makers in order to adequately respond to vastly different circumstances between sites, without

jeopardising the integrity if the process per se.

LLPP, with some additional expert inputs, has proven to be a suitable vehicle in the pursuit of the

following objectives:

• Being a structured, transparent and participatory process enable local residents and the MLR to

reduce excessive rent-seeking;

• Resulting in a high degree of awareness, involvement and ownership amongst stakeholders;

• Ensuring tenure security according to the local needs through individual or group rights;

• Ensuring that the resulted plans fit the available resources and result in socially and economically

viable and thus sustainable investments;

• Beneficiaries agree to their responsibilities vis a vis the maintenance of the infrastructure through

the application of designated rules of affiliation and the regulatory tools available to the MLR.

However, LLPP is also a costly exercise – both in terms of required human resources and means to

mobilise expertise, to hold consultative workshops at various levels, the time it requires from (often quite

senior) personnel of the host institution, and the inherent risk of participation revealing latent conflicts

and yielding demands outside the scope of a programme.

4.1 The Use of GIS and Maps in LLPP

Maps are of essential importance, both in the land registration and in the IRLUP and LLPP processes. It is

only since the introduction of orthophoto maps and the NCLAS (Namibian Communal Land

Administration System) databases that the CLBs have become equipped to be able to detect and address

double allocations, as well as land grabbing and illegal fencing. However, due to the limited capacity of

the CLBs and the regional MLR offices, the incomplete first registration of land rights, and the missing

political pressure, the full potential of the NCLAS had not been utilized yet.

Page 26: Local Level Participatory Planning, an approach towards

During the LLPP process it became clear that development of an area will not be possible without solving

the land disputes, assessing the legality of land claims and (as applicable) the removal of illegal fences.

Therefore it has only been during the LLPP process that the NCLAS, other GIS tools and the use of maps

has been fully used to facilitate land use and investment planning in designated areas.

The basis of many of the LLPP processes forms the mapping of all infrastructure and claims to land in the

selected area. This is done by collecting data from stakeholders, mapping from orthophotos and satellite

images as well as by doing site surveys with hand held GPSes. The maps produced are then validated

through the LLPP process after which the land tenure issues are discussed and recommendations to the

CLB made.

The results of the planning (often done by drawing on printed maps) are again captured in the GIS and

validated in public LLPP meetings. In many cases, maps are not easily translated to the ground by local

stakeholders. In these cases, the results of the maps are again verified in the field by using hand held

GPSes. By doing this, a high buy in and understanding from the local population has been achieved.

The maps are also used in the public display period, when people have the chance to lodge an objection to

the outcome of the LLPP process.

Finally the resulted plans are translated into land rights as well as investment plans.

The limitation of these maps is that they may be rather intimidating and extra care needs to be taken to

ensure that people have understood the map and its consequences to the reality on the ground.

4.2 Replication

Entities using a LLPP process are advised to allow for some general best practice rules when conducting

such a process:

• Make allowance for sufficient time; time during workshops but also between workshops not to force

decisions and to allow for community internal process to ponder the trade-offs, impact and

expectations of decisions. Be prepared for the need for repetition of contents of previous workshops

and be ready to answer questions which have been answered before. Meetings are often one step

back and two steps forward.

• Allow for translation during workshops.

• Involve respected local leaders in the work who do not bias the discussion disproportionately.

• Where feasible, let the Communal Land Board have an active part of the LLPP. Ideally they should

chair the LLPP workshops and answer questions of land administration.

Page 27: Local Level Participatory Planning, an approach towards

• The most senior regional officials of the hosting institution, or a duly designated member of staff,

should be actively involved in the LLPP process and be present in all public consultations.

• The use of visual aids is strongly encouraged, but should be given appropriate time and guidance to

ensure that all participants are included in the discussions around them.

• A site file, freely available in strategic places and with all relevant and up-to-date information,

should be developed and continuously updated.

In summary, replicability may principally be a function of political will, programme resources and time

available for implementation. Sufficient amounts of all three are required. Maybe surprisingly,

replicability is to a lesser extent influenced by the geographic scale of the intervention and the complexity

of the land uses in a rural setting, as experience in the PCLD has shown.

4.3 Sustainability of results of the PCLD

Programme beneficiaries, with improved tenure security and full understanding of their rights, will not

only feel safe to invest in their land but have a greater incentive to influence the overall development of

their areas in the long term. At the local level the process of participatory land use planning propagated by

the PCLD, performed from within a secured tenure base, is a developmental and empowerment process

contributing to sustainability. Besides the LLPP, Integrated Regional Land Use Plans are valuable across

institutions for concerted and informed planning processes. The maintenance and periodic update of the

data underpinning these plans is supported by MLR staff in the regions, and strengthens the longevity of

the plans.

Investments in tenure security, and the provision of infrastructure and advisory services in support of

better land and animal husbandry, enhance the resilience and adaptive capacity of Namibia’s communal

population to climate change. The programme provides the incentives/ mandate to ensure the maintenance

and further development of the infrastructure. It also contributes to the building of capacity needed to

successfully commercialize operations in the designated areas. Furthermore, close collaboration with

MET and other relevant stakeholders tries to ensure that physical infrastructure will be adapted to

minimize the potential for human-wildlife conflicts, as well as the preservation of, and access to, strategic

natural resources.

Page 28: Local Level Participatory Planning, an approach towards

5 References

1. Johann Malan, Guide to the Communal Land Reform Act, No. 5 of 2002. Windhoek, Namibia. Legal

Assistance Centre and Namibia National Farmers Union, 2003

2. Republic of Namibia. Communal Land Reform Act, No 5 of 2002. Windhoek, Namibia. Government

Gazette, 2002

3. Republic of Namibia. National Land Policy. Windhoek, Namibia. Government Gazette, 1998

4. Ministry of Lands and Resettlement, Road Map for the development of small-scale farming areas on

communal land in Namibia. Windhoek, Namibia, Project documentation, 2012

5. Ministry of Lands and Resettlement, Local Level Participatory Planning for the Development of

Infrastructure for Small Scale Commercial Farming in the Communal Areas of Namibia. Windhoek,

Namibia, Project documentation, 2013

6 Figures

Figure 1: Map of the PCLD intervention sites

Figure 2: Illustration of core elements of the LLPP process

Figure 3: Validation process

Figure 4: Map of the LLPP pilot areas

Figure 5: The Otjetjekua example

Figure 6: The Okongo example

Figure 7: The Ongandjera East example