long-term plan update
DESCRIPTION
Long-Term Plan Update. Process Development and Engineering (PDE) February 28, 2006 Long-Term Plan Annual Update Matahel Ansar, P.E. Acquisition of Survey Data. Project Manager: Howard Ehmke Project Description: - PowerPoint PPT PresentationTRANSCRIPT
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Long-Term Plan UpdateLong-Term Plan Update
Process Development and Engineering (PDE)
February 28, 2006 Long-Term Plan Annual Update
Matahel Ansar, P.E.
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Acquisition of Survey DataAcquisition of Survey Data
Project Manager: Howard Ehmke
Project Description: Topographic surveys were performed inside the STAs to
more clearly delineate ground surface elevations between interior levees and control structures
Vertical control surveys were conducted at flow measurement stations to confirm, and correct where necessary, gage datum elevations
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Acquisition of Survey DataAcquisition of Survey Data
Project status
Work completed to date (FY04 and FY05):Vertical Control Surveys
All planned vertical control survey work complete
Topographic Surveys All planned STA surveys complete
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Additional Flow & Water Quality Additional Flow & Water Quality Monitoring StationsMonitoring Stations
Project Manager: Matahel Ansar
Project Description:
Establishment of 47 new flow and water quality monitoring stations for the STAs
These additional monitoring stations are mostly in STA-
3/4 in FY04 (11 structures), in STA-1E in FY05 (19 structures), and in STA-2 & STA-1W in FY06 (4 structures)
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Additional Flow & Water Quality Additional Flow & Water Quality Monitoring StationsMonitoring Stations
STA FY’04 FY’05 FY’06 FY’07 Total
STA1_W 2 culverts: G258 (gate sensor only) and G259
2 new stations in Cell 2A 2 new stations in
Cell 1A
0 6
STA1-E 0 19 structures:S363B,S364B,S365A&B, S366B&D,S367B&D,S368B&D,
S369A&D,S370,S371B,S372B&D,
S373B,S374B,S375
0 19
STA2 0 0 1 new station in Cells 1&2
1 new station in Cell 3 3
STA3-4 9 culverts: G374B & E, G375 B &E (only D for the stilling
wells), G377B&D, G378B&D
(Only C for the stilling
wells), G3832 pumps: G-
370 seep, G372 seep
4 structures: G380B&E, and G381B&E
0 15
STA6 0 0 0 4 structures : G353B,G603,G396B,G3
51B
4
Total 13 25 4 5 47
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Additional Flow & Water Quality Additional Flow & Water Quality Monitoring StationsMonitoring Stations
Project status
Work completed to date
All FY04 stage-related work completed: 9 culverts in STA-3/4 and 2 culverts in STA-1W (G-258 gate sensors & G-259)
FY05 work completed: STA-3/4 structures G-380 B&E, G-381 B&E certified and registered and flow computations have been implemented in the FLOW program
All 9 culverts in STA-3/4 certified and registered and flow computations have been implemented in the FLOW program
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Additional Flow & Water Quality Additional Flow & Water Quality Monitoring StationsMonitoring Stations
Project status
Work planned for remainder of FY06
Validation tests for water quality samplers at G-370 and G-372 seepage pumps – scheduled for completion on 28th February 2006
Validation tests for water quality samplers at 9 culverts: G-374B&E, G-375B&E, G-377B&D, G-378B&D, and G-383 - scheduled for completion on 28th February 2006
Install and survey stilling wells at G-383 - scheduled for completion by May 2006
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Additional Flow & Water Quality Additional Flow & Water Quality Monitoring StationsMonitoring Stations
19 structures in STA-1E completed, certification to be completed by March 2006
2 new stations in Cell 2A of STA-1W – to be completed May 2006
By end of FY06, 42 of 47 stations will be complete, with 5 stations to be completed in FY07
Work planned for remainder of FY06 (Continued)
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Correction of Flow Measurements Correction of Flow Measurements AnomaliesAnomalies
Project Manager: Emile Damisse
Project Description: To address anomalies in discharge
measurements, and provide good quality flow data at all major flow stations in the STAs
Complete correction of Flow Measurement Anomalies in STA-1E and STA-3/4 by the end of FY06
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Correction of Flow Measurement Correction of Flow Measurement AnomaliesAnomalies
Project status Work completed to date
465 streamflow measurements
Flow Measurements
70
4223
135138
4224
204
52
8 5
65
255 3
33
127 28
0
50
100
150
200
250
FY03 FY04 FY05 Total
Fiscal Year
Num
ber of
flow
mea
sure
men
ts
.
STA1W
STA1E
STA2
STA5
STA6
STA3/4
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Correction of Flow Measurement Correction of Flow Measurement AnomaliesAnomalies
Project status Work completed to date
106 rating analyses at 99 stations
Rating Implementation
2
16
2
20
16 16
0
16
11
27
9
0
96 6 6
1816 16
0
5
10
15
20
25
30
FY03 FY04 FY05 Total
Fiscal Year
# of
rat
ings
impl
emen
ted
.
STA1W
STA1E
STA2
STA5
STA6
STA3/4
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Rating Analysis calibration and validation
• 90% Completed at STA-3/4 culverts• 50% Completed at STA-3/4 pumps - two major pumps are validated while the seepage pumps will be validated during FY06• 25% Preliminary rating validation at STA-3/4• 90% Completed at STA-2• 50% Completed at STA-6 culverts• 100% Completed at STA-6 pumps• 100% Completed at the two pumps in STA-1W• 100% Completed at the two spillways in STA-1W• 90% Completed at culverts in Cell 5 STA-1W - implementation is pending on the SOP
Correction of Flow Measurement Correction of Flow Measurement AnomaliesAnomalies
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Correction of Flow Measurement Correction of Flow Measurement AnomaliesAnomalies
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Correction of Flow Measurement Correction of Flow Measurement AnomaliesAnomalies
Flow Rating Equations for G-370 and G-372
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Correction of Flow Measurement Correction of Flow Measurement AnomaliesAnomalies
Project status Work planned for remainder of FY06
Perform streamflow measurements: 132 measurements at 70 stations
05
101520253035404550 M
easurem
ents/S
tations
Flow Measurement prediction for FY06
Measurements Stations
Measurements 12 18 20 12 40 30
Stations 5 6 6 3 25 25
STA-1W STA-2 STA-5 STA-6 STA-1E STA-3/4
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Correction of Flow Measurement Correction of Flow Measurement AnomaliesAnomalies
Project status Work planned for remainder of FY06
Perform/complete Rating Analysis: 147 rating analyses at 49 stations
•0
•10
•20
•30
•40
•50
•60
•70
•Rating Analysis Prediction for FY 2006
•Analysis •10 •7 •5 •3 •62 •60
•# of Station •4 •8 •5 •3 •17 •12
•STA1W •STA2 •STA5 •STA6 •STA1E •STA3/4
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Long-Term Plan UpdateLong-Term Plan Update
Process Development and Engineering (PDE)
February 28, 2006
Long-Term Plan Annual Update
Tracey Piccone, P.E.
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Update and Maintenance of Update and Maintenance of Hydraulic ModelsHydraulic Models
Project Manager: Tracey Piccone
Project Description: Evaluate and predict changes in flow distribution as the
STAs mature and change with time Develop calibrated two-dimensional hydraulic simulation
model of each STA Regularly update and calibrate the models as new
information is received (topo, structural, vegetation)
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Update and Maintenance of Update and Maintenance of Hydraulic ModelsHydraulic Models
Work completed to date
Work Order completed with Sutron Corporation • Used FESWMS/SMS• New models of STA-2, STA-6, STA-1E, STA-1W,
STA-5 and STA-3/4• Three flow conditions: Low Flow, Design Flow, and
Peak Flow Developed, calibrated, and verified models for STA-1W,
STA-2, STA-3/4, STA-6 Section 1 Future efforts will improve upon STA models for which
calibration data was not available (STA-5, STA-1E)
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Update and Maintenance of Update and Maintenance of Hydraulic ModelsHydraulic Models
All reports posted at: http://www.sfwmd.gov/org/erd/longtermplan/documents.shtml
Work planned for remainder of FY06: Refine models with updated calibration, topographic,
and vegetation data when available Modeling in support of decision-making for
operational and structural modifications
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Continued Development Continued Development DMSTADMSTA
Project Manager: Kathy Pietro
Project Description:
Refine and update the DMSTA model, including reservoir component
Develop calibrated DMSTA model for each STA as additional full-scale data becomes available
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Continued Development Continued Development DMSTADMSTA
Project status Work completed to date:
FY05 and FY06 work funded by the U.S. Army Corps of Engineers and Department of the Interior (Dr. Bill Walker)
Tasks completed to date:• Built reservoir module• Updated STA calibration• Enhanced Phosphorus Cycling component• Updated model platform
DMSTA v.2 was released April 2005 Used for EAARFS evaluations in mid-2005
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Water Quality Impacts of Water Quality Impacts of ReservoirsReservoirs
Project Manager: Yanling Zhao
Project Description:
Assist the EAA Storage Reservoirs Phase 1 PDT in the acquisition and analysis of calibration data sets for water quality impacts associated with reservoirs. These calibration data sets will be obtained from similar water bodies in central and southern Florida i.e., Lake Apopka, Lake Jessup, the Brevard County Stick Marsh and the Sun Ag reservoir, as well as Lake Istokpoga and other large-scale water supply reservoirs in South Florida.
Develop data files and summary report(s) of data sets collected and analyzed for use in calibrating reservoir components of water quality model(s)
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Water Quality Impacts of Water Quality Impacts of ReservoirsReservoirs
Project Status: All lake and reservoir data was provided to Dr. Bill Walker
for use in calibrating reservoir module of DMSTA2
All data is accessible through District’s web site:
• http://spatial1.sfwmd.gov/wqir/
All Project Deliverables are posted at:• http://www.sfwmd.gov/org/erd/longtermplan/documents.shtml
All work complete 1.5 years early $1.2 million under recommended budget
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Evaluation of Full-Scale STA Evaluation of Full-Scale STA EnhancementsEnhancements
Project Manager: Tracey Piccone
Project Description: Complete demonstration projects including construction of a
limerock berm in Cell 5B of STA-1W and implementation of vegetation management measures designed to improve STA performance
Project is being funded by a cost-share agreement between the District and the DEP
District received grant funding in the revised amount of $1.1 million from DEP/EPA (original proposal $1.3 million)
Project includes management of DEP Grant Agreement G0040 Results of the demonstration projects can be applied to other STAs
to improve their performance
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Evaluation of Full-Scale STA Evaluation of Full-Scale STA EnhancementsEnhancements
Project Status – Limerock Berm
Limerock berm was completed in STA-1W Cell 5 in August 2003• With-berm Cell 5 outflow
phosphorus concentrations will be compared to pre-berm values
• Dye Tracer Project was completed in early FY05
• 2004 Hurricane Damage Repairs completed in early FY05
• Top elevation of berm was lowered in 2005 for consistency with revised Cell 5 target stage
• Summary report underway
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Project status - STA-3/4 Vegetation Management Demonstration Project
50 sites inoculated with SAV in August 2004 Inoculated species root in October-November 2004 Natural colonization at locations without vegetation Initial SAV grow-in assessed March 2005 Second assessment March 2006
Evaluation of Full-Scale STA Evaluation of Full-Scale STA EnhancementsEnhancements
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Evaluation of Full-Scale STA Evaluation of Full-Scale STA EnhancementsEnhancements
Work planned for remainder of FY06
Complete summary report for limerock berm Continue monitoring STA-3/4 Cell 2B vegetation
management demonstration project Ongoing submittal of quarterly progress reports and
invoices to FDEP Amend agreement with FDEP to extend by 6 months
• To include results of March 2006 SAV assessment Complete Final Grant Project Report
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Update Baseline Data SetsUpdate Baseline Data Sets
Project Manager: Tracey Piccone
Project Description: Update the analyses presented in the Baseline
Data report to continually improve the degree of confidence in the projected total phosphorus loads in inflows to the stormwater treatment areas (or, in some instances, discharged directly to the EPA)
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Update Baseline Data SetsUpdate Baseline Data Sets
Status
First update completed in FY05 as part of EAA Regional Feasibility Study Work was completed by District staff and consultants Flows and loads entering STAs higher than estimated in LTP Revised flows and loads used during Regional Feasibility
Study to evaluate alternatives for optimizing STA performance
No work scheduled for FY06 Next update scheduled for FY07
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Basins with Limited Current Basins with Limited Current DataData
Project Manager: Kathy Pietro
Project Description: To enhance the water quality and quantity
data for basins with limited current data, e.g., C-51 West and C-11 West Basins
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Basins with Limited Current Basins with Limited Current DataData
Project status Work completed to date:
C-51 West Basin • Final Report posted at:
–http://www.sfwmd.gov/org/erd/longtermplan/documents.shtml
A regression equation was developed for estimating daily phosphorus concentrations, and this was applied to the 31-year simulated runoff used in the Long-Term Plan, a document developed for achieving compliance with the phosphorus criterion
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Basins with Limited Current Basins with Limited Current DataData
Project status The resulting phosphorus levels were 38%
lower (115 ppb compared to 185 ppb) than the estimates used in developing the STA performance projections associated with the Long-Term Plan
Updated projections were used in EAA Regional Feasibility Study
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Basins with Limited Current Basins with Limited Current DataData
Project status
No work scheduled for FY06 Next work scheduled for FY07
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Influence of CERP Projects on Influence of CERP Projects on Inflow Volumes and LoadsInflow Volumes and Loads
Project Manager: Tracey Piccone
Project Description: Update the projected impact of CERP projects on inflow
volumes and loads to STAs and receiving water bodies of the Everglades Protection Area
Two updates to the estimated STA inflows (one upon completion of EAA Storage Reservoirs Project Phase 1 PDT and one upon completion of Phase 2 PDT)
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Influence of CERP Projects on Influence of CERP Projects on Inflow Volumes and LoadsInflow Volumes and Loads
Status
First update completed in FY05 as part of EAA Regional Feasibility Study
Updated information on the EAA Storage Reservoir project used during the EAA Regional Feasibility Study
Second update scheduled for end of FY2010
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Lake Okeechobee Long-Lake Okeechobee Long-Term TrendsTerm Trends
Project Manager: Kathy Pietro
Project Description: To better understand the temporal and spatial relationship
between Lake Okeechobee nutrient status and operation (e.g., choice of outflow point) on phosphorus loads discharged to the STAs
In conjunction with Lake Okeechobee PDT, update the TMDL modeling and trend analyses
Conduct a temporal and spatial trend analyses for TP at outflow points that deliver water to the STAs and reservoirs
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Lake Okeechobee Long-Lake Okeechobee Long-Term TrendsTerm Trends
Project status
Work completed to date: Reviewed project with Lake Okeechobee staff Obtained available data
Work planned for remainder of FY06: Continue to coordinate with Lake Okeechobee staff Develop approach for updating STA input data sets
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Long-Term Plan UpdateLong-Term Plan Update
Determine Relationship Between Discharges and Water Quality Within the EPA
Tracey Piccone, P.E.
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Determine Relationship Between Determine Relationship Between Discharges and Water Quality Within Discharges and Water Quality Within
the EPAthe EPA
Project Manager: Tracey Piccone (interim)
Project Description: Define the relationships between the quality of
water discharged into, and the water quality within, the Everglades Protection Area.
The Parameter of Concern: Phosphorus
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Project Status
Work completed to date: Initial analyses conducted by District staff in
FY04 and FY05 No clear relationship was determined Currently working with FDEP to revise scope of
project to obtain necessary information
Determine Relationship Between Determine Relationship Between Discharges and Water Quality Within Discharges and Water Quality Within
the EPAthe EPA
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Determine Relationship Between Determine Relationship Between Discharges and Water Quality Within Discharges and Water Quality Within
the EPAthe EPA
Work planned for remainder of FY06: Proposed revision to extend project completion
date by 2 years (from FY05 to FY07) Provide funding for soil phosphorus reflux study New soil data to be used with forthcoming
models (EPGM/DMSTA/Refuge model) to gain information on relationship between discharges and water quality within the EPA
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Long-Term Plan UpdateLong-Term Plan Update
Process Development and Engineering (PDE)
February 28, 2006
Long-Term Plan Annual Update
Jana Newman
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
ECP Operational MonitoringECP Operational Monitoring
Project Manager: Linda Crean
Project Description: Operational monitoring of the STAs Weekly/biweekly water quality collection and sample analysis
for TP, SRP, TDPO4, OPO4, TSS, Ca, Cl, ALK, TKN, NH4, and NOx
Maintenance (plus purchase and installation as required) of sampling and flow monitoring equipment
Calibration of autosamplers and weir structures Quality control for the collection, analysis, and archiving of
the data collected Calibration, installation, monitoring, data collection,
maintenance, QA, and archiving of flow data for all the flow structures indirectly associated with permit compliance but necessary for flood control and STA Optimization
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
ECP Operational MonitoringECP Operational Monitoring
Project Status Collection of flow measurements and weekly/
biweekly water quality samples (grabs and autosamplers) from interior non-permit sites in STA-1W, STA-2, STA-3/4, STA-5, and STA-6 on-going
Collection of bi-weekly grabs at internal STA-1E stations by March 2006
Activation of autosamplers in STA-1E should be completed in FY06
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Analysis and InterpretationAnalysis and Interpretation
Project Manager: Jana Newman
Project Description: Ecological assessment of data obtained from the permit
compliance and operational monitoring Annual vegetation maps and synoptic water collection
along with tri-annual collection and analysis of sediment from all internal cells of the STAs
Staff will provide annual phosphorus inflow/outflow budgets for the internal cells, short-term and long-term analyses in support of operational assessment
Establish sampling design for all STA internal cells
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Analysis and InterpretationAnalysis and Interpretation
Project status Work completed to date
Hired contract staff for data analysis and project management through Sept. 2009
2005 internal water collection completed Biweekly nutrient sampling at inflow and outflow of each cell
ongoing Vegetation maps for STAs 1W, 1E, 2, 5, and 6 completed Optimized number of internal sample sites Calculated TP mass budgets for each cell of each STA; results
reported in the 2006 SFER Work planned for remainder of FY06
Calculation of inflow/outflow TP mass budgets for each cell of each STA
Complete annual vegetation maps for all STAs Monitor STA-1W, Cell 5 drawdown and enhancements effort
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
STA-5 Vegetation MapSTA-5 Vegetation Map
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
STA Sediment AnalysisSTA Sediment Analysis
Bulk density (g/cm3)
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
TP (mg/kg)
200
400
600
800
TN (mg/kg)
10000
20000
30000
TC (mg/kg)
100000
200000
300000
400000
500000
S (mg/kg)
2000
4000
6000
8000
10000
Fe (mg/kg)
1000
2000
3000
4000
5000
6000
ST
A1W
ST
A1E
ST
A2
ST
A3/
4
ST
A5
ST
A6
ST
A1W
ST
A1E
ST
A2
ST
A3/
4
ST
A5
ST
A6
ST
A1W
ST
A1E
ST
A2
ST
A3/
4
ST
A5
ST
A6
ST
A1W
ST
A1E
ST
A2
ST
A3/
4
ST
A5
ST
A6
ST
A1W
ST
A1E
ST
A2
ST
A3/
4
ST
A5
ST
A6
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
PSTA InvestigationsPSTA Investigations
Project Manager: Jana Newman
Project Description: To track the performance of District PSTA field-scale
and test cell demonstration projects and factor the results into Post-2006 projects, as appropriate
Additionally, periphyton systems under investigation by the USACE at STA-1E and C-111 are under investigations, and to the extent possible, the District will invite the researchers to submit their data to the District for use in DMSTA model forecasting
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
PSTA InvestigationsPSTA Investigations
Project status
Work completed to date The PSTA test cell monitoring was on schedule
• Assessment of continued monitoring is in progress due to extensive damage from Hurricane Wilma
All requested data to support the DMSTA model update effort has been provided to Dr. Bill Walker
District staff is assisting as needed with the STA-1E PSTA project
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
PSTA InvestigationsPSTA Investigations
Project status
Work planned for remainder of FY06 Assess the need to continue PSTA test cell
monitoring Assisting with other PSTA projects
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
PSTA Test CellsPSTA Test CellsWY02-WY04WY02-WY04
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
PSTA Demonstration ProjectPSTA Demonstration Project
Project Manager: Mike Chimney
Project Description: To construct and operate a large-scale PSTA
demonstration project in STA-3/4
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
PSTA Demonstration ProjectPSTA Demonstration Project
Project Status Work completed to date
Construction of earthwork completed Construction of outflow pump station completed Area flooded since December 2004 Water quality sampling initiated Vegetation percent coverage estimates conducted Vegetation management activities initiated
Work planned for remainder of FY06 Registration of telemetry and other electronics (est.
April/May 2006) Continue vegetation management activities Continue water quality sampling
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Hydrologic and Hydraulic Hydrologic and Hydraulic Assessment &Assessment &
Internal Measurements Internal Measurements
Project Manager: Jana Newman
Project Description: To perform and evaluate the results of dye tracer
study in STA-2 Cell 3 during FY05 Analysis of Lithium Tracer Injected into STA-2,
Cell 3 Collect and evaluate additional internal synoptic
phosphorus measurements to correspond with the dye tracer studies and to aid in interpretation of STA-2 Cell 3 performance
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Hydrologic and Hydraulic Assessment Hydrologic and Hydraulic Assessment &&
Internal Measurements Internal Measurements
Project status Work completed to date
Tracer study completed Data collection completed 11/11/04 Technical review meeting 4/18/05 Final report received Summary report presented in 2006 SFER
No other work planned for remainder of FY06 Next phase will be initiated following construction of STA-
2, Cell 3 internal levee
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
STA-2, Cell 3 Tracer STA-2, Cell 3 Tracer Sampling DesignSampling Design
G-333EA B C D
Seepage return canal station
Seepage return canal
G-334
QA/QC Internal Stations
G-333EA B C D
Seepage return canal station
Seepage return canal
G-334
QA/QC Internal Stations
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
STA-2, Cell 3 Tracer STA-2, Cell 3 Tracer Response Curve (G334)Response Curve (G334)
0
50
100
150
200
250
10/21/040:00
10/26/040:00
10/31/040:00
11/5/040:00
11/10/040:00
11/15/040:00
Lit
hiu
m (
µg
/L)
Date and time
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Comparative AnalysisComparative Analysis
Project Manager: Jana Newman
Project Description: Prepare report documenting the effectiveness of
the attempt at optimizing SAV performance in STA-2 Cell 3, including recommendations for other STAs
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Comparative AnalysisComparative Analysis
Status
Work not scheduled to start until FY08 Plan includes recommended funding of $100,000
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Long-Term Plan UpdateLong-Term Plan Update
Accelerate Recovery of Impacted Areas
February 28, 2006
Long-Term Plan Annual Update
Jana Newman
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Downstream Influences of Adding Clean Downstream Influences of Adding Clean Water to Previously Impacted AreasWater to Previously Impacted Areas
Project Manager: Brian Garrett
Project Description: Determine the ecological response of impacted
areas following the addition of clean water, in order to permit full development and calibration of the recovery model in Bc87(1)
Calculate nutrient flux in impacted areas Document nutrient front recession or reduced
rate of expansion Determine coefficients for recovery model
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Downstream Influences of Adding Clean Downstream Influences of Adding Clean Water to Previously Impacted AreasWater to Previously Impacted Areas
Project status Work completed to date
Flux experiment concluded, data analysis underway P-adsorption experiment concluded, data analysis
underway; additional sampling may be needed Began pilot studies on methods to quantify particle
transport related to flow in WCA2A
Work planned for remainder of FY06 Install necessary equipment to measure flow through
the G-336 culverts discharging into WCA-2A Continue pilot studies on methods to quantify particle
transport related to flow in WCA2A
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals
P flux – Station N4P flux – Station N4
0
0.025
0.05
0.075
0.1
0 1 4 8 18 24 72 144 288
Dry
Flooded
Time (hours)
SR
P (
mg
/L)