Transformation/Repurposing of Face Equipment
Longwall USA 2017
![Page 2: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/2.jpg)
About Me
Name: Jacob Smith Education:
Bachelor of Science – Civil Engineering Master of Science – Geotechnical Engineering
Experience: Over 7 years of engineering experience in the Civil and Mining industries Licensed Professional Engineer in the State of Utah
Employer: Canyon Fuel Company Position: Engineering Manger – Sufco Mine
2
![Page 3: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/3.jpg)
Canyon Fuel Company is a subsidiary of Bowie Resource Partners, LLC. Operations:
Sufco Mine Skyline Mine Dugout Canyon Mine Fossil Rock Mine (Future)
Bowie Resource Partners is the largest coal producer in the Uinta Basin
3
California
Nevada
ArizonaNew Mexico
Colorado
Richmond
Stockton
Long Beach
Utah
Sufco
Dugout CanyonSalt Lake City
Fossil Rock
Skyline
About Canyon Fuel Company
![Page 4: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/4.jpg)
Challenges Facing Our Industry
“Over the past decade, the coal mining industry has faced a series of challenges including competition from other fuel sources, as well as increased regulations”
– Advancing Utah Coal, May 2017
Primary Contributors: New Government Regulations Market Competition Aging Facilities Public Perception
4
![Page 5: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/5.jpg)
Challenges Facing Our Industry
“If somebody wants to build a coal-fired power plant, they can. It’s just that it will bankrupt them.”
– Barack Obama, 2008
New or Proposed Regulations: Mercury and Air Toxics Plan Clean Power Plan Regional Haze Plan Stream Protection Plan Coal Lease Moratorium New Respirable Dust Standards Proximity Detection
5
![Page 6: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/6.jpg)
Challenges Facing Our Industry
Opening the Door for Market Competition: Risk of increase operating costs, due to environmental regulations Aging coal-fired power generation facilities (Average 39 years) Increase in natural gas production from domestic shale basins which reduced
the price of natural gas
VS
6
![Page 7: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/7.jpg)
Market Demand
7
Since 2006, total US power generation from Coal dropped from 49% to 30%
The number of operating underground coal mines declined from 862 in 2006 to 470 in 2015, which is a 45% reduction
2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 20160%
10%
20%
30%
40%
50%
60%
U.S. Energy Generation and Generation Share by Energy Source 2006-2016
Coal Natura l Gas NuclearHydroelectric Other Renewables
Year
Shar
e by
Per
cent
age U.S. Generation by Share (2006-2016)
Year CoalNatural
Gas Nuclear HydroOther
Renewables
2006 49% 20% 19% 7% 2%
2007 49% 22% 19% 6% 3%
2008 48% 21% 20% 6% 3%
2009 44% 23% 20% 7% 4%
2010 45% 24% 20% 6% 4%
2011 42% 25% 19% 8% 5%
2012 37% 30% 19% 7% 5%
2013 39% 28% 19% 7% 6%
2014 39% 28% 19% 6% 7%
2015 33% 33% 20% 6% 7%
2016 30% 34% 20% 7% 8%
Data source: U.S. Energy Information Administration
![Page 8: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/8.jpg)
The Financial Dilemma
Decreasing Market Demand + Increasing Operating Costs = ?
The Ultimate Question: How does an operator safely maintain profitability, while meeting all state and federal regulations?
A Solution: By transforming and repurposing existing equipment
8
![Page 9: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/9.jpg)
Mine Type – Underground Coal
Location – Central Utah
Year Started – 1941
Customers – Utilities & Western Industrial
Mining Method –
1 Longwall
3 Continuous Miners
Annual Production – 6 - 6.5 million tons
Reserves –
Upper Hiawatha Seam
Total Tons Produced = Over 190 Million
Total Tons Remaining = Over 20 Million
Lower Hiawatha Seam
Total Tons Remaining = Over 56 Million
Sufco Mine - Background
9
![Page 10: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/10.jpg)
Sufco Mine - Challenges
Upper Hiawatha Seam Historical Reserve Thickness = 9 – 17 feet Remaining Reserve Thickness = 7 – 11 feet
Current Longwall Equipment (2) Complete Caterpillar 2.0-meter AFC, Crusher, and BSL
Face Width = 1,110 feet (168) Caterpillar 2.0-meter Shields
Operating Height = 8.5 – 14.5 feet
First Challenge Managing Quality and Out-of-seam Dillution
10
![Page 11: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/11.jpg)
Mine Type – Underground Coal
Location – Central Utah
Year Started – 1998
Customers – Utilities, Western Industrial, & Export
Mining Method – Continuous Miner
Annual Production – 0.75 - 1 million tons
Available Equipment
(157) Joy 1.75-meter Shields
Operating Height = 7 – 11 feet
Total Cycles = 30,000
No Panline
Dugout Canyon Mine
11
![Page 12: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/12.jpg)
Sufco Mine – Challenges Current LW Equipment
Face Width = 1,110 feet Operating Height = 8.5 – 14 feet Pan Width = 1342 mm Web Depth = 42 inches
Available LW Equipment Face Width = 905 feet Operating Height = 7 - 11 feet Pan Width = 1042 mm Web Depth = 36 inches
12
Difference Face Width = 205 feet (18%) Operating Height = 1.5 - 3 feet (21%) Pan Width = 300 mm (22%) Web Depth = 6 inches (14%)
Second Challenge Maintaining Current Production
![Page 13: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/13.jpg)
Challenges and Solution
Define the Challenge Maintaining Coal Quality Maintaining Current Production
Identify the Solution Use the Available Joy 1.75-meter shields
Increase Web Depth from 36 inches to 1 meter Purchase new AFC, BSL, and Crusher
Increase pan width from 1042 mm to 1142 mm
Make a Plan1. Perform Shield Evaluation2. Develop Shield Rebuild and AFC Scope-of-Work3. Bid Shield Rebuild and AFC4. Award Contracts 5. Complete Work6. Compatibility 7. Install Equipment
13
![Page 14: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/14.jpg)
1 - Shield Evaluation
Identified three potential vendors Each vendor was provided two shields Evaluation scope-of-work:
Perform Visual Inspection and Functionality Test Clean, Strip, and Sandblast all Structures Fully inspect all structures and welds Fully inspect all leg pockets Inspect all pins and bores Provide report including:
Description of findings Recommendations for rebuild
14
![Page 15: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/15.jpg)
1 - Shield Evaluation
Evaluation Findings: Structurally in good condition Base rear-bridge cracking Pin and bore wear
Recommendations: Replace hosing and valves Repair/replace base rear-bridge Replace pins and recover bores
Additional Items: Lamniscate Modification (Fill holes and provide hose hangers) Base Lift Repair (Add stops to prevent bolt fatigue)
15
![Page 16: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/16.jpg)
1 - Shield Evaluation
16
Key Process and Win-Win Solution Provided Sufco with accurate and reliable information
Comprehensive rebuild scope-of-work Avoid unexpected surprises/change-orders
Provided the vendor with an opportunity to become familiar with the shield Reduced uncertainty during bid process Confident and competitive bids
![Page 17: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/17.jpg)
2 – Scope-of-Work
Shield Rebuild – Standard Specifications Clean, strip, and sandblast all structures Inspect all structures and welds (highlight paint, dye penetrant, and mag particle) Gouge and weld cracks, correct misalignment issues, and replace blocks and stops Test all shield cylinders and rebuild to OEM specifications, as-needed Install all new valve banks, control units, hosing, and cables Replace all shield pins and recover bores to OEM tolerances Reassemble shield Paint all structures with one coat primer and one coat white paint
17
![Page 18: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/18.jpg)
2 – Scope-of-Work
Shield Rebuild – Unique SpecificationsStructural: Install 8-inch canopy tip extension Provide new relay bar and DA ram to accommodate 1-meter web Replace base rear-bridge Plug access holes in lemniscate links and provide hose hangers Provide base lift support blocks Provide Loctite leg pocket foam protectantSafety: Provide and install two water-curtain spray blocks recessed in canopy Install new anti-skid surface plate on shield toes with pinned connection Install fully-integrated multi-color lighting package
18
![Page 19: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/19.jpg)
3 - 4 – Bid and Award Contract
Bids were requested from three vendors The Shield Rebuild contract was awarded
19
![Page 20: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/20.jpg)
5 – Complete Work
20
![Page 21: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/21.jpg)
5 – Complete Work
21
![Page 22: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/22.jpg)
5 – Complete Work
22
![Page 23: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/23.jpg)
5 – Complete Work
23
Updated Gimble-Style Base Lift
Anti-Skid Toe Surface Cover
![Page 24: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/24.jpg)
5 – Complete Work
24
Angled faces of hydraulic ports ensure that the inter-support hoses are steered away from the legs in lower part of working range
![Page 25: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/25.jpg)
2 - 3 – Scope-of-Work and Bid
The initial Scope-of-Work included 1142 mm AFC, BSL, crusher, power-units, and drives
Through the bid process, Sufco identified that the incremental cost of purchasing new BSL, crusher, and power units did not make good financial sense
Sufco elected to reuse a portion of the existing LW equipment: CAT 65 Series Headgate and Tailgate CST power units 1650 HP Motors Crusher BSL
25
![Page 26: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/26.jpg)
4 – Award Contract
The Scope-of-Work was changed, to reflect the equipment that would be reused, and bids were requested from three vendors
The AFC contract was awarded
26
![Page 27: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/27.jpg)
5 – Complete Work
27
![Page 28: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/28.jpg)
5 – Complete Work
28
![Page 29: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/29.jpg)
6 - Compatibility
29
![Page 30: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/30.jpg)
6 - Compatability
30
![Page 31: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/31.jpg)
7 – Install Equipment
31
![Page 32: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/32.jpg)
Summary
The Challenge: How to economically maintain coal quality and current production levels, with lower seam conditionsThe Solution: Rebuilt 157 1.75-meter Joy longwall shields
Increased web-depth from 36 inches to 1 meter Purchased two new AFC panline with headgate and tailgate drives
Utilized existing BSL, crusher, and power units Entered LCM agreement with Joy on two rebuilt shearersWe feel this is a great example of how transforming and repurposing equipment can help maintain profitability during strenuous times
32
![Page 33: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/33.jpg)
Thank You!
33
![Page 34: Longwall USA 2017](https://reader031.vdocuments.net/reader031/viewer/2022012019/616881e4d394e9041f700c3a/html5/thumbnails/34.jpg)
Any Questions?
34