loss & expense (l&e) principles - trent global€¦ · loss & expense (l&e)...
TRANSCRIPT
1
Loss & Expense (L&E)
principles
Anand ANTHONY 安杰 褔<[email protected]> [M: 9693 0407]
CHARTERED BUILDING ENGINEER (UK), Adjudicator (Malaysia), Mediator (UK)
EXPERT in FORENSIC PLANNING (Delay/Disruption/Production/Acceleration)
EXPERT in COST ENGINEERING (Quantum of Costs/Loss/Expense/Damages)
EXPERT in PRODUCTIVITY ANALYSIS (Production capacity, Optimum manpower)
Education
• Master of Laws (Commercial & Corporate) LL.M London
• Master of Science (International construction Management) M.Sc. NTU S’pore
• Bachelor of Laws LL.B (Hons) London
• Bachelor of Engineering B.Eng. (Civil) NU S’pore
Working Experience
• 27 years of leadership and management in the construction industry
• 19 years as Construction Contracts Commercial Consultant
• 19 years lecturing in the areas of law, management, business, finance & insurance
2
Loss & Expense (L&E)
principles
Loss & Expense
Claims
3
Loss & Expense (L&E)
principles
Loss & Expense Claims arise due to: -
• Delays & EOT
• Changes to the nature of the project
• Disruptions caused by the Employer and/or its agents
• Variations to the contract
4
Loss & Expense (L&E)
principles
Types of Variation Order (VO) Claims (claims
for Works ordered/instructed in writing in
accordance with the contract provisions)
• “True” variations to the contract
• Additional Works required for the project
• New Scope of Works
5
Loss & Expense (L&E)
principles
“True” variations to the contract
• Often changes to quantity and/or quality and/or
methods to be adopted
• Often within the contract contemplation
• Use of contract terms and rates
6
Loss & Expense (L&E)
principles
Variations, in general, for Construction Contracts
come under two(2) broad categories:
Category 1: Variation/Change in Contract Documents
These include: changes to designs / drawings / specifications etc.
Category 2: Variation/Change to Working Conditions
These include: changes to working hours / working methods / sequence of working / acceleration of works etc.
7
Loss & Expense (L&E)
principles
Additional Scope of Works
• Often changes necessary to complete the
project
• Often outside the contract contemplation
• Use of contract terms and rates, only if
provided for if not new terms and rates to apply
8
Loss & Expense (L&E)
principles
New Scope of Works
• Changes by Employer
• Outside the contract contemplation
• New terms and rates to apply
9
Loss & Expense (L&E)
principles
“………. the Contractor undertakes to do the work for a definite sum and he takes the risk of the cost being greater or less than he
expected.”
-Lord Reid’s judgement in
- Davis Contractors Ltd v Fareham Urban District Council [1956] (House of Lords) (U.K.)
Introduction to Claims
10
Loss & Expense (L&E)
principles
Client’s goalsAll Clients have finite resources
They must balance competing goals
11
Loss & Expense (L&E)
principles
Contractor’s goals
All Contractors have finite resources
They must balance competing goals
We need
longer time
12
Loss & Expense (L&E)
principles
Quality v Cost v Time
The risk drivers for the two parties to a construction project are often directly conflicting. Thus, a contract is an attempt to distribute the risk and clearly identify who owns what risk
In the diagram:
if you reduce the time of the project then the cost will go up and the quality will go down.
If you increase the quality then the cost and time are likely to increase.
In any event it is likely that only 2 of the 3 can ever be controlled at the same time.
The contract therefore is a balancing mechanism between the three and if the contract is unbalanced there will be impacts between the three factors.
TimeCost
Quality
Three factors constrain every project.You control two, and only two
13
Loss & Expense (L&E)
principles
14
Loss & Expense (L&E)
principles
Delay & Acceleration to Cost-Time
15
Loss & Expense (L&E)
principles
Examples of problem projects
Time and cost overruns in key public sector projects (UK):
Wembley Stadium £757m £1bn 4 years
16
Loss & Expense (L&E)
principles
Introduction to Claims
Types of Claims
17
Loss & Expense (L&E)
principles
What are claims?
Claims:
are made by the Contractor to the Employer
are requests for additional payment due to:
• non-material breach of the Contract due to:
– action or inaction of the Employer (or its Agents)
– action or inaction of parties brought to the project by the
Employer
• unforeseen circumstances
are often associated with delays or variations
18
Loss & Expense (L&E)
principles
Time & Cost Claims
Time & Cost Claims:
claims that result in an addition to the TIME available for
completion of the Works
claims that result in the payment of money (COSTS) from one party
to another
Claims are submitted in accordance with
procedures defined by the Contract
19
Loss & Expense (L&E)
principles
Establishing “Causes” of Claims
It may not be possible to keep to the Time and Costs as agreed in the Contract due to:
Delays/Changes caused by the Contractor (or its Sub-contractors)
Delays/Changes caused by the Employer (or its Agents)
Delays/Changes caused by events which neither the Contractor or Employer can control [These are “Neutral Events”]
The contract defines how to manage Time and Costs when/if these events occur
20
Loss & Expense (L&E)
principles
Type of Claims
Delay and Extension of Time (EOT) Claims
Disruption & Loss of Productivity Claims
Prolongation Claims
Acceleration Claims
Variation / Change Order Claims
(General) Loss & Expense Claims
21
Loss & Expense (L&E)
principles
Delay(the management of time)
&
Disruption(the management of productivity)
22
Loss & Expense (L&E)
principles
Delay may be either: -
Delay to Progress or Delay to Completion
Delay to progress; delay which affects progress but does not cause the completion date, whether planned or contractual, to change
Delay to completion; delay which affects progress and causes the completion date to change
EOT = Delay to Completion
Delay to Progress vs.
Delay to Completion
23
Loss & Expense (L&E)
principles
Disruption may be described as “Disturbance, hindrance or interruption of a Contractor’s normal work progress, resulting in lower efficiency or lower productivity than would otherwise be achieved”
- SCL Delay and Disruption Protocol
Disruption
24
Loss & Expense (L&E)
principles
Disruption is not necessarily a consequence of delay and neither is
delay to completion a necessary consequence of disruption, although delay
to progress is
Disruption
25
Loss & Expense (L&E)
principles
What is disruption?
It is when work cannot be carried out in a logical, planned and efficient way.
It is when trades end up out of sequence, working in the same area, tripping over each other and being less efficient than normal.
Put simply, disruption is when there is a loss of productivity.
Source: Andrew Hemsley 2007 issue 18
26
Loss & Expense (L&E)
principles
Delay and disruption impact (in different ways) on the two general areas of a contractor’s operations: -
(1) The execution of the work required by the contract – often referred to as the measured works in more traditional contract arrangements
(2) The contractor’s administrative and enabling processes relating to the execution of the work – what may be termed Preliminary and General Items (Prelims)
Delay & Disruption Impact
27
Loss & Expense (L&E)
principles
Extensions of Time: Principles
It may not be possible to keep to the dates agreed in the
Contract due to:
Delays caused by the Contractor
Delays caused by the Employer (or its Agents)
Delays caused by events which neither the Contractor or Employer
can control
• These are “Neutral Events”
The contract defines how to manage time if these events occur
28
Loss & Expense (L&E)
principles
Loss caused by delay or disruption
The prevention principle stops a party benefiting from its
own breach of contract
For example, if the Employer’s actions (or inactions) prevent the
Contractor completing the Works by the agreed Date for
Completion, the Contractor cannot be expected to pay damages
to the Employer for late completion.
In this situation, time becomes “at large” and the Contractor must
complete within a reasonable time.
29
Loss & Expense (L&E)
principles
The Contractor’s obligation to complete the
works within the time stipulated in the contract
operates on the premise that the Employer
does not do anything which has the effect of
impeding the Contractor’s progress.
A breach of this by the Employer constitutes an
“act of prevention”.
Obligations of the Parties
30
Loss & Expense (L&E)
principles
The Contractor’s liability for Liquidated Damages
The Contractor’s Claim against the Employer
The fact that extensions of time are granted on account ofdelays attributable to some act of prevention by theEmployer may afford a basis for a claim by the Contractoragainst the Employer for time related damages anddisruption losses
Significance of EOT
31
Loss & Expense (L&E)
principles
Notice Of Delay (by the Contractor) being
“Condition Precedent” to the Architect’s or
Superintending Officer’s (SO’s) or
Engineer’s granting of Extension Of Time
(EOT) to the Contractor
The Courts do not always take strict positions
of these notice requirements
Notice being “Condition Precedent”
32
Loss & Expense (L&E)
principles
An act of prevention operates to prevent, impede or otherwise
make it more difficult for a Contractor to complete the works by
the date stipulated in the contract. It includes any breach of
contract by the Employer as where the Employer interferes
improperly through the agent in the carrying out of the works or
where he fails to give timely possession of site.
The expression “act of prevention” is also frequently taken to
extend to acts which are, in fact, authorised or at least fall
within the range of events contemplated by the contract, such
as the ordering of extra works or a failure on the part of the
Employer’s Consultants to provide plans and drawings
expeditiously.
Effects of Employer’s Act of Prevention
33
Loss & Expense (L&E)
principles
The legal consequence of an act of prevention is
that the date for completion originally stipulated in
the contract ceases to be the operating date for the
completion of the works.
Effects of Employer’s Acts of Prevention
34
Loss & Expense (L&E)
principles
Unless an extension of time provision exists
which can substitute a new date for completion for
the original completion date, the principle is that
there is no longer a date from which liquidated
damages can run and the Employer thereby loses
his right to enforce the liquidated damages
provisions i.e. this operated to set time at large
and to render inoperative the liquidated
damages clause of the contract.
Effects of Employer’s Acts of Prevention
35
Loss & Expense (L&E)
principles
A delay on the part of the Employer’s Engineer or
Architect in approving drawings or in making critical
decisions which affect the progress of the works can
constitute an act of prevention by the Employer.
There is little difficulty in reading into the time
extension provisions of the major standard forms as to
the power to fix a new completion date on account of
these contingencies
Effects of Late Design/Drawings approvals
36
Loss & Expense (L&E)
principles
The question which then arises is whether the Contractor
can allege that the Architect or Engineer or Superintending
Officer (SO) had failed to discharge his duty to administer
the contract fairly by virtue of the fact that he had failed to
certify the extension of time (EOT) claims within a
reasonable time from the date of the Contractor’s
application for extension.
Acceleration of Works when EOT
Claims have not been Settled
37
Loss & Expense (L&E)
principles
This in turn determines whether the
Contractor is entitled to proceed against the
Employer on an acceleration claim.
This position is well established in the United
States of America (USA).
Acceleration of Works when EOT
Claims have not been Settled
38
Loss & Expense (L&E)
principles
In Norair Engineering Corporation v United States [1981]
(USA), the Employer was a United States government
agency.
The court ruled that an order to accelerate the progress of
the works might be formulated in the form of a request and
need not be couched in the form of mandatory instruction. It
held that, on the evidence, the Contractor was led to
accelerate the works beyond the level which the Contractor
considered was the proper rate of progress in order to avoid
any potential liability for liquidated damages, and that,
accordingly, the Contractor in this case was entitled to recover
his acceleration costs
Acceleration when EOT Claims have not been Settled
39
Loss & Expense (L&E)
principles
USA LAW – CONSTRUCTIVE ACCELERATION
Appeal of Continental Heller Corp [1984] (USA, General Service Board of Contract Appeal [GSBCA]).
The General Service Board of Contract Appeal held for the Contractor finding the following facts as elements which together constituted a constructive acceleration, namely that:-
(1) the Contractor had encountered an excusable delay;
(2) the Contractor had requested for an extension of time (EOT);
(3) the Government refused to grant the extension of time (EOT);
(4) the Government required the Contractor to complete the work within the original performance period;
(5) the Contractor whereupon gave notice of acceleration; AND
(6) the Contractor actually did incur additional costs by accelerating performance.
Acceleration when EOT Claims have not been Settled
40
Loss & Expense (L&E)
principles
ACCELERATION CLAIMS & CONSTRUCTIVE ACCELERATION CLAIMS – UK LAW
According to “Constructive Acceleration” by Russel W. Wray of Wray & Pierce, L.L.P,case law has identified five(5) elements normally required to establish a claim forconstructive acceleration.
Those five(5) elements are as follows: -(i) An excusable delay must exist;(ii) Timely notice of the delay and a proper request for a time extension must have
beengiven;
(iii) The time extension must have been postponed or refused;(iv) The owner must have ordered (either by coercion, direction or some other manner)
the project completed within its original performance period; and(v) The contractor must actually accelerate its performance, thereby incurring excess
costs.
Excusable delay, by Russel W. Wray of Wray & Pierce, L.L.P, means that the contractoris entitled to an extension of time under the contract.
41
Loss & Expense (L&E)
principles
According to “Acceleration” by Daniel Atkinson of Atkinson Law, London, UK, thepossible acceleration measures are in summary, as follows: -(i) Increased resources to reduce the time taken for critical activities. The
increase in resource may at some level have the effect of reducingproductivity and thereby increasing unit cost of construction. There willnormally be an optimum level of resource for any one activity.
(ii) Increased man hours is a means of increasing resource input, but willintroduce inefficiency and both quality and health and safety issues.
(iii) Incentives will motivate labour to increased productivity.(iv) Changed method of working may open up additional workforces or
workplaces as well as introducing economies in the use of plant andequipment.
(v) Resequencing work is a fundamental part of managing the progress of thework and is why float is always required on most of the activities on a project.
ACCELERATION CLAIMS & CONSTRUCTIVE ACCELERATION CLAIMS – UK LAW
42
Loss & Expense (L&E)
principles
There may be more substance to an
acceleration claim arising from a
Superintending Officer’s or an Engineer’s or an
Architect’s refusal to grant an extension of time
(EOT) where the refusal is triggered directly by
some breach or overt act on the part of the
Employer
Acceleration of Works when EOT
Claims have not been Settled
43
Loss & Expense (L&E)
principles
Consequences of Acceleration
(1) “Out of Sequence” Work
(2) Idle Time
(3) Lack of proper documentation
Acceleration of Works when EOT Claims
have not been Settled
44
Loss & Expense (L&E)
principles
“Float” in
Programmes
45
Loss & Expense (L&E)
principles
“Float” is to absorb inevitable delays
• inclement weather• strikes• breakdowns• non-performance of sub-contractors• defects• etc.
46
Loss & Expense (L&E)
principles
Under most forms of Contract:
• Early completion within time for
completion
• Programming tolerances
• EOT for delays to progress
• Fair entitlement to EOT
• Therefore, Contractor owns float under
the Contract
47
Loss & Expense (L&E)
principles
Concurrent Delays
48
Loss & Expense (L&E)
principles
Concurrent Delays
“A period of project overrun which is caused
by two or more effective causes of delay which
are of appropriate equal causative potency.”
49
Loss & Expense (L&E)
principles
Concurrent Causes & Sequential Effect
Concurrent Causes
CA
CB
(Rare)
Sequential Effect
DA
DB
50
Loss & Expense (L&E)
principles
Sequential Causes & Concurrent Effect
Sequential Causes
CX
CY
(Common)
Concurrent Effect
DX
DY
51
Loss & Expense (L&E)
principles
Notices of Delay
52
Loss & Expense (L&E)
principles
EOT gives more time to
complete concurrent
activities
LDs cannot be levied for
period of Employer’s delay
53
Loss & Expense (L&E)
principles
Notice is not condition precedent for granting
EOT under some contracts
Otherwise risk to Employer of losing LDs
However, notice is condition precedent for
financial claims in many contracts
54
Loss & Expense (L&E)
principles
Claims (by the Contractor to recover Costs)
Loss & Expense
55
Loss & Expense (L&E)
principles
Claims: Principles
“Claims” = requests made by Contractors for additional
payment to account for their Loss or Expense caused by
the actions of others.
Claims may arise due to:
delays and Extensions of Time;
changes to the nature of the project;
disruption caused by the Employer (or its Agents); or
variations to the Contract.
56
Loss & Expense (L&E)
principles
Extension of Time vs. Loss and Expense
Extensions of Time:
Decisions are made on the impact of a EOT Event on the time required to complete the Works
Loss and Expense:
Claims are made by the Contractor to recover additional expenditure or loss arising due to delay and/or disruption caused by others
There is no direct link between Extension of Time claims and Loss & Expense claims
An Extension of Time does not always justify a claim for Loss & Expense
57
Loss & Expense (L&E)
principles
Types of claim (for loss and/or expense)
Contractual claims
Follow the procedures defined by the Contract
• Quick and (usually) simple to settle
Common law claims
Result from breaches of implied Contract terms
Can be recovered via Contract or litigation
Quantum meruit claims
If no prior agreement of cost
Ex gratia claims
58
Loss & Expense (L&E)
principles
Introduction to Claims
Supporting Documents
59
Loss & Expense (L&E)
principles
Supporting a claim
The Contractor must support every claim with full and
detailed records, including:
Relevant Contract Documents
Relevant Contract Conditions
Master Programme
Contractor’s own routine records
• Including Clerk of Work’s certification of their accuracy or
record (but not of claim validity)
Contractor’s additional records specific to the claim
• Including Site Meeting Minutes, relevant correspondence,
Progress Reports, photographs, emails, Time Sheets/Cards,
Daywork Records, Daily Site Report etc.
60
Loss & Expense (L&E)
principles
Heads of Claim
The documentation submitted by the Contractor
to support a claim for loss and/or expense is
called a “Heads of Claim”
The Heads of Claim must clearly state the
payment requested for each Extension of
Time event“Global” claims will only be accepted if costs cannot be isolated
61
Loss & Expense (L&E)
principles
Heads of Claim
The Heads of Claim must document:
Additional preliminaries costs
• Site infrastructure and plant costs
Reduced labour productivity (Disruption Analysis)
Extra waste or unused materials
Increase in the cost of resources (e.g. inflation)
Extra head office overheads and profit required
Additional finance charges
Correspondence, site meetings, photographs, etc.
62
Loss & Expense (L&E)
principles
• additional payment in respect of prolongation of Contractor’s resources
• extensions of time do not give automatic entitlement to payment for prolongation
• can be reduced by Contractor’s culpable delay, particularly for damages
Prolongation
63
Loss & Expense (L&E)
principles
Quantity Surveyor’s duty to determine the value of
variations
Meaning of:
- “same or similar character”
- “same or similar conditions and
circumstances”
- “valuation based on the rates in the Contract”
64
Loss & Expense (L&E)
principles
Elements of Prolongation
65
Loss & Expense (L&E)
principles
Prolongation includes:
• plant hire / depreciation • general labour • manufacturing facilities etc • site staff • offices and equipment • utility services• transportation and storage
66
Loss & Expense (L&E)
principles
• safety and quality• bonds, insurances, warranties • head office services• external consultants • increased costs due to inflation • increased cost of overheads • idle resources due to inclement weather • profit (variations)• financing
Prolongation includes (contd):
67
Loss & Expense (L&E)
principles
Allow for recovery through direct value of variations
68
Loss & Expense (L&E)
principles
Notices of Claim
69
Loss & Expense (L&E)
principles
Time barring provisions of Contract
Breach of Contract
Effect of Contractor’s culpable delay on
payment for prolongation
70
Loss & Expense (L&E)
principles
Concurrent Delays
71
Loss & Expense (L&E)
principles
Periods of prolongation
for
assessment of cost or valuation
72
Loss & Expense (L&E)
principles
Prolongation claims due to VARIATIONS must be claimed using TIME-RELATED Preliminary Rates from the Contract BQ
73
Loss & Expense (L&E)
principles
Prolongation claims due to Employer’s breach of Contract can be claimed using TIME-RELATED Actual Site Overhead Costs
74
Loss & Expense (L&E)
principles
Prolonged Costs
Based on As-Built Programme after running Delay & Disruption Analysis
Includes:
(1) Prolonged employment of resources
(2) Committed additional resources
(3) Delayed employment of resources
Excludes:
(4) Postponed employment of resources