LOWER BAKER
UNIT 4
POWERHOUSE
-
7/21/2019 Lower Baker Presentation (1)
2/43
INTRODUCTIONS
DANNY ROBERTSFIELD ENGINEER
JASON MCLAUCHLINPROJECT ENGINEER
-
7/21/2019 Lower Baker Presentation (1)
3/43
PROJECT TEAM
-
7/21/2019 Lower Baker Presentation (1)
4/43
32 MW Francis Turbine/Gen
1000 Steel Lined Power Tunnel
Subterranean Concrete Structure
and Tailrace: 7,949CY placed Mechanical and Electrical Building
Systems
Integrated Facility Controls of
Units 3 and 4 Upgraded Unit 3 controls and
Governor
Synchronous Bypass
THE PROJECT
-
7/21/2019 Lower Baker Presentation (1)
5/43
Manage In-streamFlows of the Baker andSkagit Rivers
Restore FacilityGenerating CapacityLost in 1960s landslide
Maintain Water Supplyto Lower Baker AdultFish Trap
PROJECT GOALS
-
7/21/2019 Lower Baker Presentation (1)
6/43
Design-Build Delivery
Collaborative Team Approach
Focus on achieving PSEsperformance requirements
Phased Design and
Construction
PROJECT STRATEGY
-
7/21/2019 Lower Baker Presentation (1)
7/43
CONSTRUCTION
-
7/21/2019 Lower Baker Presentation (1)
8/43
PHASE I - EXCAVATION
-
7/21/2019 Lower Baker Presentation (1)
9/43
PHASE 1 EXCAVATION
-
7/21/2019 Lower Baker Presentation (1)
10/43
PHASE 1 EXCAVATION
-
7/21/2019 Lower Baker Presentation (1)
11/43
PHASE 1 EXCAVATION
-
7/21/2019 Lower Baker Presentation (1)
12/43
PHASE 1 EXCAVATION
-
7/21/2019 Lower Baker Presentation (1)
13/43
PHASE IITUNNELING
-
7/21/2019 Lower Baker Presentation (1)
14/43
PHASE II - TUNNELING
Surge Shaft Tie In
1000LF
Drill and shoot 12 dia steel lining
Full Penetration Welding
Carboline Coating
-
7/21/2019 Lower Baker Presentation (1)
15/43
PHASE II - TUNNELING
Unit 4 Tie-In
Bottom of 270
Surge Shaft
50LF in 22day
shutdown
Laser Scanned
-
7/21/2019 Lower Baker Presentation (1)
16/43
PHASE II - TUNNELING
-
7/21/2019 Lower Baker Presentation (1)
17/43
PHASE II - TUNNELING
-
7/21/2019 Lower Baker Presentation (1)
18/43
PHASE II - TUNNELING
-
7/21/2019 Lower Baker Presentation (1)
19/43
PHASE IIIPOWERHOUSE
-
7/21/2019 Lower Baker Presentation (1)
20/43
PHASE III - POWERHOUSE
Draft TubeElbow
Liner
-
7/21/2019 Lower Baker Presentation (1)
21/43
PHASE III - POWERHOUSE
Scrollcase andStay Vanes
-
7/21/2019 Lower Baker Presentation (1)
22/43
PHASE III - POWERHOUSE
Inlet Pipelowering
into
position forfit up to
Scroll Case
-
7/21/2019 Lower Baker Presentation (1)
23/43
PHASE III - POWERHOUSE
Fitting PitLiner onto
Scroll Case
-
7/21/2019 Lower Baker Presentation (1)
24/43
PHASE III - POWERHOUSE
Structural work builtconcurrently with
embedment of
turbine components
-
7/21/2019 Lower Baker Presentation (1)
25/43
PHASE III - POWERHOUSE
GeneratorFoundation Core
-
7/21/2019 Lower Baker Presentation (1)
26/43
PHASE III - POWERHOUSE
Removable Draft Tube Cone Tripping Runner/Turbine Shaft
-
7/21/2019 Lower Baker Presentation (1)
27/43
PHASE III - POWERHOUSE
Installing Wicket Gates Runner and Turbine Shaftlowered onto Bottom Ring
-
7/21/2019 Lower Baker Presentation (1)
28/43
PHASE III - POWERHOUSE
LoweringHead Cover
over the
TurbineShaft
-
7/21/2019 Lower Baker Presentation (1)
29/43
PHASE III - POWERHOUSE
LoweringBottom Ring
into
Powerhouse
-
7/21/2019 Lower Baker Presentation (1)
30/43
PHASE III - POWERHOUSE
LowerBearing
Bracket
and Statorprepped
for Rotor
install
-
7/21/2019 Lower Baker Presentation (1)
31/43
PHASE III - POWERHOUSE
Tipping the Rotor 90tons
-
7/21/2019 Lower Baker Presentation (1)
32/43
PHASE III - POWERHOUSE Shaft Coupling
Lower Bearing Assembly
-
7/21/2019 Lower Baker Presentation (1)
33/43
PHASE III - POWERHOUSE
Installingthe Slip Ring
Housing
-
7/21/2019 Lower Baker Presentation (1)
34/43
PHASE III - POWERHOUSE
Turbine Pit and Coolingwater piping systemsnearing completion
-
7/21/2019 Lower Baker Presentation (1)
35/43
PHASE III - POWERHOUSE
Gate Guides for theDraft Tube Gate
-
7/21/2019 Lower Baker Presentation (1)
36/43
PHASE III - POWERHOUSE
GSU andTransmission
Structures
-
7/21/2019 Lower Baker Presentation (1)
37/43
PHASE IVTAILRACE
-
7/21/2019 Lower Baker Presentation (1)
38/43
PHASE IV - TAILRACE
-
7/21/2019 Lower Baker Presentation (1)
39/43
PHASE IV - TAILRACE
-
7/21/2019 Lower Baker Presentation (1)
40/43
PHASE IV - TAILRACE
-
7/21/2019 Lower Baker Presentation (1)
41/43
FINISHED PRODUCT
-
7/21/2019 Lower Baker Presentation (1)
42/43
Tunneling Operation Extremely Accurate
Achieved all Tolerances in Stacking Unit
Digital Upgrade of Unit 3 Control Room and
hydraulic system Commercially Operational 100 days ahead of
schedule
Successful Overall Design Coordination withOwner provided Unit
No interruptions to ongoing Unit 3 generation
SUCCESSFUL PROJECT
-
7/21/2019 Lower Baker Presentation (1)
43/43
LOWER BAKER
UNIT 4
POWERHOUSE
QUESTIONS?