ls2-lhc status · • the first (a26r8) will be reconnected this week except x-ray and leak tests....
TRANSCRIPT
LS2-LHC StatusLMC, 3rd July 2019
Marzia Bernardini, Sebastien Bustamante, Michela Pirozzi, Estrella Vergara (EN-ACE-OSS)
Thanks to the contributions of groups and WSS!
LMC, 29th May 2019
Content
• LS2 general status
• LS2 LHC activities progress
• Conclusions
2
LMC, 29th May 2019
LS2 Master Schedule (EDMS ACC-PM-MS-0002 v.1.4)
22 months of works
3
LH
C M
achin
e b
ack to B
E-O
P
W
27
LMC, 29th May 2019 4
The Frame: where we are Sequencing beginning LS2
• Powering tests and training quench campaign
• Machine Lockout:
• Cryogenics preparation for Christmas closure
& cryo reconditioning after Christmas
• ElQA @ cold
• Warm up at ambient temperature
• Vacuum leak tests & Inspection (IV and BV)
• Cryoplant capacity tests
• ElQA @ warm
• Tightness tests and cryo lockout
Sequencing End LS2
• Pressure tests
• ElQA @ warm
• Vacuum leak tests & BV inspections
• Cool down & vacuum leak tests
• Machine levelling (survey) at cold
• ElQA @ cold
• DSO test (16th Oct. 2020)
• Powering tests and training quench
campaigns Machine to 3 shifts BE-OP
W44-2020
- Major cryogenics maintenance
- DISMAC (s12 +s78 +s81)
- All other works (HL, Consolidation, …)
LMC, 29th May 2019
LHC-LS2 EN-CV Maintenance
5
Point Activity Week Start Start Date End Date Duration Status
LHC5
SF - CV Maintenance W50 10-Dec-18 01-Feb-19 6 wks Completed
SU - AC Maintenance W50 10-Dec-18 14-Dec-18 1 wk Completed
USC55 - CV Maintenance W50 10-Dec-18 08-Mar-19 11 wks Completed
SU - Ventilation Maintenance W10 04-Mar-19 29-Mar-19 4 wks Completed
Ventilation Maintenance in RRW14W15
01-Apr-1908-Apr-19
30-Apr-19 4 wks Not Started
SF+SU reduced - CV Maintenance W50 07-Dec-20 08-Jan-21 3 wks Not Started
USC55 reduced - CV Maintenance W3 11-Jan-21 29-Jan-21 3 wks Not Started
Point Activity Week Start Start Date End Date Duration Status
LHC6
UW, UA, RE - CV Maintenance W40 30-Sep-19 25-Oct-19 4 wks Not Started
SF - CV Maintenance W44 28-Oct-19 10-Jan-20 9 wks Not Started
SU - CV Maintenance W3 13-Jan-20 07-Feb-20 4 wks Not Started
UW reduced - CV Maintenance (TBC) W28 06-Jul-20 24-Jul-20 3 wks Not Started
SF+SU reduced - CV Maintenance (TBC) W46 09-Nov-20 27-Nov-20 3 wks Not Started
Point Activity Week Start Start Date End Date Duration Status
LHC8
SF - CV Maintenance W7 10-Feb-20 08-Apr-20 8.5 wks Not Started
SU - CV Maintenance W16 14-Apr-20 19-May-20 5 wks Not Started
UW, UA , RE - CV Maintenance W21 20-May-20 18-Jun-20 4 wks Not Started
SF+SU reduced - CV Maintenance W42 12-Oct-20 30-Oct-20 3 wks Not Started
UW reduced - CV Maintenance W42 12-Oct-20 30-Oct-20 3 wks Not Started
Point ActivityWeek Start
Start Date End Date Duration Status
LHC1
SU1 - Ventilation Maintenance (RR, RE) W51 17-Dec-18 21-Dec-18 1 wk Completed
SU1 - Cooling Maintenance W2 07-Jan-19 01-Feb-19 4 wks Completed
SF - CV Maintenance - Dependant from SPS tests in BA6
W4 21-Jan-19 29-Mar-19 10 wks Completed
USA15 + US15 cooling + ventilation maintenance - Impact on LHC Tunnel
VentilationW6 04-Feb-19 01-Mar-19 4 wks Completed
USA15 EM W10 04-Mar-19 29-Mar-19 4 wks Completed
SF+SU reduced - CV Maintenance W50 07-Dec-20 08-Jan-21 3 wks Not Started
USA reduced - CV Maintenance + ventilation RR, RE
W3 11-Jan-21 29-Jan-21 3 wks Not Started
Point ActivityWeek Start
Start Date End Date Duration Status
LHC2
UW - CV Maintenance -Cooling, UA, RE W40 30-Sep-19 01-Nov-19 5 wks Not Started
SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started
SU - CV Maintenance W16 15-Apr-20 20-May-20 5 wks Not Started
UW reduced - CV Maintenance -EG Only W34 17-Aug-20 14-Sep-20 4 wks Not Started
SF+SU + Ventilation UA- CV reduced Maintenance
W45 02-Nov-20 20-Nov-20 3 wks Not Started
Point ActivityWeek Start
Start Date End Date Duration Status
LHC4
SF - CV Maintenance W4 20-Jan-20 13-Mar-20 8 wks Not Started
SU - CV Maintenance W12 16-Mar-20 14-Apr-20 4 wks Not Started
UW - CV Maintenance - Cooling, UA, RE W21 22-May-20 19-Jun-20 4 wks Not Started
UW reduced - Cooling Maintenance -Ventilation reduced
W37 07-Sep-20 28-Sep-20 3 wks Not Started
SF+SU reduced - CV Maintenance W42 12-Oct-20 30-Oct-20 3 wks Not Started
LMC, 29th May 2019
LHC-LS2 EN-EL Maintenance (EDMS ELG-ADMIN-QE-0033 V.19 )
6
* NO ACCESS in SURFACE and UNDERGROUNG (Guardian at the point entrance)
Maintenance NO ACCESS* AUG NO ACCESS*
Point Day Point Day
LHC1 + ATLAS 6 -10 January 2020 (W2) LHC1 + ATLAS 13 January 2020 (W3)
LHC18 + SM18 23-25 April 2019 (W17) LHC18 + SM1826 April 2019 (W17)
11 February 2020 (W7)
LHC2 + ALICE11-14 June 2019 (W24) – Access OK
LHC2 + ALICE 27 January 2020 (W5)20-24 January 2020 (W4)
LHC3 + PM32 9-12 March 2020 (W11) LHC3 + PM3230 April 2019 (W18)
13 March 2020 (W11)
LHC417-20 June 2019 (W25) – Access OK
LHC47 Oct. 2019 (W41)
24-28 February 2020 (W3) 2 March 2020 (W10)
LHC5 + CMS 20-24 May 2019 (W21)
LHC5 + CMS 27 May 2019 (W22) TO BE RESCHEDULED
24-27 June 2019 (W26) – Access OK 5 May 2020 (W19)
LHC63-6 June 2019 (W23) TBC – Access OK
LHC6 20 Sept. 2019 (W38)17-19 Sept. 2019 (W38)
LHC7 23-27 Sept. 2019 (W39) LHC7 30 Sept. 2019 (W40)
LHC815-19 April 2019 (W16) – Access OK
LHC8 16 Dec. 2019 (W51)9-13 Dec. 2019 (W50)
TEST SECOURS (10min)All points on 19th December
(6am – 6:10am) (W51)Prevessin 4 April 2020 (W14)
Meyrin + Adm. 4th January 2019 (W1)
LMC, 29th May 2019
LHC-LS2 EN-EL: 66 kV Maintenance in progress
7
400 kV maintenance 22 July – 27 Sept 2019 (W30-39)
4 July – 27 Sept 2019 (W27-39)
66 kV maintenance (reduced consumption 15MVA LHC, 90 MVA CERN)
28 Mai – 19 July 2019 (W22-29)
28 June– 4 July 2019 (W26-27)Dates updated on 18/06/19
LMC, 29th May 2019
DISMAC start of activities
8
7/2/2019
8-1 1-2 2-3 3-4 4-5 5-6 6-7 7-8
BL
M
rem
oval VSC Done! N/A N/A N/A N/A Done! Done! Done!
SIT Done! Done! Done! Done! Done! Done! Done! Done!
Diodes Done! Done! Done! Done! Done! Done! Done! Done!
IC o
pen
ing VSC Done! N/A N/A N/A N/A Done! Done! Done!
SIT Done! Done! Done! Done! Done! W29 Done! W28
DIODES Done! Done! Done! In progress W28 W30 W32 W34 (4IC
training)
Consolidation In progress In progress In progress W28 W31 W36 W39 W43
Reclosing & FT W38 W41 W44 W47 W50 W3/2020 W6/2020 W9/2020
BLM installation W47 W50 W2/2020 W6/2020 W9/2020 W13/2020 W16/2020 W19/2020
ELQA LV In progress In progress W30 W35 W39 W42 W46 W49
HV In progress
(Monday)
In progress
(Tuesday)
W28 W31 W36 W39 W43 W46
Updated on 2nd July 2019
LMC, 29th May 2019
• No accident so far
• Many non-conformities are encountered, including pre-existing ones
Their management is efficient and implies frequent procedures optimisations and definition of new
procedures ; it is slowing down the progress
• DISMAC is globally progressing according to schedule (about one week ahead of schedule)
• Confident that the global schedule can be respected
• BUT the rate of 10 ICs is not yet achieved sustainably for the consolidation of the diodes insulation
itself ; resources were reallocated
• Updates will be required (impact to be assessed) :WP11 cryoassemblies & Q16L2 and C16L2
removal for beam screens exchange
• DISMAC QA review on 11-12 July 2019
Courtesy J.Ph.TockDISMAC (see LS2C @ Friday 28th June)
DISCO: Diode InSulation Consolidation
SIT: Special Intervention Team
CLEM: Current Leads Maintenance
9
LMC, 29th May 2019
• 19/22 cryomagnets have been removed from the tunnel; they were
disconnected and prepared for transport on time. Priority is put on this,
to avoid co-activity with transport asap.
All will be removed for 24th July-19.
• There is work in 6 sectors in parallel
• The first (A26R8) will be reconnected this week except X-ray and leak
tests. There could be some delay in cryomagnets reconnection but
remaining within the DISMAC time window
• The second cryodipole for BIHL study (C21R6) is under disconnection
• In-situ fit-test of the first flowmeter for BIHL study is about to start
Courtesy J.Ph.TockDISMAC (see LS2C @ Friday 28th June)
10
LMC, 29th May 2019 11
LHC-LS2: Magnet exchange status
• 19/26 removed
• 19/26 reinstalled Magnet
locationMagnet Week Start Date Transport
Sector 45 B24L5 W2701-07-2019
03-Jul-19Removal old magnet + stdby in UL55
Sector 45 B24L5 W2702-07-2019
04-Jul-19Old magnet transport from P5 to UJ22
W27 05-Jul-19 Convoy transport from UJ22 to UL55
Sector 67 C21R6 W28 08-Jul-19 Removal old Magnet and back to UL55
Sector 67 C21R6 W28 09-Jul-19 Old magnet transport from UL55 to UJ22
Sector 45 B24L5 W28 10-Jul-19 New magnet transport from UJ22 to UJ44
Sector 45 B24L5 W28 11-Jul-19 Transport + Installation new magnet + go to P6
Sector 67 B13R6 W28 12-Jul-19 Removal old Magnet and back to P4
Sector 67 B13R6 W29 15-Jul-19 Old magnet transport from P4 to UJ22
Sector 67 C21R6 W29 16-Jul-19 New magnet transport from UJ22 to P5
Sector 67 C21R6 W29 17-Jul-19 Transport + Installation new magnet + go back to
W29 18-Jul-19 Convoy back to UJ22
Sector 67 B13R6 W30 22-Jul-19 New magnet transport from UJ22 to P5
Sector 67 B13R6 W30 23-Jul-19 Transport + Installation new magnet + go back to
W30 24-Jul-19 Convoy back to UJ22
Sector 81 - Completed
Sector 12 - Completed (Ecxept LEBR for CC)
Sector23 - Completed (Ecxept LECL for CC)
Sector34 - Completed
LMC, 29th May 2019 12
Where we are: HL-LHC UPRsUPR activities before breakthrough and machine de-installation
• Rerouting of all the services: GSM, Optical fibers, Safety cables and panel, 18 kV and Fire detection
• UPR Survey and RP test cores:
• UPR13: week 21 (23.05.2019)
• UPR17: week 16 (15.04.2019)
• UPR53: week 18 (29.04.2019)
• UPR57: week 24 (11.06.2019)
Nex
tm
ilest
on
es–
Nex
tm
ain
act
ivit
ies
-O
n g
oin
g–
Co
mp
lete
d
Activity During LS2
UPR13 UPR17 UPR53 UPR57
Fire detection rerouting
Survey and RP cores
Cable trays installation and cable pulling in LHC
(Start)
2020 Oct-19 Dec-19 Dec-19
UPR53 UPR13 UPR57 RP Samples
LMC, 29th May 2019
LHC-LS2 activities progress
(from 29th May to 3rd July 2019)
13
LMC, 29th May 2019 14
Where we are: Sector 1-2 (1/2)N
ext
mile
sto
nes
–N
ext
ma
in a
ctiv
itie
s-
On
go
ing–
Co
mp
lete
d
• Flow meter in P18 installed already completed
• Roman Pot station maintenance postponed to August
• R2E in RR17 completed ahead of schedule
• Magnet reconnexion duration extended
• Cryostat Connexion replacement postponed to October 2019
• DISMAC local ELQA ahead of planning
• Longitudinal monitoring system Q2 and Q3 completed ahead
of baseline planning
• Flow meter installation in P18 QUI and WRL
• Optical Fiber campaign in PM15 pit completed
• Investigation on QRL Leak in Vacuum SS B QRL bellow opening
in progress (in preparation of Helium leak tests)
LHC-LIU in TI2:
• TI2 Line is vented
• TCDI electrically locked and disconnected
• TCDI removal in September 2019
• Cabling campaign in December 2019
• TCDI installation in January 2020
Request from TREX@26th June 2019 in TI18
QRL bellow opening S.1-2
LMC, 29th May 2019
Where we are: LSS1R-LSS2L
15
LSS1R
• LH1ORS0-FL202 (EN-EA) (Only Pit an US15): Optical fibre campaign
completed
• PT100 upgrade on DFBX completed
• AFP activities: movement test done
• ZDC disinstallation and transport completed
• Triplet area: Longitudinal monitoring system Q2 and Q3 tracing and
drills completed, installation of monitoring system in 2 weeks
LSS2L
• PT100 upgrade on DFBX completed
• Triplet area: Longitudinal monitoring system Q2 and Q3 completed
• Survey alignment Q12-Q12
• Alignment secondary components (Q7-Q7)
• TDI removal , Mark the new position done - Mounting of rails to support
the TDIS completedNex
tm
ilest
on
es–
Nex
tm
ain
act
ivit
ies
-O
n g
oin
g–
Co
mp
lete
d
Crane installation for TDIS ZDC disinstallation
LMC, 29th May 2019 16
Where we are Sector 2-3N
extm
ilesto
ne
s–
Ne
xtm
ain
activitie
s-
On
go
ing–
Co
mp
lete
d
General Status
• Racks ODH consolidation + maintenance
• R2E 600A-10V consolidation
• 18kV, 3.3kV and LV machine network Maintenance
• Optical Fiber campaign
LSS2R
• PT100 upgrade on DFBX completed
• Triplet area: Longitudinal monitoring system Q2 and Q3
marking and drills completed, installation in 2 weeks
• TCLIA A4R2 : Mechanical works, removal and transport
completed; floor marking, drills in 2 weeks, installation and
bake out in 3 weeks
• Survey alignement@warm Q12-Q12 on going
LSS3L
• -
Survey Alignment TCLIA removal
• In-situ a-C coating SAM Q5-Q6 postponed to
September
• Longitudinal monitoring system Q2 and Q3
completed ahead of baseline planning
• DISMAC local ELQA ahead of planning
LMC, 29th May 2019 17
Where we are: Sector 3-4
General Status
• 48V Maintenance
• Optical Fiber campaign
• UPS Maintenance
Ne
xtm
ilesto
ne
s–
Ne
xtm
ain
activitie
s-
On
go
ing–
Co
mp
lete
d
LSS3R
• -
LSS4L
• Survey measurements@warm Q12-Q12 completed
• Pumping crosses leak check ACS modules completed
• Removal BSRT redundant support completed
• Mechanical work for D3L4 pumping port relocation in 2 weeks
• Soupapes replacement and scaffolding installation in 3 weeks
Survey measurement
• Wire Scanner sectorization duration
extended up to December 2019 due to the
need of a technology modification on the
beam wire scanner (new activity)
• BSRT mirror installation and works duration
extended up to December 2019
• Magnet reconnection ahed of planning
LMC, 29th May 2019 18
Where we are: Sector 4-5General Status
• EL Maintenance week completed
AUG test @P5 postponed
• 18kV, 3.3kV and LV machine network Maintenance
(access ok)
• Gaz and ODH maintenance 2019 + Consolidation
Racks ODH
• UPS maintenance
• PZ45 replacement
• UJ43, UJ47 PAD/MAD Upgrade
• PZ45 MAD extension
• Water cooled cables replacement on DFBA in progress
in RR53
• LHC600A-10V consolidation Batch 1
• 13kA EE switch maintenance
• Optical fiber campaign
Nex
tm
ilest
on
es–N
ext
ma
in a
ctiv
itie
s-
On
go
ing–
Co
mp
lete
d
• Wire scanner sectorisation: E5R4/E5L4 activities to
be rescheduled due to the need of a technology
modification on the beam wire scanner (new
activity)
• BSRT mirror installation and works duration
extended up to December 2019
• 13kA switch refurbishement already started
• RF Ball in S4-5 on hold
• Change of faulty VVGSH.36R4.B ahead of
planning
LMC, 29th May 2019
LSS4R : ACS module validation
19
C1B1 Antenna problem
• Detected during the cavity conditioning in 2017: the field level ~10
dB less than expected (wrong tune and coupler position were ruled
out)
• Measuring the transmission between operational and spare antenna
showed indeed 10 dB less signal on C1B1 than on other cavities,
• Since April 2017 the cavity is operated using the spare antenna.
Activities to be performed:
• Opening the side panel and perform RF measurements and validation
• If nothing is detected Leak check
According to leak check : Option 1 there is a leak ACS module removal and swap
Option 2 no leak detected cable reconnection and side panel closing performed
LMC, 29th May 2019 20
Where we are: LSS4R – LSS5LN
extm
ilesto
ne
s–
Ne
xtm
ain
activitie
s-
On
go
ing–
Co
mp
lete
d
LSS4R
• Survey measurements@warm Q12-Q12 completed
• ACS module validation completed no needs to replace the ACS module
• Pumping crosses leak check ACS modules completed
• Removal BSRT redundant support completed
• Mechanical works for faulty VVGSH.36R4.B on going
• Mechanical works for D3R4 pumping port relocation in 2 weeks
• Soupapes replacement and scaffolding installation in 3 weeks
LSS5L
• PT100 upgrade on DFBX completed
• ZDC disinstallation and transport completed
• Optical fibre campaign LH5ORS0-FL202 (only Pit and UJ56) in 2 weeks
• Triplet area: Longitudinal monitoring system Q2 and Q3 in 3 weeks
Survey measurements
??????
LMC, 29th May 2019 21
Where we are: Sector 5-6
• 18kV, 3.3kV and LV machine network Maintenance
• Gaz and ODH maintenance + Consolidation Racks
• UPS Maintenance
• 13kA EE switch maintenance
• Water cooled cables replacement on DFBL in progress in RR57
• 48V Maintenance
• Optical fiber campaign
Nex
tm
ilest
on
es–
Nex
tm
ain
act
ivit
ies
-O
n g
oin
g–
Co
mp
lete
d
• Vacuum faulty gauge change to be rescheduled
• Survey Core in LSS5R postponed
• RF Ball in S5-6 on hold
• MKD Tests postponed to Mid-August
• 48V Maintenance postponed to mid-July
• UPS Maintenance
LMC, 29th May 2019 22
Where we are: LSS5R – LSS6LN
ext
mile
sto
nes
–Nex
tm
ain
act
ivit
ies
-O
n g
oin
g–
Co
mp
lete
d
LSS5R
• PT100 upgrade on DFBX completed
• ZDC disinstallation and transport completed
• Optical fibre campaign LH5ORS0-FL202 (only Pit and UJ56) in 2 weeks
LSS6L
• New MKBV transport and installation done : Alignment next week
• Cable campaign LH6UGT0-CL201 in UA63 completed
• A4L6 NC 3 RF fingers bake out and NEG completed, X-Ray done
Cable campaign LH6UGT0-CL201
TE-VSC works for A4L6
LMC, 29th May 2019 23
Where we are: Sector 6-7
• 48V Maintenance
• UPS Maintenance
• 18kV, 3.3kV and LV machine network Maintenance
• Gaz and ODH maintenance + Consolidation Racks ODH
• 13kA EE Switch Maintenance
• Cryo Maintenance
• MKD-MKB Upgrade
• Validation Test on MKD Generators postponed to mid-August
Nex
tm
ilest
on
es–
Nex
tm
ain
act
ivit
ies
-O
n g
oin
g–
Co
mp
lete
d
• Cryo Flowmeter installation postponed to 2020
• MKD Tests postponed to Mid-August
• BTVSE reparation duration augmented
• TCDQ maintenance started ahead of planning
• RF Finger NC already completed
QUICB General Maintenance
UPS maintenance
13kA EE switch maintenance
LMC, 29th May 2019 24
Nex
tm
ilest
on
es–
Nex
tm
ain
act
ivit
ies
-O
n g
oin
g–
Co
mp
lete
d
Where we are: LSS6R – LSS7L
LSS6R
• Survey measurement@warm Q12-Q12 next week
• Cable campaign LH6UDT0-CL201 in UA67 done
• Re-installation of BTSVE completed: new removal due to problems
arise during re-installation, maintenance and re-installation in 3 weeks
• A4R6 RF fingers NC NEG completed, X-ray next week
LSS7L
• RP VETO No Access until 11/07/2019
• Pulling Cable campaign LH7UGT0-CL201, HL7HIL0-CC01 in 3 weeks
• Optical fibre campaign LH7ORS0-FL202 (only Pit and UJ76) in 3
weeks
TE-VSC works for A4R6
LMC, 29th May 2019 25
Where we are: Sector 7-8
• LHC PAD/MAD Upgrade
• UPS Maintenance
• PM76 Lift replacement in progress
• LSS7: RP VETO No Access
• 48V Maintenance
• Gaz and ODH maintenance + Consolidation Racks ODH
• Red Phone maintenance
• Optical fiber campaign
Ne
xtm
ilesto
ne
s–
Ne
xtm
ain
activitie
s-
On
go
ing–
Co
mp
lete
d
PM76 lift replacement
• UPS Maintenance RE78• PM76 duration extended of 1week
• 13kA EE maintenance preparatory works
completed
• TANB installation postponed 1 week
• DISMAC IC Opening already started
LMC, 29th May 2019 26
TANB removal
Nex
tm
ilest
on
es–
Nex
tm
ain
act
ivit
ies
-O
n g
oin
g–
Co
mp
lete
d
Where we are: LSS7R – LSS8L
LSS7R
• RP VETO No Access
• Pulling Cable campaign LH7UPT0-CL201, HL7HIL0-CC03 in 3 weeks
• Optical fibre campaign LH7ORS0-FL202 (only Pit and UJ76) in 3
weeks
LSS8L
• PT100 upgrade on DFBX completed
• Triplet area: Longitudinal monitoring system Q2 and Q3 installation on
going
• TANB works: removal, mark on the ground and drills completed;
installation, alignment next week, bake out in 2 weeks
• In-situ a-C coating Q5L8 in 2 weeks
LMC, 29th May 2019 27
Where we are: Sector 8-1• SD8 PR722 crane replacement completed
• Optical fiber campaign
• Cryo maintenance
LHC-LIU in TI8:
• TI8 line is vented and line opening is done
• 6/6 TCDI removed
• Drills for support installation
• RH87 cryo platform cutting
• Cable tray folding in RH87
• Lifting crane installation
Nex
tm
ilest
on
es–
Nex
tm
ain
act
ivit
ies
-O
n g
oin
g–
Co
mp
lete
d
• A28R8 reconnection duration extended
• Roman Pot station maintenance postponed to
August
• TE-EPC R2E activities anticipated in RR13
• TANB installation postponed 1 week
• TCLIA floor renovation TBC
• IT monitoring system consolidation postponed
• Cabling campaign started ahead of planning
• DISMAC local ELQA ahead of planning
LMC, 29th May 2019 28
Ne
xtm
ilesto
ne
s–
Ne
xtm
ain
activitie
s-
On
go
ing–
Co
mp
lete
d
Where we are: LSS8R – LSS1L
LSS8R
• PT100 upgrade on DFBX completed
• Cable campaign LH8UDT0-CL202 (cable tray RH87 + LIU) pulling
completed
• Triplet area: Longitudinal monitoring system Q2 and Q3 on going
• TDI removal completed, mark the crane position next week
• TANB works: removal, mark on the ground and drills completed;
installation and alignment next week, bake out in 3 weeks
• Survey alignment@warm Q12-Q12 on going
LSS1L
• PT100 upgrade on DFBX completed
• AFP activities: movement test completed
• ZDC disconnection and transport done
• Triplet area: Longitudinal monitoring system Q2 and Q3 in one week
RH87 cable tray
Cable campaign LH8UDT0-CL202
LMC, 29th May 2019 29
Where we are: Sector 8-1
FASER
• Cores drilling completed
• SAS installation and dismantling activities in progress from July September 2019
• Civil engineering Jan.- Feb 2020
Nex
tm
ilest
on
es–
Nex
tm
ain
act
ivit
ies
-O
n g
oin
g–
Co
mp
lete
d
LMC, 29th May 2019 30
DISMAC: Sector 8-1
DISMAC and magnet replacement
• All IC opened
• DLM done
• QBBI.A14R8 welded
• Measurement half moon R in progress
• Diodes consolidation in progress (3 weeks before foreseen)
• A26R8 being reconnected
• Welding cold mass train from 4th of June
• HV test will start the 3rd of June
First diode weldedDiode box opening Diode box cleaning
LMC, 29th May 2019
Conclusions
31
• The LHC Machine is under full cryogenics lockout
• The first big period of LS2 is completed (warm up and tests), the main activities related to consolidation are fully ongoing,
including major overhauling
• DISMAC and the Magnets Exchange Campaign is in progress, in advance wrt the baseline, but still in the learning phase for some
tasks
• Due to and issue in SCX 5, the AUG test @P5 must be rescheduled
• The strategies for RF ball, 16L2, QRL vacuum leak repair and the rescheduling of cryostat connexion in P2 are under discussion
LMC, 29th May 2019
Thank you !!
33
LMC, 29th May 2019 34
LHC-LS2: cryogenics lock out
LMC, 29th May 2019
7/2/2019
J Perez Espinos35/38