Page 1: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LS2-LHC StatusLMC, 3rd July 2019

Marzia Bernardini, Sebastien Bustamante, Michela Pirozzi, Estrella Vergara (EN-ACE-OSS)

Thanks to the contributions of groups and WSS!

Page 2: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019

Content

• LS2 general status

• LS2 LHC activities progress

• Conclusions

2

Page 3: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019

LS2 Master Schedule (EDMS ACC-PM-MS-0002 v.1.4)

22 months of works

3

LH

C M

achin

e b

ack to B

E-O

P

W

27

Page 4: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019 4

The Frame: where we are Sequencing beginning LS2

• Powering tests and training quench campaign

• Machine Lockout:

• Cryogenics preparation for Christmas closure

& cryo reconditioning after Christmas

• ElQA @ cold

• Warm up at ambient temperature

• Vacuum leak tests & Inspection (IV and BV)

• Cryoplant capacity tests

• ElQA @ warm

• Tightness tests and cryo lockout

Sequencing End LS2

• Pressure tests

• ElQA @ warm

• Vacuum leak tests & BV inspections

• Cool down & vacuum leak tests

• Machine levelling (survey) at cold

• ElQA @ cold

• DSO test (16th Oct. 2020)

• Powering tests and training quench

campaigns Machine to 3 shifts BE-OP

W44-2020

- Major cryogenics maintenance

- DISMAC (s12 +s78 +s81)

- All other works (HL, Consolidation, …)

Page 5: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019

LHC-LS2 EN-CV Maintenance

5

Point Activity Week Start Start Date End Date Duration Status

LHC5

SF - CV Maintenance W50 10-Dec-18 01-Feb-19 6 wks Completed

SU - AC Maintenance W50 10-Dec-18 14-Dec-18 1 wk Completed

USC55 - CV Maintenance W50 10-Dec-18 08-Mar-19 11 wks Completed

SU - Ventilation Maintenance W10 04-Mar-19 29-Mar-19 4 wks Completed

Ventilation Maintenance in RRW14W15

01-Apr-1908-Apr-19

30-Apr-19 4 wks Not Started

SF+SU reduced - CV Maintenance W50 07-Dec-20 08-Jan-21 3 wks Not Started

USC55 reduced - CV Maintenance W3 11-Jan-21 29-Jan-21 3 wks Not Started

Point Activity Week Start Start Date End Date Duration Status

LHC6

UW, UA, RE - CV Maintenance W40 30-Sep-19 25-Oct-19 4 wks Not Started

SF - CV Maintenance W44 28-Oct-19 10-Jan-20 9 wks Not Started

SU - CV Maintenance W3 13-Jan-20 07-Feb-20 4 wks Not Started

UW reduced - CV Maintenance (TBC) W28 06-Jul-20 24-Jul-20 3 wks Not Started

SF+SU reduced - CV Maintenance (TBC) W46 09-Nov-20 27-Nov-20 3 wks Not Started

Point Activity Week Start Start Date End Date Duration Status

LHC8

SF - CV Maintenance W7 10-Feb-20 08-Apr-20 8.5 wks Not Started

SU - CV Maintenance W16 14-Apr-20 19-May-20 5 wks Not Started

UW, UA , RE - CV Maintenance W21 20-May-20 18-Jun-20 4 wks Not Started

SF+SU reduced - CV Maintenance W42 12-Oct-20 30-Oct-20 3 wks Not Started

UW reduced - CV Maintenance W42 12-Oct-20 30-Oct-20 3 wks Not Started

Point ActivityWeek Start

Start Date End Date Duration Status

LHC1

SU1 - Ventilation Maintenance (RR, RE) W51 17-Dec-18 21-Dec-18 1 wk Completed

SU1 - Cooling Maintenance W2 07-Jan-19 01-Feb-19 4 wks Completed

SF - CV Maintenance - Dependant from SPS tests in BA6

W4 21-Jan-19 29-Mar-19 10 wks Completed

USA15 + US15 cooling + ventilation maintenance - Impact on LHC Tunnel

VentilationW6 04-Feb-19 01-Mar-19 4 wks Completed

USA15 EM W10 04-Mar-19 29-Mar-19 4 wks Completed

SF+SU reduced - CV Maintenance W50 07-Dec-20 08-Jan-21 3 wks Not Started

USA reduced - CV Maintenance + ventilation RR, RE

W3 11-Jan-21 29-Jan-21 3 wks Not Started

Point ActivityWeek Start

Start Date End Date Duration Status

LHC2

UW - CV Maintenance -Cooling, UA, RE W40 30-Sep-19 01-Nov-19 5 wks Not Started

SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

SU - CV Maintenance W16 15-Apr-20 20-May-20 5 wks Not Started

UW reduced - CV Maintenance -EG Only W34 17-Aug-20 14-Sep-20 4 wks Not Started

SF+SU + Ventilation UA- CV reduced Maintenance

W45 02-Nov-20 20-Nov-20 3 wks Not Started

Point ActivityWeek Start

Start Date End Date Duration Status

LHC4

SF - CV Maintenance W4 20-Jan-20 13-Mar-20 8 wks Not Started

SU - CV Maintenance W12 16-Mar-20 14-Apr-20 4 wks Not Started

UW - CV Maintenance - Cooling, UA, RE W21 22-May-20 19-Jun-20 4 wks Not Started

UW reduced - Cooling Maintenance -Ventilation reduced

W37 07-Sep-20 28-Sep-20 3 wks Not Started

SF+SU reduced - CV Maintenance W42 12-Oct-20 30-Oct-20 3 wks Not Started

Page 6: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019

LHC-LS2 EN-EL Maintenance (EDMS ELG-ADMIN-QE-0033 V.19 )

6

* NO ACCESS in SURFACE and UNDERGROUNG (Guardian at the point entrance)

Maintenance NO ACCESS* AUG NO ACCESS*

Point Day Point Day

LHC1 + ATLAS 6 -10 January 2020 (W2) LHC1 + ATLAS 13 January 2020 (W3)

LHC18 + SM18 23-25 April 2019 (W17) LHC18 + SM1826 April 2019 (W17)

11 February 2020 (W7)

LHC2 + ALICE11-14 June 2019 (W24) – Access OK

LHC2 + ALICE 27 January 2020 (W5)20-24 January 2020 (W4)

LHC3 + PM32 9-12 March 2020 (W11) LHC3 + PM3230 April 2019 (W18)

13 March 2020 (W11)

LHC417-20 June 2019 (W25) – Access OK

LHC47 Oct. 2019 (W41)

24-28 February 2020 (W3) 2 March 2020 (W10)

LHC5 + CMS 20-24 May 2019 (W21)

LHC5 + CMS 27 May 2019 (W22) TO BE RESCHEDULED

24-27 June 2019 (W26) – Access OK 5 May 2020 (W19)

LHC63-6 June 2019 (W23) TBC – Access OK

LHC6 20 Sept. 2019 (W38)17-19 Sept. 2019 (W38)

LHC7 23-27 Sept. 2019 (W39) LHC7 30 Sept. 2019 (W40)

LHC815-19 April 2019 (W16) – Access OK

LHC8 16 Dec. 2019 (W51)9-13 Dec. 2019 (W50)

TEST SECOURS (10min)All points on 19th December

(6am – 6:10am) (W51)Prevessin 4 April 2020 (W14)

Meyrin + Adm. 4th January 2019 (W1)

Page 7: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019

LHC-LS2 EN-EL: 66 kV Maintenance in progress

7

400 kV maintenance 22 July – 27 Sept 2019 (W30-39)

4 July – 27 Sept 2019 (W27-39)

66 kV maintenance (reduced consumption 15MVA LHC, 90 MVA CERN)

28 Mai – 19 July 2019 (W22-29)

28 June– 4 July 2019 (W26-27)Dates updated on 18/06/19

Page 8: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019

DISMAC start of activities

8

7/2/2019

8-1 1-2 2-3 3-4 4-5 5-6 6-7 7-8

BL

M

rem

oval VSC Done! N/A N/A N/A N/A Done! Done! Done!

SIT Done! Done! Done! Done! Done! Done! Done! Done!

Diodes Done! Done! Done! Done! Done! Done! Done! Done!

IC o

pen

ing VSC Done! N/A N/A N/A N/A Done! Done! Done!

SIT Done! Done! Done! Done! Done! W29 Done! W28

DIODES Done! Done! Done! In progress W28 W30 W32 W34 (4IC

training)

Consolidation In progress In progress In progress W28 W31 W36 W39 W43

Reclosing & FT W38 W41 W44 W47 W50 W3/2020 W6/2020 W9/2020

BLM installation W47 W50 W2/2020 W6/2020 W9/2020 W13/2020 W16/2020 W19/2020

ELQA LV In progress In progress W30 W35 W39 W42 W46 W49

HV In progress

(Monday)

In progress

(Tuesday)

W28 W31 W36 W39 W43 W46

Updated on 2nd July 2019

Page 9: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019

• No accident so far

• Many non-conformities are encountered, including pre-existing ones

Their management is efficient and implies frequent procedures optimisations and definition of new

procedures ; it is slowing down the progress

• DISMAC is globally progressing according to schedule (about one week ahead of schedule)

• Confident that the global schedule can be respected

• BUT the rate of 10 ICs is not yet achieved sustainably for the consolidation of the diodes insulation

itself ; resources were reallocated

• Updates will be required (impact to be assessed) :WP11 cryoassemblies & Q16L2 and C16L2

removal for beam screens exchange

• DISMAC QA review on 11-12 July 2019

Courtesy J.Ph.TockDISMAC (see LS2C @ Friday 28th June)

DISCO: Diode InSulation Consolidation

SIT: Special Intervention Team

CLEM: Current Leads Maintenance

9

Page 10: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019

• 19/22 cryomagnets have been removed from the tunnel; they were

disconnected and prepared for transport on time. Priority is put on this,

to avoid co-activity with transport asap.

All will be removed for 24th July-19.

• There is work in 6 sectors in parallel

• The first (A26R8) will be reconnected this week except X-ray and leak

tests. There could be some delay in cryomagnets reconnection but

remaining within the DISMAC time window

• The second cryodipole for BIHL study (C21R6) is under disconnection

• In-situ fit-test of the first flowmeter for BIHL study is about to start

Courtesy J.Ph.TockDISMAC (see LS2C @ Friday 28th June)

10

Page 11: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019 11

LHC-LS2: Magnet exchange status

• 19/26 removed

• 19/26 reinstalled Magnet

locationMagnet Week Start Date Transport

Sector 45 B24L5 W2701-07-2019

03-Jul-19Removal old magnet + stdby in UL55

Sector 45 B24L5 W2702-07-2019

04-Jul-19Old magnet transport from P5 to UJ22

W27 05-Jul-19 Convoy transport from UJ22 to UL55

Sector 67 C21R6 W28 08-Jul-19 Removal old Magnet and back to UL55

Sector 67 C21R6 W28 09-Jul-19 Old magnet transport from UL55 to UJ22

Sector 45 B24L5 W28 10-Jul-19 New magnet transport from UJ22 to UJ44

Sector 45 B24L5 W28 11-Jul-19 Transport + Installation new magnet + go to P6

Sector 67 B13R6 W28 12-Jul-19 Removal old Magnet and back to P4

Sector 67 B13R6 W29 15-Jul-19 Old magnet transport from P4 to UJ22

Sector 67 C21R6 W29 16-Jul-19 New magnet transport from UJ22 to P5

Sector 67 C21R6 W29 17-Jul-19 Transport + Installation new magnet + go back to

W29 18-Jul-19 Convoy back to UJ22

Sector 67 B13R6 W30 22-Jul-19 New magnet transport from UJ22 to P5

Sector 67 B13R6 W30 23-Jul-19 Transport + Installation new magnet + go back to

W30 24-Jul-19 Convoy back to UJ22

Sector 81 - Completed

Sector 12 - Completed (Ecxept LEBR for CC)

Sector23 - Completed (Ecxept LECL for CC)

Sector34 - Completed

Page 12: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019 12

Where we are: HL-LHC UPRsUPR activities before breakthrough and machine de-installation

• Rerouting of all the services: GSM, Optical fibers, Safety cables and panel, 18 kV and Fire detection

• UPR Survey and RP test cores:

• UPR13: week 21 (23.05.2019)

• UPR17: week 16 (15.04.2019)

• UPR53: week 18 (29.04.2019)

• UPR57: week 24 (11.06.2019)

Nex

tm

ilest

on

es–

Nex

tm

ain

act

ivit

ies

-O

n g

oin

g–

Co

mp

lete

d

Activity During LS2

UPR13 UPR17 UPR53 UPR57

Fire detection rerouting

Survey and RP cores

Cable trays installation and cable pulling in LHC

(Start)

2020 Oct-19 Dec-19 Dec-19

UPR53 UPR13 UPR57 RP Samples

Page 13: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019

LHC-LS2 activities progress

(from 29th May to 3rd July 2019)

13

Page 14: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019 14

Where we are: Sector 1-2 (1/2)N

ext

mile

sto

nes

–N

ext

ma

in a

ctiv

itie

s-

On

go

ing–

Co

mp

lete

d

• Flow meter in P18 installed already completed

• Roman Pot station maintenance postponed to August

• R2E in RR17 completed ahead of schedule

• Magnet reconnexion duration extended

• Cryostat Connexion replacement postponed to October 2019

• DISMAC local ELQA ahead of planning

• Longitudinal monitoring system Q2 and Q3 completed ahead

of baseline planning

• Flow meter installation in P18 QUI and WRL

• Optical Fiber campaign in PM15 pit completed

• Investigation on QRL Leak in Vacuum SS B QRL bellow opening

in progress (in preparation of Helium leak tests)

LHC-LIU in TI2:

• TI2 Line is vented

• TCDI electrically locked and disconnected

• TCDI removal in September 2019

• Cabling campaign in December 2019

• TCDI installation in January 2020

Request from TREX@26th June 2019 in TI18

QRL bellow opening S.1-2

Page 15: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019

Where we are: LSS1R-LSS2L

15

LSS1R

• LH1ORS0-FL202 (EN-EA) (Only Pit an US15): Optical fibre campaign

completed

• PT100 upgrade on DFBX completed

• AFP activities: movement test done

• ZDC disinstallation and transport completed

• Triplet area: Longitudinal monitoring system Q2 and Q3 tracing and

drills completed, installation of monitoring system in 2 weeks

LSS2L

• PT100 upgrade on DFBX completed

• Triplet area: Longitudinal monitoring system Q2 and Q3 completed

• Survey alignment Q12-Q12

• Alignment secondary components (Q7-Q7)

• TDI removal , Mark the new position done - Mounting of rails to support

the TDIS completedNex

tm

ilest

on

es–

Nex

tm

ain

act

ivit

ies

-O

n g

oin

g–

Co

mp

lete

d

Crane installation for TDIS ZDC disinstallation

Page 16: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019 16

Where we are Sector 2-3N

extm

ilesto

ne

s–

Ne

xtm

ain

activitie

s-

On

go

ing–

Co

mp

lete

d

General Status

• Racks ODH consolidation + maintenance

• R2E 600A-10V consolidation

• 18kV, 3.3kV and LV machine network Maintenance

• Optical Fiber campaign

LSS2R

• PT100 upgrade on DFBX completed

• Triplet area: Longitudinal monitoring system Q2 and Q3

marking and drills completed, installation in 2 weeks

• TCLIA A4R2 : Mechanical works, removal and transport

completed; floor marking, drills in 2 weeks, installation and

bake out in 3 weeks

• Survey alignement@warm Q12-Q12 on going

LSS3L

• -

Survey Alignment TCLIA removal

• In-situ a-C coating SAM Q5-Q6 postponed to

September

• Longitudinal monitoring system Q2 and Q3

completed ahead of baseline planning

• DISMAC local ELQA ahead of planning

Page 17: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019 17

Where we are: Sector 3-4

General Status

• 48V Maintenance

• Optical Fiber campaign

• UPS Maintenance

Ne

xtm

ilesto

ne

s–

Ne

xtm

ain

activitie

s-

On

go

ing–

Co

mp

lete

d

LSS3R

• -

LSS4L

• Survey measurements@warm Q12-Q12 completed

• Pumping crosses leak check ACS modules completed

• Removal BSRT redundant support completed

• Mechanical work for D3L4 pumping port relocation in 2 weeks

• Soupapes replacement and scaffolding installation in 3 weeks

Survey measurement

• Wire Scanner sectorization duration

extended up to December 2019 due to the

need of a technology modification on the

beam wire scanner (new activity)

• BSRT mirror installation and works duration

extended up to December 2019

• Magnet reconnection ahed of planning

Page 18: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019 18

Where we are: Sector 4-5General Status

• EL Maintenance week completed

AUG test @P5 postponed

• 18kV, 3.3kV and LV machine network Maintenance

(access ok)

• Gaz and ODH maintenance 2019 + Consolidation

Racks ODH

• UPS maintenance

• PZ45 replacement

• UJ43, UJ47 PAD/MAD Upgrade

• PZ45 MAD extension

• Water cooled cables replacement on DFBA in progress

in RR53

• LHC600A-10V consolidation Batch 1

• 13kA EE switch maintenance

• Optical fiber campaign

Nex

tm

ilest

on

es–N

ext

ma

in a

ctiv

itie

s-

On

go

ing–

Co

mp

lete

d

• Wire scanner sectorisation: E5R4/E5L4 activities to

be rescheduled due to the need of a technology

modification on the beam wire scanner (new

activity)

• BSRT mirror installation and works duration

extended up to December 2019

• 13kA switch refurbishement already started

• RF Ball in S4-5 on hold

• Change of faulty VVGSH.36R4.B ahead of

planning

Page 19: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019

LSS4R : ACS module validation

19

C1B1 Antenna problem

• Detected during the cavity conditioning in 2017: the field level ~10

dB less than expected (wrong tune and coupler position were ruled

out)

• Measuring the transmission between operational and spare antenna

showed indeed 10 dB less signal on C1B1 than on other cavities,

• Since April 2017 the cavity is operated using the spare antenna.

Activities to be performed:

• Opening the side panel and perform RF measurements and validation

• If nothing is detected Leak check

According to leak check : Option 1 there is a leak ACS module removal and swap

Option 2 no leak detected cable reconnection and side panel closing performed

Page 20: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019 20

Where we are: LSS4R – LSS5LN

extm

ilesto

ne

s–

Ne

xtm

ain

activitie

s-

On

go

ing–

Co

mp

lete

d

LSS4R

• Survey measurements@warm Q12-Q12 completed

• ACS module validation completed no needs to replace the ACS module

• Pumping crosses leak check ACS modules completed

• Removal BSRT redundant support completed

• Mechanical works for faulty VVGSH.36R4.B on going

• Mechanical works for D3R4 pumping port relocation in 2 weeks

• Soupapes replacement and scaffolding installation in 3 weeks

LSS5L

• PT100 upgrade on DFBX completed

• ZDC disinstallation and transport completed

• Optical fibre campaign LH5ORS0-FL202 (only Pit and UJ56) in 2 weeks

• Triplet area: Longitudinal monitoring system Q2 and Q3 in 3 weeks

Survey measurements

??????

Page 21: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019 21

Where we are: Sector 5-6

• 18kV, 3.3kV and LV machine network Maintenance

• Gaz and ODH maintenance + Consolidation Racks

• UPS Maintenance

• 13kA EE switch maintenance

• Water cooled cables replacement on DFBL in progress in RR57

• 48V Maintenance

• Optical fiber campaign

Nex

tm

ilest

on

es–

Nex

tm

ain

act

ivit

ies

-O

n g

oin

g–

Co

mp

lete

d

• Vacuum faulty gauge change to be rescheduled

• Survey Core in LSS5R postponed

• RF Ball in S5-6 on hold

• MKD Tests postponed to Mid-August

• 48V Maintenance postponed to mid-July

• UPS Maintenance

Page 22: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019 22

Where we are: LSS5R – LSS6LN

ext

mile

sto

nes

–Nex

tm

ain

act

ivit

ies

-O

n g

oin

g–

Co

mp

lete

d

LSS5R

• PT100 upgrade on DFBX completed

• ZDC disinstallation and transport completed

• Optical fibre campaign LH5ORS0-FL202 (only Pit and UJ56) in 2 weeks

LSS6L

• New MKBV transport and installation done : Alignment next week

• Cable campaign LH6UGT0-CL201 in UA63 completed

• A4L6 NC 3 RF fingers bake out and NEG completed, X-Ray done

Cable campaign LH6UGT0-CL201

TE-VSC works for A4L6

Page 23: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019 23

Where we are: Sector 6-7

• 48V Maintenance

• UPS Maintenance

• 18kV, 3.3kV and LV machine network Maintenance

• Gaz and ODH maintenance + Consolidation Racks ODH

• 13kA EE Switch Maintenance

• Cryo Maintenance

• MKD-MKB Upgrade

• Validation Test on MKD Generators postponed to mid-August

Nex

tm

ilest

on

es–

Nex

tm

ain

act

ivit

ies

-O

n g

oin

g–

Co

mp

lete

d

• Cryo Flowmeter installation postponed to 2020

• MKD Tests postponed to Mid-August

• BTVSE reparation duration augmented

• TCDQ maintenance started ahead of planning

• RF Finger NC already completed

QUICB General Maintenance

UPS maintenance

13kA EE switch maintenance

Page 24: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019 24

Nex

tm

ilest

on

es–

Nex

tm

ain

act

ivit

ies

-O

n g

oin

g–

Co

mp

lete

d

Where we are: LSS6R – LSS7L

LSS6R

• Survey measurement@warm Q12-Q12 next week

• Cable campaign LH6UDT0-CL201 in UA67 done

• Re-installation of BTSVE completed: new removal due to problems

arise during re-installation, maintenance and re-installation in 3 weeks

• A4R6 RF fingers NC NEG completed, X-ray next week

LSS7L

• RP VETO No Access until 11/07/2019

• Pulling Cable campaign LH7UGT0-CL201, HL7HIL0-CC01 in 3 weeks

• Optical fibre campaign LH7ORS0-FL202 (only Pit and UJ76) in 3

weeks

TE-VSC works for A4R6

Page 25: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019 25

Where we are: Sector 7-8

• LHC PAD/MAD Upgrade

• UPS Maintenance

• PM76 Lift replacement in progress

• LSS7: RP VETO No Access

• 48V Maintenance

• Gaz and ODH maintenance + Consolidation Racks ODH

• Red Phone maintenance

• Optical fiber campaign

Ne

xtm

ilesto

ne

s–

Ne

xtm

ain

activitie

s-

On

go

ing–

Co

mp

lete

d

PM76 lift replacement

• UPS Maintenance RE78• PM76 duration extended of 1week

• 13kA EE maintenance preparatory works

completed

• TANB installation postponed 1 week

• DISMAC IC Opening already started

Page 26: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019 26

TANB removal

Nex

tm

ilest

on

es–

Nex

tm

ain

act

ivit

ies

-O

n g

oin

g–

Co

mp

lete

d

Where we are: LSS7R – LSS8L

LSS7R

• RP VETO No Access

• Pulling Cable campaign LH7UPT0-CL201, HL7HIL0-CC03 in 3 weeks

• Optical fibre campaign LH7ORS0-FL202 (only Pit and UJ76) in 3

weeks

LSS8L

• PT100 upgrade on DFBX completed

• Triplet area: Longitudinal monitoring system Q2 and Q3 installation on

going

• TANB works: removal, mark on the ground and drills completed;

installation, alignment next week, bake out in 2 weeks

• In-situ a-C coating Q5L8 in 2 weeks

Page 27: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019 27

Where we are: Sector 8-1• SD8 PR722 crane replacement completed

• Optical fiber campaign

• Cryo maintenance

LHC-LIU in TI8:

• TI8 line is vented and line opening is done

• 6/6 TCDI removed

• Drills for support installation

• RH87 cryo platform cutting

• Cable tray folding in RH87

• Lifting crane installation

Nex

tm

ilest

on

es–

Nex

tm

ain

act

ivit

ies

-O

n g

oin

g–

Co

mp

lete

d

• A28R8 reconnection duration extended

• Roman Pot station maintenance postponed to

August

• TE-EPC R2E activities anticipated in RR13

• TANB installation postponed 1 week

• TCLIA floor renovation TBC

• IT monitoring system consolidation postponed

• Cabling campaign started ahead of planning

• DISMAC local ELQA ahead of planning

Page 28: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019 28

Ne

xtm

ilesto

ne

s–

Ne

xtm

ain

activitie

s-

On

go

ing–

Co

mp

lete

d

Where we are: LSS8R – LSS1L

LSS8R

• PT100 upgrade on DFBX completed

• Cable campaign LH8UDT0-CL202 (cable tray RH87 + LIU) pulling

completed

• Triplet area: Longitudinal monitoring system Q2 and Q3 on going

• TDI removal completed, mark the crane position next week

• TANB works: removal, mark on the ground and drills completed;

installation and alignment next week, bake out in 3 weeks

• Survey alignment@warm Q12-Q12 on going

LSS1L

• PT100 upgrade on DFBX completed

• AFP activities: movement test completed

• ZDC disconnection and transport done

• Triplet area: Longitudinal monitoring system Q2 and Q3 in one week

RH87 cable tray

Cable campaign LH8UDT0-CL202

Page 29: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019 29

Where we are: Sector 8-1

FASER

• Cores drilling completed

• SAS installation and dismantling activities in progress from July September 2019

• Civil engineering Jan.- Feb 2020

Nex

tm

ilest

on

es–

Nex

tm

ain

act

ivit

ies

-O

n g

oin

g–

Co

mp

lete

d

Page 30: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019 30

DISMAC: Sector 8-1

DISMAC and magnet replacement

• All IC opened

• DLM done

• QBBI.A14R8 welded

• Measurement half moon R in progress

• Diodes consolidation in progress (3 weeks before foreseen)

• A26R8 being reconnected

• Welding cold mass train from 4th of June

• HV test will start the 3rd of June

First diode weldedDiode box opening Diode box cleaning

Page 31: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019

Conclusions

31

• The LHC Machine is under full cryogenics lockout

• The first big period of LS2 is completed (warm up and tests), the main activities related to consolidation are fully ongoing,

including major overhauling

• DISMAC and the Magnets Exchange Campaign is in progress, in advance wrt the baseline, but still in the learning phase for some

tasks

• Due to and issue in SCX 5, the AUG test @P5 must be rescheduled

• The strategies for RF ball, 16L2, QRL vacuum leak repair and the rescheduling of cryostat connexion in P2 are under discussion

Page 32: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC
Page 33: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019

Thank you !!

33

Page 34: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019 34

LHC-LS2: cryogenics lock out

Page 35: LS2-LHC Status · • The first (A26R8) will be reconnected this week except X-ray and leak tests. There could be some delay in cryomagnets reconnection but remaining within the DISMAC

LMC, 29th May 2019

7/2/2019

J Perez Espinos35/38