lsc may 2013 outcome of the magnets tests from the ps, leir and transfer lines dominique bodart

Download LSC May 2013 Outcome of the magnets tests from the PS, Leir and transfer lines Dominique Bodart

If you can't read please download the document

Upload: shanon-henderson

Post on 20-Jan-2018

216 views

Category:

Documents


0 download

DESCRIPTION

LSC May 2013 Preventive maintenance, piquet & planning in the PS All intervention performed in the machines are recorded in the Norma database to ensure traceability, preventive and corrective maintenance. Last recorded event in the PS machine is a Bus Bar water pipe burst on 18 th January, repair organized between two LHC beam filling up. PS Hardware test period: 1 week assigned for hardware testing in the PS, 3 weeks needed with 2 weeks of night shifts re- scheduled. PS coordination planning