lydian construction update

11
1 Amulsar – Path to Production November 2016 – Photo Journal Lydianinternational.co.uk | TSX:LYD

Upload: terrepartners

Post on 16-Apr-2017

7.135 views

Category:

Business


0 download

TRANSCRIPT

Page 1: Lydian Construction Update

1Amulsar – Path to ProductionNovember 2016 – Photo Journal

Lydianinternational.co.uk | TSX:LYD

Page 2: Lydian Construction Update

2

Topsoil Removal at the Camp Platform.

Page 3: Lydian Construction Update

3

Excavation for the Temporary Construction Office / Contractor Laydown Area Platform

Page 4: Lydian Construction Update

4

Initial Upgrades to RD-5 from Gndevaz to Site 14

Page 5: Lydian Construction Update

5

Sediment Control Near the Temporary Construction Offices Platform, at the Base of the HLF

Sediment Control on the Extended Side of the Temporary Construction Offices Platform

Page 6: Lydian Construction Update

6

Widening of RD-5

Page 7: Lydian Construction Update

7

Ripping and Removal of Materials as Part of Access Road Construction

Page 8: Lydian Construction Update

8

RD-5 Widening

Page 9: Lydian Construction Update

9

Slope Cutting and Material Removal

Page 10: Lydian Construction Update

10

Re-Routed Powerline Near the HLF

Page 11: Lydian Construction Update

Lydianinternational.co.uk | TSX:LYD

Thank You