m enr.com iconic eyrienkissoff/pdf/cet-1000/enr... · 12/17/2006 · the iconic new york city...
TRANSCRIPT
JUNE 12, 2017 m enr.comJUNE 12, 2017 m enr.com
ICONIC EYRIE
UPGRADE THE EMPIRE STATE BUILDING’S STEEL BROADCASTING TOWER?
WEAVE A SKYSCRAPING, HURRICANE-DEFYING
WORKERS’ NEST FIRST (P. 26)
INSIDE: THE
TOP 100
PROJECT
DELIVERY
FIRMS
open-air observatory at the 86th floor and premium viewing spaces at the 102nd and 103rd levels. Annually, these
26 ENR June 12, 2017 enr.com
SPINNING ACHRYSALIS
PH
OTO
BY T
IMO
TH
Y S
CH
EN
CK
, CO
UR
TES
Y O
F S
KA
NS
KA
US
A
W hen engineers made plans to
reinforce and up-grade the carrying capacity of the Em-pire State Building’s mast and tower by adding 39 tons of steel, they had to find a way to protect pedestrians from fall-ing rivets, tools and materials. Roofing the observatory and building bridges over the sidewalks 1,250 ft below were lousy options. The top of the iconic New York City building has an
Workers weave a cocoon of steel, aluminum and cloth to create a safe work space far above the streets of Manhattan By Tom Sawyer
spaces host about 4.3 million visitors and generate about $85 million in revenue. Soaring above the busy streets, a 200-ft-tall steel broadcast tower bristles with antennas that generate about $20 million more. Together, the
enr.com June 12, 2017 ENR 27
SEPTEMBER DAWN
By the light of blue LEDs illuminating the top of the Empire State Building, Local 40 ironworker Ruben Villagran nears the end of another shift at 6:10 a.m. He is working on one of the aluminum truss towers of the Haki Trak system, whose vertical rails capture and support the ballistic-fabric walls of a workspace cocoon.
BROADCAST HUB
The mast of the Empire State Building is topped by a premium, glazed observation space at the 102nd floor and an open-air VIP parapet at the
103rd. A temporary, hard-sided workspace and support for the “cocoon” brace back to the
conical ice shield above the VIP parapet; the cocoon floor is at the top of the steel panels. Fabric panels rise about 25 ft to a solid roof. The cocoon surrounds the lower part of the
broadcast tower, which has just been reinforced to carry backup antennas for a similar
array (here, seen above the worker on the cocoon roof). To improve future configuration flexibility, the strengthening goes well beyond
immediate requirements.
enr.com June 12, 2017 ENR 29
observatory, mast and tower are the
crowning jewel of the 86-year-old
icon, which is owned by the Empire
State Realty Trust Inc.
The search for an alternative to
scaffolding dates to February 2014,
when the ESRT’s building engineer, engineer-of-
record Thornton Tomasetti, site safety engineer Plan
B Engineering and contractor Skanska USA Building
Inc. began to consult with New York City Dept. of
Buildings officials to devise a plan that would not only
protect the public and workers but also allow for the
strengthening of the mast and tower without having
to resort to sidewalk bridges.
They came up with a design for a sheltering
“cocoon,” which sits on a 560-sq-ft aluminum ele-
vated work platform, or “dance floor.” The platform
is braced from below by steel brackets through the
conical ice shield, which is there to shatter ice falling
from the tower.
Further, the outer edges of the dance floor are
guyed by cables leading up to the roof of the cocoon
and the tower above. Encircling the exposed base of
the tower just above the ESB’s roof, the floor is
enclosed by walls created by aluminum truss towers
arranged in an octagon and bridged by panels of
ballistic cloth, which slide in edge tracks from bottom
to top. To reduce exposure to dangerous winds, the
panels can be drawn down in a few minutes by rollers.
“The planning of the project took two years, in-
cluding six months to design the cocoon and [perform
the wind] testing in Florida,” says Tom Durels, ESRT’s
executive vice president and director of leasing and
operations. “That gives an idea of the amount of
thought and engineering that went into it.”
The assembly is designed to meet city codes for a
300-psf live load and a three-second wind gust of 98
mph. “It was wind-tunnel-tested to failure at 140 miles
per hour, and it was the test-sample support structure
that failed. It wasn’t the envelope,” says Peter Sjolund,
the ESRT’s senior vice president of construction. “You
are on the top of the Empire State Building, the most
famous office building in the world. You don’t want to
be on ‘film at 11.’ ”
Stealthy Work
Scott Seydor was project manager for the cocoon con-
struction. An architect, he joined Skanska USA in 2011
as a design manager for mission-critical, design-build
data-center work, which brought him to the attention
of Skanska executives looking for someone with a
strong design background to manage mission-critical
work in the Empire State Building, he says. One one
such project, Seydor managed the replacement of the
Art Deco mast’s 480 pieces of glass between the 90th
floor and 101st floor.
When he heard of the mast-strengthening project,
Seydor says he jumped at the chance to manage it, too.
“I said, ‘We can do it right. We can do it safe. Let me
do it. The project needs to be done.’ ” He adds, “I live
in Philly. I get up at 3:30 in the morning because I get
to do this. … I am an architect, and this is the most
iconic building in the world.”
Few New Yorkers—not to mention the hundreds
of thousands of annual visitors who meander around
the observation decks—are aware of the work being
performed above them by a small Skanska USA crew
and the handful of steelworkers from Skanska Civil
NE, a sister business unit. “It’s such a small space,
there’s only so many guys you can throw at it,”
Seydor observes.
Because the materials-handling path makes use of
the passenger elevators and public observation areas,
crews had to construct and, starting this week, will
COVER STORY
PROJECT DELIVERY
PH
OTO
(LEF
T) C
OU
RTE
SY
OF
SK
AN
SK
A U
SA
. DR
AW
ING
(RIG
HT)
CO
UR
TES
Y O
F PLA
N B
EN
GIN
EER
ING
/TH
OR
NTO
N T
OM
AS
ETTI
, WIT
H IL
LUS
TRAT
ION
MA
NIP
ULA
TIO
N B
Y EV
A S
AW
YER
Handrail
Cocoon roof
Cocoon tower
Fabric panel
Handrail
Light-gaugesteel siding
Iceshield
“Dance floor” support
Existing tower withnew steel panels
TOPPER The temporary cocoon structure encloses the base of the broadcast tower as it emerges from the truncated cone at the building’s roof.
LOGISTICAL CONSTRAINTS
Ultimately, all materials are delivered by brute force up a series of ladders and out through a submarine hatch in the ice shield. The fi rst workspace was created on a temporary extension of the skirt around the ice shield, which was given steel-sided walls to protect the workers as they next assembled the aluminum platform and fabric cocoon above.
enr.com June 12, 2017 ENR 31
have to deconstruct the cocoon between the hours of
2 a.m. and 7 a.m., when the public spaces are closed.
From the loading dock, materials are navigated
through security scanners, down to a lower concourse
and up a service elevator to the 79th floor, where they
are carted to a passenger-elevator bank for a lift to the
85th floor and then transferred to a manually operated
1930s “mast elevator” for a ride to the 102nd floor.
After that, materials are hoisted up ladders and through
hatches by hand and with chain falls out through a
single “submarine hatch” in the flat-topped conical
roof that crowns the building.
Due to handling constraints, including the size of
the legacy elevator in the mast, the largest piece taken
up was a 6-ft, 4-in.-long W12 steel beam, says ESRT’s
Sjolund. A support for the platform framing, it weighs
2,833 lb.
To maneuver beams out of the submarine hatch and
into place, the assembly sequence first required the
installation of chain hoists on lifting booms projecting
from the tower. The steel beams were placed first,
building up the ice-shield roof just beyond the perim-
eter of the planned dance floor. Then, crews erected a
hard-sided wall around the first work area to prepare
for assembly of the dance floor, just above.
Creating a Safe Space
While there is only a few feet between the cone and
the hard side, the clearance creates a small storage area
and just enough of a safe space to bolt and splice the
hundreds of pieces of aluminum beams, floor plates
and vertical truss sections required to create the alu-
minum floor, towers and roof of the cocoon, which
begins just overhead.
The purpose of the work is to increase the steel tow-
er’s carrying capacity by beefing up the lower section of
tower above the roof, as well as by reinforcing its ties
into the structure. The ironworkers accomplished the
work with hundreds of pieces of steel plate and bar of
various thicknesses, with the majority of it 1 1/4-in.
plate, stitch-welded and bolted to the existing steel. The
maximum dimensions and weight of the components
are strictly constrained by the tortured logistics required
to get them there and the frequent need to fit them
between and around the structural features of the exist-
ing tower. “If we could have brought up 25-foot-long
pieces, we would have loved it,” says Sjolund.
The strengthening work included several phases,
the first of which started in fall 2015 and involved
strengthening the tower legs as they enter the build-
ing’s roof and carry loads down to the 101st level.
Crews added bars and plate to the existing steel by
replacing rivets with longer torsion-control bolts or
fitting plate between existing members and introducing
new braces, gussets and diagonals.
On the 101st to 103rd levels, the interior work re-
quired opening ceilings, walls and floors in public
spaces and was conducted during an around-the-clock,
three-week push during February and March 2016. It
was the only part of the work that interrupted visitor
access to the observatory spaces, and the interruption
affected only the smaller, premium spaces on the 102nd
and 103rd levels.
Work inside the completed cocoon enabled the
next phase of the tower strengthening. “The cocoon
allowed us to work uninterrupted through inclement
weather and 24/7, without disruption to our broad-
casters,” Sjolund says.
COVER STORY
PROJECT DELIVERY
SAFETY, SAFETY, SAFETY Wearing climbing helmets and fall protection, a crew of about a dozen Local 40 ironworkers as-sembled the 22-ton cocoon, beginning in late May 2016. The first steps were in the open air, but by the time the cocoon was finished and the workspace en-closed, “you could have been working in your basement,” says Scott Seydor, Skanska’s project manager through the assembly phase. The sound of the faraway city streets are lost when the wind rises and the cocoon’s fabric sides start rustling like luffing sails.
PH
OTO
S C
OU
RTES
Y O
F S
KA
NS
KA
US
A
32 ENR June 12, 2017 enr.com
TOWER SET
A triangular “Tomcat Truss”
tower segment is set in place (above)
as the cocoon frame takes form. All
assembly work atop the building had to
be accomplished between 2 a.m.
and 7 a.m., during the hours when the public observation areas below were
closed. Now that the tower
strengthening has been accomplished, cocoon disassembly
soon will begin.
PHOTOS COURTESY OF SKANSKA USA AND ESRT
HANDCRAFTED Worker (center) positions a Hugen portable drill to make a hole for a torsion-control bolt to fasten steel plates to the existing tower structure. Once positioned, a switch activates the drill’s electromagnetic base to hold it in place. Ironworkers (above) adjust a template to mark locations for new holes.
enr.com June 12, 2017 ENR 33
To strengthen the tower, crews
welded and bolted on additional steel.
Further, crews enclosed the lower
part of the tower in new steel plate.
When workers need to de-energize
and service the existing upper
antenna array, the new, lower backup antenna array will
be used to continue broadcasting and its steel-plate
backing will protect the workers from radio-frequency
radiation as they climb up.
Antenna Upgrade
The mast’s antennas are licensed to third-party televi-
sion and radio broadcasters and data communications
providers. Further, space in the building’s upper floors
is leased to house transmission equipment and related
facilities, including “multichannel combiners” that send broadcasts of multiple
frequencies through common antenna arrays.
Nineteen FM radio and about a dozen television channels currently broadcast
from the tower. The FM stations use either a primary array about 100 ft above
the building’s roof or, lower down, the 50-year-old Alford Antennas backup
array, to which signals can be diverted when changes or repairs are needed on
the primary array.
Signals are conducted from the channel combiners on a lower floor via 31/8-
in.- or 61/8-in.-dia copper-clad coaxial cables in nitrogen-filled jackets. “We call it
plumbing—think … of 6-inch-diameter copper pipe,” says Ed Driscoll, the
ESRT’s manager of broadcasting. The big copper lines rise through the upper
floors and travel up the tower to the antenna. Having run additional lines for the
new backup array, the antenna installers will soon start to hang the 4.5-ton backup
array on the now-strengthened tower. Work will begin after the cocoon comes
down in mid-June.
A 2014 reconfiguration plan mapped out an upgrade to the tower’s antenna-
carrying capacity. The addition is driven by market forces, according to the ESRT’s
most recent quarterly SEC filing.
“The business of broadcasting TV and radio signals over the air is in flux,
due to deteriorating industry fundamentals and the ongoing Federal Commu-
nications Commission spectrum auction, and there is competition from other
broadcasting operations,” the statement acknowledges. New generations of
broadcasting equipment are expected to begin populating the tower in the
months and years to come.
Moving On
“One of the things about working on the Empire State Building, the world’s most
famous building, is we are constantly innovating and have the benefit of working
with the world’s leading experts,” says ESRT’s Durels. “Building this protective
cocoon is an example of that,” he notes, adding that the project “may lead others
to see what can be done on towers worldwide when it comes to this type of work.”
Seydor will not be around for the cocoon demolition. After years of getting up
at 3:30 a.m. and commuting 240 miles a day to lead what he calls a project of a
lifetime, the project manager has moved on to work closer to home at Genesis
Engineers, Plymouth Meeting, Pa. “It was … an incredible project. They knew
it wasn’t just a job to me—it was a passion,” he says. “This is the Empire State
Building: Things are different here.”
COVER STORY
PROJECT DELIVERY
TEMPORARY WORKS Part of the temporary works installed to facilitate cocoon construction, outriggers and chain hoists jut from the tower above the cocoon’s hard roof. The cocoon roof and deck were engineered for 300-psf dynamic loading and impacts from falling objects, as per code. The new screen antenna array will be installed in the space where the cocoon is now; the new array will look like the existing array (at left, between the X-shaped “turnstile” antennas). The turnstile antennas are scheduled for removal. The tall white column is a digital television antenna installed for CBS in 1999.