M. Gilchriese - April 2001
Disk Sector Status
M. Gilchriese - April 20012
Technical Status• Three prototypes to current dimensions(8-sector disks) except
for tube length made or will be done by next week.
• One with CGL and two with epoxy(AIT EG7658) between Al tube/faceplate.
• So far, sectors made with CGL meet all specs. Epoxy is backup in case we find difficulties during production. Don’t have time to completely qualify sectors with epoxy before PRR.
• Has been little additional testing in last months. – “Loss of coolant” test at room temperature of irradiated sector. Sector
reached 135oC, steady state, held for some minutes and then coolant turned on. Thermal performance still OK.
– Irradiated sector piece exposed for weeks to 100% C3F8 vapor at room temperature. No effect seen in thermal performance.
• All old(FDR) requirements met by baseline design
M. Gilchriese - April 20013
Technical Status(2)• Thermal shock to -35 needs to be done
• This would require new set up(LN2 vapor?), that doesn’t yet exist.
• Also use for thermal cycling?
M. Gilchriese - April 20014
Disk Sector Production Page
M. Gilchriese - April 20015
Status(1)• Requirements(Gil)
– Revised version sent to Marco
– Needs final checking, global changes(eg. fault conditions)
• Interfaces(Eric/Gil)– FDR version “marked up”. Needs new drawings, grounding defined..a
number of changes
• Drawings(Dave, Jon, Eric)– Preliminary set of drawings complete(Dave, Eric, Jon)
– Detailed list of outstanding fabrication and tooling drawings/figures made(Eric/Jon) and in progress. Next complete update by end of May?
– Tolerances and other information(Eric). Will be largely included in revised drawing set.
• Schedule(Gil, Jon, Mike)– Preliminary baseline schedule complete. Next update by mid-June, for
PRR.
M. Gilchriese - April 20016
Status(2)• Component purchases(Jon, Gil)
– Production tubes on order, delivery by June
– Production carbon-carbon plates ordered, first inspection(before heat treatment and CVD) complete(OK), processing progress.
– Foam just ordered
– Miscellaneous materials(adhesives, etc) to be ordered
– Mounting button material still not finally fixed yet. PEEK, C-filled PEEK or C-C.
• Vendor QC/QA– Allcomp visited, plates inspected, travellers with each plate OK
– Allcomp will also make CVDed foam. QC to be worked out but is essentially weight of each piece.
– No other significant vendor QC/QA
M. Gilchriese - April 20017
Status(3)• QC/QA at LBL(Gil, Jon)
– Preliminary ATLAS part number ID made
– Draft individual travellers complete for• aluminum tubes
• faceplates
• assembled sectors
– Will be batch travellers(not each part) for fittings, strain relief pieces, hardpoints
– Detailed QC procedures for each piece/assembly(what to measure) largely exist and have been tried on prototypes but need to be formally documented in “how to” manual.
– Summary QC/QA document for PRR needs to be written, mostly referring to these more detailed procedures, etc.
M. Gilchriese - April 20018
Status(4)• Production personnel
– Primarily Jon and Tom
• Current plan– Start pre-production in July
– Produce enough sectors to populate one disk
– Test
– Go ahead for full production Jan. ‘02