1 Madrid, 27 th February 2013 21 st IG Meeting South Gas Regional Initiative

Upload: chacha

Post on 24-Feb-2016

38 views

Category:

Documents


0 download

DESCRIPTION

21 st IG Meeting South Gas Regional Initiative. Madrid, 27 th February 2013. 21 st IG meeting SGRI- Agenda. II. Capacity Allocation Mechanisms Harmonization. II.1. Draft Roadmap in the Region II.2. CAM between Spain and Portugal: next auction . II. Capacity Allocation Mechanisms. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Madrid, 27 th  February 2013

1

Madrid, 27th February 2013

21st IG Meeting South Gas Regional Initiative

Page 2: Madrid, 27 th  February 2013

2

21st IG meeting SGRI- Agenda

Page 3: Madrid, 27 th  February 2013

3

II. Capacity Allocation Mechanisms Harmonization

Area of work Responsible Starting Deadline

OSP France-Spain: annual allocation of short-term capacities

TSOs Nov. (yearly)

Dec. (yearly)

CAM harmonisation proposal between Spain and Portugal

NRAs-TSOs Jan. 2011 Jun. 2012

CAM harmonisation proposal in the whole region NRAs-TSOs Jan.2012 Dec.2013

Set up a common TSO Allocation Platform: Roadmap and Implementation

TSOs Jan.2014 Dec.2014

II.1. Draft Roadmap in the Region

II.2. CAM between Spain and Portugal: next auction

Page 4: Madrid, 27 th  February 2013

4

II. Capacity Allocation Mechanisms

II.1. Draft CAM Roadmap in the Region

(for information by Regulators)

Page 5: Madrid, 27 th  February 2013

5

II.1 Draft CAM Roadmap in the Region

Early implementation of the Draft CAM NC

Coordinated CAM in the Region FRANCE-PORTUGAL-SPAIN in 2014

PRODUCTSCALENDAR

REGULATORY NEEDS IT SYSTEMs

1 2 3

GOAL

In line with the CAM NC Roadmap in Europe, developing by ACER and ENTSOG

Page 6: Madrid, 27 th  February 2013

6

II.1 Draft CAM Roadmap in the Region

Capacity product definition and calendar (I)

• Definition of available bundled capacity for the next 15 years (Oct 2014...), agreement on the split of capacity (Q, yearly, 15 years)

• When will the capcity be allocated at VIP?

• Common criteria on: unbundled / interruptible / backhaul

• Monthly capacity products have been allocated by OSP until 31st March 2014

• Capacity products to be offered before March 2014 for the period April 2014-September 2014. Proposal: Maintain prorate or new CAM NC?

1

SPAIN-FRANCE (I)

Page 7: Madrid, 27 th  February 2013

7

II.1 Draft CAM Roadmap in the Region

1 Capacity product definition and calendar (II)

Proposal of Auctions:• Annual quarterly capacity auction in June 2014: first Q capacity

products from Oct 2014 to Sept 2015 (Q1-Q4) ---- common platform

• Rolling monthly auction in Sept 2014 ?• Daily auctions from October 2014 ?• Annual yearly capacity auction in March 2014: first yearly capacity

products from Oct 2014 (Y1-Y15)

SPAIN-FRANCE (II)

Page 8: Madrid, 27 th  February 2013

8

II.1 Draft CAM Roadmap in the Region

1 Capacity product definition and calendar (III)

• Definition of available bundled capacity for the next years (Oct 2014...), agreement on the split of capacity (Q, yearly, 15 years), Longest allocation period = 1 year ?

• VIP

• Common criteria on: unbundled / interruptible / backhaul

• Yearly and Monthly capacity products have been offered by auction in June 2012, from Oct 2012 to Sept 2013

• To be decided: Quarterly capacity product could be offered in June 2013 (Oct 2013-Sept 2014) the same methodology as last year?

SPAIN-PORTUGA L (I)

Page 9: Madrid, 27 th  February 2013

9

II.1 Draft CAM Roadmap in the Region

1 Capacity product definition and calendar (IV)

Proposal of Auctions:• Annual quarterly capacity auction in June 2014: Q capacity

products from Oct 2014 to Sept 2015 ----- common platform for the first time

• Rolling monthly capacity auction Sept 2014 ?• Daily auctions from October 2014 ?• Annual yearly capacity auction in March 2014/2015: first yearly

capacity products from Oct 2014/2015, for one year?

SPAIN-PORTUGA L (II)

Page 10: Madrid, 27 th  February 2013

10

II.1 Draft CAM Roadmap in the Region

1 Capacity product definition and calendar

Proposal of Auctions:

INSIDE FRANCE

Page 11: Madrid, 27 th  February 2013

11

1

Annual yearly auctions: 1st Monday of March / Y1: 1st Oct-31st SeptAnnual quarterly auctions: 1st Monday of June / Q1: 1st Oct-1st Jan.Monthly capacity auctions: 3rd Monday of each monthDaily auctions: 16.30 CET D-1

… 2013 2014 2015 2016 2029 …

Se Oc No De Ja Fe Ma Ap Ma Ju Ju Au Se Oc No De Ja Fe Ma Ap Ma Ju Ju Ag Se Oc

Prorata allocation

SP -FR

Annual yearly capacity auctions

Annual quarterly capacity auctions

Rolling monthly capacity auctions

Rolling day ahead capacity auctions

Within -day capacity auctions

AuctionSP -PT

II.1 Draft CAM Roadmap in the Region

Page 12: Madrid, 27 th  February 2013

12

Regulatory needs (I)Auction mechanism as a default CAM in the interconnectionsMoving towards bundled and virtual capacityHarmonizing the capacity products and timeframesNew regulation need to be consistent with European NC:

• CMP NC • Balancing NC

o Agreement on nomination and renomination schemes• Interoperability and Data Exchange NC

o Harmonization of gas day / gas year- 2014o Temperature to measure gas- 2014o Units used to allocate capacity and sign contracts- 2014

• Tariffs NC:o Reserve priceo Price to be paid by subscribers during all the contract life

2

II.1 Draft CAM Roadmap in the Region

Page 13: Madrid, 27 th  February 2013

13

Regulatory needs (II)To be discussed:

• Shipper license to participate in auctions process, allowing the same shipper to book unbundled capacity. Qualification steps.

• Price steps definition and allocation of revenues arising from the auction among TSOs

• Release of information to the market. Calendar• Capacity contracts: obligation to subscribe the capacity allocated

in the auction, timing, financial deposit...• Responsibilities of TSOs (implementation) and NRAs

(supervision)• Secondary capacity market: bundled virtual capacity to remain as

allocated in the auction• Coexistence of old and new contracts

2

II.1 Draft CAM Roadmap in the Region

Page 14: Madrid, 27 th  February 2013

14

IT System

To develop a single platform to allocate capacity: Best available technologies, functionalities, secure, smooth exchange of information

Calendar to join existent platforms by TSOs in the SGRI: European Capacity Platform / others

TSOs to develop its own IT system to integrate the information from the capacity auctions

TSOs to collaborate bilaterally to develop IT systems for nomination and renomination of bundled capacity, CMP implementation, exchange information for balancing process.

3

II.1 Draft CAM Roadmap in the Region

Joint European CAM platform

Page 15: Madrid, 27 th  February 2013

15

Way forward

Public consultation of this document with Stakeholders- along this week: to be

launched in ACER website, comments will be welcome until 19th March

2013. (by regulators)

Final CAM Roadmap of the SGRI – March 2013 (approval by regulators)

Discussions and definition of the capacity products, available capacity and IT

systems– March/May 2013 (to be proposed by TSOs)

Start of the development of IT systems –Summer 2013 (by TSOs)

National regulation modification – Starting summer 2013 (by regulators)

II.1 Draft CAM Roadmap in the Region

Discussion and definition of CAM process

May 2013

Start development of IT SystemStart analysis regulation

changesSummer 2013

IT readyRegulation in place

Draft MOUsDecember 2013

Page 16: Madrid, 27 th  February 2013

16

Way forward (cont.)

Available capacity, Products, and IT systems. First draft to be presented in the next SG meeting (24th April). Available capacity in all borders, for the next 15 years, and proposal of capacity split

for the different auctions, from October 2014: virtual Point between Spain and Portugal, physical/virtual point between France and Spain, and inside France ( to be sent by TSOs to regulators before 15th March) .

IT development (to be sent by TSOs before 29th March)

Capacity allocation platform utilisation: what capabilities...

TSOs IT systems: what need to be developed and when, interface to support primary and secondary capacity markets, nomination and renomination schemes...

II.1 Draft CAM Roadmap in the Region

Page 17: Madrid, 27 th  February 2013

17

Way forward (cont.) Available capacity, Products, and IT systems. First draft to be presented in the next SG meeting (24 th

April). Products:

•Long term vision of the whole process: ( proposals to be sent by TSOs before 24th April)• Bundled, virtual auctions simultaneously conducted in the whole region• Definition of the auction mechanism ( reserve price, price steps, rounds, allocation of revenues...)

• Decision to be made prior to the auction announcement ( financial deposit, obligation to subscribe capacity, contracts, shippers licence...)

• Interruptible capacity• Unbundled capacity offer?

•Short – term decisions on the initial products and the calendar ( proposals to be sent by TSOs before 10th May)

• Interoperability amendments needed: (gas day, gas year, amendment of gas quality measurement and calendar)

• Decision on the Larrau capacity to be sold before March 2014, in two quarters, from April 2014 to September 2014. Pilot of the IT system in late 2013, early 2014?

• Allocation of yearly capacity in all borders in March 2014, quarterly capacity in June 2014, monthly capacity in September 2014...

II.1 Draft CAM Roadmap in the Region

Page 18: Madrid, 27 th  February 2013

18

II. Capacity Allocation Mechanisms

II.2. CAM between Spain-Portugal. Next auction

(for information by TSOs)

Page 19: Madrid, 27 th  February 2013

19

II.2 CAM between Spain-Portugal. Next auction

ENAGÁS and REN are developing the procedure of the 2nd annual auction

Issues already decided:

• Capacity Products to be offered for the gas year 1st Oct 2013 to 30th Sept 2014:

Firm yearly products

Firm quarterly products

Interruptible products if more than 95% of firm capacity has been allocated at the previous firm products auctions

Issues to be decided: IT system to allocate capacity?

To be proposed by TSOs by mid March

Page 20: Madrid, 27 th  February 2013

20

II.2 CAM between Spain-Portugal. Next auction

National regulations to be approved in advance in order stakeholders will be timely informed:

• Resolución CNE on methodology for the coordinated capacity allocation at the IP between Spain and Portugal.

• Mecanismo de atribuição de capacidade da RNTGN - ERSE

• Information Memorandum and Standard Contracts: to be elaborated by TSOs describing the procedures for the annual auction (following the Draft CAM NC): rules, price steps, reserve price, capacity offered, application form, contract information, calendar…. To be approved by NRAs.

Page 21: Madrid, 27 th  February 2013

21

II.2 CAM between Spain-Portugal. Next auction

CALENDAR for the 2nd annual auction between Spain and Portugal

2013Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

27: 21thIG

24: 20thSG

12: 22thIG

Stakeholders involvement

Issues to be decided

Development of National

regulations

Info Memo

Coordination NRASTSOs

NRAs/TSOs

REGULATION APPROVAL

IT system: development/ tests/formation/implementation

3rd June 2013 (first Monday-quarterly auctions)

Page 22: Madrid, 27 th  February 2013

22

III. Congestion Management Procedures

III.1. Draft CMP Roadmap in the Region

Area of work Responsible Starting Deadline

CMP harmonization in the whole region

NRAs-TSOs Oct. 2012 Oct. 2013

CMP harmonization in the whole region (including UIOLI firm ST)

NRAs-TSOs Oct. 2012 Jul. 2016

Page 23: Madrid, 27 th  February 2013

23

III. Congestion Management Procedures

III.1. Draft CMP Roadmap in the Region

• RCC meeting to discuss CMP the 13th March

• IG meeting at the end of March to share main ideas regarding CMPs. TSOs to propose preliminary Roadmap (videoteleconference)

• TSOs to send a final CMP Roadmap agreed by the four TSOs in May

Page 24: Madrid, 27 th  February 2013

24

IV. Investment

Area of work Responsible

Starting Deadline

Regular update and publication in CEER website of project status of OS 2013 and 2015

TSOs-NRAs Dec. (yearly) Jun. (yearly)

Drafting of the South Regional Investment Plan 2012 TSOs Jul. 2011 Jan. 2012 (COMPLETED)

Feedback to ENTSO-G on contents and methodology of the regional investment plan

NRAs Jan. 2012Jul. 2012(COMPLETED)

Input to ENTSO-G for the Community-wide TYNDP 2013

TSOs Jan. 2012 Apr. 2013

Creation of a working group in the region in order to test the process of PCI identification NRAs -TSOs Mar. 2012 March 2013

Drafting of the South Regional Investment Plan 2014 TSOs Jan. 2013 Apr. 2014

IV.1. Update on PCI Identification

IV.2. 2013 Gas Regional Investment Plan (GRIP)

Page 25: Madrid, 27 th  February 2013

25

IV. Investment

IV.1. Update on PCI Identification

(for information by Regulators)

Page 26: Madrid, 27 th  February 2013

26

IV.1. Update on PCI Identification

6th meeting held on 18 January: Previous meeting organized by EC with NRAs with the aim to know NRAs’ opinion. Summary on NRAS’ opinion on impact areas

• Main rule: a project must impact on at least two Member States to be eligible

• Clusters: projects considered in a cluster represent just one PCI.

• Presentation of analysis of qualitative and quantitative assessment carried out by consultants, as well as a preliminary PCIs list

• Main comments from attendants: impact areas, quantitative assessment (formulas application, parameters used, inputs, etc.). As a result, new calculations are being considered and a new list will be elaborated

• Participants were given time to send their opinion on impact areas and clusters

Next meeting to be held on 7th March 2013.

North-South Gas Interconnections in Western Europe

Page 27: Madrid, 27 th  February 2013

27

North-South interconnections in Western Europe

1º G82 TWINNING OF SOUTHWEST SCOTLAND ONSHORE SYSTEM Interconnection2º G58 REVERSE FLOW SWITZERLAND-FRANCE SECTION Interconnection3º G56 REVERSE CAPACITY FROM FRANCE TO BELGIUM Interconnection4º G48 MERGING OF GRTGAZ NORTH AND SOUTH ZONES Internal project5º G103 CONNECTION OF MALTA TO THE EUROPEAN GAS NETWORK Interconnection6º G61 NEW IP TO LUXEMBOURG Interconnection7º G136 PHYSICAL REVERSE FLOW AT MOFFAT INTERCONNECTION POINT Interconnection

8º G133+135 Physical reverse flow from Northern Ireland to Great Britain and Republic of Ireland via Scotland to Northern Ireland pipeline Interconnection

9º G114 3RD INTERCONNECTION POINT PORTUGAL-SPAIN Interconnection10º G45 ARC DE DIERREY Internal project11º G6 BRETELLA (GERMANY

‐BELGIUM) Interconnection

12º G5 RERVERSE FLOW (SOUTH

‐NORTH) FROM SWITZERLAND TO GERMANY Interconnection

13º G44 NEW LINE BETWEEN CHEMERY AND DIERREY Internal project14º G7&8 LNG TERMINAL ZEEBRUGGE

‐ CAPACITY EXTENSION & 2ND JETTY LNG

15º G60 IBERIAN-FRENCH CORRIDOR: EASTERN AXIS-MIDCAT PROJECT Interconnection

Order according to total score Project Code Project Name Type

IV.1. Update on PCI Identification

Page 28: Madrid, 27 th  February 2013

28

North-South interconnections in Western Europe

16º G10 BELGIUM/ LUXEMBOURG Interconnection17º G91 CROSS BORDER BI-DIRECTIONAL FLOWS (ITALY - SWITZERLAND) Interconnection18º G96 BAGNOLO MELLA GAS STORAGE Storage19º G104 GAS COMPRESSOR OPTIMISATION PROGRAM IN NETHERLANDS Interconnection20º G47 DEVELOPMENT OF ENTRY CAPACITIES IN THE SOUTH ZONE OF FRANCE Internal project21º G93 GALSI PROJECT(Gazoduc Algérie – Italie) Interconnection22º G59 REVERSE FLOW FR-DE Interconnection23º G28 Monaco Pipeline Interconnection24º G85 OLT OFFSHORE LNG TOSCANA SPA LNG25º G94 BORDOLANO Storage26º G57 NORTH-SOUTH FRANCE TO SWITZERLAND CAPACITY INCREASE Interconnection27º G88 PORTO EMPEDOCLE LNG TERMINAL LNG28º G79 SOUTHWEST KINSALE GAS STORAGE EXPANSION PROJECT Storage29º G144 CARRIÇO UGS DEVELOPMENT (REN-C8 E REN-C10) Storage30º G53 LNG MONTOIR TERMINAL EXPANSION LNG

Order according to total score Project Code Project Name Type

IV.1. Update on PCI Identification

Page 29: Madrid, 27 th  February 2013

29

North-South interconnections in Western Europe

31º G87 LNG Medgas Terminal LNG32º G52 LNG Fos Faster LNG33º G92 CORNEGLIANO UGS Storage34º G51 LNG FOS CAVAOU TERMINAL EXPANSION LNG35º G81 PHYSICAL REVERSE FLOW ON SOUTH NORTH PIPELINE (UK - IRELAND) Interconnection36º G78 KING STREET GAS STORAGE Storage37º G50 SALINS DES LANDES Storage38º G140 LES PINASSES UNDERGROUND GAS STORAGE Storage39º G80 Shannon LNG terminal LNG40º G54 Stublach storage Storage41º G113 UNDERGROUND STORAGE (UGS) CARRIÇO Storage42º G138 IBERIAN CORRIDOR: CROSS-BORDER OPTIMIZATION: EBRO VALLEY PROJECT Interconnection43º G46 ERIDAN Internal project44º G49 CONNECTING CORSICA TO GALSI (CYRENEE) Interconnection

Order according to total score Project Code Project Name Type

G55 Peckensen storage Storage

G139 PROJECT STUDY ON THE INTEGRATION OF POWER TO GAS (PTG) FACILITIES INTO THE GAS TRANSMISSION SYSTEM Storage

Main projects affecting the Region

Non eligible projects

IV.1. Update on PCI Identification

Page 30: Madrid, 27 th  February 2013

30

IV. Investment

IV.2. 2013 Gas Regional Investment Plan (GRIP)

(for information by TSOs)

Page 31: Madrid, 27 th  February 2013

31

V. AOB and next meetings

Page 32: Madrid, 27 th  February 2013

32

Meetings calendar for the first semester 2013

Next meetings:• 25th March, 15:00 CET , 22th IG (videoconference)• 24th April: 20th SG• 12th June: 23th IG