main ppt.pptx
TRANSCRIPT
-
7/27/2019 main ppt.pptx
1/28
D. Babu(101798)
-
7/27/2019 main ppt.pptx
2/28
The first central electric station was
installed by Edison in Newyork in1882 which is operated at 110v DC
It is interesting to know as to why
then AC almost replaced all DC lines
and why DC is again being used forsome high voltage transmission lines
-
7/27/2019 main ppt.pptx
3/28
Reasons for power generated,
transmitted, distributed andconsumed as alternating current
Transformer
Induction motors
Commutators
-
7/27/2019 main ppt.pptx
4/28
Strong technical reasons for direct
current transmission
High charging currents in AC Asynchronous interconnection
Economical after break even distance
-
7/27/2019 main ppt.pptx
5/28
Cost comparison of ac and dc
transmission
Cost of DC terminal
Cost of AC terminal
Cost
Break even distance
Distance in km
Cost of AC Line
Cost of DC Line
500 700 km
-
7/27/2019 main ppt.pptx
6/28
Types of HVDC links
Monopolar
Bipolar
Homopolar
-
7/27/2019 main ppt.pptx
7/28
Monopolar line
Usually the line is operated with negative
polarity as the corona loss and radio
interferences are less
-
7/27/2019 main ppt.pptx
8/28
Modes of Operation
DC OH Line
Converter
Transformer
Thyristor
Valves
400 kVAC Bus
AC Filters,
Reactors
Smoothing Reactor
Converter
Transformer
Thyristor
Valves
400 kVAC Bus
AC Filters
Smoothing ReactorBipolar
Current
Current
-
7/27/2019 main ppt.pptx
9/28
Modes of Operation
DC OH Line
Converter
Transformer
Thyristor
Valves
400 kVAC Bus
AC Filters,
Reactors
Smoothing Reactor
Converter
Transformer
Thyristor
Valves
400 kVAC Bus
AC Filters
Smoothing ReactorMonopolar Metallic Return
Current
-
7/27/2019 main ppt.pptx
10/28
Modes of Operation
DC OH Line
Converter
Transformer
Thyristor
Valves
400 kVAC Bus
AC Filters,
Reactors
Smoothing Reactor
Converter
Transformer
Thyristor
Valves
400 kVAC Bus
AC Filters
Smoothing ReactorMonopolar Ground Return
Current
-
7/27/2019 main ppt.pptx
11/28
Homopolar link
Two or more conductors with same polarity usually
negative for the reason of corona and radio interference
and always operate with ground as the return
-
7/27/2019 main ppt.pptx
12/28
Parallel and series connections ofthyristor
o Parallel -Current rating will increase
o Series voltage ratings will increase
-
7/27/2019 main ppt.pptx
13/28
Parallel operation of DC link with
AC network
Stability of AC network can be increased if it iskept in parallel with DC line
-
7/27/2019 main ppt.pptx
14/28
POWERGRID (Engg-HVDC)
Single Line Diagram
DC OH Line
ConverterTransformer
DC Filter:
DT 12/24
DT 12/36
DC Filter:
DT 12/24
DT 12/36
ThyristorValves
400 kVAC Bus
AC Filters,
Reactors
Talcher ConverterStation
Smoothing Reactor
ConverterTransformer
DC Filter:
DT 12/24
DT 12/36
DC Filter:
DT 12/24
DT 12/36
ThyristorValves
400 kVAC Bus
AC Filters
Kolar ConverterStation
Smoothing Reactor
-
7/27/2019 main ppt.pptx
15/28
6-Pulse Convertor Bridge
3
6
CiLs
4
E1 L
s
Ls
Bi
iA
1
2
I
V'd
5
Vd
IddL
d
-
7/27/2019 main ppt.pptx
16/28
12-Pulse Convertor Bridge
Y
-
7/27/2019 main ppt.pptx
17/28
POWERGRID (Engg-HVDC)
Salient Features
Rectifier Talcher, Orissa
Inverter Kolar, Karnataka
Distance 1400 km
Rated Power 2000 MW
Operating Voltage 500 kV DC
Reduced Voltage 400 kV DC
-
7/27/2019 main ppt.pptx
18/28
POWERGRID (Engg-HVDC)
Simplified SLD at Talcher
Y
YACF3 ACF1
Y
Y ACF2
Meramundali-I
Meramundali-II Rengali-II
Rengali-I
Rourkela-II
Rourkela-I
ICT
BS 1B
BS 1A
Gen 1Gen 2Gen 3Gen 4Gen 6
BS 2B
BS 2A
BS 3A
BS 3B
Pole2 Pole1
ICTGen 5
-
7/27/2019 main ppt.pptx
19/28
Bus # 3 Bus # 5
Bus # 4 Bus # 6
STAGE-II POWER FLOW SINGLE LINE DIAGRAM
GENERATOR # 6GENERATOR # 5GENERATOR # 4
ST # 2
GENERATOR # 3
ST # 3
HVDC # 1 HVDC # 2
GT # 5
HVDC # 3 HVDC # 4
HVDC POLE-2HVDC POLE-1
400 KV BUS-1
400 KV BUS-2
TO FILTER-2
MWT-6MWT-5MWT-4MWT-3
GT # 3 GT # 4
TO FILTER-1
GT # 6
-
7/27/2019 main ppt.pptx
20/28
POWERGRID (Engg-HVDC)
Simplified SLD at Kolar
Y
YACF2ACF1
Y
Y ACF3
Future
ICT
BS 1A
BS 1B
ICT
Pole1 Pole2
Chennai Hosur
I
Hosur
I
Hosur
II
Hoody
I
Hoody
II Bangalore
Cuddapah Future
Line
-
7/27/2019 main ppt.pptx
21/28
Logic for unit tripping during HVDC single
pole outage
block
blockdeblock
deblock
Pole 1 Pole 2
S
Power
>
1750
Trip
Identified
Unit
TSTPP Stg II all four Units running with full capacity
Ex-bus Generation shall be around 1850 MW or less.
While all four Units running, if one HVDC pole isblocked & NTPC Ex-bus Generation is more than 1750
MW, one identified unit shall trip instantaneously.
-
7/27/2019 main ppt.pptx
22/28
Logic for unit tripping during HVDC
Both pole outage
block block
Pole 1 Pole 2
S Power> 550
S Power> 1100
Trip Unit # 5
Trip Unit # 4
250 ms
500 ms
Trip
Unit # 6
T1
T2
-
7/27/2019 main ppt.pptx
23/28
Logic for unit tripping during HVDC Both pole
outage
Both HVDC poles blocked & TSTPP Stg II Ex-bus generation is morethan 550 MW & less than 1100MW.
Unit # 5 shall trip instantaneously.
Unit # 4 shall trip after time delay of 250 m sec.
Unit # 6 shall trip after time delay of 500 m sec.
Both HVDC poles blocked & TSTPP Stg II Ex-bus generation is more than 1100
MW.
Unit # 5 & 6 shall trip instantaneously.
Unit # 4 shall trip after time delay of 250 m sec.
-
7/27/2019 main ppt.pptx
24/28
Existing HVDC in INDIA
1 Rihand-Dadri (1500MW)
2 - Vindyachal (500MW)
3 - Chandrapur-Padghe (1500MW)
4 - Chandrapur-Ramagundam(1000MW)
5 Barsoor-Lower Sileru(100MW)
6 Gajuwaka (500MW)
7 - Sasaram (500MW)
8 - Talcher-Kolar (2000MW)
-
7/27/2019 main ppt.pptx
25/28
HVDC Bipolar LineChandrapur-PadgheRihand-Dadri
Talcher-KolarBalia-BhiwadiBiswanath-Agra
HVDC Back-to-backVindhachalChandrapurGazuwakaSasaram
HVDC Monopole LineBarsur-Lower Sileru
Existing HVDC projects in INDIA
-
7/27/2019 main ppt.pptx
26/28
Advantages
Power per conductor
Power per circuit
No charging current
No skin effect
Less corona loss and radio interference
No stability problem
Less short circuit currents
No compensation
-
7/27/2019 main ppt.pptx
27/28
Disadvantages
Expensive converters and transmission lines
Voltage transformations
DC circuit breaking is difficult
-
7/27/2019 main ppt.pptx
28/28