maintenance and building conceptual approach
DESCRIPTION
Maintenance and Building Conceptual Approach. L. Waganer and R. Peipert The Boeing Company 4 October 2006 PPPL Project Meeting. Maintenance Design Approach. Port maintenance adopted, replacing large blanket and divertor modules - PowerPoint PPT PresentationTRANSCRIPT
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 1
Maintenance and BuildingConceptual Approach
L. Waganer and R. PeipertThe Boeing Company
4 October 2006PPPL Project Meeting
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 2
Maintenance Design Approach• Port maintenance adopted, replacing large blanket and divertor modules
• Replace all first wall/blanket and diverter modules ECH launchers every 3.0 FPY. Remainder is life-of-plant.
– Blanket and divertor modules removable inside core
– ECH launcher designed as a removable assembly
• All power core maintenance fully robotic and automated based on prototypes and production plants
• Work simultaneously on all three field periods
• Employ maintenance machines inside fixed port transfer chambers just outside bio-shield
• Pass all used and new modules via airlocks to mobile transporters
• If conventional tube welding is used, auxiliary maintenance machines ports are needed. Remote disconnects would cut maintenance time by a factor of 4.
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 3
Compare similar 1950’s and 2000’s technologies and Project into the Future!
•Automobile Assembly
• Surgery (knee, hernia, heart, lung )
• Vision Correction (glasses vs. laser)
• Electronics (transistor vs. LSIC)
• Data Storage (tape drive » floppy drive
» hard drive » solid state) (20 yr time span)
Deburring movie Tool Changer movie
How To Forecast Maintenance Technologies 40-50 Years in Future?
Consider physical laws as limiting values
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 4
Mid-Plane View Shows Maintenance At Main and ECH/Aux Maintenance Ports
• Simultaneous maintenance in 3 FP
• Fixed Transfer Chambers control contamination and enhance times
• Mobile Transporters transfer used and new components to/from Hot Cell
• Main Port is used for removing blanket and divertor modules
• ECH launcher/waveguide removed as an assembly
• ECH port can then be used as Auxiliary maintenance port
• Manipulators inside Bioshield at center of power core remove divertor inner tubes and shielding and cut outer divertor tube/support
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 5
Example of Pallet Transfer Technology for ECH Module Assembly
We may want to adapt a conveyor approach similar to the efficient pallet handling transfer system used in freighter aircraft, C5, C17, C141, et. al.
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 6
Removable ECH Assembly at 35º PortECH Waveguide, 0.54 m H x 0.24 m WOpening in VV and Coil Structure, 1.54m H x 1.24 m WOpening through Bioshield, 1.6 m H x 1.6 m W
Note: Removable ECH Module includesWaveguide, All Shielding, Bioshield, Mirror, and Exo-Bioshield Vacuum Vessel
PermanentTransfer Chamber
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 7
Extraction of ECH Assembly Into Transfer Chamber • Maintenance machine removes
waveguide segment and coolant coupling
• Complete assembly removed into Transfer Chamber by pallet system
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 8
ECH Module Moved Into Mobile Transporter for Transit to Hot Cell for Refurbishment
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 9
ECH/Aux Port Maintenance ActionsRemoves blanket shielding blocks, shielding rings, and cuts coolant tubes
while main port arm supports and removes blankets
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 10
View of Main Port (0º), Operational
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 11
Initial Position of Extractor Machine
• This is the position of Extractor after plasma shutdown and cool-down
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 12
First Action Is To Remove Bioshield Door
• After the door is positioned inside Transfer Chamber, bridging structure is positioned
• Vacuum vessel door and port shielding is removed and set aside inside Transfer Chamber
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 13
Removal of Port Manifold/Structure
• The manifold/hot structure connections are disconnected and the structure is removed and set aside
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 14
Removal of Port Blanket and Shield
• This port blanket and shield module is the largest component to be removed
• It is also the only module that has an integral shield
• It is sized to clear port opening and provide maximum access to interior of power core
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 15
Design Approach to Extract Inner Coolant Tube and Shielding to Access Welded Joint
• If welded joints are to be used to secure outer divertor coolant tubes, joint must be shielded
• Entire inner tube and shielding assembly is removed allowing access to outer tube weld region
• Access is from outside of coil structure near center of machine
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 16
Removal of Divertor Tubes and Shielding
• The inner tubes and shielding for the Divertor plates are removed by floor and ceiling mounted manipulators (24 places at ± 12.5°)
• This is done simultaneously with ECH assembly removal and main port opening procedures
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 17
Preparation for Divertor Plate Removal
• This depicts the main port Extractor holding the Divertor Plates (24 pl) while the cutting bore tool on the central manipulator severs the outer coolant tube, which is the Divertor structural support
• The Diverter plates span two blanket modules but they fit through the main port opening
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 18
Divertor Plate Removal
• This view shows the removal of the Divertor plates
• After removal, they are moved to the Hot Cell via the Mobile Transporter
• During this step, the inner manipulator can be removing other coolant tube assemblies
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 19
Removal of Blanket Modules
• This is a typical procedure for removal of the blanket modules
• The Blanket modules are attached to the Hot Shield with four fasteners deep within the blanket close to the Hot Shield
• Tools disengage the fasteners while gripping the walls of the access holes, thus providing holding force for fastener removal and blanket handling
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 20
Removal of Blanket Module (Cont’d)
• Blanket module is being removed from Power Core and placed in Mobile Transporter
• As soon as this module is moved from its position on the Hot Shield, the Auxiliary Manipulators can begin to remove the shield blocks and shield rings for access to and severing the Blanket coolant tubes
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 21
Maintenance and Availability Analysis
Availability AnalysisSummary of Maintenance Actions Maint Days, Total Maint Days/FPY Availability
Scheduled Power Core, Major 50.27 16.76 95.6%Scheduled Power Core, Minor (ref ARIES-AT) 6.05 98.4%
Unscheduled Power Core (ref ARIES-AT) 20.56 94.7%Reactor Plant Equipment, Sched + UnSched (ref ARIES-AT) 9.27 97.5%
Balance of Plant, Sched + UnSched (ref ARIES-AT) 9.37 97.5%Total 84.7%
Main Port Shutdown Port OpeningDivertor Plates
Shielding Blocks
&Blanket Modules
Shielding Rings & Coolant Tubes
Shield & Support System
Insp.
Shielding Rings & Coolant Tubes
Shielding Blocks
&Blanket Modules
Divertor Plates
Chamber Inspection
Port Installation
Start-Up
TaskShutdown &
Prep for Maint.
Open Three Main Maint.
Ports
Twenty-four Divertor
Plates (8 x 3 Sectors)
Blanket Modules (65 x 3 Sectors)
Shielding Rings & Inner Coolant Tube
(65 x 2 x 3 Sectors)
Inspect, Clean &
Vacuum - Inspect Repairs
Shielding Rings & Inner Coolant Tube
(65 x 2 x 3 Sectors)
Blanket Modules (65 x 3 Sectors)
Twenty-four Divertor
Plates (8 x 3 Sectors)
Inspect Chamber
After Build-Up
Close Three Main Maint.
Ports
Inspect, Diagnostics &
Prep for Operation
Time (Hrs) 30.00 10.20 20.40 240.50 139.75 26.00 230.75 429.00 26.40 2.00 13.40 38.00
ECH/Aux Port ShutdownECH
Assembly
Shielding Blocks
&Blanket Modules
Shielding Rings & Coolant Tubes
Shield & Support System
Insp.
Shielding Rings & Coolant Tubes
Shielding Blocks
&Blanket Modules
Chamber Inspection
ECH Installation
Start-Up
TaskShutdown &
Prep for Maint.
Remove Three ECH
Assemblies
Shielding Blocks & Cut Weld (65x 6 x 3 Sectors)
Shielding Rings & Inner Coolant Tube
(65 x 2 x 3 Sectors)
Make Any Needed Repairs
Shielding Rings & Inner Coolant Tube
(65 x 2 x 3 Sectors)
Shielding Blocks &
Welds (65x 6 x 3 Sectors)
Inspect Chamber
After Build-Up
Install Three ECH
Assemblies
Time (Hrs) 30.00 8.40 240.50 139.75 24.00 230.75 429.00 2.00 9.60 38.00
BIO-Chamber ShutdownDivertor Coolant Tubes
Divertor Plates
Shield & Support System
Insp.
Divertor Plates
NDI WeldsCoolant Tubes
InstallationStart-Up
TaskShutdown &
Prep for Maint.
Twenty-four Coolant Tubes (8 x 3 Sectors)
Cut Plates Coolant Tube Weld (8 x 3
Sectors)
Inspect Outside for Damage &
Repair
Weld Plates Coolant Tube
(8 x 3 Sectors)
Complete Coolant Tube Weld Inspect.
Twenty-four Coolant
Tubes (8 x 3 Sectors)
Time (Hrs) 30.00 9.40 20.40 12.00 26.40 0.55 13.10 38.00
Total Time (Hrs)
Total Time (Hrs)
KEYSOperational Tasks
Parallel/Simultaneous Tasks
ARIES MAINTENANCE TASKS
Disassembly 466.85 Hrs. Replacement 739.55 Hrs.
Total Maintenance Time 1,206.40 Hrs. Inherent Availability 95.6%
Removal Tasks Replacement Tasks
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 22
Alternative to Cutting and WeldingBlanket Coolant Tubes
Current Technology
• Embed shielding blocks and rings to protect weld region
• Time-consuming procedure that generates contamination
Proposed Future Technology
• Remotely operated coolant clamp, Marmon type?
• Clamp and actuating mechanism can be replaced during refurbishment period
• Eliminates need for auxiliary port and equipment
• Reduces core maintenance time by factor of 4
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 23
Main Port Shutdown Port OpeningDivertor Plates
Blanket Modules
Shielding Rings & Coolant Tubes
Shield & Support System
Insp.
Shielding Rings & Coolant Tubes
Blanket Modules
Divertor Plates
Chamber Inspection
Port Installation
Start-Up
TaskShutdown &
Prep for Maint.
Open Three Main Maint.
Ports
Twenty-four Divertor
Plates (8 x 3 Sectors)
Blanket Modules (65 x 3 Sectors)
N/A
Inspect, Clean &
Vacuum - Inspect Repairs
N/ABlanket
Modules (65 x 3 Sectors)
Twenty-four Divertor
Plates (8 x 3 Sectors)
Inspect Chamber
After Build-Up
Close Three Main Maint.
Ports
Inspect, Diagnostics &
Prep for Operation
Time (Hrs) 30.00 10.20 20.40 72.80 26.00 53.40 26.40 2.00 13.40 38.00
ECH/Aux Port ShutdownECH
Assembly
Shielding Rings & Coolant Tubes
Shield & Support System
Insp.
Shielding Rings & Coolant Tubes
Chamber Inspection
ECH Installation
Start-Up
TaskShutdown &
Prep for Maint.
Remove Three ECH
AssembliesN/A
Make Any Needed Repairs
N/A
Inspect Chamber
After Build-Up
Install Three ECH
Assemblies
Time (Hrs) 30.00 8.40 24.00 2.00 9.60 38.00
BIO-Chamber ShutdownDivertor Coolant Tubes
Divertor Plates
Shield & Support System
Insp.
Divertor Plates
NDI WeldsCoolant Tubes
InstallationStart-Up
TaskShutdown &
Prep for Maint.
Twenty-four Coolant Tubes (8 x 3 Sectors)
Cut Plates Coolant Tube Weld (8 x 3
Sectors)
Inspect Outside for Damage &
Repair
Weld Plates Coolant Tube
(8 x 3 Sectors)
Complete Coolant Tube Weld Inspect.
Twenty-four Coolant
Tubes (8 x 3 Sectors)
Time (Hrs) 30.00 9.40 20.40 12.00 26.40 0.55 13.10 38.00
Total Time (Hrs)
Total Time (Hrs) Total Maintenance Time 292.6 Hrs. Inherent Availability 98.9%
KEYSOperational Tasks
Parallel/Simultaneous Tasks
Aries Estimated Maintenance Times = Using Couplings ConnectionsRemoval Tasks Replacement Tasks
Disassembly 159.4 Hrs. Replacement 133.2 Hrs.
Maintenance and Availability Analysis
Advanced Remote Coolant DisconnectsSummary of Maintenance Actions Maint Days, Total Maint Days/FPY Availability
Scheduled Power Core, Major 12.19 4.06 98.9%Scheduled Power Core, Minor (ref ARIES-AT) 6.05 98.4%
Unscheduled Power Core (ref ARIES-AT) 20.56 94.7%Reactor Plant Equipment, Sched + UnSched (ref ARIES-AT) 9.27 97.5%
Balance of Plant, Sched + UnSched (ref ARIES-AT) 9.37 97.5%Total 87.6%
Yearly Electricity Capacity 8,766,000,000 kwhrPrice of Electricity $0.065 $/kwhr
Availability Revenue 100.00% $569,790,000
87.60% $499,136,04084.70% $482,612,130 $16.5 M Lost Revenue
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 24
Maintenance Slides for Engineering Summary
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 25
Maintenance Design Approach• Port maintenance adopted, replacing large blanket and divertor modules
• Replace all first wall/blanket and diverter modules ECH launchers every 3.0 FPY. Remainder is life-of-plant.
– Blanket and divertor modules removable inside core
– ECH launcher designed as a removable assembly
• All power core maintenance fully robotic and automated based on prototypes and production plants
• Work simultaneously on all three field periods
• Employ maintenance machines inside fixed port transfer chambers just outside bio-shield
• Pass all used and new modules via airlocks to mobile transporters
• If conventional tube welding is used, auxiliary maintenance machines ports are needed. Remote disconnects would cut maintenance time by a factor of 4.
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 26
Mid-Plane View Shows Maintenance At Main and ECH/Aux Maintenance Ports
• Simultaneous maintenance in 3 FP
• Fixed Transfer Chambers control contamination and enhance times
• Mobile Transporters transfer used and new components to/from Hot Cell
• Main Port is used for removing blanket and divertor modules
• ECH launcher/waveguide removed as an assembly
• ECH port can then be used as Auxiliary maintenance port
• Manipulators inside Bioshield at center of power core remove divertor inner tubes and shielding and cut outer divertor tube/support
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 27
Removable ECH Assembly/ Auxiliary Maintenance Port
• Removable ECH Module includes Waveguide, All Shielding, Bioshield, Mirror, and Exo-Bioshield Vacuum Vessel
• Entire module assembly can be withdrawn into Transfer Chamber
PermanentTransfer Chamber
Aux Manipulator removes blanket shielding blocks, shielding rings, and cuts coolant tubes while main port arm supports and removes blankets
ECH Module Moved Into Mobile Transporter for Transit to Hot Cell for Refurbishment
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 28
Preparation for Divertor Plate Removal
• This depicts the main port Extractor holding the Divertor Plates (24 pl) while the cutting bore tool on the central manipulator severs the outer coolant tube, which is the Divertor structural support
• The Diverter plates span two blanket modules but they fit through the main port opening
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 29
Maintenance and Availability Analysis
Availability AnalysisSummary of Maintenance Actions Maint Days, Total Maint Days/FPY Availability
Scheduled Power Core, Major 50.27 16.76 95.6%Scheduled Power Core, Minor (ref ARIES-AT) 6.05 98.4%
Unscheduled Power Core (ref ARIES-AT) 20.56 94.7%Reactor Plant Equipment, Sched + UnSched (ref ARIES-AT) 9.27 97.5%
Balance of Plant, Sched + UnSched (ref ARIES-AT) 9.37 97.5%Total 84.7%
Main Port Shutdown Port OpeningDivertor Plates
Shielding Blocks
&Blanket Modules
Shielding Rings & Coolant Tubes
Shield & Support System
Insp.
Shielding Rings & Coolant Tubes
Shielding Blocks
&Blanket Modules
Divertor Plates
Chamber Inspection
Port Installation
Start-Up
TaskShutdown &
Prep for Maint.
Open Three Main Maint.
Ports
Twenty-four Divertor
Plates (8 x 3 Sectors)
Blanket Modules (65 x 3 Sectors)
Shielding Rings & Inner Coolant Tube
(65 x 2 x 3 Sectors)
Inspect, Clean &
Vacuum - Inspect Repairs
Shielding Rings & Inner Coolant Tube
(65 x 2 x 3 Sectors)
Blanket Modules (65 x 3 Sectors)
Twenty-four Divertor
Plates (8 x 3 Sectors)
Inspect Chamber
After Build-Up
Close Three Main Maint.
Ports
Inspect, Diagnostics &
Prep for Operation
Time (Hrs) 30.00 10.20 20.40 240.50 139.75 26.00 230.75 429.00 26.40 2.00 13.40 38.00
ECH/Aux Port ShutdownECH
Assembly
Shielding Blocks
&Blanket Modules
Shielding Rings & Coolant Tubes
Shield & Support System
Insp.
Shielding Rings & Coolant Tubes
Shielding Blocks
&Blanket Modules
Chamber Inspection
ECH Installation
Start-Up
TaskShutdown &
Prep for Maint.
Remove Three ECH
Assemblies
Shielding Blocks & Cut Weld (65x 6 x 3 Sectors)
Shielding Rings & Inner Coolant Tube
(65 x 2 x 3 Sectors)
Make Any Needed Repairs
Shielding Rings & Inner Coolant Tube
(65 x 2 x 3 Sectors)
Shielding Blocks &
Welds (65x 6 x 3 Sectors)
Inspect Chamber
After Build-Up
Install Three ECH
Assemblies
Time (Hrs) 30.00 8.40 240.50 139.75 24.00 230.75 429.00 2.00 9.60 38.00
BIO-Chamber ShutdownDivertor Coolant Tubes
Divertor Plates
Shield & Support System
Insp.
Divertor Plates
NDI WeldsCoolant Tubes
InstallationStart-Up
TaskShutdown &
Prep for Maint.
Twenty-four Coolant Tubes (8 x 3 Sectors)
Cut Plates Coolant Tube Weld (8 x 3
Sectors)
Inspect Outside for Damage &
Repair
Weld Plates Coolant Tube
(8 x 3 Sectors)
Complete Coolant Tube Weld Inspect.
Twenty-four Coolant
Tubes (8 x 3 Sectors)
Time (Hrs) 30.00 9.40 20.40 12.00 26.40 0.55 13.10 38.00
Total Time (Hrs)
Total Time (Hrs)
KEYSOperational Tasks
Parallel/Simultaneous Tasks
ARIES MAINTENANCE TASKS
Disassembly 466.85 Hrs. Replacement 739.55 Hrs.
Total Maintenance Time 1,206.40 Hrs. Inherent Availability 95.6%
Removal Tasks Replacement Tasks