maintenance and building conceptual approach

29
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006 Page 1 Maintenance and Building Conceptual Approach L. Waganer and R. Peipert The Boeing Company 4 October 2006 PPPL Project Meeting

Upload: tara

Post on 04-Feb-2016

112 views

Category:

Documents


0 download

DESCRIPTION

Maintenance and Building Conceptual Approach. L. Waganer and R. Peipert The Boeing Company 4 October 2006 PPPL Project Meeting. Maintenance Design Approach. Port maintenance adopted, replacing large blanket and divertor modules - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 1

Maintenance and BuildingConceptual Approach

L. Waganer and R. PeipertThe Boeing Company

4 October 2006PPPL Project Meeting

Page 2: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 2

Maintenance Design Approach• Port maintenance adopted, replacing large blanket and divertor modules

• Replace all first wall/blanket and diverter modules ECH launchers every 3.0 FPY. Remainder is life-of-plant.

– Blanket and divertor modules removable inside core

– ECH launcher designed as a removable assembly

• All power core maintenance fully robotic and automated based on prototypes and production plants

• Work simultaneously on all three field periods

• Employ maintenance machines inside fixed port transfer chambers just outside bio-shield

• Pass all used and new modules via airlocks to mobile transporters

• If conventional tube welding is used, auxiliary maintenance machines ports are needed. Remote disconnects would cut maintenance time by a factor of 4.

Page 3: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 3

Compare similar 1950’s and 2000’s technologies and Project into the Future!

•Automobile Assembly

• Surgery (knee, hernia, heart, lung )

• Vision Correction (glasses vs. laser)

• Electronics (transistor vs. LSIC)

• Data Storage (tape drive » floppy drive

» hard drive » solid state) (20 yr time span)

Deburring movie Tool Changer movie

How To Forecast Maintenance Technologies 40-50 Years in Future?

Consider physical laws as limiting values

Page 4: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 4

Mid-Plane View Shows Maintenance At Main and ECH/Aux Maintenance Ports

• Simultaneous maintenance in 3 FP

• Fixed Transfer Chambers control contamination and enhance times

• Mobile Transporters transfer used and new components to/from Hot Cell

• Main Port is used for removing blanket and divertor modules

• ECH launcher/waveguide removed as an assembly

• ECH port can then be used as Auxiliary maintenance port

• Manipulators inside Bioshield at center of power core remove divertor inner tubes and shielding and cut outer divertor tube/support

Page 5: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 5

Example of Pallet Transfer Technology for ECH Module Assembly

We may want to adapt a conveyor approach similar to the efficient pallet handling transfer system used in freighter aircraft, C5, C17, C141, et. al.

Page 6: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 6

Removable ECH Assembly at 35º PortECH Waveguide, 0.54 m H x 0.24 m WOpening in VV and Coil Structure, 1.54m H x 1.24 m WOpening through Bioshield, 1.6 m H x 1.6 m W

Note: Removable ECH Module includesWaveguide, All Shielding, Bioshield, Mirror, and Exo-Bioshield Vacuum Vessel

PermanentTransfer Chamber

Page 7: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 7

Extraction of ECH Assembly Into Transfer Chamber • Maintenance machine removes

waveguide segment and coolant coupling

• Complete assembly removed into Transfer Chamber by pallet system

Page 8: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 8

ECH Module Moved Into Mobile Transporter for Transit to Hot Cell for Refurbishment

Page 9: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 9

ECH/Aux Port Maintenance ActionsRemoves blanket shielding blocks, shielding rings, and cuts coolant tubes

while main port arm supports and removes blankets

Page 10: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 10

View of Main Port (0º), Operational

Page 11: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 11

Initial Position of Extractor Machine

• This is the position of Extractor after plasma shutdown and cool-down

Page 12: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 12

First Action Is To Remove Bioshield Door

• After the door is positioned inside Transfer Chamber, bridging structure is positioned

• Vacuum vessel door and port shielding is removed and set aside inside Transfer Chamber

Page 13: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 13

Removal of Port Manifold/Structure

• The manifold/hot structure connections are disconnected and the structure is removed and set aside

Page 14: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 14

Removal of Port Blanket and Shield

• This port blanket and shield module is the largest component to be removed

• It is also the only module that has an integral shield

• It is sized to clear port opening and provide maximum access to interior of power core

Page 15: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 15

Design Approach to Extract Inner Coolant Tube and Shielding to Access Welded Joint

• If welded joints are to be used to secure outer divertor coolant tubes, joint must be shielded

• Entire inner tube and shielding assembly is removed allowing access to outer tube weld region

• Access is from outside of coil structure near center of machine

Page 16: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 16

Removal of Divertor Tubes and Shielding

• The inner tubes and shielding for the Divertor plates are removed by floor and ceiling mounted manipulators (24 places at ± 12.5°)

• This is done simultaneously with ECH assembly removal and main port opening procedures

Page 17: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 17

Preparation for Divertor Plate Removal

• This depicts the main port Extractor holding the Divertor Plates (24 pl) while the cutting bore tool on the central manipulator severs the outer coolant tube, which is the Divertor structural support

• The Diverter plates span two blanket modules but they fit through the main port opening

Page 18: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 18

Divertor Plate Removal

• This view shows the removal of the Divertor plates

• After removal, they are moved to the Hot Cell via the Mobile Transporter

• During this step, the inner manipulator can be removing other coolant tube assemblies

Page 19: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 19

Removal of Blanket Modules

• This is a typical procedure for removal of the blanket modules

• The Blanket modules are attached to the Hot Shield with four fasteners deep within the blanket close to the Hot Shield

• Tools disengage the fasteners while gripping the walls of the access holes, thus providing holding force for fastener removal and blanket handling

Page 20: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 20

Removal of Blanket Module (Cont’d)

• Blanket module is being removed from Power Core and placed in Mobile Transporter

• As soon as this module is moved from its position on the Hot Shield, the Auxiliary Manipulators can begin to remove the shield blocks and shield rings for access to and severing the Blanket coolant tubes

Page 21: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 21

Maintenance and Availability Analysis

Availability AnalysisSummary of Maintenance Actions Maint Days, Total Maint Days/FPY Availability

Scheduled Power Core, Major 50.27 16.76 95.6%Scheduled Power Core, Minor (ref ARIES-AT) 6.05 98.4%

Unscheduled Power Core (ref ARIES-AT) 20.56 94.7%Reactor Plant Equipment, Sched + UnSched (ref ARIES-AT) 9.27 97.5%

Balance of Plant, Sched + UnSched (ref ARIES-AT) 9.37 97.5%Total 84.7%

Main Port Shutdown Port OpeningDivertor Plates

Shielding Blocks

&Blanket Modules

Shielding Rings & Coolant Tubes

Shield & Support System

Insp.

Shielding Rings & Coolant Tubes

Shielding Blocks

&Blanket Modules

Divertor Plates

Chamber Inspection

Port Installation

Start-Up

TaskShutdown &

Prep for Maint.

Open Three Main Maint.

Ports

Twenty-four Divertor

Plates (8 x 3 Sectors)

Blanket Modules (65 x 3 Sectors)

Shielding Rings & Inner Coolant Tube

(65 x 2 x 3 Sectors)

Inspect, Clean &

Vacuum - Inspect Repairs

Shielding Rings & Inner Coolant Tube

(65 x 2 x 3 Sectors)

Blanket Modules (65 x 3 Sectors)

Twenty-four Divertor

Plates (8 x 3 Sectors)

Inspect Chamber

After Build-Up

Close Three Main Maint.

Ports

Inspect, Diagnostics &

Prep for Operation

Time (Hrs) 30.00 10.20 20.40 240.50 139.75 26.00 230.75 429.00 26.40 2.00 13.40 38.00

ECH/Aux Port ShutdownECH

Assembly

Shielding Blocks

&Blanket Modules

Shielding Rings & Coolant Tubes

Shield & Support System

Insp.

Shielding Rings & Coolant Tubes

Shielding Blocks

&Blanket Modules

Chamber Inspection

ECH Installation

Start-Up

TaskShutdown &

Prep for Maint.

Remove Three ECH

Assemblies

Shielding Blocks & Cut Weld (65x 6 x 3 Sectors)

Shielding Rings & Inner Coolant Tube

(65 x 2 x 3 Sectors)

Make Any Needed Repairs

Shielding Rings & Inner Coolant Tube

(65 x 2 x 3 Sectors)

Shielding Blocks &

Welds (65x 6 x 3 Sectors)

Inspect Chamber

After Build-Up

Install Three ECH

Assemblies

Time (Hrs) 30.00 8.40 240.50 139.75 24.00 230.75 429.00 2.00 9.60 38.00

BIO-Chamber ShutdownDivertor Coolant Tubes

Divertor Plates

Shield & Support System

Insp.

Divertor Plates

NDI WeldsCoolant Tubes

InstallationStart-Up

TaskShutdown &

Prep for Maint.

Twenty-four Coolant Tubes (8 x 3 Sectors)

Cut Plates Coolant Tube Weld (8 x 3

Sectors)

Inspect Outside for Damage &

Repair

Weld Plates Coolant Tube

(8 x 3 Sectors)

Complete Coolant Tube Weld Inspect.

Twenty-four Coolant

Tubes (8 x 3 Sectors)

Time (Hrs) 30.00 9.40 20.40 12.00 26.40 0.55 13.10 38.00

Total Time (Hrs)

Total Time (Hrs)

KEYSOperational Tasks

Parallel/Simultaneous Tasks

ARIES MAINTENANCE TASKS

Disassembly 466.85 Hrs. Replacement 739.55 Hrs.

Total Maintenance Time 1,206.40 Hrs. Inherent Availability 95.6%

Removal Tasks Replacement Tasks

Page 22: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 22

Alternative to Cutting and WeldingBlanket Coolant Tubes

Current Technology

• Embed shielding blocks and rings to protect weld region

• Time-consuming procedure that generates contamination

Proposed Future Technology

• Remotely operated coolant clamp, Marmon type?

• Clamp and actuating mechanism can be replaced during refurbishment period

• Eliminates need for auxiliary port and equipment

• Reduces core maintenance time by factor of 4

Page 23: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 23

Main Port Shutdown Port OpeningDivertor Plates

Blanket Modules

Shielding Rings & Coolant Tubes

Shield & Support System

Insp.

Shielding Rings & Coolant Tubes

Blanket Modules

Divertor Plates

Chamber Inspection

Port Installation

Start-Up

TaskShutdown &

Prep for Maint.

Open Three Main Maint.

Ports

Twenty-four Divertor

Plates (8 x 3 Sectors)

Blanket Modules (65 x 3 Sectors)

N/A

Inspect, Clean &

Vacuum - Inspect Repairs

N/ABlanket

Modules (65 x 3 Sectors)

Twenty-four Divertor

Plates (8 x 3 Sectors)

Inspect Chamber

After Build-Up

Close Three Main Maint.

Ports

Inspect, Diagnostics &

Prep for Operation

Time (Hrs) 30.00 10.20 20.40 72.80 26.00 53.40 26.40 2.00 13.40 38.00

ECH/Aux Port ShutdownECH

Assembly

Shielding Rings & Coolant Tubes

Shield & Support System

Insp.

Shielding Rings & Coolant Tubes

Chamber Inspection

ECH Installation

Start-Up

TaskShutdown &

Prep for Maint.

Remove Three ECH

AssembliesN/A

Make Any Needed Repairs

N/A

Inspect Chamber

After Build-Up

Install Three ECH

Assemblies

Time (Hrs) 30.00 8.40 24.00 2.00 9.60 38.00

BIO-Chamber ShutdownDivertor Coolant Tubes

Divertor Plates

Shield & Support System

Insp.

Divertor Plates

NDI WeldsCoolant Tubes

InstallationStart-Up

TaskShutdown &

Prep for Maint.

Twenty-four Coolant Tubes (8 x 3 Sectors)

Cut Plates Coolant Tube Weld (8 x 3

Sectors)

Inspect Outside for Damage &

Repair

Weld Plates Coolant Tube

(8 x 3 Sectors)

Complete Coolant Tube Weld Inspect.

Twenty-four Coolant

Tubes (8 x 3 Sectors)

Time (Hrs) 30.00 9.40 20.40 12.00 26.40 0.55 13.10 38.00

Total Time (Hrs)

Total Time (Hrs) Total Maintenance Time 292.6 Hrs. Inherent Availability 98.9%

KEYSOperational Tasks

Parallel/Simultaneous Tasks

Aries Estimated Maintenance Times = Using Couplings ConnectionsRemoval Tasks Replacement Tasks

Disassembly 159.4 Hrs. Replacement 133.2 Hrs.

Maintenance and Availability Analysis

Advanced Remote Coolant DisconnectsSummary of Maintenance Actions Maint Days, Total Maint Days/FPY Availability

Scheduled Power Core, Major 12.19 4.06 98.9%Scheduled Power Core, Minor (ref ARIES-AT) 6.05 98.4%

Unscheduled Power Core (ref ARIES-AT) 20.56 94.7%Reactor Plant Equipment, Sched + UnSched (ref ARIES-AT) 9.27 97.5%

Balance of Plant, Sched + UnSched (ref ARIES-AT) 9.37 97.5%Total 87.6%

Yearly Electricity Capacity 8,766,000,000 kwhrPrice of Electricity $0.065 $/kwhr

Availability Revenue 100.00% $569,790,000

87.60% $499,136,04084.70% $482,612,130 $16.5 M Lost Revenue

Page 24: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 24

Maintenance Slides for Engineering Summary

Page 25: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 25

Maintenance Design Approach• Port maintenance adopted, replacing large blanket and divertor modules

• Replace all first wall/blanket and diverter modules ECH launchers every 3.0 FPY. Remainder is life-of-plant.

– Blanket and divertor modules removable inside core

– ECH launcher designed as a removable assembly

• All power core maintenance fully robotic and automated based on prototypes and production plants

• Work simultaneously on all three field periods

• Employ maintenance machines inside fixed port transfer chambers just outside bio-shield

• Pass all used and new modules via airlocks to mobile transporters

• If conventional tube welding is used, auxiliary maintenance machines ports are needed. Remote disconnects would cut maintenance time by a factor of 4.

Page 26: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 26

Mid-Plane View Shows Maintenance At Main and ECH/Aux Maintenance Ports

• Simultaneous maintenance in 3 FP

• Fixed Transfer Chambers control contamination and enhance times

• Mobile Transporters transfer used and new components to/from Hot Cell

• Main Port is used for removing blanket and divertor modules

• ECH launcher/waveguide removed as an assembly

• ECH port can then be used as Auxiliary maintenance port

• Manipulators inside Bioshield at center of power core remove divertor inner tubes and shielding and cut outer divertor tube/support

Page 27: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 27

Removable ECH Assembly/ Auxiliary Maintenance Port

• Removable ECH Module includes Waveguide, All Shielding, Bioshield, Mirror, and Exo-Bioshield Vacuum Vessel

• Entire module assembly can be withdrawn into Transfer Chamber

PermanentTransfer Chamber

Aux Manipulator removes blanket shielding blocks, shielding rings, and cuts coolant tubes while main port arm supports and removes blankets

ECH Module Moved Into Mobile Transporter for Transit to Hot Cell for Refurbishment

Page 28: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 28

Preparation for Divertor Plate Removal

• This depicts the main port Extractor holding the Divertor Plates (24 pl) while the cutting bore tool on the central manipulator severs the outer coolant tube, which is the Divertor structural support

• The Diverter plates span two blanket modules but they fit through the main port opening

Page 29: Maintenance and Building Conceptual Approach

ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006Page 29

Maintenance and Availability Analysis

Availability AnalysisSummary of Maintenance Actions Maint Days, Total Maint Days/FPY Availability

Scheduled Power Core, Major 50.27 16.76 95.6%Scheduled Power Core, Minor (ref ARIES-AT) 6.05 98.4%

Unscheduled Power Core (ref ARIES-AT) 20.56 94.7%Reactor Plant Equipment, Sched + UnSched (ref ARIES-AT) 9.27 97.5%

Balance of Plant, Sched + UnSched (ref ARIES-AT) 9.37 97.5%Total 84.7%

Main Port Shutdown Port OpeningDivertor Plates

Shielding Blocks

&Blanket Modules

Shielding Rings & Coolant Tubes

Shield & Support System

Insp.

Shielding Rings & Coolant Tubes

Shielding Blocks

&Blanket Modules

Divertor Plates

Chamber Inspection

Port Installation

Start-Up

TaskShutdown &

Prep for Maint.

Open Three Main Maint.

Ports

Twenty-four Divertor

Plates (8 x 3 Sectors)

Blanket Modules (65 x 3 Sectors)

Shielding Rings & Inner Coolant Tube

(65 x 2 x 3 Sectors)

Inspect, Clean &

Vacuum - Inspect Repairs

Shielding Rings & Inner Coolant Tube

(65 x 2 x 3 Sectors)

Blanket Modules (65 x 3 Sectors)

Twenty-four Divertor

Plates (8 x 3 Sectors)

Inspect Chamber

After Build-Up

Close Three Main Maint.

Ports

Inspect, Diagnostics &

Prep for Operation

Time (Hrs) 30.00 10.20 20.40 240.50 139.75 26.00 230.75 429.00 26.40 2.00 13.40 38.00

ECH/Aux Port ShutdownECH

Assembly

Shielding Blocks

&Blanket Modules

Shielding Rings & Coolant Tubes

Shield & Support System

Insp.

Shielding Rings & Coolant Tubes

Shielding Blocks

&Blanket Modules

Chamber Inspection

ECH Installation

Start-Up

TaskShutdown &

Prep for Maint.

Remove Three ECH

Assemblies

Shielding Blocks & Cut Weld (65x 6 x 3 Sectors)

Shielding Rings & Inner Coolant Tube

(65 x 2 x 3 Sectors)

Make Any Needed Repairs

Shielding Rings & Inner Coolant Tube

(65 x 2 x 3 Sectors)

Shielding Blocks &

Welds (65x 6 x 3 Sectors)

Inspect Chamber

After Build-Up

Install Three ECH

Assemblies

Time (Hrs) 30.00 8.40 240.50 139.75 24.00 230.75 429.00 2.00 9.60 38.00

BIO-Chamber ShutdownDivertor Coolant Tubes

Divertor Plates

Shield & Support System

Insp.

Divertor Plates

NDI WeldsCoolant Tubes

InstallationStart-Up

TaskShutdown &

Prep for Maint.

Twenty-four Coolant Tubes (8 x 3 Sectors)

Cut Plates Coolant Tube Weld (8 x 3

Sectors)

Inspect Outside for Damage &

Repair

Weld Plates Coolant Tube

(8 x 3 Sectors)

Complete Coolant Tube Weld Inspect.

Twenty-four Coolant

Tubes (8 x 3 Sectors)

Time (Hrs) 30.00 9.40 20.40 12.00 26.40 0.55 13.10 38.00

Total Time (Hrs)

Total Time (Hrs)

KEYSOperational Tasks

Parallel/Simultaneous Tasks

ARIES MAINTENANCE TASKS

Disassembly 466.85 Hrs. Replacement 739.55 Hrs.

Total Maintenance Time 1,206.40 Hrs. Inherent Availability 95.6%

Removal Tasks Replacement Tasks