maintenance report

108
(December 15, 2009 to March 31, 2010) Submitted To: Mr. Mushtaq Ahmad Principal Engineer (Mechanical) Block-II Submitted by:

Upload: muddasirmasood

Post on 20-Nov-2014

557 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Maintenance Report

(December 15, 2009 to March 31, 2010)

Submitted To:Mr. Mushtaq Ahmad Principal Engineer (Mechanical) Block-II

Submitted by: Muhammad Arshad Mukhtar Trainee Engineer (Mechanical) Block-II

Page 2: Maintenance Report

CONTENTSSummary 4

CHAPTER 1:

Maintenance Overview

1.1 What is Maintenance?? 8

1.2 Types of Maintenance 8

Preventive Maintenance

Breakdown Maintenance

Scheduled Maintenance

Predictive Maintenance

1.3 Responsibilities of Maintenance Engineer (Mechanical) 10

1.4 Responsibilities of Maintenance department 11

1. Routine PMs

2. Planed outages

3. Forced outages 4. Calibration

1.5 Objectives and targets of Mechanical Maintenance Block-II 13

1.6 Maintenance activities of Gas turbine 13

1. Combustion Inspection (CI)

2. Hot gas path inspection (HGPI)

3. Major overhauling (MOH)

1.7 Maintenance activities of Steam turbine 13

1. Minor overhauling

2. Major overhauling

2

Page 3: Maintenance Report

1.8 Data Sheet operating Hours 14

CHAPTER 2:

Case Studies

2.1 Case Study No 1

Washing of GT-8 20

2.2 Case Study No 2

Condenser Tubes Leakage 26

2.3 Case Study No 3

Gear Box Replacement 30

2.4 Case Study No 4

Booster Air Compressor 35

2.5 Case Study No 5

High Differential Pressure Problem 39

2.6 Case Study No 6

Circulating Water Pump 42

2.7 Case Study No 7

Hydraulic Power System 49

2.8 Case Study No 8

Atomizing Air System 75

3

Page 4: Maintenance Report

Summary

“All activities involved in keeping system’s equipment working are termed as

maintenance. Objective of the maintenance is to maintain the system capability &

minimize total costs.”

I was deputed in Mechanical maintenance Block II. Here I have spent about four

months. During this period major emphasis has been given to the observation of the

maintenance activities performed by the maintenance staff which includes attending

to the PMs as well as break-down maintenance. The aim has been to get familiarized

with the mechanics of the hardware used at the plant, their maintenance procedures,

manpower handling and utilization, documentation and planning activities. CI

activities were also observed during this tenure. Besides this different tasks were

performed which were assigned by seniors.

Case Studies

The following case studies were done during this tenure.

1. Washing of GT 5-8

2. Condenser Tubes Leakage

3. Gear Box Replacement

4. Booster Air Compressor

5. High Differential Pressure Problem

6. Circulating Water Pump

7. Hydraulic Power System

8. Atomizing Air System

4

Page 5: Maintenance Report

Presentations

I have also given training to the mechanical staff on the following topics.

1. Mechanical power transmission

2. GT-5 spread problem

3. Hydraulic power pack system

4. Water treatment system

5. Centrifugal Pumps

Systems

Line tracing of the following systems has been completed:

1. Fuel Oil forwarding & filtration Skid GT-5-8

2. Fuel oil system GT 5-8

3. Lube Oil System GT 5-8

4. Gas Skid GT 5-8

5. Cooling and sealing air system GT 5-8

6. Atomizing Air System GT 5-8

7. Turbine cooling water system GT 5-8

8. Lube Oil System ST 11-12

Challenges/faults to KB2MM during Training

During this period I have seen so many problems which were rectified by mechanical

section. The following were the major problems which were list down.

1. HP feed water pump jam due to damaged balance sleeve

2. Repairing of gear box

3. Tripping of GT 7 due to hydraulic oil filter leakage

4. HP feed water pump vibration high due to bearings damage

5. Leakage of water from closed cooling water of GT cooling system (cooler was

leak) so it was isolated.

6. Atomizing air temp remained high at GT-5

7. Auxiliary hydraulic oil pump running continuously

5

Page 6: Maintenance Report

8. Replacement of bleed v/v NO 3 at GT- 6

9. Water cooler cleaning , vacuum improvement

10. Flue gas leakage from broken bolt after CI

11. GT- 8 fire , Manual shut down of machine (due to electrical short circuiting)

12. High spread problem at GT 5

13. Fuel shortage Problem

14. Leakage from flow divider junction box

15. Fire on GT 6. tripping of M/c but not fond any reason

16. STG 11 trip due to HP drum level high

17. GT 8,7,5 tripping with following indication

18. heavy skid trouble

19. low liquid fuel pressure trip

20. heavy fuel pressure low

21. HSD down stem differential pressure high

22. STG 12 trip due to tripping of GT 7,8

23. Vacuum pump jam due to impeller damage

24. Acid Unloading pump (Centrifugal pump impeller replacement…..Teflon)

25. Main fuel oil pump repairing

26. Neutralization pump

27. BSDG Compressor piston rings changed

28. Gear box repairing (wheel rubbing with upper casing)

29. LP Evaporator (leakage)

30. Inspection of lifting tackle

a. Chain Block

b. D Shackle

c. Eye Bolt

d. Sling Wire

e. Sling wire Endless

f. Polyester Sling

g. Beam Trolley

31. Replacement of 2nd stage nozzle during CI

32. Replacement of torque converter during CI Due to Seizing

6

Page 7: Maintenance Report

Modifications

Some systems were modified for efficiency improvement.

1. New line was installed at booster air compressor

2. HRSG Isolation valve

3. Sump tank modification

7

Page 8: Maintenance Report

1.1 What is Maintenance??

Maintenance may be defined as, "All actions which have the objective of retaining or

restoring an item in or to a state in which it can perform its required function. The

actions include the combination of all technical and corresponding administrative,

managerial, and supervision actions."

1.2 Types of Maintenance

(a) Preventive Maintenance

(b) Breakdown Maintenance

(c) Scheduled Maintenance

(d) Predictive Maintenance

Preventive Maintenance 

A system of scheduled, planned or preventive maintenance tries to minimize the

problems of breakdown maintenance. It is a stitch in time procedure.

It locates weak spots (such as bearing surfaces, parts under excessive vibrations, etc.)

in all equipments, provides them regular inspection and minor repairs there by

reducing the danger of unanticipated breakdown. The underlying principle of

preventive maintenance is that prevention is better than cure. 

Objectives of Preventive Maintenance

(i) To minimize the possibility of unanticipated production interruption or major

breakdown by locating or uncovering any condition which may lead to it?

(ii) To make machine tools always available and ready for use.

(iii) To maintain the optimum productive efficiency of the machine tools.

(iv) To maintain the operational accuracy of the machine tools.

8

Page 9: Maintenance Report

(v) To reduce the work content of maintenance jobs.

(vi) To achieve maximum production at minimum repair cost.

(vii) To ensure safety of life and limb of the machine tool operators.

Scheduled Maintenance 

Scheduled maintenance is a stitch in time procedure aimed at avoiding breakdowns.

Breakdowns can be dangerous to life and as far as possible should be minimized.

Scheduled maintenance practice incorporates; inspection, lubrication, repair and

overhaul of certain equipments which if neglected can result in breakdown.

Inspection, lubrication, servicing of these equipments are included in the

predetermined schedule. Scheduled maintenance practice is generally followed for

overhauling of machines; cleaning of water and other tanks, etc.

Predictive Maintenance 

In predictive maintenance, equipment conditions are measured periodically or on a

continuous basis and this enable maintenance men to take a timely action such as

equipment adjustments, repair or overhaul. Predictive maintenance extends the

service life of equipment without fear of failure.

It is comparatively a newer maintenance technique. It makes use of human senses or

other sensitive instruments such as Audio gauges, Vibration analyzers, Amplitude

meters, and Pressure, temperature and resistance strain gauges to predict troubles

before the equipment fails.

9

Page 10: Maintenance Report

Breakdown Maintenance 

Breakdown maintenance implies that repairs are made after the equipment is out of

order and it cannot perform its normal function any longer, an electric motor of a

machine tool will not start, a belt is broken.

Under such conditions, operation department calls on the maintenance department to

rectify the defect. The maintenance department checks into the fault and makes the

necessary repairs. After removing the fault, maintenance engineers do not attend the

equipment again until another failure or breakdown occurs.

Causes of Equipment Breakdown 

Failure to replace worn out parts.

Lack of lubrication.

Neglected cooling system.

Indifference towards minor faults.

External factors (such as too low or too high line voltage, wrong fuel, etc.)

Indifference towards equipment vibrations, unusual sounds coming out of the

rotating machinery, equipment getting too much heated up.

1.3 Responsibilities of Maintenance Engineer (Mechanical)

Following are the responsibilities of Mechanical Maintenance Engineer.

1. Responsible for all mechanical maintenance and overhauling activities of

respective Block.

2. Provide supervision, leadership, specialist knowledge and expertise to his team for

mechanical maintenance and fault finding/trouble shooting.

10

Page 11: Maintenance Report

3. Identify, evaluate, plan and assign / execute preventive & corrective maintenance

jobs as per OEM recommendations.

4. Ensure timely response of job cards raised to his section.

5. Establish and maintain good working relations and coordination with Operation and

other sections.

6. Monitor stores stock to ensure availability of minimum quantity of required spare

parts.

7. Initiate spare parts requisition timely for the procurement of spare parts/material.

8. Act as Accepter / Issuer as per KAPCO Safety Rules subject to his nomination /

authorization.

9. Ensure implementation of KAPCO Safety Rules by his team.

10. Assist PE Mechanical in preparation and control of Sectional Budget.

11. Assist PE Mechanical in preparation of specifications, evaluation of bids, follow

up and execution of CAPEX & MRR projects, etc.

12. Assist PE Mechanical in appropriate management of resources and cost effective

maintenance.

13. Train and develop staff to improve their technical knowledge, commercial

awareness.

14. Implement IMS in his area of responsibilities.

15. Perform any other relevant task assigned by his seniors.

1.4 Responsibilities of Maintenance department:

The following are the responsibilities of Mechanical Maintenance department.

11

Page 12: Maintenance Report

1. Routine PMs

2. Planed outages

3. Forced outages

4. Calibration

1. ROUTINE PMs

Receiving of PMs/Work Orders

Daily Planning

Receiving of Safety Documents

Assigning of Work

Execution of Work

Closing of Job Cards

2. PLANED OUTAGES

Receiving of Outage Plan

Pre-Outage Meetings

Receiving of Work Orders

Daily Planning

Obtaining Safety Documents

Daily Progress Meeting

Assigning of Work

Execution of Work

Filling of Protocols

Closing of Outage Job Cards

Submission of Outage Maintenance Report

3. FORCED OUTAGES

Communication of Problem

Arrival of Maintenance Team at Site

Commencement of Work

Completion of Work

Closing of Job Cards

12

Page 13: Maintenance Report

4. CALIBRATION

Receiving of work orders

Execution of Calibration

Closing of jobs

Calibration Record

Storage and Record of Tools/Instruments

1.5 Objectives and targets of Mechanical Maintenance Block-II

The objectives and targets of the mechanical section are

1. To reduce forced outage of block II units due to Mechanical fault from

135GWH to 122 GWH.

2. To reduce No of trips of maintenance Block II units from 6 to 5 due to

Mechanical.

3. To maintain the thermal efficiency of maintenance Block II units above 42.30

%.

4. To limit overdue PM jobs of Mechanical section to 6 %.

5. To ensure the manpower utilization at least 78 % of Mechanical II section.

1.6 Maintenance activities of Gas turbine

1. Combustion Inspection (CI)

2. Hot gas path inspection (HGPI)

3. Major overhauling (MOH)

1.7 Maintenance activities of Steam turbine

1. Minor overhauling

2. Major overhauling

13

Page 14: Maintenance Report

1.8 Data Sheet operating Hours

Unit Maintenance EOH Duration (Days)

5-8 Combustion

Inspection

7500 10

Hot Gas Path

Inspection

22500 45

Mojor

Overhauling

45000 45

11-12 Minor

Overhauling

25000 10

Major

Overhauling

50000 45

Activities during CI

The following are the maintenance of combustion inspection.

Preparation and removal of turbine compartment roof.

Removal of liquid fuel lines

Removal of atomizing air lines

Removal of gas fuel lines

Removal of liquid fuel check valves.

Removal of fuel nozzles

Unbolt and open up combustion chamber covers

Remove x-fire tube retainers and x-fire tubes

Removal of combustion liners & Flow sleeves

Unbolt and remove transition pieces.

14

Page 15: Maintenance Report

Removal of 11th stage cooling sealing air Lines extraction valves & conduit.

Place mechanical support jacks under unit casings

Removal of turbine casing bolts & upper half first stage nozzle eccentric pin

Removal of upper half turbine casing

Take turbine clearances check. Fill protocol

Remove lower half second and third stage nozzle radial retaining pins &

plugs.

Remove lower half second and third stage nozzle segments

Remove upper half second and third stage nozzle radial retaining pins & plugs

Remove upper half second and third stage nozzle segments

Stage nozzle segments check valves

Dismantling & cleaning of fuel nozzles & fill protocols

Assembly and bench test fuel nozzle & check valve assembly (pressure test)

replacement of fuel nozzle & check valve assembly parts if required

Inspect combustion liners & fill protocols

Inspect x-fire tubes & retainers & fill protocols

Inspect transition pieces & fill protocols

Inspect combustion chamber flow sleeve & fill protocols

Inspect combustion wrapper & fill protocols

Inspect first stage nozzle crackness and fill protocol.

Repair/ welding of turning vanes.

Cleaning of t/b casing faces, taping, bolts, and segment slit & pins holes etc.

Activities during MOH

The following are the maintenance activities during MOH.

Removal of accessory gear coupling, checking of acc gear alignment, and

installation of rotating fixture.

Preparation and removal of three pieces of turbine compartment roof

Removal of exhaust and inlet duct access panels

Removal of turbine compartment side panels

Preparation and removal of t/b compartment roof.

Removal of liquid fuel lines

15

Page 16: Maintenance Report

Removal of atomizing air lines

Removal of gas fuel lines

Removals of liquid fuel check valves.

Removal of fuel nozzles

Unbolt and open up combustion chamber covers

Remove x-fire tube retainers and x-fire tubes

Removal of combustion liners & Flow sleeves

Unbolt and remove transition pieces.

Removal of 11th stage cooling sealing air Lines extraction valves & conduit.

Place mechanical support jacks under unit casings

Removal of turbine casing bolts & upper half first stage nozzle eccentric pin

Removal of upper half turbine casing

Take turbine clearances check. Fill protocol

Remove lower half second and third stage nozzle radial retaining pins &

plugs.

Remove lower half second and third stage nozzle segments

Remove upper half second and third stage nozzle radial retaining pins & plugs

Remove upper half second and third stage nozzle segments

Stage nozzle segments check valves

Dismantling & cleaning of fuel nozzles & fill protocols

Assembly and bench test fuel nozzle & check valve assembly (pressure test)

replacement of fuel nozzle & check valve assembly parts if required

Inspect combustion liners & fill protocols

Inspect x-fire tubes & retainers & fill protocols

Inspect transition pieces & fill protocols

Inspect combustion chamber flow sleeve & fill protocols

Inspect combustion wrapper & fill protocols

Inspect first stage nozzle crackness and fill protocol.

Repair/ welding of turning vanes.

Cleaning of t/b casing faces, taping, bolts, and segment slit & pins holes etc.

Unbolt and remove forward and after compressor casing

Unbolt and remove upper half inlet casing (bell mouth)

Unbolting & remove compressor discharge casing,

Remove upper half exhaust diffuser, exhaust hood and air cone

16

Page 17: Maintenance Report

Remove lower half first stage nozzle eccentric pin & horizontal nozzle clamps.

Remove lower half first stage nozzle

Remove the upper half of the 1st stage nozzle support ring and cleaning

Remove the inner compressor discharge casing

Remove upper half 2nd & third stage nozzle retaining pins & plug

Remove upper half 2nd & third stage nozzle segments

Checking rotor thrust and compressor clearances.

Take initial readings of IGV, noting backlash, bush clearances and fill

protocol

Remove upper half #1, #2 and #3 bearing housing& bearing upper half

Take initial clearances for bearing #1,2,3 and their labyrinth seals clearances

Remove lower half 2nd & third stage nozzle segments

Lube oil supply line leak test near bearing connection

Remove turbine side load coupling bolts

Removal of intermediate coupling bolts

Remove thrust bearing loaded and unloaded

Remove compressor rotor

Removal of lower half IGVS from casing

Removal of upper half IGVS from casing

Cleaning of IGVS before inspection

NDT & inspect inlet guide vanes rack ring, segments spacer gears etc.

Remove turbine rotor

Removal of turbine blades

Inspect first, second and third stage turbine buckets installation

NDT test on the turbine rotor (especially dovetail) + compressor rotor

NDT test on the compressor rotor

Installation of new turbine blades

Remove lower half bearing 2 &3

Cleaning of turbine casing upper / lower halves and replacement of insulation

boxes of 2nd & 3rd stage if required.

Cleaning of compressor, wrapper and exhaust casings faces, holes, taping and

cleaning of bolts, pins etc

Inspect bearings, for any defects / NDT

Cleaning and inspection of first stage nozzle support ring.

17

Page 18: Maintenance Report

Cleaning and inspection/ adjustment of the compressor rotor.

Compressor stator upper half backlash repair by inserting shims

Compressor stator upper half inspection and filling protocol

Compressor stator lower half backlash repair by inserting shims

Compressor stator lower half inspection and filling protocol

Inspection / removal / cleaning of shrouds blocks (upper and lower halves)

Inspect first, second and third stage nozzles vanes and diaphragms.

Make first stage nozzle ellipticity check

Major Overhauling Of Steam Turbine

The following are the maintenance activities during major overhauling.

Acoustical package removal, turbine enclosure fan supply to be disconnected

and its removal

Cladding and insulation removal of control valves

Scaffolding to be erected around the HP casing (left side).

Removal of coupling safe guard

Opening of coupling bolts protection plates

Steam turbine/generator coupling bolts removal with the help of hydraulic

machine

Removal of generator bearing's turbine side and exciter side bearing's exciter

side oil deflector

Steam turbine/generator alignment checking

Stop valves removal

Control valves removal

Balancing check of casing

LP casing rupturing diaphragms removal

Hp loop pipe upper removal

Motor & turning gear removal

Inlet & outlet bearings pedestal cover removal

Thrust bearing clearance checking

Removal of exhaust bearing upper half liner

Exhaust bearing clearance checking

Disassembly of thrust bearing

18

Page 19: Maintenance Report

Rotor displacement checking

Opening of gland steam supply and return pipe flanges

Insertion of shims under lower HP casing left and right sides

Casing joint plane unscrew

Upper casing removal

Casing joint plane studs removal

1/2 upper diaphragms & sealing boxes removal

Radial clearances (l-r) and axial clearances checking

Bottom radial clearances checking

Rotor removal

1/2 lower diaphragms and sealing removal

Lower halves of inlet and exhaust bearings removal

Cleaning by sand blasting (gland sealing/diaphragms)

Rotor expertise (Mp testing)

Journal/thrust bearings expertise (ultrasonic and NDT)

Turning gear expertise

19

Page 20: Maintenance Report

20

Page 21: Maintenance Report

Washing of GT-8

Introduction

Gas turbine performance is affected by the deposits on compressor and turbine blades

during operation. Due to this loss of power and fuel consumption may increases.

Compressor performance decreases due to reduced air flow, lower compressor

efficiency and lower compressor pressure ratio. It may be due to ingested air which

may contains dust, sand, hydrocarbons, fumes and salts. The deposits at turbine blades

occur as a result of type and treatment of fuel being burned. Therefore to increase the

efficiency of turbine, washing of gas turbine is required.

Washing

Washing of gas turbine is done with washing liquid to remove the deposits at turbine

blades and solid air particles from compressor blades. Washing is carried out

according to the OEM recommendation. Normally to increase the efficiency of gas

turbine, compressor and turbine blades washing is recommended.

Turbine Washing:

Turbine washing is carried out after every 250 EOH of machine at FO. If the

machine is running on gas then there is no need for carrying out the washing as the

gas is a clean fuel with negligible proportion of impurities in it.

Compressor Washing:

Compressor washing is carried out after every 1800-2200 EOH of gas turbine

running at FO. But in normal operation it is carried out after third or fourth Turbine

washing depending on the condition of the IGV’s.

21

Page 22: Maintenance Report

Detergent

For compressor washing detergent TURCO 5884 is used as a washing liquid. TURCO

5884 is concentrated liquid cleaner which is effective in removal of oil, salt and solid

deposits from compressor blades.

Properties

Ash free

Readily miscible with water

Typically very low in phenol, chloride and sulpher

Determination of Washing Liquid

Washing liquid is mixed with water at 80°C in the ratio of 1:4. The quantity of

washing liquid used normally is 100 liters in the washing liquid reservoir and

according to the ratio water is added up to 400 liters. Usually during compressor

washing 40-50 liters of the detergent is used.

Washing Requirements

Washing water is heated up to 80°C in the washing tank and the turbine wheel space

should be less than 150°C (difference of temperature between turbine and washing

liquid < 67°C, called spread). If the spread is greater than 67°C, then thermal stresses

will be caused in the turbine blades.

Atomizing air discharge valve located on atomizing air manifold in GT compartment

should close.

Booster air compressor breaker should rack out.

22

Page 23: Maintenance Report

Major components of washing System

Washing Pump:

Washing pump is installed with the washing tank for pumping the water in the

washing nozzles. The specifications of pump are:

Type: Centrifugal Pump

Flow rate: 6 liter/sec

Power of motor: 12 KW

Rpm: 2900

Liquid Detergent Washing Pump:

The pump is installed with the washing tank for pumping the liquid detergent

in the washing nozzles. The specifications of pump are:

Type: Centrifugal Pump

Flow rate: 1.5 liter/sec

Rpm: 2900

Washing Tank

A tank with a capacity of 20 ton is used as a reservoir.

Arrangement of Nozzles

During turbine washing the water is sprayed onto the turbine blades trough the

nozzles provided for atomizing air. At the compressor side eight fixed nozzles are

provided for compressor washing.

Drainage

There are total 23 drains of water provided with a common header.

23

Page 24: Maintenance Report

PROCEDURE

Compressor Washing

The Gas turbine is desynchronized about six to eight hours prior to washing activity.

Washing speed of gas turbine is 18 %. For this purpose water is sprayed through eight

nozzles. The inlet guide vanes and inlet dampers are closed as the machine is on

turning gear, so if the rotor temperature does not drop then the crank start is given to

lower the rotor temperature.

Compressor washing is being started by using detergent TURCO 5884 by giving

washing start. Washing pump is started for 5 mints. After that liquid detergent

washing pump is started and washing is done by mixing of water and detergent. After

this again only water pump is started for five mints to remove the detergent from

compressor blades. Then give shut down command, both detergent and washing pump

will stop and machine will remain at stand still speed for 15 mints for soaking

purpose.

Now again give the washing start to machine and rinse only with water for 15 mint.

Then we have stopped the pump but machine remain at washing speed for turbine

blades washing.

Turbine Washing

Turbine washing is carried out in three steps;

1. First turbine blade washing for 25 min.

2. Soaking time of 45 min.

3. Second turbine blade washing for 25 min.

Machine is given the washing start bypassing the ignition. During washing the turbine

speed is nearly 580 rpm. The water is injected with the help of washing pump at about

6 liters/sec for 25 min.

Then the turbine is kept at zero rpm for giving a soaking time of 45 min so that the

deposited sulpher and other complex salts can be easily removed during second

turbine blade washing. Also the maintenance section can work during the standstill

position of the shaft. During this time period maintenance section can perform its

duty.

24

Page 25: Maintenance Report

Maintenance activities during soaking time

Inspection of compressor inlet and IGVs.

Inspection of turbine exhaust end after clearance report by the chemist.

Manual operation of compressor bleed valve.

Changing of lube oil of main fuel oil pump.

Change of in service HP filter with cleaned ones. HP filter #2 filter elements

were changed.

Inspection of air intake filter house.

Booster air compressor was replaced. Technician removed its coupling with

the help of puller and then put on at other booster compressor which was

installed.

After completion of all inspections and soaking time machine again started by

giving washing start for 25 mints only with water. At the end of completion of

washing GT put on turning gear.

25

Page 26: Maintenance Report

26

Page 27: Maintenance Report

Condenser:

In thermal power plants, the primary purpose of a surface condenser is

to condense the exhaust steam from a steam turbine to obtain

maximum efficiency and also to convert the turbine exhaust steam into pure water so

that it may be reused in the steam generator or boiler as boiler feed water. This

condenser is just like a shell and tube heat exchanger. Water drops down and collects

in hot well from where water is extracted through condensate extraction pump and

discharged to the feed water tank.

Condenser view (General)

The condenser view which has been shown above is not a view of STG-12 condenser,

but the working principle is same. The steam turbine itself is a device to convert

the heat in steam to mechanical power. The difference between the heat of steam per

unit weight at the inlet to the turbine and the heat of steam per unit weight at the outlet

to the turbine represents the heat which is converted to mechanical power. Therefore,

the more the conversion of heat per pound or kilogram of steam to mechanical power

in the turbine, the better is its efficiency. By condensing the exhaust steam of a

turbine at a pressure below atmospheric pressure, the steam pressure drop between the

27

Page 28: Maintenance Report

inlet and exhaust of the turbine is increased, which increases the amount of heat

available for conversion to mechanical power. Most of the heat liberated due

to condensation of the exhaust steam is carried away by the cooling medium (water)

used by the surface condenser.

Main Functions of Condenser

Condensation of bled steam from the LP turbine.

Water reserve in the condenser hot well.

Normal and emergency make-up water in the circuit.

Collection of liquid drain returns.

Condenser Tubes Leakage

STG 12 condenser tubes were leaking. To attend this leakage STG-12 was on forced

outage.

Tubes Technical data

Number of tubes per condenser 12532

Tube size, outer dia * wall thickness (24 * 1) mm

Tubes Leakage Observation

Tubes leakage is observed through variation in the chemistry of demi water. In each

shift once a time sample is taken from condenser. Chemical section analyzes its ph

value and performs all other necessary tests. If its chemistry is disturbed then it is to

be thought that some condenser tubes are leaking.

Effect of Tubes Leakage

If tubes are leaking then cooling water will mix with condensate water. This mixture

of water will go into the feed water tank, HRSG and Steam turbine. This water will

corrode the HP, LP drum and tubes in HRSG.

Besides this it will also effect on steam turbine blades. There will be chance of

erosion and corrosion on steam turbine blades which will reduce the efficiency of

steam turbine.

Methods of Leakage Detection

28

Page 29: Maintenance Report

Here three methods are used for identification of leakage tubes.

1. Filling of condenser

2. Through candle flame

3. By applying polythene

Procedure

Today maintenance team used first method. First of all condenser was filled up with

demi water. Condenser manholes were opened. When condenser was fully filled up

with water then it was observed that water start to flow outside from some tubes.

All tubes were inspected one by one. The tube in which there was leakage, plugged

from one side with copper plug. Then water starts to flow on other side and was

inspected that which tubes leaking, same tube on other side was also plugged with

copper plug. At the end total six tubes were plugged. At the end all the tubes counted

which were plugged. Whenever tubes are plugged, it will be counted. Maximum 5 %

tubes of each tube bundle can be plugged. When condenser efficiency decreases and

maximum tubes are plugged then condenser is replaced with new one.

Condenser Tubes Plugged Status STG-12

East side top 14

East side bottom 142

West side top 24

West side bottom 150

29

Page 30: Maintenance Report

30

Page 31: Maintenance Report

Cooling Tower

Cooling towers operate on the principle of removing heat from water to an air stream

by evaporating a small portion of water flow.

The induced draught cooling tower is manufactured with high quality material and

should retain their original performance for many years. Therefore high attention is

given for its maintenance.

Components of cooling tower

Each cooling tower consists of the following components

cold water basin

ventilation group

6 cells casing

In each cell, an interior equipment

Drift eliminator

Water distribution pipes

Filling system

Ventilation Group

Each ventilation group comprises of the following

1. fan

2. reducer

3. motor

4. transmission system

Fan

Each cell of tower is fitted with an axial flow fan type. The fan blades slope can be

adjusted when fan is stopped. The blades are made of fiberglass reinforced polyester.

They are statically balanced. The high efficiency propeller type designed and a tip

speed not exceeding 60 m/s assure a low operation noise and a minimum of vibration

effects.

31

Page 32: Maintenance Report

Gear box

The fans are driven via right angle double reduction gear boxes of the bevel spiral

pattern.

The gearboxes are mounted centrally within the fan case on a common structural steel

weldment and the fan hub is mounted directly upon the vertical low speed shaft.

Gear Box

Gear box replacement of cooling tower fan (11 CRF 302AF)

Cooling tower fan of unit 11 was tripped due to some reasons then it was requested to

maintenance section to cause of failure of cooling tower fan. Maintenance team

inspected that gears were rubbing with gear box body due to large play between

couplings. At the end it was decided to replace the gear box with refurbished one.

Procedure

Following steps are used for replacement of gear box.

Installation of scaffolding.

Lube oil was drained and level switch removed.

U-clamp bolts were removed.

Five blades of fan were removed one by one with the help of chain block.

Fan hub plate removed and put on side by keeping it up with overhead crane

and chain block.

Four bolts of gear box were replaced.

32

Page 33: Maintenance Report

Six bolts of flexible coupling (coupling spacer) were removed. Here coupling

membrane is used for flexibility.

Coupling Membrane

Small fan which is shaft driven is used for gear box cooling was also removed.

Then gear box was put outside with overhead crane.

Coupling was removed from old gear box with the help of puller and installed

at refurbished gear box.

Refurbished gear box was installed.

Clearance of coupling membrane checked with vernier caliper. It was same in

all directions.

Gear box oil filled. 50 liter is used.

Hub plate and blades were installed.

Two blades tips were damaged, instead of these refurbished blades were

installed.

Blade angle was corrected with degree set. Blade angle is 19.6

U-clamp bolts were tightened.

33

Page 34: Maintenance Report

Failure of CT fan

After completion of gear box replacement, CT fan was put into operation. As soon as

it was put into operation it was again tripped at high vibration. Reasons of failure may

be

Shafts misalignment

Blades angle

Bearing damage

But all these were correct. So it was decided to again install the two blades which

were replaced. After this problem was solved. It was occur due to unbalancing of

blades weights.

34

Page 35: Maintenance Report

35

Page 36: Maintenance Report

Booster Air Compressor

Booster air compressor is a compact, rotary lobe type axial flow compressor. The

meshing of two screw type rotors synchronized by timing gears provides controlled

compression of the air for maximum efficiency.

Operating Principle

Compression is effected by the main and gate rotors meshing enclosed in the housing.

The timing gears maintain close rotor clearance. The rotors do not touch each other,

the housing, or the bearing carrier. Although clearances are small, lubrication in the

compression chamber is not required, insuring oil free air delivery.

Main rotor Gate rotor

The compression cycle begins as the rotors unmesh at the inlet port. Air is drawn into

rotor cavities, trapped, and compressed by reducing cavities as rotation continues.

When proper compression is made, the cavities discharge port, completing the cycle.

The cycle occurs twice each revolution and is continuous.

36

Page 37: Maintenance Report

Description

Two heavy duty angular contact ball bearing are used on each rotor shaft. Rotation is

counter clockwise viewing the drive shaft. The main rotor runs twice the speed of the

gate rotor.

Bearing housing Gear Pinion

Maintenance

Blower efficiency depends on the quality of maintenance.

Gears and gear end bearings are oil splash lubricated. Gear case oil level should be

daily checked. Change oil every 100 to 1000 hours of operation. Inlet end bearings are

grease lubricated. Regrease bearings every 250 hours of operation.

Common causes of blower failure

Poor air filter maintenance

Inadequate lubrication

Discharge pressure above blower rating

Blower speed below minimum rating

Blower speed too low for discharge pressure

Shims wear and tear

37

Page 38: Maintenance Report

Repairing Procedure

Compressor was dismantled. All parts were removed one by one. It was observed that

gaskets were leak. Actually shims are used here according to manufacture design but

last time gaskets were used due to unavailability of shims. Now shims will be

installed. Repairing is still under process.

38

Page 39: Maintenance Report

39

Page 40: Maintenance Report

High Differential Pressure Problem

Today GT-6 was tripped due to high ∆P. Indication turbine inlet pressure drop was

appeared and machine put to normal shut down.

∆P is measured in Pascal.

1300 Pascal alarm

1800 Pascal normal shutdown

This differential pressure was increased due to foggy weather. In foggy weather due

to moisture, filters are choked. Due to presence of dust particles, moistures are mixed

with it and it becomes like a mud and filters are choked.

Remedy

To prevent from this situation prefilters are applied so that moistures may not go

inside filter house.

Prefilters trap the moistures contents. Thus filters are prevented from choking.

∆P of block II

Today ∆P of GT 5-8 was recoded as follows.

GT-5 725 Pa

GT-6 › 1800 Pa

GT-7 512 Pa

GT-8 500 Pa

It is to be thought that why this problem only at GT 6 while filters of remaining GT,s

were also replaced at the same time. It was because of more operation time than

others. It was operated about one month more than other.

After application of pre filters GT was given start. But at 60 % it was again on normal

shut down. After some time it was given two crank starts to dry the wet filters. Then

machine was again started but at 72 % it laid down on normal shutdown due to torque

40

Page 41: Maintenance Report

converter limit switch problem. Indication torque converter drain valve trouble

appeared. Then instruments section adjusted its limit switch. Then GT was started.

Initially its ∆P increase up to 1650 Pa at 100 % speed and then it begin to decrease

when it was synchronized. It was observed that there was 100 Pa difference between

outer and inner gauges. At 20 MW it was 1350 Pa.

Next day normal operation was carried out. Weather condition was better. But in

night shift it was again normal shut down due to high ∆P.

In morning booster air compressor was modified. New line installed. It was given

start but machine take normal shut down at 98 %. Three time it was started but

pressure drop was high. Some prefilters were removed and instrument section

checked its manual cleaning. Machine was started. Initially differential pressure was

high so it was put on FSNL for 15 mints. After that gradually load was increased by

inspecting its ∆P. after that machine was put on temperature control. At temperature

control mode IGVs were modulated. By closing IGVs back pressure was increased

and thus differential pressure decreased. Load was increased and GT took maximum

load 92 MW.

41

Page 42: Maintenance Report

42

Page 43: Maintenance Report

Circulating Water Pump

It is a tubular casing pump with semi axial impeller. It is a single stage centrifugal

type pump. It has a propeller type impeller. This pump is used to circulate the water

from cooling tower to condenser where steam is condensed.

Pump construction

The main components of the pump are

Inlet Nozzle

Diffuser

Riser Pipes

Discharge Elbow

Pump Motor

Lantern

After having passed the inlet chamber and the inlet nozzle, the fluid pumped flows

through the impeller and diffuser to discharge nozzle of the discharge elbow.

43

Page 44: Maintenance Report

Inlet chamber

Vertical tubular casing pumps are high specific speed pumps and this pump type

reacts immediately to irregularities and disturbances in the approach flow. Such

disturbances lead to premature wear of bearing due to unsteady running of the pump

(vibration, cavitations) and secondly they cause a drop of the pump out put and

efficiency.

In all cases it is important to take the necessary steps to prevent foreign matter from

entering the pump with the flow, because these particles normally destroy the guide

bearings, damage the impeller and possibly damage other components as well.

Shaft bearing

The shafting of the pump is supported in plain bearings. These bearings are flooded

by the fluid pump. Dry running for a limited amount of time (not more than one

minute), such as is often the case during start-up of the unit, does not damage the set.

Journal bearing

Oil lubricated thrust and journal bearings

The purpose of the bearing is to absorb the axial thrust produced by the pump while it

is running the parts and to provide the top guidance for the shaft in a radial sense. By

installing the pump in an upright position, the parts of the thrust and journal bearing s

can be fully submerged in an oil bath. The heat generated during operation is

eliminated by the cooler which is also submerged in the oil bath.

44

Page 45: Maintenance Report

Bearing housing

General operating data

Operating parameters Normal operating Emergency operating

Medium pumped Cooling water

Medium temperature Approx 30 C

Density 996 kg/m

Flow 8360 m/h 11700 m/h

Head 17.2 m 13.25 m

Power 462 kw 498 kw

Speed 594 1/min

Direction of speed C.W from top

Power supply E-Motor (550 kw)

45

Page 46: Maintenance Report

Pump problem

During normal operation it was observed that there was abnormal sound from pump.

After that pump tripped at high vibration. So job card was raised and informed to

mechanical section for inspection. After inspection it was decided to open the open

for its complete inspection.

Repairing procedure

After taken permit the pump was dismantled as follows.

First of all pump coupling was removed.

After removal of coupling eclectic motor was removed with the help of crane.

Over flow line was removed.

By removing the motor, bolts of motor stool and pump elbow were removed.

Pump outlet pipe bolts were tightened to give clearance for the removal of

pump elbow.

Pump elbow was removed by tilting the motor stool.

Then motor stool was removed with the help of crane and put it on side.

Bearing lantern was removed.

Then pump body was removed with the help of two cranes and shifted to

turbine hall.

Pump

Typical weights

Weight of the different components was noted as given below.

46

Page 47: Maintenance Report

Component Weight (Manual) Weight (crane)

Motor 13.5 12.2

Motor stool 2.7 2.5

Pump 10.7 6

Water filling 3.7 -

Bearing lantern - 2

Inspection of pump

After dismantling pump inspection was carried out. It was observed that bell mouth

was ruptured. Bell mouth SS coating was damage. This coating is welded and bolted.

It was ruptured from welded joint and thus it created abnormal sound.

Shaft bearing was also damage due to which pump tripped at high vibration.

Remedy

After complete inspection it was decided to replace the bell mouth and shaft bearing.

Refurbished bell mouth was installed.

Bell mouth

Besides this impeller blades angles were misalign. Their angles were set manually.

Bolts were loosened then blades adjusted according to marking between A & B.

47

Page 48: Maintenance Report

Impeller

Bearing Lantern

It consists of combined journal and thrust bearing. First of all its cooler was removed.

Here heat is exchange through finned tubes. Service water is used for cooling the lube

oil.

It’s cleaning and inspection was carried out.

Gland packing was removed and replaced with new 16 mm. five gland packing was

changed. Bearing upper plate was opened and thrust pads were removed. It was

inspected and all pads were found ok.

After complete inspection of the pump it was again installed. The reverse procedure

was adopted to install it. First of pump casing was put into the basin at inlet cone.

Bearing lantern was installed with the help of crane. Then motor stool but its bolts

were not fitted because elbow was to be placed there it was placed by tilting on one

side then elbow installed & motor stool bolts were tightened. Adjusting nut was

placed. Motor was places on motor stool. Alignment was carried out. Coupling was

installed. Pump was started but it again tripped. It was investigated and found limit

switch problem. Instrument section checked it pump came into operation.

48

Page 49: Maintenance Report

49

Page 50: Maintenance Report

Hydraulic Power System

Electro hydraulic power pack is designed to generate sufficient power to operate one

by pass and one boiler inlet isolator. All hydraulic components are totally enclosed in

a painted weather proof cabinet.

Power Pack Main Components

1. hydraulic reservoir

2. Motor/pump unit (PU1)

3. Motor/pump unit (PU2)

4. Motor/pump unit (PU3)

5. hydraulic Accumulator (emergency Pressure relief)

6. hydraulic Accumulator (pilot control)

7. Solenoid valve

8. Manifold 91(Boiler inlet isolator solenoid valves)

9. Manifold 92(Bypass isolator solenoid valves)

10. Manifold 93(Bypass isolators emergency pressure relief valves)

11. Pump unloader valve

12. hydraulic cylinders

13. filtration

Hydraulic Reservoir

The hydraulic fluid used in this system is fire-resistant, type

HOUGHTOSAFE 620.

Reservoir Capacity: 200 liter

Its replacement is on yearly basis.

A replaceable filter element is provided in the main fluid return line to the

reservoir.

50

Page 51: Maintenance Report

A flexible pronal separator is incorporated into the reservoir venting system.

This maintains a physical barrier at the fluid/air interface so preventing

contamination of the fluid and deterioration of the reservoir lining.

Motor/Pump Unit (PU l)

Electric motor (10 kW & 1440 rpm)

Pump

Variable displacement pressure compensated in line axial piston pump.

Normal working pressure = 140 bar

This pump which only operates when normal movement of the blades is

required.

It also acts as a 'back-up' pump to the motor/pump unit (PU2) in the event of

its failure.

The output of motor/pump units (PU l) is monitored by the power unit

mounted pressure gauge (PG l).

51

Page 52: Maintenance Report

Setting of PS-1 (21)

If this switch sense less then 20 bars for 03 sec then “PU-1 Failure” indication

appeared and system shifted to emergency relief mode for opening of BYD.

Motor/Pump Unit (PU 2)

Electric motor (3 kW & 1440 rpm)

Pump Type

Variable displacement pressure compensated in line axial piston

pump.

Normal working pressure = 140 bar

This unit runs continuously when the system is energized, its primary purpose

is to supply hydraulic fluid to charge and maintain the two main linked storage

accumulators (86) and (87).

Its secondary role is to maintain pressure into the hydraulic cylinders holding

the Boiler Inlet blades in either their fully open or fully closed position.

PU2 acts as a 'back-up' to motor/pump unit (PU l).

The output of this pump may be monitored visually by pressure gauge (PG2).

In the event of a pressure loss pressure switch (PS2) will energize the main

motor pump unit (PU l).

This pressure switch will also cause directional valve (30) to operate directing

the output from pump unit (PU l) into the main accumulator circuit ensuring

52

Page 53: Maintenance Report

the availability of hydraulic stored energy in the event that emergency venting

is required.

If PU-1 already failed then “PU-2 failure” indication appeared & emergency

relief function starts.

Motor/pump unit (PU3)

Electric motor 1.5 kW & 1440 rpm with fixed displacement radial piston

pump.

Purpose of PU3 is to provide hydraulic pressure to the pilot circuit controlling

the six logic check element valves (56) to (61) via the solenoid valves (34) to

(39).

Output of PU-3 is monitored by PG-3 (20) HNY20CP011 locally & pressure

switches PS-4 (24) and PS-5 (140) used for remote signals.

Normal working pressure = 140bar

if pressure is ≥ 145 bar, PS-4 give the signal for de-energising the solenoid v/v

40 Loader / Un-loader v/v) which will start oil circulation back to reservoir till

sensing the pressure 125 bar and at 125 bar PS-4 give the signal for energising

the solenoid v/v 40 which will stop the circulation and again maintained the

system pressure up to 145 bar.

If system pressure could not rise above 125 bar even after energising the

solenoid v/v 40 then after 30 sec delay, PS-4 gives the alarm signal “Pressure

low” if said alarm / indication did not reset and also pressure further fall up to

90 bar another pressure switch # 40 PS-5) gives the trip signal of indication

“Control Fluid Pressure Low” which cause emergency opening of BYD

through emergency relief mode.

53

Page 54: Maintenance Report

Pilot accumulator 88 stored hydraulic energy through this pump.

Hydraulic Accumulators (Emergency pressure relief)

Capacity of accumulator 37.5 L

The accumulator fluid pressure is displayed by pressure gauge (PG 4)

If the gas turbine internal duct pressure exceeding the predetermined safe

maximum level, limit switches on the main frame of the bypass isolator trigger

the release of the stored hydraulic fluid, causing the by pass blades to open

rapidly in a minimum time of 10 seconds.

Drain valves (74 and 75) enable the stored fluid to be drained safely back to

the reservoir for maintenance purposes.

The speed of the emergency venting operation can be regulated using a

combination of flow regulators.

54

Page 55: Maintenance Report

Hydraulic Accumulators (Pilot control Circuit)

This accumulator has a capacity of 4 L.

To open the logic elements in the event of emergency venting.

In the event of power or PU 3 failure, this stored fluid causes the by pass

blades to go into the emergency mode.

Its pressure is displayed by pressure gauge (PG 3).

Pump Unloader Valve (40)

Pump unit (PU3) runs continuously charging the pilot control circuit accumulator

(88). At the pre-set charge pressure switch (PS4) is actuated, this causes the solenoid

(P) of valve (40) to de-energize allowing the pumped fluid to flow directly back to the

reservoir.

55

Page 56: Maintenance Report

Hydraulic Cylinders

All of the cylinders are double acting tie-rod type of cylinders incorporating

cushioned end stops in both directions. Self-aligning bearings are fitted at both ends.

Provision is made for the attachment of banjo mounted counterbalance valves for hose

failure protection.

Filtration

The cleanliness of the hydraulic fluid is of paramount importance. All three-pressure

lines from the pumps and main manifold return line are filtered to 12 micron

absolute.

56

Page 57: Maintenance Report

OPERATING MODES

Interlock System.

As an operating safety precaution, the Boiler Inlet and the By-Pass Isolators are

electrically interlocked to prevent the By-Pass blades from closing unless the Boiler

Inlet blades are open. Conversely the Boiler Inlet blades cannot be closed unless the

By-Pass blades are open.

Manual Operation

A hydraulic hand pump (101) is located within the main hydraulic power unit

enclosure. This allows movement of the Boiler Inlet or the By-Pass Isolator blades in

the event of a loss of electrical power, i.e. during commissioning or major

maintenance. A ball valve (124) allows the operator to select either the Boiler Inlet or

the By-Pass Isolators. As a safety precaution the shut-off valves are fitted with

electrical interlock to isolate the solenoid valves from the control circuit during

manual operation.

Hydraulic Pipe Failure

Pressure retention in the full-bore volumes of both sets of hydraulic cylinders is

critical. In the event of a pipe failure in the hydraulic circuit it is important to prevent

uncontrolled closing of the Bypass Isolator blades as this could cause serious damage

to the blade seals or to the Isolator main frame or the Flap To prevent this happening

each of the hydraulic cylinders for the Bypass Isolator are fitted with two pilot

operated counterbalance valves.(112,113.114 and 115) They function by allowing

fluid flow from the cylinder only when there is a pressure balance between both sides

of the cylinder. If a flexible hose fails then the controlling pressures become

imbalance and the valve shuts, locking the system in a fail-fixed condition.

57

Page 58: Maintenance Report

In the case of the Boiler Inlet Isolators the cylinders have to maintain these closed

against the supporting pressure within the cylinders. To ensure these conditions, and

to prevent structural damage in the event of flexible hose failure, counterbalance

valves (130, 131 132 and 133) are fitted directly to the base of each hydraulic

cylinder.

58

Page 59: Maintenance Report

Overload Protection

The pressure compensators of pump units (PU1) and (PU2) are set approximately at

110% of the maximum required for any operation. Should any situation arise where

an obstruction jams any blade, the generated torque imposed cannot rise above this

maximum value which is within the design safety factor for the isolators. Also, if the

situation arises where the blade is driven only on one side, again the torque imposed

on the blade is limited by the maximum hydraulic pressure to 110% of the output

from one cylinder.

Pump unit (PU3) is protected by a single relief valve (26) set a a value slightly

higher than the setting of pressure switch (PS4). Relief valves (28) and (29) protect

the system on the annulus side of the By-Pass cylinders, should any fault develop in

the main accumulator circuit Relief valve (27) protects the system controlling the

Boiler Inlet Isolator. In the closed position the Isolator blades must allow duct

pressures exceeding the specified maximum to force them open. In doing so a

situation of pressure intensification occurs as pressure is fed through the

counterbalance valve from the full bore side to the annulus side of the cylinders. The

individual relief valves in the full-bore line allow this excess fluid to drain to the

reservoir. The counterbalance valves attached to the base of the cylinders operating

the Boiler Inlet Isolator are fully compensated.

BY-PASS ISOLATOR

Closed, Pressure Relieving Position

The air barrier fan motor (BF1) is running and the shut off valve (FV1) is open.

Pump unit (PU1) is de-energized; Pump units (PU2) and (PU3) are running

continuously. Limit switches (LS1) and (LS3) are actuated by the By-Pass blades in

their closed position. Limit switches (LS8) and LS10) are actuated by the Boiler Inlet

blades in their open position. (N.B. the limit switches are actually doubled in quantity,

i.e. 2 x LS1, 2 x LS3, 2 x LS8, and 2 x LS10.)

The operation of the limit switches energize solenoid (J), (K), (1) and (M) of

valves (36) to (39) causing the pilot control pressure on logic elements (58) to ~ to

59

Page 60: Maintenance Report

decay to zero. Both logic elements open allowing the hydraulic fluid stored in the

main accumulator (86) and (87) to flow via elements (59) and (60) directly to the

annulus area of cylinders (104) to (107). The blades are then held closed against the

duct pressure. The accumulator pressure is pre-set to balance the specified duct

pressure. The full-bore sides of the cylinders are vented via elements (58) and (61) to

reservoir.

The accumulators effectively act as liquid springs allowing the horizontally closed

blades to open and close according to fluctuations of the duct pressure. The action of

opening spills the excess pressure into the vent allowing the blades to settle again to

the closed position. A pre-set maximum angle of opening is set and controlled by two

limit switches (1S5) and 1S6). If either or both of the blades reach this maximum

angle, (10 degrees), these limit switches initiate the Emergency Pressure Relief mode,

60

Page 61: Maintenance Report

61

Page 62: Maintenance Report

Normal Opening/Closing

The main pump (PUl) is energized simultaneously with the operation of the opening

or closing control, which energizes the relevant directional valves.

The pump units (PU2) and (PU3) are running continuously. Solenoids (G) and (H) of

valves (34) and (35) are energized allowing normal operation of the blades. To open

the blades, solenoids (D) and (E) are energized operating valves (32) and (33). The

combined output from pumps (PUl) and (PU2) is split and directed through the

control valuing to the hydraulic cylinders.

Two identical stacks of valves control the independent operation of each blade. Each

stack consists of a double acting directional valve (32) and (33), a double acting pilot

operated check valve (42) and (43), a dual flow regulator (46) and (47), and a double

pilot operated counterbalance valve (54) and (55).

The double' acting pilot operated check valves (42) and (43) enable the blades to be

held in any intermediate position or fully open by de-energizing the relevant

directional valves.

The dual flow regulators (46) and (47) allow the speed of normal operation to be

controlled. The fluid flow is regulated in the 'meter in' mode, i.e. it is restricted into

the hydraulic cylinder circuit, but allowed to flow freely from it. This form of

regulation allows the double counterbalance valves (54) and (55) to maintain a

smooth and controlled motion of the blades.

As the cylinders extend thus opening the blades, fluid flows from the annulus side of

the cylinders back to tank via deceleration valves (102) and (103).

Note: These valves are incorporated principally to control the speed of opening as the

blades near their fully open position when operated in the emergency relief mode.

At the 10-degree position of opening, limit switches (1S5) and (1S6) will actuate.

These have no function in the normal mode of operation. In the fully open position

limit switches (1S2) and (1S4) are actuated. It is only in this position with these limit

switches operated that the Boiler Inlet Isolator can be closed.

62

Page 63: Maintenance Report

Solenoids (D) and (E) remain energized enabling pump (PU2) to hold the blades

positively open. Solenoids (G) and (H) are continuously energized, maintaining logic

check elements in their closed condition. . Pump units (PU2) and (PU3) continue to

run.

63

Page 64: Maintenance Report

Normal Closing:

The blades cannot be closed unless limit switches (1S8) and (1S10) are actuated. To

close the blades, solenoids (C) and (F) are energized operating directional valves (32)

and (33). The hydraulic fluid is then directed through the valves described in the

opening sequence above, but in the reverse direction. During normal closing, if the

duct pressure rises sufficiently the blades will be prevented from closing. The excess

fluid pressure generated will be relieved to reservoir by relief valves (28) and (29).

Pump units (PU1) and (PU3) continue to run.

64

Page 65: Maintenance Report

Emergency Relief Mode

The emergency opening mode can be initiated at any time and is also

automatically selected if the electrical power fails. The by-pass Isolator blades are in

the normal closed pressure relief position Pump units (PU2) and (PU3) are running

and solenoids (G) and (H) are energized. As the duct pressure increases above pre-

determined levels the by-pass blades will rise to the 10-degree position. 1imit

switches (1S5) and (1S6) will be operated causing valve solenoids (G), (H), (J), (K),

(1) and (M) to de-energize. This allows logic check elements (56) and (57) to open,

and (58) to (61) to close. The effect is to direct the hydraulic fluid stored in the main

accumulators (86) and (87) to the full bore side of the cylinders (104) to (107) via

logic element (57). The annulus sides of the cylinders are vented to reservoir via the

deceleration valves (102) and (103) and logic element (56).

The blades will open rapidly, controlled initially by flow regulators (51) and

(52). At the 70-degree position cams on the blade stub shafts engage a pair of de-

celeration valves (102) and (103), these reduce the flow at a rate determined by the

cam characteristics. The time of operation is to be adjusted to give a minimum time of

4 seconds to the 70 degree position and 10 seconds to fully open.

Note: for normal operation the deceleration valve full flow setting is adjusted so as to

give control to flow regulators (51) and (52).

65

Page 66: Maintenance Report

66

Page 67: Maintenance Report

Shut Down or Electrical Power Failure

If the system is shut down or the power fails then all solenoids will de-

energize. In this state the system will revert to the fail safe emergency operating mode

and the by-pass isolator blades will open fully.

Opening the Blades with the hand pump

Open valves (136) and (137), close valves (79) and (80), (81) and (82).

Operate valve (124) to select the by-pass Isolator. Open valves (120) and (121), and

close valves (122) and (123) then operate the hand pump.

Closing the blades with the hand pump

Maintain valves (136) and (137), (79) and (80), (81) and (82) and (124) as

they are for opening. Open valves (122) and (123), and close valves (120) and (121),

67

Page 68: Maintenance Report

then operate the hand pump. The operating speeds are controlled by the capacity of

the hand pump and by the setting of the various flow regulators in the system.

BOILER INLET ISOLATOR

Closed, Static Mode

The air barrier fan motor (BF2) is running and the shut-off valve (FV2) is open. To be

in the closed position The By-Pass Isolator blades must be fully open and operating

limit switches (152) and (154). The Boiler Inlet blades will be operating limit

switches (157) and 159), which will de-energize pump unit (PU1). Pump units (PU2)

and (PU3) will be running and solenoids (G) and (H) will be energized.

Solenoids (B) of directional valve (31) will still be energized even after the blades

have fully closed. The output from pump unit (PU2) is directed via check valve (70)

and the control valves to the full bore side of the cylinders (108) to (111) maintaining

the blades in the closed position.

68

Page 69: Maintenance Report

The Boiler Inlet blades in this closed position are held shut against the duct pressure

by the continuing hydraulic pressure in the cylinders. This hydraulic pressure must be

regulated so as to hold the blades shut against a maximum of 350-mm H2O pressure

within the duct. If duct pressure increases beyond this figure then the blades must

open. The hydraulic pressure holding the flaps closed increases to a maximum at

which point a relief valve (27) allows excess pressure and fluid to escape to the tank.

Pressure compensated pilot operated counterbalance valves mounted directly to the

base of the cylinders allow them to retract thereby opening the blades.

69

Page 70: Maintenance Report

Opening/Closing Mode

70

Page 71: Maintenance Report

Pump units (PU2) and (PU3) and solenoids (G) and (H) are continually energized. To

open the Boiler Inlet Isolator, pump unit (PU1) and solenoid (A) of directional valve

(31) must be energized. Hydraulic fluid is then directed through the dual pilot

operated check valve, then divided and passed through flow regulators (44A) and

45B) to the annulus side of cylinders (108) to (111). The blades then open; by de-

energizing solenoids (A) or (B) of valve (31) the blades may be held in any

intermediate and the fully open position. To close the Boiler Inlet Isolator, limit

switches (152) and 154) must be actuated by the By-Pass blades in their fully open

position. Pump unit (PU1) and solenoid (B) of valve (31) are energized, directing the

pump output to the full bore side of the cylinders. When fully closed limit switches

(157) and (159) de-energize pump unit (PU1) allowing pump unit (PU2) to maintain

the blades in their closed state.

71

Page 72: Maintenance Report

72

Page 73: Maintenance Report

73

Page 74: Maintenance Report

Opening the blades with the hand pump

To open the boiler Inlet blades open valves (134) and (135), operate valve

(124) to select the Boiler Inlet Isolator. Open valves (118) and (119), and close valves

(116) and (117) then operate the hand pump.

Closing the blades with the hand pump

Maintain valves (134), (135) and (124) as they are for opening. Open valves

(116) and (117), close valves (118) and (119) then operate the hand pump.

74

Page 75: Maintenance Report

75

Page 76: Maintenance Report

76

Page 77: Maintenance Report

Atomizing Air System

The atomizing air system provides sufficient pressure in the air atomizing chamber of

the fuel nozzle body to maintain the ratio of atomizing air pressure to compressor

discharge pressure at approximately 1.3 or greater over the full operating range of the

turbine. Since the output of the main atomizing air compressor, driven by the

accessory gear, is low at turbine firing speed, a starting atomizing air compressor

provides a similar pressure ratio during the firing and warm-up period of the starting

cycle and during a portion of the accelerating cycle. Continuous blow-down to

atmosphere is also provided to clear the main gas turbine compressor of accumulated

dirt.

Major system components

Main atomizing air compressor

Starting atomizing air compressor

Atomizing air heat exchanger

Air filter

Operation

When liquid fuel oil is sprayed into the turbine combustors it forms large droplets as it

leaves the fuel nozzles. The droplets will not burn completely in the chambers and

many could go out of the exhaust stack in this state. A low pressure atomizing air

system is used to provide atomizing air through supplementary orifices in the fuel

nozzle which directs the air to impinge upon the fuel jet discharging from each

nozzle. This stream of atomizing air breaks the fuel jet up into a fine mist, permitting

ignition and combustion with significantly increased efficiency and a decrease of

combustion particles discharging through the exhaust into the atmosphere. It is

necessary, therefore, that the air atomizing system be operative from the time of

ignition firing through acceleration and through operation of the turbine.

Air taken from the atomizing air extraction manifold of the compressor discharge

casing passes through the air-to-water heat exchanger (cooler) HX1 to reduce the

77

Page 78: Maintenance Report

temperature of the air sufficiently to maintain a uniform air inlet temperature to the

atomizing air compressor. The atomizing air cooler heat exchanger, located in the

turbine base under the inlet plenum, uses water from the turbine cooling water system

as the cooling medium to dissipate the heat.

CAUTION

Failure to clean or replace the atomizing air filter cartridges after an alarm has been

annunciated may result in damage to the filter cartridge and/or the main atomizing

air compressor and could result in insufficient pressure ratio to properly atomize the

liquid fuel.

Switch 26 AA-1 is an adjustable heat sensitive thermo-switch provided to sound an

alarm when the temperature of the air from the atomizing air pre-cooler entering the

main atomizing air compressor is excessive. When the atomizing air reaches the

temperature setting of this switch, the alarm is activated. Improper control of the

temperature may be due to failure of the sensor, the precooler or insufficient cooling

water flow. Continued operation above 135 °C should not be permitted for any

significant length of time since it may result in failure of the main atomizing air

compressor or in insufficient atomizing air to provide proper combustion. Atomizing

air temperature high alarm is at 105°C, and machine takes shut down command if

atomizing air temperature after cooler becomes 135°C.

Main Atomizing Air Compressor

Compressor discharge air, now cleaned and cooled reaches the main atomizing air

compressor. This is a single stage, flange mounted, centrifugal compressor driven by

an inboard shaft of the turbine accessory gear. It contains a single impeller mounted

on the pinion shaft of the integral input speed-increasing gear box driven directly by

the accessory gear. Output of the main compressor provides sufficient air for

atomizing and combustion when the turbine is at approximately 60 % (1800 rpm)

speed.

78

Page 79: Maintenance Report

Differential pressure switch 63 AD-1, located in a bypass around the compressor,

monitors the air pressure and indicates an alarm if the differential pressure across the

compressor drop to a level inadequate for proper atomization of the fuel. Air, now

identified as atomizing air, leaves the compressor and is piped to the atomizing air

manifold. This manifold has many (14) piping providing equal pressure distribution of

atomizing air to the 14 individual fuel nozzles.

Booster Air Compressor

When the turbine is first fired, the accessory gear is not rotating at full speed and the

main atomizing air compressor is not outputting sufficient air for proper fuel

atomization. During this period, the starting (booster) atomizing air compressor,

driven by an electric motor, 88AB is in operation supplying the necessary atomizing

air. The starting atomizing air compressor at this time has a high pressure ratio and is

discharging through the main atomizing air compressor which has a low pressure

ratio. The main atomizing air compressor pressure ratio increases with increasing

turbine speed and at approximately 60 % speed the flow demand of the main

atomizing air compressor approximates the maximum flow capability of the starting

atomizing air compressor.

The check valve in the air input line to the main compressor begins to open allowing

air to be supplied to the main compressor simultaneously from both the main air line

and the starting air compressor. The pressure ratio of the starting atomizing air

compressor decreases to one and it is shut down at approx. 70 % (2100 rpm) when

speed relay 14 HC pickup.

Now all of the air being supplied for atomizing purpose is directed to the atomizing

air main compressor. The starting air compressor is completely bypassed.

When GT is running on Gas

During gas fuel operation, shaft driven main atomizing air compressor is still running

but there is no need of air for fuel atomization. Therefore, air discharge from main

atomizing air compressor is bypassed back to its suction and it is given at cooler inlet.

For this purpose solenoid valve 20 AA opens and it give opening air to isolation valve

VA 18. In this way, air is bypassed and very less air goes to main atomizing air

79

Page 80: Maintenance Report

manifold. Similarly, solenoid valve 20PL-1 opens to open the isolation valve VA 19-1

and through this valve purge air is supplied for purging the fuel nozzles.

80