major/area source boiler mact rule
DESCRIPTION
Eric Swisher presented at the 23rd Virginia Environmental Symposium about the Major/Area Source Boiler MACT Rule. The presentation covered the regulatory framework of the rule including emission limitations, compliance options, work practice standards, startup, shutdown, and malfunction, and provided a summary of what the rule means to facilities.TRANSCRIPT
Your environmental compliance is clearly our business.
Speaker: Eric Swisher
23rd Virginia Environmental SymposiumApril 11, 2012
Major/Area Source Boiler MACT Rule
2
Overview Ground Rules Regulatory Framework Regulated Pollutants Emission Limitations Compliance Options Work Practice Standards Startup, Shutdown, and Malfunction Things to Take Away
3
Major
Ground Rules
CISWI Rule
Boiler MACT Rules
Area
Fuel is not a Solid Waste
NHSM Rule
Fuel is a Solid Waste
4
General Information Area or Major Source New, Reconstructed, or Existing Fuel Type Design Type
5
Area Source
Comparison
Major Source
6
Area Source Not a Major
Source
>10 tons per year any single HAP OR
> 25 tons per year of any combination of HAPs
Facility Type
Major Source
7
Regulatory Citation 40 CFR Part 63 – National Emission
Standards for Hazardous Air Pollutants for Source Categories (NESHAP):• Subpart JJJJJJ – Area Source Boiler MACT
(ASBM)• Subpart DDDDD – Major Source Boiler
MACT (MSBM)
8
Area Source June 04, 2010
• Proposed• Comments Due July 19, 2010
June 09, 2010• Comment Period Extended to August 03, 2010
July 22, 2010• Comment Period Extended to August 23, 2010
March 21, 2011• Promulgated
December 23, 2011• Proposed Amendments
February 21, 2012• Comments Due
March 13, 2012• No Action Assurance Letter
History
Major Source January 13, 2003
• Proposed• Comments Due March 14, 2003
September 13, 2004• Promulgated• Compliance Date September 13, 2007
October 31, 2005• Notice of Reconsideration• Proposed Amendments
December 28, 2005• Final Rule (with Amendments)• Compliance Date September 13, 2007
December 06, 2006• Final Action on Reconsideration
June 04, 2010• Proposed• Comments Due July 19, 2010
June 09, 2010• Comment Period Extended to August 03, 2010
July 22, 2010• Comment Period Extended to August 23, 2010
March 21, 2011• Promulgated
March 21, 2011•Promulgated
December 23, 2011•Proposed Amendments
February 21, 2012•Comments Due
March 13, 2012•No Action Assurance Letter
December 23, 2011•Proposed
February 07, 2012•No Action Assurance Letter
9
Act of Congress March 08, 2012 Senate did
not pass the Collins Amendment to the Highway Bill that would delay the MSBM.
10
Area Source
Current Status
Major Source Effective Now Compliance Date
•March 21, 2014 No Action Assurance
Letter•March 13, 2012
Proposed Rule•December 23, 2011
Compliance Date•Date to Change
No Action Assurance Letter•February 07, 2012
11
Area Source
Boiler Exemptions
Source Applicability Major Source
Boiler Process Heaters Exemptions
12
Area Source Mercury (Hg) Non-Mercury
Metallic HAP Organic HAP
(including POM)
Mercury (Hg) Non-Mercury Metallic
HAP Non-Metallic
Inorganic HAP Non-Dioxin Organic
HAP Dioxins/Furans
(D/F)
Regulated Pollutants
Major Source
13
Area Source Mercury Carbon Monoxide Particulate Matter
Mercury Carbon Monoxide Particulate Matter
OR Total Selected Metals (TSM)
Hydrogen Chloride
Emission Limits
Major Source
14
Area Source Fuel Sampling Emission Testing
Fuel Sampling Emission Testing
Compliance Options
Major Source1. Comply with the Emission Standards
15
Area Source Hg Determine “Worst-
Case” Fuel Mixture
Fuel Sampling
Major Source Hg, HCl, & TSM Determine “Worst-
Case” Fuel Mixture Fuel Sampling &
Analysis Plan Monthly Fuel
Analyses
16
Area Source PM Hg CO
Emission Testing
Major Source PM or TSM Hg CO HCl
17
Area Source None Emission Averaging
Output-based Emission Standard• Emission
Reduction Credits
Compliance Options
Major Source2. Evaluate Emission Standard
Alternatives
18
Emission Averaging PM, HCl, or Hg Input or Output-based Emission
Standards Existing Boiler Only Subcategory Requirements 10% Discount Factor Common Stack Considerations Emission Averaging Plan
19
Area Source Fuel Management Fuel Switching Controls
Compliance Options
Major Source3. Can Not Comply with the Emission Standards
Fuel Management Fuel Switching Controls Synthetic Minor Energy Efficiency
Improvements
20
Output-based Emission Standards
Output-based Emission Standards• Incentivizes implementation of
energy efficient technologies to minimize the generation of emissions
21
Output-Based Emission Standards
Fuel Input Energy (lb
pollutant per MMBtu heat input)
SteamOutput Energy (lb
pollutant per MMBtu steam output)
22
Capital InvestmentAdd-on Control
Device(s)Energy
Efficiency Project(s)
23
How were they determined?• Boiler Efficiency• Heat-Input Based Limits
Subcategory
Hg Emission Limit
(lb Hg per MMBtu
of heat input)
Hg Emission
Limit(lb Hg per MMBtu of
steam output)
Boiler Efficienc
y(%)
Existing Boiler Designed to Burn Solid Fuel
3.10E-06 3.50E-06 88.6
Output-Based Emission Standards
24
How are they used?• Determine Current Boiler Output-
Based Emissions• Establish Output Energy
“Benchmark”• Investigate Energy Efficiency
Projects• Quantify Emission Reductions• Apply Percent Reduction to Current
Boiler Output-Based Emissions
Output-Based Emission Standards
25
Benchmark Year* = 2,175,000 MMBtu/yr
Year After* = 1,957,500 MMBtu/yrTested Hg Emissions
(lb Hg per MMBtu of
heat input)
Tested Hg Emissions
(lb Hg per MMBtu ofsteam output)
Adjusted Hg Emissions
(lb Hg per MMBtu of
steam output)
3.40E-06(Limit 3.10E-06)
3.84E-06(Limit 3.50E-06)
3.45E-06
Energy Output Reduction Example
*Production is assumed to be the same for both years.
26
Subcategory
Hg Emission
Limit(lb Hg per MMBtu of
steam output)
Hg Adjusted Emissions
(lb Hg per MMBtu of
steam output)
Result
Existing Boiler Designed to Burn Solid Fuel
3.50E-06 3.45E-06 PASS
Energy Output Reduction Example
27
Implementation Plan Pollutant-by-Pollutant Applicability Emissions Averaging Shutdown Boilers Future Boiler Operations Other Permitting Requirements Energy Assessment
Output-Based Other Considerations
28
What is Left? Ground Rules Regulatory Framework Regulated Pollutants Emission Limitations Compliance Options Work Practice Standards Startup, Shutdown, and Malfunction Things to Take Away
29
Area Source Tune-up Energy
Assessment Startup Shutdown
Work Practice Standards
Major Source Tune-up Energy
Assessment Good Combustion
Practices Startup Shutdown
30
ASBM
Every 2 years March 21, 2012 No Action
Assurance Letter
ASBM Tune-ups
Every 2 years Every 5 years
(Seasonal Boilers) March 21, 2013 Fuel Type
Requirements Common Fuel
Meter
Final Rule(March 21, 2011)
ASBM
Amendments(December 23, 2011)
31
Area Source New or Existing
Coal-fired Boiler <10 MMBtu/hr
New or Existing Biomass-fired Boiler New or Existing
Oil-fired Boiler
Major Source
Tune-up Applicability
Limited-use Boilers Natural gas,
Refinery Gas or Gas 1 (Other) Boilers < 5 MMBtu/hr
Gas 2 (Other), Light Liquid Boilers
32
Area Source
Burner Inspection Flame Pattern
Inspection Air-to-fuel system
Inspection CO Optimization Recordkeeping No Report Submittal
Major Source
Tune-up Requirements
Burner Inspection Flame Pattern
Inspection Air-to-fuel system
Inspection CO Optimization Recordkeeping Report Submittal
(1) As applicable, inspect the burner, and clean or replace any components of the burner as necessary (you may delay the burner inspection until the next scheduled unit shutdown, but you must inspect each burner at least once every 36 months).
(1) Inspect the burner and clean orreplace any components of the burner as necessary.
33
Energy Assessment Why? When and how often? Who is qualified? What equipment or systems need to be
included? What does “cost-effective” mean? What needs to be done?
34
ASBM
Existing ≥ 10 MMBtu/hr Boiler System Energy Use System Qualified Personnel Maximum Duration March 21, 2014
Energy Assessment
Existing ≥ 10 MMBtu/hr Boiler System Energy Use System
•Onsite Only Qualified Personnel Maximum Duration March 21, 2014
Final Rule(March 21, 2011)
ASBM
Amendments(December 23, 2011)
35
Energy Assessment
Scope Maximum Time Compliance Date
•Date to Change Emission
Reduction Credits
Major Source
36
Good Combustion Practices O2 Trim Systems
• Monitor• Optimize• Report
Operator Training• Startup Procedures• Shutdown Procedures
37
Startup/Shutdown Periods Boiler MACT standards apply at all
times. No exemptions from Boiler MACT
standards during periods of Startup and Shutdown.
U.S. EPA requires work practice standards for periods of Startup and Shutdown in lieu of numerical emission limits.
38
Area Source Minimize the
boiler’s startup and shutdown periods following the manufacturer’s recommended procedures.
Major Source
Startup/Shutdown
Good Combustion Practices
39
Area Source Startup/Shutdown
Definitions No SSM Plans
Misc. Startup/Shutdown
Major Source Startup/Shutdown
Definitions No SSM Plans
40
Malfunction Malfunction means any sudden,
infrequent, and not reasonably preventable failure of air pollution control and monitoring equipment, process equipment, or a process to operate in a normal or usual manner which causes, or has the potential to cause, the emission limitations in an applicable standard to be exceeded. Failures that are caused in part by poor maintenance or careless operation are not malfunctions.
41
Periods of Malfunction Boiler MACT standards apply at all
times. No exemptions from Boiler MACT
standards during periods of Malfunction.
U.S. EPA determines if a facility demonstrated a “good faith effort” to minimizing emissions and correcting a Malfunction.
42
Malfunction Process Notification of a Malfunction submitted to
U.S. EPA within two (2) business days. Follow-up report submitted to U.S. EPA
within 45 business days. U.S. EPA evaluates the reported information
concerning the Malfunction to determine if further inquiry or enforcement action is required.
Facility can only use Affirmative Defense in response to civil penalties if notification and report is submitted.
43
Affirmative Defense To use Affirmative Defense
facilities must show a “preponderance” of evidence that: • The excess emission was caused by a
malfunction and was not preventable or reoccurring, and
• The facility expedited repairs, actions were documented in signed logs, and a root-cause analysis was completed.
44
SSM Plan No SSM Plan required; however
may be more important now than ever due to potential enforcement action.
45
Things to Take Away The current status of the Boiler MACT
rules? Where do I stand now? What are my compliance options? What are my compliance plans? Be in action!
46
Questions?
Speaker Contact Info:
Eric M. [email protected]
610.933.5246 x17
All4 Inc. - 2393 Kimberton Road - P.O. Box 299 - Kimberton, PA 19442
610.933.5246 - www.all4inc.com