ARPA-E PERFORM Workshop
June 17, 2019
Managing Risk in the GridToday &Tomorrow
1
![Page 2: Managing Risk in the Grid Today &Tomorrow Risk in the... · ARPA-E PERFORM Workshop June 17, 2019 Managing Risk in the Grid Today &Tomorrow 1](https://reader036.vdocuments.net/reader036/viewer/2022071008/5fc657c08dc2954cdd0d5262/html5/thumbnails/2.jpg)
Grid operators take many actions over time to
prepare for real time conditions
2
$
$
$
Inter Day
No Current MISO Market Prices
Current Availability and Flexibility
Markets and Processes
$
$
Inter Day
$ Current MISO Market Prices
![Page 3: Managing Risk in the Grid Today &Tomorrow Risk in the... · ARPA-E PERFORM Workshop June 17, 2019 Managing Risk in the Grid Today &Tomorrow 1](https://reader036.vdocuments.net/reader036/viewer/2022071008/5fc657c08dc2954cdd0d5262/html5/thumbnails/3.jpg)
A series of procedures are also in place to
address emergencies…
3
• MaxGen emergencies have occurred in all seasons but have not surpassed step 2
![Page 4: Managing Risk in the Grid Today &Tomorrow Risk in the... · ARPA-E PERFORM Workshop June 17, 2019 Managing Risk in the Grid Today &Tomorrow 1](https://reader036.vdocuments.net/reader036/viewer/2022071008/5fc657c08dc2954cdd0d5262/html5/thumbnails/4.jpg)
… as conditions can deviate from the expected
4
![Page 5: Managing Risk in the Grid Today &Tomorrow Risk in the... · ARPA-E PERFORM Workshop June 17, 2019 Managing Risk in the Grid Today &Tomorrow 1](https://reader036.vdocuments.net/reader036/viewer/2022071008/5fc657c08dc2954cdd0d5262/html5/thumbnails/5.jpg)
Gaps in availability & flexibility are expected to
expand due to the combined effect of trends
• Age and retirement of the portfolio’s generating units
• High correlation in timing of planned outage for scheduled resources
• Growth in demand side and other emergency-only capacity as a percent of the overall portfolio
• Growing reliance on intermittent or unscheduled resources, including interchange
• Growth of variable energy resources as a major element of the fleet
Key industry trends
7
*Chart reflects ratios of generation.
MISO Energy Mix Transition (GWH) from 2005 to 2018 to 2030
Based on Utility Announcements &
State Integrated Resource Plans*
![Page 6: Managing Risk in the Grid Today &Tomorrow Risk in the... · ARPA-E PERFORM Workshop June 17, 2019 Managing Risk in the Grid Today &Tomorrow 1](https://reader036.vdocuments.net/reader036/viewer/2022071008/5fc657c08dc2954cdd0d5262/html5/thumbnails/6.jpg)
Long-termLong-term
Effective market, operations & planning products,
services & tools across time periods are necessary
6
15-min to hourly15-min to hourly
5-30 min5-30 min
5-10 min5-10 min
RTRT
Sub-hourly to hourly
Balancing capability
Frequency stabilityVoltage stability
Effective dispatch
Effective reserves & deliverability
Ramping capability (beyond real-time dispatch)
Unit commitment efficiency
Operating day capacity
Computational performance
Effective system planning
Effective forecasts
Effective market signals
FTR funding sufficiency
Decision-making tools
Across Timescales
SAMPLE SET OF NEEDS