manual qs en

24
USERS- AND INSTALLATION MANUAL Sunmaster QS1200 - QS2000 Grid connected solar inverter MASTERVOLT Snijdersbergweg 93, 1105 AN Amsterdam The Netherlands Tel.: +31-20-342 21 00 Fax.: +31-20-697 10 06 www.mastervolt.com English / v 1.0 October 2003

Upload: velizarko

Post on 17-Jul-2016

137 views

Category:

Documents


16 download

DESCRIPTION

PV inverter datasheet and manual.

TRANSCRIPT

Page 1: Manual QS En

USERS- AND INSTALLATION MANUAL

Sunmaster QS1200 - QS2000 Grid connected solar inverter

MASTERVOLT Snijdersbergweg 93, 1105 AN Amsterdam The Netherlands Tel.: +31-20-342 21 00 Fax.: +31-20-697 10 06 www.mastervolt.com English / v 1.0 October 2003

Page 2: Manual QS En

2 Sunmaster QS1200 - QS2000 / v 1.0 / EN

CONTENTS English / v 1.0 October 2003

1 GENERAL INFORMATION................................................................................................. 5

1.1 Product description...................................................................................................... 5 1.2 Use of this manual....................................................................................................... 5 1.3 Validity of this manual ................................................................................................. 5 1.4 Guarantee Specifications ............................................................................................ 5 1.5 Liability ........................................................................................................................ 5 1.6 Changes to the Sunmaster.......................................................................................... 5 1.7 Location of the type- and serial number indication ...................................................... 5

2 SAFETY GUIDELINES AND WARNINGS .......................................................................... 6

2.1 Warnings and symbols ................................................................................................ 6 2.2 Intended use ............................................................................................................... 6 2.3 Organisational measures ............................................................................................ 6 2.4 Installation, maintenance and repair ........................................................................... 6 2.5 Warning of special dangers......................................................................................... 6

3 INSTALLATION AND COMMISSIONING........................................................................... 7

3.1 Apparatus version ....................................................................................................... 7 3.2 Mounting and installation............................................................................................. 8

3.2.1 Use of spring-cage terminal blocks ....................................................................... 9 3.3 Connection of solar (DC) cabling .............................................................................. 10

3.3.1 DC connection by means of MultiContact connectors......................................... 10 3.3.2 Direct connection of the DC cabling onto the power board ................................. 12

3.4 Connection of the AC cabling.................................................................................... 14 3.4.1 AC connection by means of a Powercon connector............................................ 14 3.4.2 Direct connection of the AC cabling on the Power Board ................................... 15

3.5 Grounding cable........................................................................................................ 15 3.6 Installation of the QS-Display (optional) .................................................................... 15 3.7 Commissioning.......................................................................................................... 15

4 OPERATION ..................................................................................................................... 16

4.1 LED-bar..................................................................................................................... 16 4.2 QS Display (optional) ................................................................................................ 16 4.3 Monitoring ................................................................................................................. 16 4.4 Forced cooling........................................................................................................... 16

5 MAINTENANCE ................................................................................................................ 17

6 FAILURES......................................................................................................................... 17

Page 3: Manual QS En

Sunmaster QS1200 - QS2000 / v 1.0 / EN 3

7 DECOMMISSIONING AND DEMOUNTING...................................................................... 18

7.1 AC switch off ............................................................................................................. 18 7.2 Disconnection of AC cabling ..................................................................................... 18

7.2.1 Disconnecting AC by means of a Powercon connector ...................................... 18 7.2.2 Disconnection of direct AC cabling from the power board .................................. 18

7.3 Switching off DC voltage ........................................................................................... 18 7.4 Disconnection of DC (solar) cabling .......................................................................... 18

7.4.1 Disconnecting DC cabling by means of MultiContact connectors ....................... 18 7.4.2 Disconnecting DC cabling directly from the power board.................................... 19

7.5 Transportation ........................................................................................................... 19 7.6 Re-installation ........................................................................................................... 19

8 TECHNICAL SPECIFICATIONS....................................................................................... 20

9 CE DECLARATION OF CONFIRMITY ............................................................................. 22

10 OUTLINE DRAWINGS ...................................................................................................... 23

Page 4: Manual QS En

4 Sunmaster QS1200 - QS2000 / v 1.0 / EN

Page 5: Manual QS En

Sunmaster QS1200 - QS2000 / v 1.0 / EN 5

1 GENERAL INFORMATION 1.1 Product description

The Sunmaster QS1200 / QS2000, further mentioned as “Sunmaster”, is a grid connected inverter, used for the conversion and feed back into the utility grid of the power generated by photovoltaic modules.

1.2 Use of this manual This manual serves as a guideline for the safe and effective installation and operation of the Sunmaster: • For the electrician this manual gives directions for the installation, operation and commissioning. • For the end-user this manual gives directions for the operation, maintenance and possible

correction of minor malfunctions of the Sunmaster. • Every person who works with the apparatus, both the installer and the end-user, must be

completely familiar with the contents of this manual, and must carefully follow the instructions contained herein.

• The manual must be immediately accessible to the user • This English manual has 10 chapters.

1.3 Validity of this manual All the specifications, provisions and instructions contained in this manual apply solely to the Mastervolt-delivered standard versions of the Sunmaster (Refer to table 1, chapter 3.1).

1.4 Guarantee Specifications • Mastervolt assures the product guarantee of the Sunmaster during two years after your purchase,

on the condition that all instructions and warnings given in this manual are taken into account during installation and operation.

• Among other things, this means that installation is done by a qualified electrician, that installation and maintenance are executed according to the stated instructions and correct working sequence and that no changes or repairs may have been executed on the Sunmaster other than by Mastervolt.

• The warranty is limited to the costs of repair and/or replacement of the product by Mastervolt only. Costs for installation labour or shipping of the defective parts are not covered by this warranty.

• For making an appeal on warranty you can directly contact your supplier, mentioning your complaint, application, date of purchase and part number / serial number

1.5 Liability

Mastervolt can accept no liability for consequential damage due to use of the Sunmaster, possible errors in the manual and the results thereof.

1.6 Changes to the Sunmaster Changes on the Sunmaster may be carried out only after the written permission of Mastervolt

1.7 Location of the type- and serial number indication Important technical information required for service, maintenance & secondary delivery of parts can be derived from the type number indication plate and may therefore not be removed! The type number indication is placed at the following locations: • on the back side of the cabinet; • inside the cabinet: on the heatsink left to the cooling fan.

Remove the front cover plate to gain access inside the cabinet. Therefore the two screws on the bottom side of the front cover plate must be released, so that the front cover plate can be slid from the cabinet.

Page 6: Manual QS En

6 Sunmaster QS1200 - QS2000 / v 1.0 / EN

2 SAFETY GUIDELINES AND WARNINGS 2.1 Warnings and symbols

Safety instructions and warnings are marked in this manual by the following pictograms:

CAUTION ! Special information, commands and prohibitions in order to prevent damage. WARNING! A WARNING refers to possible injury to the user or installer or significant material damage to the Sunmaster if the installer / user does not (carefully) follow the stated procedures

2.2 Intended use The Sunmaster is constructed as per the applicable safety-technical guidelines. Use the Sunmaster only in installations that meet the following qualifications: • in permanent installations; • connected to a separate, grounded AC group, to which no other electrical equipment is connected; • the electrical installation must meet the applicable regulations and standards, must be carried out

correctly and must be in a good condition. • mounted in an enclosed, well ventilated environment, protected against rain, condensation,

moisture and dust; • installed according to the instructions stated in this manual • according to the technical specifications as stated in chapter 8;

WARNING! Never use the Sunmaster at locations where there is danger of gas or dust explosion! Use of the Sunmaster other than as mentioned under § 2.2 is not considered to be consistent with the intended purpose. Mastervolt is not liable for any damage resulting from the above

2.3 Organisational measures The installer / user must always: • have access to this manual; • be familiar with the contents of this manual. This applies particularly to Chapter 2, Safety

Guidelines & Warning.

2.4 Installation, maintenance and repair As lethal voltages exist, allow installation, maintenance and repair of the Sunmaster and changes in your electrical system to be carried out by qualified electricians only. • Connections and safety features must be executed according to the locally applicable regulations • In case of decommissioning and/or demounting follow the instructions as stated in chapter 7. • If such are required, use only original spare parts.

2.5 Warning of special dangers • Not only AC-grid voltage, but 450V DC may exist in the Sunmaster as well • The voltages present at the grid and solar side of the Sunmaster are not safe to touch and cannot

be switched off at the solar side. Depending on local applicable regulations the use of a additional DC switch may be obliged.

• Do not work on the Sunmaster and/or the electrical installation if it is still connected to the solar panels and/or AC-grid.

• Only allow changes in your electrical system to be carried out by qualified electricians • Check the wiring at least once a year. In case of loose connections, burned cables etc: switch off

the AC-grid immediately. Defects must be corrected immediately by an electrician

Page 7: Manual QS En

Sunmaster QS1200 - QS2000 / v 1.0 / EN 7

3 INSTALLATION AND COMMISSIONING

3.1 Apparatus version The Sunmaster is equipped with an anti-islanding device that ensures the switch off in case of grid failure. European countries maintain different regulations with regard to anti-islanding devices and the supply of energy back to the utility grid in general. The common islanding device is the QNS, which switches off the inverter if the grid voltage or frequency is out of range. In some countries like Germany the ENS device (VDE0126 compliant) which also measures the grid impedance, is compulsory. Mastervolt can provide both the QNS and the ENS versions of the Sunmaster. Both versions are available as several variants, suited to locally regulations. Check from the part number on the type number plate whether the version of the Sunmaster is appropriate to be connected to the local utility grid. Refer to table 1:

Part number Description Allowed to be used in: 130601200 Sunmaster QS1200 230V/50Hz QNS - EU Europe, except the countries mentioned below 130611200 Sunmaster QS1200 230V/50Hz ENS (MC) Germany, Belgium, France, Greece 130621200 Sunmaster QS1200 230V/50Hz ENS (Glands) Germany, Belgium, France, Greece 130631200 Sunmaster QS1200 230V/50Hz QNS - IT Italy Part number Description Allowed to be used in: 130602000 Sunmaster QS2000 230V/50Hz QNS - EU Europe, except the countries mentioned below 130612000 Sunmaster QS2000 230V/50Hz ENS (MC) Germany, Belgium, France, Greece 130622000 Sunmaster QS2000 230V/50Hz ENS (Glands) Germany, Belgium, France, Greece 130632000 Sunmaster QS2000 230V/50Hz QNS - IT Italy Table 1

WARNING! Never connect the Sunmaster to a utility grid which is not suitable for the use of the apparatus!

Page 8: Manual QS En

8 Sunmaster QS1200 - QS2000 / v 1.0 / EN

3.2 Mounting and installation The Sunmaster can be mounted in the AC distribution cabinet or in the vicinity of the solar panels. Obey the following stipulations during installation: • The Sunmaster is designed for indoor use only, according to safety class IP23. • Ambient temperature: -20 ... 50°C; (power derating above 40°C) • Humidity: 0-90% non condensing • Do not install the Sunmaster in environments where there is heavy dust

development. • If the Sunmaster is installed in the immediate vicinity of living areas, take into

account that the Sunmaster can produce a slight noise level when operating (refer to section 4.4).

• Mount the Sunmaster vertically on a solid wall. • The Sunmaster must be mounted in such a way that obstruction of the airflow

through the ventilation openings is prevented • No objects must be located within a distance of 10 cm around the Sunmaster. • Keep at least 30 cm in between the inverters when several Sunmasters are

installed next to each other. • Make sure that the hot air that is developed during operation will be discharged by

forced ventilation when installing the Sunmaster in a closed section. • Choose an appropriate AC-wire diameter, so that the wire resistance between the

Sunmaster and the AC distribution will not exceed 0.25 Ohm. Directive: up to 25 meters length, choose a wire diameter of 3 x 2.5 mm². Choose a larger wire size for lengths above 25 meter.

The AC/DC and grounding cables are connected at the bottom side of the cabinet. If necessary, the cabling can be fed from the top to the bottom side of the cabinet along the backside of the cabinet. Determine the mounting spots on the basis of figure 7 - outline drawing Sunmaster on page 23. Use suitable screws and dowels to fix the Sunmaster to the wall. Turn the mounting screws already into the wall. Place the cabinet over the screws. Then fasten the screws.

Page 9: Manual QS En

Sunmaster QS1200 - QS2000 / v 1.0 / EN 9

3.2.1 Use of spring-cage terminal blocks Depending on the model, the Sunmaster is equipped with spring-cage terminal blocks to connect the AC- and DC-wiring. Use a maximum wire diameter of 4mm² (stranded cable with cord end terminals) or 6mm² (hard-core wire) to fix to the AC and DC spring-cage connections. Strip the cable insulation 8-10mm. Use an insulated 4mm flat blade screwdriver to open the spring-cage clamp. CAUTION! Connect the wiring to the spring-cage terminals as stated in figure 1.

1

2

Figure 1: use of the spring cage terminal block 1 Push screwdriver firmly into

upper slot, as indicated in figure 1.

2 Move screwdriver upwards until connector has opened completely.

3 Place cable into opening and pull back screwdriver.

Page 10: Manual QS En

10 Sunmaster QS1200 - QS2000 / v 1.0 / EN

3.3 Connection of solar (DC) cabling The solar or DC side of the system consists of several photovoltaic (solar) modules, further mentioned as “PV modules”. The PV-modules are connected in series to form one or two strings. These strings consist of plus (+) and a minus (–) connections that can be connected directly to the Sunmaster. The Sunmaster is suited to connect two strings maximum, both existing of an equal quantity of identical PV-modules. The connection procedure described below incorporates several measurements which can only be carried out when sufficient irradiation is present. Installation should therefore be carried out during daytime only. CAUTION! • Short circuiting or reversing polarity may lead to damage to the Sunmaster, the

cabling and/or the terminal connections. • Follow all steps of the installation instructions in order of succession as described Depending on the model of the Sunmaster, the DC cabling can be connected in two ways: either using MultiContact connection material (refer to section 3.3.1 and figure 2) or directly onto the spring-cage terminal blocks on the power board inside the cabinet, by feeding the cabling through the cabinet’s cable glands (refer to section 3.3.2 and figure 3).

3.3.1 DC connection by means of MultiContact connectors

In this case the Sunmaster is equipped with four MultiContact contra plugs: two string connections each consisting of a plus (+) and a minus (–) connection. MultiContact connection material is touch proof and can be connected to the Sunmaster directly. 1 Check the voltage and polarity of each string with a suitable DC Voltmeter.

Connect the measuring pins to the corresponding plus (+) and minus (–) plug of each string. This voltage should be equal to the open circuit voltage (Voc) per PV module (refer to the specifications of the modules), multiplied by the number of modules in each string. Depending on the solar irradiation, the measured value should be equal to 70-95% of the theoretically calculated value. To match the specifications the measured voltage should be between 190 and 450VDC for Sunmaster QS1200 models and between 210 and 450VDC for Sunmaster QS2000 models

2 In case of two strings (which must be identical), check whether the two measured values are nearly identical (maximum deviation: 5%).

3 Check for each string the leakage current to ground. Measure the leakage current with a suitable meter (mADC) between the plus (+) connection and ground and the minus (–) connection and ground for each string. This value must be 0 (or less than 1mA).

4 Connect the MultiContact plugs of the string cabling to the corresponding contra plugs on the Sunmaster (Refer to figure 2: [9] for the plus (+) connections and [10] for the minus (–) connections).

Page 11: Manual QS En

Sunmaster QS1200 - QS2000 / v 1.0 / EN 11

5 If only one string is connected, the unused MultiContact contra plugs should be covered using the supplied caps.

6 When the DC-cabling has been installed correctly, some indication LEDs on the front panel will illuminate, indicating that the AC side has not yet been connected: - Both the red LED (diagnostic) and the yellow LED (0% / general fault) illuminate - With the ENS versions the yellow LED (50% / grid quality) illuminates as well.

WARNING! Never disconnect the MultiContact plugs during operation of the Sunmaster. Not complying with this instruction may cause a spark or an electric arc. Should an arc develop, both plug and socket of the Sunmaster must be replaced.

Figure 2: Connection of the DC-cabling using MultiContact connection material

Page 12: Manual QS En

12 Sunmaster QS1200 - QS2000 / v 1.0 / EN

3.3.2 Direct connection of the DC cabling onto the power board WARNING! The voltages present on the DC-cabling of the PV modules are high (up to 450 VDC) and cannot be switched off. The stripping and connection of the cabling should therefore be carried out with the utmost care and suitable tools. The voltages of the DC system are floating (class II): there is no connection to ground. This means that when one of the string connections (plus or minus) is accidentally touched, this will not directly lead to personnel harm or accidents. However, this should be avoided in any case! Short circuiting of the plus (+) and minus (–) connections must be avoided at any cost! Follow in detail all steps of the installation instructions in order of succession as described below:

1 Open the connection area at the bottom side of the cabinet. To do so, loosen the

two screws at the bottom side and slide the front cover plate from the cabinet. 2 The cabinet is fitted with four glands for the DC cabling (refer to figure 3, parts [9]

and [10]). Feed one non-stripped DC cable per gland into the cabinet. 3 Open the orange lids of both DC separators (part [4] in figure 3). 4 Strip approx. 8 mm of the plus (+) cable of string 1 with appropriate tools and

connect the cable to the first plus (+) PCB connector (part [2] in figure 3). This is a spring-cage terminal block that can be opened using a flat blade screwdriver (see section 3.2.1 and figure 1). Check the connection by pulling the cable.

5 Repeat this for the minus (–) connection of string 1 and connect the cable to the first minus (–) PCB connector on the PCB (part [3] in figure 3).

6 Check the voltage and polarity of the string with a suitable DC voltage meter. To do so, insert the voltmeter’s measuring pins into screw driver’s opening of the terminal block. This voltage should be equal to the open circuit voltage (Voc) per PV module (refer to the specifications of the modules), multiplied by the number of modules in each string. Depending on the solar irradiation, the measured value should be equal to 70-95% of the theoretically calculated value. To match the specifications the measured voltage should be between 190 and 450VDC for Sunmaster QS1200 models and between 210 and 450VDC for Sunmaster QS2000 models

7 In case of two strings, repeat steps 4, 5 and 6 for the second string. At similar circumstances (equal solar irradiation) the measured voltage of the second string must be near to the measured voltage of the first string (maximum deviation: 5%)

8 Check for each string the leakage current to ground. Measure the leakage current with a suitable meter (mADC) between the plus (+) connection [2] and ground and the minus (–) connection [3] and ground for each string. This value must be 0 (or less than 1mA).

9 Close both DC separators by pushing the orange lids back in position (part [4]). Be sure to lock these separators firmly. Beware: a loose or unreliable contact may result in a defective Sunmaster!

Page 13: Manual QS En

Sunmaster QS1200 - QS2000 / v 1.0 / EN 13

10 When the DC-cabling has been installed correctly, some indication LEDs on the front panel will illuminate, indicating that the AC side has not yet been connected: - Both the red LED (diagnostic) and the yellow LED (0% / general fault) illuminate - With the ENS versions the yellow LED (50% / grid quality) illuminates as well

11 Tie the cabling together using a tie-rap directly after the glands, inside the cabinet. Tighten the glands (parts [9] and [10] in figure 3) to ensure the pull relief.

Figure 3: Direct connection of the DC-cabling onto the power board

Page 14: Manual QS En

14 Sunmaster QS1200 - QS2000 / v 1.0 / EN

3.4 Connection of the AC cabling The Sunmaster may only be used in a in a permanent installation, connected to a separate AC distribution group, to which no other electrical equipment is connected. The cabling between the junction box or electric cable duct and the Sunmaster must be double insulated. Use an AC-wire diameter of 3 x 2.5 mm² at least. Depending on the model of the Sunmaster, the AC cabling can be connected in two ways: by means of a Powercon connector (see section 3.4.1 and figure 4) or directly on the power board inside the cabinet (refer to section 3.4.2 and figures 2 and 3). In the latter case the cabling is led through the cabinet’s cable glands

3.4.1 AC connection by means of a Powercon connector

1 Switch off the AC voltage by means of the AC distribution switch in AC distribution cabinet.

2 Connect the AC cable to the Powercon connector according to figure 5. 3 Switch on the AC voltage again and check the voltage on the Powercon connector. 4 Plug the Powercon connector into the corresponding contra plug at the bottom

side of the cabinet (refer to figure 4). CAUTION! Never disconnect the Powercon connector during operation of the Sunmaster. Not complying with this instruction may cause damage to the Sunmaster and/or to the Powercon connector.

Figure 4: Powercon connector Figure 5: Assembly of the Powercon connector

5mm

1 2 3

LN

PE

Page 15: Manual QS En

Sunmaster QS1200 - QS2000 / v 1.0 / EN 15

3.4.2 Direct connection of the AC cabling on the Power Board 1 Cut off the AC voltage by switching off the AC distribution switch in the AC

distribution cabinet. 2 Feed the AC cabling through the gland into the cabinet (part [8] in figure 2/3). 3 Connect the AC-cabling to the corresponding terminal blocks on the power board

(L, N and PE). This is a spring-cage terminal block that can be opened using a flat blade screwdriver (see section 3.2.1 and figure 1).

4 Tighten the gland to ensure the pull relief. 5 Switch on the AC voltage again and check with an adequate multimeter whether

the voltage is present at the terminal block 6 Close the connection area of the Sunmaster.

3.5 Grounding cable If you make a connection between the PV-modules and the ground, you need to lead the grounding cable together with the DC-cables to the Sunmaster and then to the AC distribution. Make a connection between the grounding cable going from the PV-modules to the AC-distribution and the cabinet of the Sunmaster. For this purpose a grounding terminal is situated at the bottom side of the cabinet (part 7 in figure 4)

3.6 Installation of the QS-Display (optional) The optional QS-Display comes with a front cover plate. To install the QS-Display, replace the standard front cover plate by the QS-display cover plate 1 Open the connection area at the bottom side of the cabinet. To do so, loosen the

two screws at the bottom side and slide the front cover plate from the cabinet 2 Connect the QS-Display to the display connector (part 11 in figure 2/3) by means

of the flatcable provided. Lead the flatcable through the right hand side of the connection area, avoiding the cable from touching the fan or DC-cabling.

3 Fix the front cover with integrated QS-Display onto the connection area and tighten the two screws again.

4 If the QS-Display is connected correctly, the text “QS1200” or “QS2000” (model dependent) appears in the display.

5 Store the original front cover along with the users manual of the Sunmaster.

3.7 Commissioning If connection has been made correctly and solar irradiation is sufficient, the Sunmaster will switch on automatically: • The red indication LED (diagnostic) on the front panel will stay illuminated for 10

up to 300 seconds (reclosure time, depending on the model); meanwhile the yellow LED (0% / general fault) will flash. With the ENS versions of the Sunmaster the yellow LED (50% / grid quality) is illuminated as well.

• Next the red LED will extinguish and the yellow LED (0%) flashes for 5 seconds, indicating a self test

• Now the Sunmaster switches on. The LED-bar displays an indication of the energy that is generated by means of your PV-modules.

Page 16: Manual QS En

16 Sunmaster QS1200 - QS2000 / v 1.0 / EN

Figure 6: LED-bar

4 OPERATION After installation the Sunmaster will switch on automatically if solar irradiation is sufficient. The Sunmaster operates automatically: there is no need for adjustment or operation.

4.1 LED-bar The Sunmaster is standard provided with an integrated LED-bar (figure 6) at the front side of the cabinet. Under normal circumstances the LED-bar indicates the amount of power that is fed into the grid by the Sunmaster: the more LED’s illuminate, the more power is converted. After connection of the PV-modules and during sunrise a system check is carried out, indicated by the illumination of several LED’s. This system check takes up to 15 seconds. In case of a system failure, the cause of the failure is displayed by means of a combination of illuminating LEDs: the red ‘diagnostic’ LED illuminates in combination with one or more yellow LEDs. Refer to table 2 (chapter 6) for an explanation of the power- and failure indications. 4.2 QS Display (optional) The QS Display can easily be installed in the Sunmaster. It enables the user to monitor the daily yields for the last 20 days, the total energy and operating hours, and a variety of actual readings. Refer to the users manual of the QS Display for extended operating instructions.

4.3 Monitoring

The Sunmaster has two RJ-45 connectors that can be connected to the QS Databus. Mastervolt provides several monitoring solutions like PC software, dataloggers, remote monitoring and so on. Consult our web-site at www.mastervoltsolar.com for a comprehensive overview of all possibilities.

4.4 Forced cooling For an optimum internal temperature control the Sunmaster is provided with a cooling fan. Depending on circumstances, the cooling fan starts running slowly at approximately 50% of the nominal power. As internal temperature rises, the cooling fan will increase its speed. This is a normal effect which has a positive contribution to the efficiency and lifetime of the Sunmaster.

Page 17: Manual QS En

Sunmaster QS1200 - QS2000 / v 1.0 / EN 17

5 MAINTENANCE No specific maintenance to the Sunmaster is required. Examine your electrical installation on a regular base, at least once a year. Defects such as loose connections, burnt wiring etc. must be corrected immediately. If necessary, use a soft clean cloth to clean cabinet of the Sunmaster. Never use any liquids, acids and/or scourers.

6 FAILURES The operation of the Sunmaster is controlled and checked by a microprocessor. If an error occurs, it is detected by the apparatus itself: the red indication LED (diagnostic) at the front of the cabinet will illuminate. If the irradiation of the PV-modules is insufficient, the Sunmaster switches off automatically. When switched off, none of the LED indications will illuminate. As long as the the red indication LED isn’t illuminated, no failure is detected: the Sunmaster is operating normally. When the red indication LED illuminates, a failure of the electrical installation or the Sunmaster is detected. The cause of failure is displayed by means of a combination of one or more illuminating yellow LED’s. Refer to table 2 for explanation of the error codes. Consult an installer, if you cannot solve the problem by means of the table below.

LED INDICATION MEANING 100% 75% 50% 25% On Diagnostic Naam Model

QS 1200 QS 2000 ☼ ☼ ☼ ☼ ☼ – Power > 87.5 % 840–960Wac 1400–1600Wac– ☼ ☼ ☼ ☼ – Power 62.5 – 87.5 % 600–840Wac 1000–1400Wac– – ☼ ☼ ☼ – Power 37.5 – 62.5 % 360–600Wac 600–1000Wac – – – ☼ ☼ – Power 12.5 – 37.5 % 120–360Wac 200–600Wac – – – – ☼ – Power < 12.5 % 0–120Wac 0–200Wac – – – – Blinking ☼ / – All conditions are normal; the inverter is

starting up. This can take up to 300 sec. ☼ – – – – ☼ Solar

Insluation Leak current between PV-modules and grounding. Contact your supplier.

– ☼ – – – ☼ Temp. Temperature of the inverter is too high. Is the airflow of the inverter blocked?

– – ☼ – – ☼ Grid Quality

Fault created by the ENS-unit. The grid quality is outside normal limits. Check the grid connection.

– – – ☼ – ☼ Solar high The DC-voltage is too high. Contact your supplier.

– – – – ☼ ☼ General Fault

The grid is cut off or outside its limits. Check the grid connection.

– – – – – Blinking Hardware Fault

A hardware failure is detected by the microprocessor. Contact your supplier.

Table 2: Operation and failure codes.

Page 18: Manual QS En

18 Sunmaster QS1200 - QS2000 / v 1.0 / EN

7 DECOMMISSIONING AND DEMOUNTING The Sunmaster can only be put out of operation if no power is converted to the public grid. To put the Sunmaster out of operation, follow the instructions in order of succession as described below:

7.1 AC switch off Cut off the AC voltage by switching off the AC distribution switch in the AC distribution cabinet before decommissioning or demounting the Sunmaster. Check whether both the red indication LED (diagnostic) and the yellow LED ‘0% / general fault’ illuminate (with the ENS versions the yellow LED ‘50% / grid quality’ illuminates as well). CAREFUL Always switch off AC voltage before decommissioning or demounting the Sunmaster.

7.2 Disconnection of AC cabling Depending on the model of the Sunmaster, the AC cabling can be disconnected in two ways: by means of a Powercon connector (see section 7.2.1) or by removing the AC cabling from the power board inside the cabinet (refer to section 7.2.2).

7.2.1 Disconnecting AC by means of a Powercon connector Pull the Powercon connector from the socket by turning the locking ring counter clockwise simultaneously.

7.2.2 Disconnection of direct AC cabling from the power board 1 Open the connection area at the bottom side of the cabinet. To do so, loosen the

two screws at the bottom side and slide the front cover plate from the cabinet. 2 Loosen the cable glands. 3 Remove the AC wiring from the terminal blocks (L, N en PE) by opening the spring

cage clamps with an insulated 4mm flat blade screwdriver (see figure 1).

7.3 Switching off DC voltage Switch off the external DC switch, if such is applied in the installation. Use extra caution and pay careful attention while removing the DC (solar) cabling if no external DC switch is applied.

7.4 Disconnection of DC (solar) cabling Depending on the model of the Sunmaster, the DC cabling can be disconnected in two ways: either by removing the MultiContact connectors (refer to section 7.4.1 and figure 2) or by disconnecting the wiring directly from the spring-cage terminal blocks on the power board inside the cabinet (refer to section 7.4.2 and figure 3).

7.4.1 Disconnecting DC cabling by means of MultiContact connectors MultiContact connection material is touch proof. Remove the MultiContact connectors one by one from the Sunmaster.

Page 19: Manual QS En

Sunmaster QS1200 - QS2000 / v 1.0 / EN 19

7.4.2 Disconnecting DC cabling directly from the power board WARNING! Hazardous voltages are present on the DC-cabling. Therefore the DC-cables must be disconnected and isolated one by one. The voltages present on the DC-cabling of the PV modules are high (up to 450 VDC) and cannot be switched off. The voltages on the DC side of the system are floating (class II): there is no connection to ground. This means that when one of the string connections (plus or minus) touched accidentally, this will not directly lead to personnel harm or accidents. However, this should be avoided in any case! Short circuiting of the of the plus (+) and minus (–) connections must be avoided at any cost Follow in detail all steps in order of succession as described below: 1 Open the connection area at the bottom side of the cabinet. To do so, loosen the

two screws at the bottom side and slide the front cover plate from the cabinet. 2 Open the orange lids of both DC separators (part [4] in figure 3). 3 Remove the DC-cable at the leftmost position from the terminal block by opening

the spring cage clamps with an insulated 4mm flat blade screwdriver (see figure 1) 4 Isolate the core of the wires with insulating tape. 5 Repeat steps 3 and 4 to remove all other DC-cables by removing and isolating

each cable one by one.

7.5 Transportation Always use the original package for transportation.

7.6 Re-installation To re-install the Sunmaster, follow the instructions as described in chapter 3.

Page 20: Manual QS En

20 Sunmaster QS1200 - QS2000 / v 1.0 / EN

8 TECHNICAL SPECIFICATIONS

General Sunmaster QS1200 Sunmaster QS2000 Typical string length 5-9 modules (72 cells); 7 -12 modules (54 cells) or 10-18 36 cells modules Operating temperature -20 to 50 °C Storage temperature -20 to 70 °C Relative humidity max. 95% Protection degree IP23 Safety class class I Galvanic isolation class II MTBF 165.000 hours Dimensions 340 x 250 x 120 mm 340 x 250 x 140 mm Weight 4.4 kg 6 kg Solar input (DC) Sunmaster QS1200 Sunmaster QS2000 Nominal power 950W DC 1700W DC Maximum power 1100W DC 1800W DC PV power range 700 - 1200 Wp 1200 - 2100 Wp MPP tracker 1 (dynamic) MPP voltage range 100 - 380V DC Maximum voltage 450 VDC Rated current (by shifting upwards the operating voltage)

5A 7.5A

Start-up power 2W String connections 2 DC connector 4 glands PG9 + PCB terminal blocks 4mm² (MultiContact is optional) Grid output (AC) Sunmaster QS1200 Sunmaster QS2000 Nominal power 900W AC 1600W AC Maximum power 1050W AC 1725W AC Voltage 230V (184 - 276V, model dependent) Nominal current: 4 A (5A max.) 7 A (8,3A max.) Fuse 5 x 20 mm. 250V / 6.3A T 5 x 20 mm. 250V / 10A T Frequency 50Hz (49.7 - 51.3Hz, model dependent) Power factor 0.99 Stand-by power 0W EU efficiency 94.5% 94% Maximum efficiency 95% 95% AC entrance gland PG-11 + PCB terminal blocks 4mm² (Powercon is optional) Safety devices General Galvanic separation between DC and AC side by means of a HF transformer

(class II) Island protection Redundant voltage and frequency window monitoring (QNS);

Independent cut-off by means of 2 pole relay and solid state switch. ENS VDE 0126 compliant (optional). UK - G83: software frequency shift

Reclosure time 10 - 300s (model dependent) Temperature protection Power derating above 75°C internal temperature; switch off at 90°C DC side earth fault detection, over-voltage detection, polarity protection (diodes),

current limitation, transients (varistor and buffer capacitor), overload (temperature controlled power derating)

AC side Current limitation, over- and under-voltage, over- and under-frequency Short circuit (ceramic fuse), transients / surge (varistors)

Page 21: Manual QS En

Sunmaster QS1200 - QS2000 / v 1.0 / EN 21

Monitoring Indicator 6 LED’s for indication of power and fault diagnoses External communication 2 RS 485 connections to connect to the QS Databus Monitoring (optional) QS Display integrated LCD,

(languages: English, German, Dutch, Italian, Spanish, French, Danish) QS Data Control Basic software for PC

(shareware from www.mastervoltsolar.com) QS PC-Link to connect the QS-Databus to the PC QS Data Control Premium datalogger and software with telephone dial

facilities QS Data Control Professional datalogger using meteo data from the

Internet Regulations and directives CE conformity yes EMC directive 89/336/EEG Emission EN 50081-1, EN55011, EN55014, EN55022, VDE0871 class B Harmonics EN 61000-3-2 IEEEp929 Flicker EN 61000-3-3 Immunity EN 50082-2 LV directive 73/23/EEG Safety EN60950 ENS VDE 0126 UK engineering recommendation G83-2003

Page 22: Manual QS En

22 Sunmaster QS1200 - QS2000 / v 1.0 / EN

9 CE DECLARATION OF CONFIRMITY Manufacturer: Mastervolt Address: Snijdersbergweg 93 1105 AN Amsterdam The Netherlands Herewith declares that: Product: Sunmaster QS1200 230V/50Hz Sunmaster QS2000 230V/50Hz is CE-marked and complies with the following standards: EMC directive: EMC 89/336/EEG Emission: EN 50081-1 EN 55011 class B (VDE 0875-11) EN 55014-1 EN 55022 VDE 0871 class B Harmonics: EN 61000-3-2 IEEE 929 Flicker: EN 61000-3-3 Electro static discharges (ESD): EN 61000-6-1 / EN50082-1 Radiated Immunity: EN 61000-6-1 / EN50082-1 Electrical fast transients (EFT): EN 61000-6-1 / EN50082-1 Conducted immunity : EN 61000-6-1 / EN50082-1 LV directive: LV 73/23 EEC Electrical safety : EN 60950 ENS: DIN VDE 0126 Amsterdam,

Dr. F.J. ter Heide, General Manager MASTERVOLT

Page 23: Manual QS En

Sunmaster QS1200 - QS2000 / v 1.0 / EN 23

10 OUTLINE DRAWINGS

Figure 7: outline drawings

Page 24: Manual QS En

24 Sunmaster QS1200 - QS2000 / v 1.0 / EN