marafiq / masa clean water team

30
MARAFIQ / MaSa Clean water Team

Upload: joel-garner

Post on 02-Jan-2016

110 views

Category:

Documents


11 download

DESCRIPTION

MARAFIQ / MaSa Clean water Team. Wastewater Department. Wastewater Department : 2 separate networks (industrial and sanitary) 1 industrial plant (design capacity 96,700 m3/d) 1 sanitary plant (design capacity 144,000 m3 /d ). Manpower TP 8: Industrial - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: MARAFIQ /  MaSa  Clean water Team

MARAFIQ / MaSa Clean water Team

Page 2: MARAFIQ /  MaSa  Clean water Team

2

Manpower TP 8: Industrial 4 shifts for operation (96 employees)1 day shift for maintenance (48 employees)

Wastewater Department

Wastewater department: 479 employees

Manpower TP 9: Sanitary4 shift for operation (76 employees)1 day shift for maintenance (52 employees)

Aeration tank stage 2 lagoon lagoonExtension side

Wastewater Department : 2 separate networks (industrial and sanitary) 1 industrial plant (design capacity 96,700 m3/d) 1 sanitary plant (design capacity 144,000 m3 /d )

Page 3: MARAFIQ /  MaSa  Clean water Team

Water cycle for Jubail

Irrigation

Wastewater treatment

plants

Network collectionIndustrial and

domestic consumption

Return to the environment

JUBAILWATER OPEN CYCLE

3

Potable water plant

Page 4: MARAFIQ /  MaSa  Clean water Team

4

The main purpose of wastewater treatment is to remove harmful material from water and reuse it.

Wastewater treatment objectives

Waste waterwater

sludgeInlet wastewater TP8

Environment return

Sludge production TP8

Page 5: MARAFIQ /  MaSa  Clean water Team

Total 165, 000cu.m of wastewater on a daily basis, through physical, biological, and chemical treatment systems, to be reused or returned to Seawater Cooling Return Canal.

Treatment

There are two kinds of Wastewater Treatment Plants in Jubail Industrial City.Industrial Wastewater Treatment Plant and Sanitary Wastewater Treatment Plant

Page 6: MARAFIQ /  MaSa  Clean water Team

6

Industrial Wastewater Network

Page 7: MARAFIQ /  MaSa  Clean water Team

7

59 Km industrial network

623 km sanitary network

224 lifting stations

58 pumping stations

Key figures:

PS10: pumping station

Page 8: MARAFIQ /  MaSa  Clean water Team

8

Stage 1 commissioning in 1983 RCER 1999Contact stabilization process, pressure filter and ozone

treatment

Stage 2 commissioning in 1989 RCER 1999Settlement tank, activated sludge, pressure filter and

chlorination

Stage 3 commissioning in 12/2012 RCER 2004Chemical and biological treatment

Stage 4 design phase RCER 2010Will be commissioned in 2017

Tp8 history

RCER: Royal Commission Environment Regulation

Page 9: MARAFIQ /  MaSa  Clean water Team

Primary and secondary industrial waste water network

400 IBN BAYTAR

126 2 234 2 29 2 2442 2 360 3

400

700

36 2

200

200

350

160

342 2 367 2 110 244 2 86 2 230 2 360 2 1404 3 979 3 781 3 259 3

600

800

450

1058 2 450 1634 2 250

110

300 2826 2 29 2 126 2 1961 3

SIPC NIPC

350

300

360 2 410 2 3143 3 2979 3 1019 2 900 2

200

450

150

300 700 350 300 300

389 2 122 2 198 3 1705 3 1256 3 352 3 299 2

PETROKEMYA

Pump Station No.

Pump Capacity 299 2 # of Pumps

(M3/Hr)

SFCCL-02

GULF ARABI

GULF

STABILISERS

AL BILAD

TAYF

SAUDI KAYAN

1200

900

20

LEGENDΣ35 PS200

250

400

16

HADEED KEMYA(Ibn Hayyan)

200

800IWTP-08

10

UNITED

PRIME AND SECONDARY INDUSTRIAL FLOW CHART

200/1

10

200/3

50/4 SAMAD

Hamrani

Modern

LATEX

GFTI Décor

16SASREF

BEE'AH

MOBEED

21

56 59

57

200

58 18

SHARQ

11SADAF

1

AR RAZI

2

Gas Co

15

Ibn Sina Ibn Zahr

9

SODA

SUCCo

300

47

GULF PLASTIC

52

54

53

ASLAK

CHEVRON

GULF GUARD

CHEMANOL

49

UGSC

46 47

Saudi Formaldehyde

SFCCL 01

TRIOMADA

gpc

UNICOIL

68

DERMABIT

22

51

500

79

23

24

55

69

74

SCPF

SABAYEK

450

7

3

AMF

70 5 6250

SAFCo

ALWAHA

JANA-01

400

200

JANA-02 APPC

PS22

PS18

PS1

Page 10: MARAFIQ /  MaSa  Clean water Team

10

PARAMETER UNITS Maximum Allowable 1999

Maximum Allowable 2004

Maximum Allowable 2010

Total Suspended Solids (TSS) mg/l 2000 2000 2000

Total Dissolved Solids (TDS) mg/l 2000 2000 2000

Ammonia (NH4) mg/l 120 120 120Chemical oxygen demand (COD) mg/l - - 1800Total organic carbon (TOC) mg/l 800 800 800

RCER main inlet parameters – table 3B

The regulations have changed to improve control on the quality of discharge to the

environment!

Page 11: MARAFIQ /  MaSa  Clean water Team

PUMPSPRESSURE

FILTERS

GRIT COLLECTION

OVER FLOW

OZONE CONTACT TANK

RECLAIMED WATER DISCHARGE

OZONE GENERATORS

SLUDGE THICKENING TANKS

SECONDARY SETTLEMENT TANKS

OIL SEPARATION PLANT RETURN

SLUDGE PUMP STATION RETURN SLUDGE

AERATION TANK-3

FROM PUMP STATIONS

WASTE SLUDGE

SETTLEMENT LAGOON

PRIMARY TANKS

AERATED SLUDGE LAGOONAERATED LAGOON # 1

INTERMEDIATE FILTERS

INLET WORKS

BALANCING TANKS

INLET PUMPS

SLUDGE TREATMENT

NEUTRALIZATION DOSING PLANT

SETTLEMENT LAGOON

SCREENING

1 2

EMERGENCY PUMP STATION

AERATED LAGOON # 4

IWTP - PROCESS DIAGRAM

dmr.sahib/07/ may/ 05

SLUDGE FILTRATION

HOUSE

AERATION TANK-2

AERATION TANK-1

DEWATERED SLUDGE TO LANDFILL

AERATED LAGOON # 3

AERATED LAGOON # 2

NEUTRALIZATION TANK

2 1

4

1

3

2 3 4

5 6 7 8

EFFLUENT PUMPS

RECLAIMED WATER STORAGE TANK- 1

CHLORINE PLANT- 1

CHLORINE PLANT- 2

RECLAIMED WATER STORAGE TANK- 2

Page 12: MARAFIQ /  MaSa  Clean water Team

LAGOONS INLET

Inlet works including flow distribution and oil retention facilities, floating oil skimmer and oil holding sump.

Page 13: MARAFIQ /  MaSa  Clean water Team

AERATED LAGOONS

Four aerated lagoons providing approximately five days retention equipped with floating surface aerators.

Page 14: MARAFIQ /  MaSa  Clean water Team

PRELIMINARY TREATMENT

Preliminary Treatment : Screening Grit removal� �The purpose of these units is to produce an approximately constant flow to the treatment units free from gross and abrasive material.

Page 15: MARAFIQ /  MaSa  Clean water Team

PRIMARY SEDIMENTATION TANKS

The wastewater enters the tanks through the central inlet pipe and leaves over the peripheral weir. The settled solids are removed from the base of the tanks as primary sludge, while grease, oil and floating solids are retained on the surface by baffles and removed with the scum.

Page 16: MARAFIQ /  MaSa  Clean water Team

AERATION TANKS

Activated sludge process and comprises three aeration tanks fitted with five fixed mechanical surface aerators per tank

Page 17: MARAFIQ /  MaSa  Clean water Team

SECONDARY SETTLEMENT TANKS

Secondary treatment comprises Aeration tanks, eight Final settling tanks, and three return activated sludge pumps.

Page 18: MARAFIQ /  MaSa  Clean water Team

PRESSURE FILTERS

Tertiary Filtration is necessary to effect sufficient suspended solids removal, and reduction of non-biodegradable organic compounds to produce a high quality effluent suitable for irrigation purposes.

Page 19: MARAFIQ /  MaSa  Clean water Team

CHLORINE PLANT

A chlorination system is installed to produce a residual concentration of this chemical.

Page 20: MARAFIQ /  MaSa  Clean water Team

SLUDGE DEWATERING BELT PRESS

The Sludge is first thickened in tanks where the supernatant liquors return to the upstream of the screens. The thickened sludge are passed to filter belt presses where additional moisture is removed by mechanical means after the addition of polyelectrolyte.

Page 21: MARAFIQ /  MaSa  Clean water Team

DEWATERED SLUDGE CONVEYOR

The sludge cake is transferred by a series of belt conveyors to storage bins prior to disposal at the Sanitary Landfill.

Page 22: MARAFIQ /  MaSa  Clean water Team

22

PARAMETER UNITSMaximu

m Allowable

1999

Monthly Average

1999

Maximum

Allowable 2004

Monthly Average

2004

Maximum

Allowable 2010

Monthly Average

2010

Total Suspended Solids mg/l 15 10 10 10 10 10

Total Dissolved Solids mg/l 2000 1750 2000 1750 2000 1750Turbidity N.T.U. 5 2 5 2 5 2AmmoniaTotal as N mg/l 40 15 5 - 5 -COD mg/l 350 150 50 - 50 -BOD5 mg/l 50 25 10 - 10 -Nitrate mg/l - - 10 - 10 -

RCER reclaimed water outlet main parameters – table 3D

Among the best quality irrigation water in the world!

Page 23: MARAFIQ /  MaSa  Clean water Team

23

General Information about IWTP-8

Design Criteria for Stage-2 : Daily Average flow 41,700 m3/d

Parameters unit Design

incoming Outlet

Chemical Oxygen Demand (COD) mg/l 1800 50Biochemical Oxygen Demand (BOD5) mg/l 475 10Total Suspended solids ( TSS) mg/l 300 10Ammonia (NH4) mg/l 60 5

Design Criteria for Stage-3 : Daily Average flow 55,000 m3/d

Parameters unit Design

Incoming outlet

Biochemical Oxygen Demand (BOD)

mg/l 260 20

Total Suspended solids (TSS) mg/l 215 15

Stage 3 has additional capacity to treat higher

level of pollution.

Page 24: MARAFIQ /  MaSa  Clean water Team

TP8 process general view

25 000 m3/day

To environment

Daily average flow

Daily average flow

Trea

tmen

t cap

acity

55,

000m

3 /da

y

Trea

tmen

t cap

acity

41,

700m

3 /da

y

Industrial pumping station

Effluent pumping station

7 lagoons (3 in operation)

clarifiers

Page 25: MARAFIQ /  MaSa  Clean water Team

25

TP8 process Diagram

Fenton Reaction Tanks

Chlorine Chlorine

Effl uent Discharge

Emergency Pump Station

Lagoon-5

Lagoon-1

Lagoon-4

Lagoon-2

Lagoon-3

INLETPS-1

Lagoon-7

Lagoon-6

PS-18PS-22

Bar ScreensGrit

Removal

Neutralization Tank

Coagulation Tank

Flocculation Tank

Bar ScreensGrit

Removal

Aluminium Sulphate

Anionic Polyelectrolyte

Caustic Sulpuric Acid

Oil Separation Tanks

Neutralization Tank

Aeration Tanks Mechanical Aerators

Primary Clarifiers Lamella Separator

Aeration Tanks

Ferrous chloride

Hydrogen Peroxide

Caustic Soda

Sulfuric Acid

Polyelectrolyte- C

K Chamber

Chlorine Contact Tank

Chlorine Contact Tank

Primary Clarifiers

Intermediate Filters

SecondaryClarifiers Settling Tank

Pressure Filters

ReclaimeddWater

storage Tanks

Equalization Tank

Secondary Clarifiers

Fenton Clarifiers

Lamella Separator

Pressure Filters GAC Filters

Page 26: MARAFIQ /  MaSa  Clean water Team

26

Stage 2, existing biological treatmentRCER 1999

Design capacity 41,700m3/dayProcess equipment:

Inlet

Pretreatment

PST

Intermediate filter

Aeration tank

Tertiary filter

SSTchlorination

outlet

Sludge treatment

Waste waterSludgeTreated water

• Primary settlement tank PST (natural settlement)

• Classic biological process with surface aerator and blower.

• Secondary settlement tank SST (natural settlement)

• Tertiary filter

• Chlorination (chemical disinfection)

• 4 belt presses to treat sludge production (chemical polymer used)

Page 27: MARAFIQ /  MaSa  Clean water Team

Commissioning completed: 22/12/12Process equipment:

• Design capacity: 55000m3/day

• Coagulation flocculation (chemical reaction for settlement)

• Aeration tank by diffusor fine bubble

• Dissolved air flotation (DAF)(chemical reaction for coagulation)

• Fenton reactor(chemical oxidation)

• Multi Media Filter (MMF)

• Granular Activated Carbon (GAC) (chemical adsorption)

• Chlorination(chemical disinfection)

• One additional belt press to enhance the sludge treatment capacity

Stage 3 new bio/chemical treatmentRCER 2004

Inlet Outlet

Pre-treatment

Primary treatment

Aeration tank

Equalization tank

DAF

Fenton

MMF

GAC

Chlorination

Sludge treatment

27

Waste watersludgeTreated water

Page 28: MARAFIQ /  MaSa  Clean water Team

28

Chemical treatment:– Primary treatment with coagulation / flocculation

– Dissolved air flotation

– Fenton– Granular Activated Carbon filter

Additional value of stage 3

Coagulation / flocculation process

time

Stage 3 DAF

Page 29: MARAFIQ /  MaSa  Clean water Team

29

To provide the best services and continuity, MaSa performs more than 500 analyses each day to meet RCER and ensure that stringent water quality standards are met at all times.

QUALITY MONITORING AND CONTROL

TP8 laboratory(Potable water, Waste water, Sea water cooling)

Total Organic Carbon analyzer TP8 control room

RCER: Royal Commission Environmental Regulations

Page 30: MARAFIQ /  MaSa  Clean water Team

30

WASTEWATER DEPARTMENTBetter customer services strategy:

Work more closely with our customerto produce better reclaimed waterto be proactive to your needsto support your pretreatment requirement

Increase the automatic monitoring and control of daily operation and maintenance

Installing new online analyzers

Enhance real time data reporting to the Cockpit Performance O&M (CPO)