![Page 2: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/2.jpg)
What is GPU?
Marioff HI-FOG GPU is the only water-mist system propelled by a Gas-driven Pump Unit.
Like accumulator units, the GPU is using compressed gas as propellant and as atomizing agent, yet the GPU utilizes non-compressed water source.
GPU system is actuated either manually or automatically.
Provided with gas cylinders and a water tank, the GPU is a self contained unit, requiring no supply of electric power or water for operation
Marioff HI-FOG GPU was tested for both fire-righting ability and for component qualities to the satisfaction of FM (USA), VdS (Germany), and VNIIPO (Russia).
![Page 3: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/3.jpg)
Applicable Standards
NFPA 750 Standard on Water Mist Fire Protection Systems
FM Approval Standard Class 5560
VdS Standard
IMO
![Page 4: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/4.jpg)
Applications
Machinery Space:
oil pumps
oil tanks
fuel filters
transformer vaults
gear boxes
drive shafts
lubrication skids
diesel engine driven generators
other similar machinery using fuel and/or lubrication fluids with volatilities less than or equal to light diesel
![Page 5: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/5.jpg)
Applications
Special Hazard Machinery Space:
internal combustion engines, other equipment using fuel and/or lubrication fluids with volatilities less than or equal to Heptane.
incidental use, or storage of limited quantities of flammable liquids of not more than two 55 gal (208 L) drums.
![Page 6: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/6.jpg)
Applications
Turbine Enclosures
![Page 7: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/7.jpg)
Protected Enclosures
VdS Approved:
Maximum enclosure height 5 m
Maximum enclosure volume 500 m3
FM Approved:
Maximum enclosure height 7,5 m
Maximum enclosure volume 750 m3
IMO Approved:
Maximum enclosure height 7,5 m
Maximum enclosure volume 1500 m3
Also:
All ventilation openings and\or forced ventilation arrangement shall be capable of automatic closure or shut-down prior to system discharge.
![Page 8: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/8.jpg)
Structure & Components
Each GPU consists of:
Gas-Driven Pump Unit module
Bank of compressed gas cylinders, including actuator valves.
Section Valve
Monitoring devices (pressure gauge etc’.)
![Page 9: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/9.jpg)
Structure & Components
Actuator Valves
Hydraulic Valve
Solenoid Valve
dP (delta P) Valve
Slave Valve
![Page 10: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/10.jpg)
Structure & Components
Gas cylinders
Preferably provided by local supplier.
Dimensions:
Diameter: ca. 240 mm
Maximum cylinder height: 1390 mm - 1525 mm
Thread type: 24,32 1,814 SFS2292
(adaptor applicable for several options)
Amount of gas cylinders depends on:
Number of spray-heads
Duration of discharge
![Page 11: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/11.jpg)
Structure & Components
Monitoring Devices Pressure Gauge- Water Input line
Pressure Gauge- Output line
Pressure Gauge- Gas Cylinder (included in actuation valves)
Pressure Switch- Gas Cylinder (included in actuation valves)
![Page 12: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/12.jpg)
Structure & Components
Additional Devices
Shutoff Valve
Protection caps
Protective cabinet
![Page 13: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/13.jpg)
Operation
Standby
All section valves closed.
Pressure of ca. 25 bar in maintained by the standby pump.
All actuator salves are closed.
There is no flow in the system.
H DPSSSSSSSSS
SSSSSSSSS
H DPSSSSSSSSS
SSSSSSSSS
![Page 14: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/14.jpg)
Operation
Start Signal
One Section Valves opened.
Some flow generated by the standby pump, but the pressure drops. H DP
SSSSSSSSS
SSSSSSSSS
H DPSSSSSSSSS
SSSSSSSSS
![Page 15: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/15.jpg)
Operation
First Cylinder, Bank I
Hydraulic Valve opens.
Pressure increases in the manifold of cylinder bank I.
H DPSSSSSSSSS
SSSSSSSSS
H DPSSSSSSSSS
SSSSSSSSS
![Page 16: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/16.jpg)
Operation
Bank I
Slave Valves of bank I open.
H DPSSSSSSSSS
SSSSSSSSS
H DPSSSSSSSSS
SSSSSSSSS
![Page 17: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/17.jpg)
Operation
Discharge with Bank I
Pressure of bank I drops.
H DPSSSSSSSSS
SSSSSSSSS
H DPSSSSSSSSS
SSSSSSSSS
![Page 18: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/18.jpg)
Operation
First Cylinder, Bank II
dP valves releases the first cylinder of bank II.
Pressure increases in the manifold of cylinder bank II. H DP
SSSSSSSSS
SSSSSSSSS
H DPSSSSSSSSS
SSSSSSSSS
![Page 19: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/19.jpg)
Operation
Bank I
Slave Valves of bank II open.
H DPSSSSSSSSS
SSSSSSSSS
H DPSSSSSSSSS
SSSSSSSSS
![Page 20: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/20.jpg)
Spray-Heads
4S 1MC 8MC 1000
Installed at ceiling level or above a 2m wide door
discharging downward.
4S 1MC 8MB 1000
Installed above a 2m wide door
discharging downward.
![Page 21: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/21.jpg)
Spray-Heads
Ceiling height
Enclosure’s volume
Compressed gas
door spray-heads
5 m 500 m3 Air required for Special Hazard Machinery Spaces 5 m 500 m3 Nitrogen not required 5 m 750 m3 Air required 5 m 750 m3 Nitrogen not required
7,5 m - Air required 7,5 m - Nitrogen not required
Door spray-heads are not required for IMO approved systems.Door spray-heads are not required for IMO approved systems.
![Page 22: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/22.jpg)
Spray-Heads
Ceiling height up to 5 m and total volume of no more than 500 m3:
Max. spacing between spray-heads 5 m.
Max. distance from walls 2,5 m.
Ceiling height up to 7,5 m and\or total volume of no more than 750 m3:
Max. area between four adjacent spray-heads 12,5 m2.
Max. distance from walls 2,5 m.
![Page 23: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/23.jpg)
Distribution Network
Pressure Calculation:
Darcy-Weisbach calculation method is applied, assuming complete mixing of the water and gas mixture.
The spray head-specific nominal water flow rate of 12,5 litre/minute is multiplied by 1.8 and hydraulic calculations are run normally.
The calculated pressure drop must be within 5 – 15 bar.
![Page 24: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/24.jpg)
Distribution Network
![Page 25: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/25.jpg)
System Design
1) Application & Requirements
2) Enclosure
3) Spray-Heads location
4) Gas cylinders & Piping Network
![Page 26: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/26.jpg)
System Design
Sample RFQ No. 1
Application: fuel storage
Dimensions: 10 m (L) 8 m (W) 6 m (H)
Fire hazard: five fuel tanks, 350 litre of Diesel fuel each
Approval authority: FM
Protection time: 30 minutes
![Page 27: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/27.jpg)
System Design
Sample RFQ No. 2
Application: generators room
Dimensions: 14 m (L) 9 m (W) 10 m (H)
Fire hazard: two diesel generators
Approval authority: N.A.
Protection time: 60 minutes
![Page 28: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/28.jpg)
System Design
Sample RFQ No. 3
Application: steam turbine
Dimensions: 14 m (L) 9 m (W) 7,5 m (H)
Fire hazard: steam turbine
Approval authority: FM
Protection time: 15 minutes
945 m3 945 m3
![Page 29: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/29.jpg)
reminder: Spray-Heads
Ceiling height up to 5 m and total volume of no more than 500 m3:
Max. spacing between spray-heads 5 m.
Max. distance from walls 2,5 m.
Ceiling height up to 7,5 m and\or total volume of no more than 750 m3:
Max. area between four adjacent spray-heads 12,5 m2.
Max. distance from walls 2,5 m.
![Page 30: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/30.jpg)
System DesignSample Spray-Heads location No. 1
Application: compressors room
Dimensions: 10 m (L) 8 m (W) 6 m (H)
Fire hazard: electric motors, compressors, oil skid (150 litre)
Compressed gas: nitrogen, 200 bar
Approval authority: FM
Protection time: 30 minutes
volume = 480 m3volume = 480 m3
door spray-heads: not required door spray-heads: not required
grid: 2 \ 1 \ 2grid: 2 \ 1 \ 2
5 m
3,2 m
2,5 m2,5 m
2 m
4 m 10,25 m2
![Page 31: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/31.jpg)
System DesignSample Spray-Heads location No. 2
Application: generator room
Dimensions: 14 m (L) 10 m (W) 7 m (H)
Fire hazard: generator, electric cabinet
Compressed gas: air, 200 bar
Approval authority: IMO
Protection time: 60 minutes
volume = 980 m3volume = 980 m3
door spray-heads: not required door spray-heads: not required
grid: 3 \ 2 \ 3grid: 3 \ 2 \ 3
4,6 m
2,5
m5
m
2,4 m
11,5 m2
![Page 32: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/32.jpg)
System DesignSample Spray-Heads location No. 3
Application: engine test cell
Dimensions: 12 m (L) 8 m (W) 4 m (H)
Fire hazard: motor
Compressed gas: air, 200 bar
Approval authority: FM
Protection time: 60 minutes
volume = 384 m3volume = 384 m3
door spray-heads: required door spray-heads: required
grid: 2 x 3grid: 2 x 3
4 m 2 m
2,5 m
5 m
4 m 2 m
2,5 m
5 m
![Page 33: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/33.jpg)
reminder: Distribution Network
Pressure Calculation:
Darcy-Weisbach calculation method is applied, assuming complete mixing of the water and gas mixture.
The spray head-specific nominal water flow rate of 12,5 litre/minute is multiplied by 1.8 and hydraulic calculations are run normally.
The calculated pressure drop must be within 5 – 15 bar.
![Page 34: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/34.jpg)
System Design
Sample Piping Network No. 1
5 m
2 m
4 m
5 m
2 m
4 m
5 m
2 m
4 m
5 m
2 m
4 m
![Page 35: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/35.jpg)
reminder: Gas Cylinders
Amount of gas cylinders depends on:
Number of spray-heads
Duration of discharge
![Page 36: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/36.jpg)
System Design
Gas Cylinders and Actuation Valves for Sample No. 1
5 spray-heads
30 minutes discharge
5 m
3,2 m
2,5 m2,5 m
2 m
4 m 10,25 m2
15 cylinders = two banks of 8 cylinders = two banks of 4 + two banks of 415 cylinders = two banks of 8 cylinders = two banks of 4 + two banks of 4
First release valve: HydraulicFirst release valve: Hydraulic
Second bank release: dPSecond bank release: dP
![Page 37: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/37.jpg)
Restrictions
Site Specific:
Hazardous Areas
Temperature Range
Construction Materials
Water supply
Enclosure:
Shut-down time
Forced ventilation and openings
GPU:
Max. amount amount of spray-heads
![Page 38: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/38.jpg)
Don’t Forget
Other system:
Detection System
Alarm
Gas supply
Additional:
Enclosure
Warenty and service
![Page 39: Marioff HI-FOG GPU Systems for the protection of Industrial Applications Marioff HI-FOG Training 5 August 2008 Amit Lior](https://reader034.vdocuments.net/reader034/viewer/2022050711/56649c7b5503460f9492eb15/html5/thumbnails/39.jpg)
ThanksThanks