Marion Street Green Infrastructure Project Whittier Neighborhood Community Meeting June 20, 2018

Upload: others

Post on 02-Aug-2020

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

Marion StreetGreen Infrastructure ProjectWhittier Neighborhood Community MeetingJune 20, 2018

Page 2: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

Marion Street Green Infrastructure ProjectWhittier Neighborhood Community Meeting | June 20, 2018

Agenda

• Marion Street stormwater project• Water quality and green infrastructure• Marion Street green infrastructure project

• 29th and 30th Ave• 25th Ave

• Discussion

Page 3: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and
Page 4: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

Marion Street Green Infrastructure ProjectWhittier Neighborhood Community Meeting | June 20, 2018

Existing Conditions

July 11, 2011

Page 5: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

EXIS

TIN

G C

ON

DIT

ION

S (F

LO 2

D)

Estim

ated

max

imum

flow

dep

ths

for t

he 1

00-y

ear s

torm

prio

r to

the

cons

truc

tion

of th

e 33

rdSt

reet

Out

fall

Page 6: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

PRO

POSE

D C

ON

DIT

ION

S (F

LO 2

D)

Estim

ated

max

imum

flow

dep

ths

for t

he 1

00-y

ear s

torm

afte

r the

con

stru

ctio

n of

the

33rd

Stre

et O

utfa

ll

Page 7: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

Marion Street Green Infrastructure ProjectWhittier Neighborhood Community Meeting | June 20, 2018

33RD STREET OUTFALL PROJECT

1 2 3 4

MARION STREET SYSTEM

Phases

Page 8: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

Marion Street Green Infrastructure ProjectWhittier Neighborhood Community Meeting | June 20, 2018

Marion Street Project:Increase Storm Drain Capacity

3x Capacity

Page 9: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

Marion Street Green Infrastructure ProjectWhittier Neighborhood Community Meeting | June 20, 2018

SURFACE DRAINAGE IMPROVEMENTS

PRE-IMPROVEMENT(example)

POST-IMPROVEMENT(example)

Page 10: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

Marion Street Green Infrastructure ProjectWhittier Neighborhood Community Meeting | June 20, 2018

PHASES & SCHEDULE

Phase 1:• MLK Blvd to 26th Ave• Fall 2019

Phase 2:• 26th Ave to 21st Ave & Downing St• Summer 2020

Outreach & Next Steps:• 2019: Will be back to talk community about

construction schedule and impacts once have contractor on board

1

2

Page 11: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

Marion Street Green Infrastructure ProjectWhittier Neighborhood Community Meeting | June 20, 2018

Comprehensive Stormwater Management

Page 12: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

Denver’s Water Quality Problem

Over 1200 Total Outfalls• 300+ Outfalls into Cherry Creek

• 300+ Outfalls into South Platte

13% of Denver’s 98,900+ acres receive water quality treatment2013 Matrix Report

Denver’s Streams:

0/10 meet recreation standards7/10 suitable for aquatic life2016 Water Quality Report, Denver Dept. of Environmental Health

Page 13: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

Marion Street Green Infrastructure ProjectWhittier Neighborhood Community Meeting | June 20, 2018

City’s New Approach to Stormwater Management

Grey Infrastructure

Community Engagement

Green Infrastructure

Strategic Planning

Page 14: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

Marion Street Green Infrastructure ProjectWhittier Neighborhood Community Meeting | June 20, 2018

Green Infrastructure• Natural or built systems that use

vegetation and soils to manage stormwater runoff

• More resilient approach than relying on gray alone

• Numerous benefits

• Varying scales

Page 15: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

Marion Street Green Infrastructure ProjectWhittier Neighborhood Community Meeting | June 20, 2018

Benefits of Green Infrastructure• Improve water quality

• Reduce flood risks

• Reduce Urban Heat Island effect

• Improve air quality

• Absorb local carbon emissions

• Improve public health outcomes• Increase physical activity

• Improve mental wellbeing

• Reduce stress

• Lower traffic speeds and reduce injury

crashes

• Improve property values

Page 16: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

Marion Street Green Infrastructure ProjectWhittier Neighborhood Community Meeting | June 20, 2018

Sub/Regional Scale Green Infrastructure

Site-Scale Green Infrastructure

Page 17: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

Marion Street Green Infrastructure ProjectWhittier Neighborhood Community Meeting | June 20, 2018

Denver’s Residential Green Infrastructure

Lowell and Evans 16th Street (Upper Montclair Basin)

Page 18: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

Marion Street Green Infrastructure ProjectWhittier Neighborhood Community Meeting | June 20, 2018

Opportunity:Green Infrastructure on Marion Street• Implement GI on Marion Street as part of pipe project• Cost-efficient

Page 19: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

Marion Street Green Infrastructure ProjectWhittier Neighborhood Community Meeting | June 20, 2018

Public Engagement• Saturday, April 14: Meeting with Marion St. residents

• Wednesday, April 18: Whittier Community Meeting• ~20 attendees• Presentation + Table-top exercise

• Tuesday, May 22: Meeting with Principal Palmer at Whittier K-8

• Key themes:• Cut-through traffic from Downing

• Traffic calming• Safer pedestrian crossings

• Safety concerns at 25th Ave. and Marion St. • Maintenance & inspections• Make Marion Street greener

Page 20: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

29th

& 30

thAv

e In

ters

ectio

ns

• Consistent design• Traffic calming• Minimal ROW constraints• Surface Improvements

Page 21: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

29th

& 30

thAv

e In

ters

ectio

ns

• Consistent design• Traffic calming• Minimal ROW constraints• Surface Improvements

Page 22: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

29th and 30th

Designs

Page 23: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

Marion Street Green Infrastructure ProjectWhittier Neighborhood Community Meeting | June 20, 2018

25th Ave Intersection

• Central concern: Safety for students

• Partners in finding a solution:• Marion St. Stormwater Project Team• DPW Transportation & Mobility• Whittier K-8 Community

• August 24: Whittier K-8 “Back to School Night”

• Interested in this conversation? Make sure to check “25th and Marion” box on sign-in sheet

Page 24: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

Marion Street Green Infrastructure ProjectWhittier Neighborhood Community Meeting | June 20, 2018

Next Steps

Page 25: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

Marion Street Green Infrastructure ProjectWhittier Neighborhood Community Meeting | June 20, 2018

Planter Design and Education Event• What: Join the Denver Botanic Garden Horticulture Outreach

Manager and the Marion Green Infrastructure Project Team to:• learn about which low maintenance, low water, quick growing plants

are appropriate for Marion Street green infrastructure facilities• provide feedback about vegetation design for the facilities

• When: Morning, July 28th

• Where: Corner of Marion St. and 30th Ave.

Page 26: Marion Street Green Infrastructure Project...2018/06/20  · Whittier Neighborhood Community Meeting | June 20, 2018 Agenda • Marion Street stormwater project • Water quality and

Marion Street Green Infrastructure ProjectWhittier Neighborhood Community Meeting | June 20, 2018

Contact

Stormwater Improvements:Steve ChoiSenior [email protected]

Green Infrastructure:Ashlee GraceSenior Water Quality [email protected]