  • 7/27/2019 Master Data for SCM 2

    1/63

    SCM Master Data - 2

    Master Data for Distribution &Production Processes

    EGN 5623 Enterprise Systems Optimization(Professional MSEM)

    Fall, 2011

  • 7/27/2019 Master Data for SCM 2

    2/63

    SCM Master Data - 2

    Theories & Concepts

    EGN 5623 Enterprise Systems Optimization(Professional MSEM)

    Fall, 2011

  • 7/27/2019 Master Data for SCM 2

    3/63

    Distribution Planning in SCM (review)

    THEORY AND PRACTICE OF ADVANCED PLANNER AND OPTIMIZER IN SUPPLY CHAIN DOMAIN by Sam Bansal

  • 7/27/2019 Master Data for SCM 2

    4/63

    Time Horizons for Distribution andProduction Planning in SCM (review)

  • 7/27/2019 Master Data for SCM 2

    5/63

    Level of Detail and Time Horizonof Distribution and PP in APOModules (review)

  • 7/27/2019 Master Data for SCM 2

    6/63

    Distribution Planning and Production PlanningProcesses in APO Modules (review)

  • 7/27/2019 Master Data for SCM 2

    7/63

    Distribution and PP Modules in APO SystemStructure and Integration with ERP (review)

  • 7/27/2019 Master Data for SCM 2

    8/63

    Overview Master Data andApplication in DP and PP (review)

  • 7/27/2019 Master Data for SCM 2

    9/63

    Master Data and Application inDistribution Planning and PP (overview)

    Master Data for Distribution Planning:

    Location, Product, Resource, Transportation lane,

    Quota arrangement, Interchangeability group.

    Master data for Production Planning:Location, Product, Resource, PPM/PDS , Quota

    arrangement, Set up Group & matrix, and

    Interchangeability group.

  • 7/27/2019 Master Data for SCM 2

    10/63

    Master Data and Application in DistributionPlanning and PP (Overview)

    Transportation lanes:

    Transportation lanes are required from plant and

    distribution center to the transportation zone and have to

    be created manually. The allowed carriers have to be

    assigned per means of transport and transportation laneexplicitly.

    Quota arrangement (vendorss quota):

    If it is intended to source from multiple locations on aregular basis, quota arrangement must be used. The

    concerned products are assigned to the quota

    arrangement, and the ratio of the resources is defined

    per product.

  • 7/27/2019 Master Data for SCM 2

    11/63

    SCM Master Data - 2

    Master Data for Distribution

    Planning

    EGN 5623 Enterprise Systems Optimization(Professional MSEM)

    Fall, 2011

  • 7/27/2019 Master Data for SCM 2

    12/63

    Distribution and Supply ChainPlanning

    Distribution planning between the manufacturing

    plants and warehouses becomes important, as many

    companies change their logistics processes from non-

    coordinated local inventory management to a global

    inventory management in order to reduce inventories.

    The focus for distribution and supply chain planning is

    on make-to-stock production.

  • 7/27/2019 Master Data for SCM 2

    13/63

    Distribution Planning, Supply ChainPlanning, and Replenishment

  • 7/27/2019 Master Data for SCM 2

    14/63

    Process Chain for Distribution andSupply Chain Planning

  • 7/27/2019 Master Data for SCM 2

    15/63

    Distribution and Supply ChainPlanning

    1. Distribution planning is performed based on demand andstock information with the result of planned stock

    transfers.

    2. The most important issues are usually the netting of thelocal stocks, safety stock levels, sourcing options,

    transportation times and lot sizes for the planned stock

    transfers.

    3. If required, restrictions are considered regarding storagecapacity and handling capacity for goods issue and

    goods receipt.

  • 7/27/2019 Master Data for SCM 2

    16/63

    Distribution and Supply ChainPlanning

    Two processes exist within replenishment:

    1. Deployment, and

    Deployment is concerned with the fair share of

    quantities to the requesting parties in case of

    shortage or surplus. The constraints areavailable quantities.

    2. Transport load building.

    Transport load building is one step closer to

    execution and focuses on the creation of truckloads, where the task is to adjust the planned

    stock transports to the available

    trucks/transport means and take their capacity

    restrictions into account.

  • 7/27/2019 Master Data for SCM 2

    17/63

    Distribution and Supply ChainPlanning

    In SAP APO, there are four applications that support

    distribution and production planning:

    1. SNP heuristic

    2. SNP optimizer3. CTM (with SNP or PP/DS master data)

    4. PP/DS heuristics

    li i f i ib i d

  • 7/27/2019 Master Data for SCM 2

    18/63

    Applications for Distribution andSupply Chain Planning

  • 7/27/2019 Master Data for SCM 2

    19/63

    Features of the Application forDistribution

  • 7/27/2019 Master Data for SCM 2

    20/63

    Distribution and Supply ChainPlanning

    Distribution planning with SNP heuristic is often used in theenvironments where multiple sourcing is not an issue and

    production is usually able to meet the demands, so that the

    main task forSNP heuristic is to calculate the demands for

    production planning based on local inventories, transportation

    times, safety stocks and lot sizes.

    SNP optimization allows a complete consideration of the supply

    chain determinants (i.e., sources and cost, production capacity,

    transport, storage and handling). The aim ofSNP optimizer is

    to find a global optimum for supply chain based on cost andpenalty cost.

    CTM pursues a priority based on approaches such as FIFS.

  • 7/27/2019 Master Data for SCM 2

    21/63

    Order Cycle for Stock Transfer

  • 7/27/2019 Master Data for SCM 2

    22/63

    Order Cycle for Stock Transfers

    The stock transfer order has two aspects as a demand inthe source location and as a supply in the target location. The

    documents differ in SAP ERP and SAP APO.

    The creation of the planned stock transfer, deployment and

    transport load building (TLB) is performed in SAP APO.

    The execution part from the creation of the outbound delivery

    in the source location until the goods receipt in the target

    location is performed in SAP ERP, and the information is

    displayed in SAP APO.

  • 7/27/2019 Master Data for SCM 2

    23/63

    Order Cycle for Stock Transfers

    Three order types in SAP APO1. Planned stock transfer,

    2. Deployment confirmed stock transfer and

    3. TLB-confirmed stock transfer

    They are matched to the stock transfer requisition and thestock transfer order in SAP ERP according to the setting for

    SNP transfer (SAPAPO/SDP110).

  • 7/27/2019 Master Data for SCM 2

    24/63

    Order Flow for Stock Transfer onSAP ERP side

  • 7/27/2019 Master Data for SCM 2

    25/63

    Stock Transfer Order

    Stock transfer order is first scheduled in SAP APO, thentransferred to SAP ERP and scheduled again in SAP ERP

    according to the delivery date. The scheduled dates in SAP

    ERP are not transferred back to SAP APO.

    Stock transfers are executed according to the order dates inSAP ERP, therefore it is important to keep the scheduling in

    SAP APO and SAP ERP consistent.

    The transport duration in SAP APO is calculated using the

    entry from the transportation lane, whereas SAP ERP uses

    the planned delivery time of the material master of the target

    location.

  • 7/27/2019 Master Data for SCM 2

    26/63

    Stock Transfer Scheduling

    for transportation

    for transportation

  • 7/27/2019 Master Data for SCM 2

    27/63

    Setting for Stock Transfer within andacross Company Codes in SAP ERP

    Since SAP APO does not know any company codes, there isno difference in SAP APO whether stock transfers are planned

    within one company code or across company codes. On SAP

    ERP side, cross company stock transfers require the

    additional settings. The assignment of the sales area and the

    customer to the plant is made with maintenance viewV_001W_IV.

  • 7/27/2019 Master Data for SCM 2

    28/63

    Setting for Stock Transfer within andacross Company Codes in SAP ERP

  • 7/27/2019 Master Data for SCM 2

    29/63

    Setting for Stock Transfer AcrossSystems

    Stock transfer across two SAP ERP systems is modelled by a

    purchase order in the target plant and a sales order in the

    source plant.

    Setting for Stock Transfer Across

  • 7/27/2019 Master Data for SCM 2

    30/63

    Setting for Stock Transfer AcrossSystems

  • 7/27/2019 Master Data for SCM 2

    31/63

    SCM Master Data - 2

    Master Data for Production

    Planning Process

    EGN 5623 Enterprise Systems Optimization(Professional MSEM)

    Fall, 2011

  • 7/27/2019 Master Data for SCM 2

    32/63

    Production Master Data OverviewThe relevant master data for production planning:

    LocationProduct

    Resources

    PPM and PDS

    Quota arrangement,

    Set up Group & matrix, andInterchangeability group.

    Note on resources:SNP and PP/DS require a different view of the capacity.

    SNP in bucketsPP/DS time-continuous capacity

  • 7/27/2019 Master Data for SCM 2

    33/63

    Resources for SNPThe idea of SNP is to perform an aggregated planning.

    Since SNP is an application for bucket-oriented planning,the resources for SNP offer a certain capacity per time

    bucket usually per day. The bucket resources provide

    the capacity e.g. the amount of working hours per day

    of the resource which is used for the capacity

    consumption of the orders.

    For the scheduling of the production orders, the factory

    calendar is assigned to the resources. The standard

    capacity is defined in the resource master.

    Figure 13.13 shows these setting for the bucket

    resource. Another way to define the capacity is the use of

    a reference resource to save time.

  • 7/27/2019 Master Data for SCM 2

    34/63

    Settings for a Bucket Resource

  • 7/27/2019 Master Data for SCM 2

    35/63

    Resources for PP/DSIn PP/DS, scheduling and capacity consumption are not

    separate steps, but the capacity is consumed by thescheduled operation.

    The basic resource property in PP/DS is the working

    time, which depends on the standard working hours, the

    break time, and factory calendar.

    Usually the available working time is modelled per shift,

    and the shifts are assigned to a shift sequence to model

    circumstances.

  • 7/27/2019 Master Data for SCM 2

    36/63

    Settings for PP/DS (single Resource)

  • 7/27/2019 Master Data for SCM 2

    37/63

    Production Master Data OverviewPPM

    The Production Process Model (PPM) defines thedetailed information required for manufacturing a

    product. The PPM combines routing and the bill of

    materials (BOM) into one master data object. Each PPM

    includes one or more operations. Each operation, inturn, includes one or more activities, for which materials,

    relationships and resources are maintained. The

    activities and resources defined in the PPM are assigned

    to costs that are used by the SNP Optimizer and for finite

    scheduling by Production Planning and DetailedScheduling (PP/DS).

  • 7/27/2019 Master Data for SCM 2

    38/63

    Production Master Data Overview

    Supply Network Planning (SNP) is a long term, rough cut planning tool.

    SNP requires a PPM with less information than the one used forproduction planning and detailed scheduling (PP/DS).

    During a planning run, SNP can schedule resources down to the day. In

    order to perform scheduling at the day level, the PPMs and resources

    must be simplified. Additionally, when using optimization technologies, itis important to limit the number of inputs (materials) to find a proper

    solution in a reasonable runtime.

    Restriction to a specific lot size is required to determine the exact

    production consumption or mode duration.SAP SCM allows you to generate SNP production process models

    (PPMs) based on existing PP/DS PPMs.

  • 7/27/2019 Master Data for SCM 2

    39/63

    Production Master Data Overview

    PDS (production data structure)SAP initially developed the Production Process Model

    (PPM) to model manufacturing master data. It was

    replaced in SCM 4.1 by PDS. However PPMs are still

    supported.

    In some industries modeling the production and evolution

    of a certain product can be very complicated. When a

    product has many variations due to customers choosing

    a combination of features and options they typically usedthe variant configuration solution in standard SAP ERP.

  • 7/27/2019 Master Data for SCM 2

    40/63

    Production Master Data OverviewFrom SCM 4.1 on, the Production Data Structure (PDS)

    is the key master data for all kinds of production planningrelated processes. The PDS is supported by the

    applications of PP/DS, SNP, CTM and DP.

    Like the PPM, the PDS corresponds to the production

    version on SAP ERP system. Though both PPM and

    PDS are still available as alternatives, there is no further

    development for the PPM since SCM 4.0.

    The main motivation to develop the PDS was to have anintegration of the Engineering Change Management

    (ECM) and the Variant Configuration between SAP ERP

    and APO.

  • 7/27/2019 Master Data for SCM 2

    41/63

    Structure of PDS and PPM

  • 7/27/2019 Master Data for SCM 2

    42/63

    Transfer of PPM and PDS

  • 7/27/2019 Master Data for SCM 2

    43/63

    Production Process Overview

    Production Planning consists mainly ofcreation of plannedorder, purchase requisition for the demand, the detailed

    scheduling to create a sequence for the orders which is

    sufficiently capacity-feasible (usually in the short-term) and

    execution of the production order. In many cases it is desired

    to have at least a rough feasibility check of the production plan

    in the mid-term as well.

    The detailed scheduling is usually only performed for the short

    term horizon.

    Traditionally both production planning and scheduling are

    limited to the plant level.

  • 7/27/2019 Master Data for SCM 2

    44/63

    Production Process Overview

    If a supply chain contains alternative production plans(possibilities), the process becomes more complex. It often

    requires an integrated distribution and production planning.

    Depending on the business requirements it might be

    favourable to create a rough-cut production plan for the mid-

    term or even long-term before the more detailed production

    plan. The approach represents the idea of a hierarchical

    planning, i.e. to plan with less detail for the farther future and

    has the benefits of avoiding unnecessary information andunnecessary system load and to have a tighter integration

    with the distribution planning.

    Process Chain for a Make to Stock

  • 7/27/2019 Master Data for SCM 2

    45/63

    Process Chain for a Make-to StockProduction

  • 7/27/2019 Master Data for SCM 2

    46/63

    Production Process Overview

    Objectives for Production Planning: to meet the demand

    to consider the resource capacities and the

    material availabilities

    to improve utilisation of the resources to low set up time

    to minimise the stock, and

    to minimise the work in process (WIP)

    to improve stability of the plan

  • 7/27/2019 Master Data for SCM 2

    47/63

    Production Process Overview

    1. Generally the complexity of a production planning taskincreases with the number of BOM-levels, number of

    operations, and finite resources, the use of fixed, or

    minimized lot sizes and sequence dependent set-up.

    2. Though APS (Advanced planning and Scheduling)

    systems allow theoreticallya one-step approach,

    experience shows it is better and more reliable to keep the

    constraints as less as possible in modeling and to use a

    two step approach to create a feasible plan, i.e. infiniteproduction planning first and finite scheduling on the key

    resources later.

  • 7/27/2019 Master Data for SCM 2

    48/63

    Order Cycle for Production

  • 7/27/2019 Master Data for SCM 2

    49/63

    Order Cycle for Production

    The result of production planning are planned orders whichcontain the information about the dependent demand and the

    capacity requirement in SAP APO.

    The production orders are reduced by the order confirmation

    and remain in SAP APO until it is technically completed.

  • 7/27/2019 Master Data for SCM 2

    50/63

    Production Planning Applications

    SAP APO offers different applications for production planningand detailed scheduling. Production planning is supported by

    the modules SNP and PP/DS with two different levels of

    details.

    - rough-cut and bucket-oriented planning (SNP), and

    - time-continuous planning (PP/DS).

    Detailed scheduling with the purpose of creating a sequence

    for order execution is only supported by PP/DS since SNP is

    limited to bucket-oriented planning and there is no sequencewithin a bucket.

    Applications for Production

  • 7/27/2019 Master Data for SCM 2

    51/63

    Applications for ProductionPlanning and Scheduling

  • 7/27/2019 Master Data for SCM 2

    52/63

    Production Planning ApplicationsBased on the variety of the applications there are many

    options for creating a feasible plan in SAP APO. Each has itsadvantages and disadvantages.

    1. Distribution and medium-term production planning with

    SNP heuristic, the SNP optimiser or CTM with SNP

    master data, short-term production planning by

    conversion of SNP orders to PP/DS orders anddetailed scheduling with the DS heuristics or PP/DS

    optimiser.

    2. Distribution planning with SNP heuristic, medium-term

    production planning with SNP optimiser, short-term

    production planning by conversion of SNP orders toPP/DS orders and detailed scheduling with DS

    heuristic or PP/DS optimiser.

  • 7/27/2019 Master Data for SCM 2

    53/63

    Production Planning Applications3. Production planning for medium-term and short-term

    horizon with higher level of detail in PP/DS using PPheuristics or TM and detailed scheduling with DS heuristic

    or PP/DS optimiser.

    4. Demand planning in SAP ERP especially when there is

    already a sufficient solution using SOP or long-term

    planning. Production planning is performed with PPheuristics, scheduling with DS heuristics or PP/DS

    optimiser.

    5. Demand planning and production in SAP ERP SAP APO

    is used only for scheduling.

  • 7/27/2019 Master Data for SCM 2

    54/63

    Production Planning Applications6. Only medium-term production planning on rough-cut

    level is performed in SAP APO either by SNPheuristic, SNP optimiser or CTM. The benefit is having

    a capacity check and purchase requisitions for

    components with long lead time. Planned orders are

    transferred to SAP ERP, where production planning

    and scheduling on detailed level are for the short-termhorizon.

    7. Production planning is triggered by the sales order entry

    either via CTP or multi-level ATP. Scheduling is

    performed with scheduling heuristics or PP/DS

    optimizer.

    PP/DS optimiser is used only for scheduling, not for creation

    of orders.

    Scenarios for Production Planning

  • 7/27/2019 Master Data for SCM 2

    55/63

    gusing Different Applications

  • 7/27/2019 Master Data for SCM 2

    56/63

    Lot SizeLot sizes have a significant impact on the production planning

    result and challenges for scheduling. The fixed, minimum andperiodical lot sizes in material master data increase the

    complexity of the planning problem.

  • 7/27/2019 Master Data for SCM 2

    57/63

    Lot Size Methods

  • 7/27/2019 Master Data for SCM 2

    58/63

    Lot Size

    Though CTM supports minimum and fixed lot sizes, but CTM

    performs a finite planning and does not split orders across

    buckets which might lead to a very low utilisation.

  • 7/27/2019 Master Data for SCM 2

    59/63

    SCMMaster Data - 2

    Master Data for Distribution &Production Processes

    SAP Implementation

    EGN 5623 Enterprise Systems Optimization(Professional MSEM)

    Fall, 2011

  • 7/27/2019 Master Data for SCM 2

    60/63

    PP/DS Module in SAP SCM

    Note: Strategic network design issues

    are not handled by SAP SCM

  • 7/27/2019 Master Data for SCM 2

    61/63

    Order Cycle for Stock TransfersThe outbound delivery for the stock transfer order is created

    with transaction VL10B in SAP ERP, picking and the posting of

    goods issue is done with the transaction VL02N in the

    delivery.

    Using the message type LAVA the inbound delivery in source

    location can be triggered with the posting of the goods issue(or manually with the transaction VL31N).

    For the use of deliveries it is necessary that a vendor is

    assigned to the source location and that an info record exists

    in SAP ERP.

    The inbound delivery is transferred to SAP APO as a purchase

    order memo with the significance of the stock transit.

    i

  • 7/27/2019 Master Data for SCM 2

    62/63

    Exercises:1. Module 4 (Section 2)

    Create a forecast for the finished products

    Product groupCreate product group in SAP ERP system

    Create SOP plan for product group

    Create SOP plan

    Transfer plan to demand management

    Transfer plan

    Check the transfer results in demand management

    2. Module 5 (Section 2)Generation and activation of integration models

    Integration models

    Create integration model for plants in SAP ERP system

    Activate integration model

    Confirm data transfer in SCM system

    Create integration model for DCs in SAP ERP system

    Activate integration model for DCs in SAP ERP system

    Confirm data transfer for DCs in SCM system

    E i ( ti d)

  • 7/27/2019 Master Data for SCM 2

    63/63

    Exercises (- continued):

    Create integration model for vendors in SAP ERP system

    Activate integration model for vendors in SAP ERP system

    Confirm data transfer for vendors in SCM system

    Create integration model for customers in SAP ERP system

    Activate integration model for customers in SAP ERP system

    Confirm data transfer for customers in SCM system

    Create integration model for materials at plant level in SAP ERP system

    Activate integration model for materials in SAP ERP systemConfirm data transfer in SCM system

    Create integration model for materials at DCs level in SAP ERP system

    Activate integration model for DC materials in SAP ERP system

    Confirm data transfer materials (DCs) in SCM system