master of forestry - oregon state university
TRANSCRIPT
Silvicultural Mechanical Site Preparation
by
William Wardlaw Moore
A TECHNICAL REPORT
submitted to
Department of Forest Enginee ring
School of Forestry
Oregon State University
in partial fulfillment ofthe requirements for the
degree of
Master of Forestry
Completed May 5, 1976
Commencement June 1976
APPROVED:
rofessor of Forest Engineeringa7in charge of major
tment of F4'st Engineering
Date technical report was presented May 5, 1976
Typed by Ilene Anderton for William Wardlaw Moore
AN ABSTRACT OF THE TECHNICAL REPORT OF
William Wardlaw Moore for the degree of Master of Forestry
in Forest Engineering presented on May 5, 1976
Title: SILVICULTURAL MECHANICAL SITE PREPARATION
Abstract approved:JohnE. O'Leary
The preparation of suitable sites for planting and growing of
tree seedlings following logging is recognized by British Columbia
Forest Service as a major silvicultural problem in the Central and
Northern Interior regions of the province. Over the past few
decades, scarification trials have been made with various types of
drag and blade scarifiers. Substantial areas, particularly on the dry
lodgepole pine (Pinus contorta latifolia) sites have also received
mechanical scarification on an operational scale.
The wet white spruce--alpine fir (Picea glauca ssp. glauca--
Abies lasiocarpa) sites, which often have a deep layer of undecom-
posed organic material on the forest floor, have traditionally been
winter logged. The resulting accumulation of undisturbed duff, and
logging slash, has normally been either windrow or broadcast burned.
Some recent escape fires, e. g. the Eden Fire in the Kamloops
Forest District in September 1973, caused considerable personal
property damage, and have heightened interest in mechanical scarifi-
cation as an alternative to prescribed burning.
The author had occasion during the summer of 1974 to be
employed by British Columbia Forest Service on a research project
in the Prince George area entitled, Silvicultural Mechanical Site
Preparation (S. M.S. P.). The purpose of this study was to measure
and evaluate the performance of selected mechanical scarifiers, in
producing an economically, and silviculturally acceptable level of
planting site preparation.
This report examines the findings of the S.M.S. P. project,
and where appropriate, compares them with earlier Canadian forest
scarification studies. Recommendations for the use of specific
mechanical site preparation equipment are viewed both singly, and
in combination with other forest management practices.
ACKNOWLEDGMENTS
I would like to acknowledge the help of many people during the
field work, research, and preparation of this report.
To Ed Nelitz of British Columbia Forest Service, and Bob
McMinn of Environment Canada, with whom I had the pleasure of
"bushwhacking" and exchanging ideas, a very special thank you.
My thanks are also extended to Ken Apt, Peter Castley, Robin
Brown and others of B. C. Forest Service, who supplied data and
information.
For the guidance and assistance provided by faculty at Oregon
State University, particularly Hank Froehlich, Ed Aulerich, Mike
Newton, Chet Youngberg and my advisor John O'Leary, my sincere
appreciation.
LIST OF FIGURES
Figure Page
Winter cut-over on Naver Creek Road. 3
Teapot Lake cut-over in Big Valley Forest. 3
Drag scarifier used on Lodgepole pine flats. 7
Slashburn htescap&T at Mile 19 on the BowronRiver Forest Road. 7
Competitive vegetation: black twinberry, firewood,cow parsnip at Kenneth Creek Block. 14
Re-establishment of vegetation one month followingblading at Kenneth Creek. 14
Bateman Road Block. T. S. H. L. A04098, C. P."A", Unit 7. 16
Swampy section in Bateman Road Block. 16
Trakmac crossing swamp between drumlinridges in Vama Vama Creek Block. 18
C. P. 223, Unit 1A at Mile 19 on Tumuch SouthRoad. 18
Site Assessment crew taking slash measurementsat Bateman Road Block. 22
Washington Iron Works, model TM 72 Trakmac inKenneth Creek Block. 31
Trakmac planting spots at Kenneth Creek. 31
Beales brush blade mounted on Caterpillar D7ETractor. 34
Figure Page
Brush bladed planter access road at Kenneth CreekBlock. 34
V-plow moving heavy logging slash in KennethCreek Block. 37
V-plow planting spots at Kenneth Creek. 37
Sharkfin drag scarifier at Kenneth Creek. 40
Sharkfin planting spots and planter access trailat Kenneth Creek. 40
20, Finnish T. T. 5. model 35 Disc Trencher. 43
Disc Trencher at Kenneth Creek Block. 43
Swedish Bracke.Cultivator in Bateman Road Block. 47
Bracke Cultivator planting spots and planteraccess trail at Kenneth Creek. 47
Rubber-tired skidder trail in salvage cutover atVama Vama Creek. August 1974. 64
Skidder tracks in Bateman Road Block. 64
Morbark Chiparvestor on Northwood logging showat Vama Vama Creek. 66
Logging residue at Tumuch Lake. 66
TABLE OF CONTENTS
Chapter Page
INTRODUCTION
OBJECTIVES 9
STUDY DESCIUPTION 11Treatment Areas 11Testing Procedure 20Equipment Trials 23
SUMMARY OF RESULTS 48Prime Movers 48Self-Propelled Scarifiers 51Site Preparation Attachments 52Work Specification Comparison 54Site and Planting Productivity Rating 58Planting Trials 59
HYDROLOGIC IMPLICATIONS 61Vegetation and Litter Removal 61Mechanical Equipment Passage 62Topography 63
ALTERNATIVE MANAGEMENT PRACTICES 65Residue Logging 65Slashburning 67Chemical Treatment 67
CONCLUSIONS AND RECOMMENDATIONS 69Prescarification 69Logging 69Site Preparation 70Cost Benefit Consideration 71
BIBLIOGRAPHY 72
APPENDIX A - Maps 74APPENDIX B - Production Tables 84APPENDIX C - Forms 92
LIST OF TABLES
Table Page
1,, HD 16 Backhoe Production and Cost Data. 29
TM-72 Production and Cost Data. 32
Brush Blade Production and Cost Data. 35
V-Plow Production and Cost Data. 36
Sharkfin Production and Cost Data. 41
Finnish Disc Trencher Production and Cost Data. 44
Swedish Bracke Cultivator-Production and Cost Data. 46
Machine Production in Minutes Per Acre Treated. 56
Anticipated Planting Production. 58
SILVICULTURAL MECHANICAL SITE PREPARATION
I. INTRODUCTION
At the "big bendtT, near Prince Goerge in central British
Columbia, the silty glacial-fed Fraser River leaves its northerly
route through the narrow Rocky Mountain Trench, to plunge south-
ward to the Pacific Ocean. The broadened "trench", a rolling,
glacial and fluvial-incised plateau extends north-westerly through
the headwater drainage of the Peace River. This waterway in turn
cuts through the Rocky Mountains to join the Slave and Mackenzie
Rivers in their northward flow to the Arctic Ocean (Appendix A).
To the north lies the boreal forest which extends eastward
across Canada. To the south, the wet interior cedar- -hemlock
(Thuja plicata_ -Tsuga heterophylla) forest type reaches the limits
of its interior range, as does the dry Douglas-fir- -lodgepole pine
(Pseudotsuga menziesii--Pinus contorta latifolia) type of the Cariboo
region.
The vast area lying between these extremes is covered with a
sub-alpine forest comprised mainly of white spruce (Picea glauca
ssp. glauca) and alpine fir (Abies lasiocarpa) on the wetter lowland
sites, and lodgepole pine (Pinus contorta .latifolia) on the drier ridge
sites. The encompassing Prince George Forest District harvests
annually, by clear cut logging of 100, 000 acres (40,470 hectares),
2
in excess of 400MM cubic feet (11,327,400 meters3), of the prov-
ince's total annual cut of some 2,000 MM cubic feet (56, 637,000 m3)
of timber. Over half of this volume is white spruce (Picea glauca
ssp. glauca), the majority of which is logged during the winter
months, when the frozen snow-covered ground facilitates access and
log transport. It has been estimated (Appendix II) that 60 percent of
the logged area requires site preparation; 79 percent of this by
mechanical scarification, and 21 percent by prescribed burning
(Figure 1).
The variable local climates can be generalized for this region
as: rainfall, 20 to 36 inches (51 to 91 cm.); average monthly temper-0 0 0 0 0 0atures: July, 58 to 60 F. (14 to 16 C.), January, 5 to 14 F.
(-15° to _10 C.) with extremes of -59° to 102° F. (-51° to 390 C.);
frost-free period is 50 to 100 days.
The white spruce- -alpine fir (Picea glauca ssp. glauca- -Abies
lasiocarpa) forest types which predominate here are generally over-
mature, and occur in the heavier precipitation zones. Wood fibre
productivity on five different site types ranges from 8, 000 cubic
feet per acre (226 M3), down to 4,000 cubic feet per acre (113 M3);
with average corresponding heights of dominant spruce from 130 feet
(40 M) to 95 feet (29 M), and co-dominant alpine fire from 108 feet
(33 M) to 81 feet (25 M), as reported by Illingworth and Arlidge (6).
These conditions often result in a deep organic or duff layer,
Figure 1. Winter cut-over on Naver Creek Road.
Figure 2. Teapot Lake cut-over in Big Valley Forest.
3
4
with a thick ground cover of shrub species, particularly the site type
indicator devil's club (Oplopanax horridus), and black twinberry
(Lonicera involucrata). Because of stand overmaturity, windfalls,
rotten wood, and snags are common. Soil types are generally
moderately-well to imperfectly drained, and heavy textured. Springs,
swamps, and perched water tables are typically dispersed through-
out the region, and account for the high proportions of winter logging.
The aforementioned situation creates moderate to heavy concentra-
tions of cull logs, slash, and undisturbed duff following logging
(Figure 2) particularly in valley bottoms. The resulting ground condi-
tions are considered by B. C. Forest Service to constitute a serious
fire hazard, as well as a significant impedance to the progress and
success of subsequent reforestation operations.
As reported by Rieche (14), scarification for the amelioration
of seed bed conditions was attempted in British Columbia as early as
1929. However, it was not until 1956 that the first formal mechan-
ical scarification program was initiated by Decie and Fraser (3).
These trials, which extended through 1959, were conducted on
twenty-five timber sales, and covered some 2, 000 acres (809 ha.)
in the Prince George Forest District. The ultimate aim was to
provide a seed bed suitable for natural regeneration through
scarification, either prior to, or following logging (Figure 3).
Further detailed work studies in 1960 and 1961 assessed influencing
5
physical factors such as soil condition, topography, and slash; and
grouped mechanical equipment by performance ratings (15).
During the period from 1950 to 1956, mechanical scarification
trials were also conducted in Alberta (2), and northwestern Ontario
(5), on ground and stand conditions somewhat similar to those
covered in this report. Results of these antecedent forest soil
scarification projects will be referred to where appropriate herein.
The establishment in the sixties of three large pulp mills at
Prince George converted the local economy from sawmilling to an
integrated forest products orientation. Subsequently, in the result-
ing large clearcut areas, many extending over hundreds of acres,
it soon became apparent that planting of tree seedlings was a silvi--
cultural necessity.
A greatly accelerated Forest District planting program was
up fromfive million seedlings in 1973, to nine million in 1974, with
further increases to twelve million in 1975, and a forecasted sixteen
million seedlings in 1976. This fact, which can only magnify an
already critical manpower situation, as requirements soar from
12, 000 planter days to 50, 000 planter days (13), points up the need of
improving conditions for planter access, and of assuring the success
of planted stock.
Of the 49, 430 acres (20, 004 ha.) which received site prepara-
tion treatment in 1974 in the Prince George Forest District, 18, 390
6
acres (7, 442 ha.) was broadcast burned, and 10, 342 acres (4, 185 ha.)
was windrow burned, for a total of 58 percent receiving prescribed
burning treatment (Appendix B). It was shown earlier that only 21
percent of the total area requiring site preparation should be burned.
It follows that there is considerable scope for expansion of mechan-
ical site preparation activities.
Even with the increased vigilance and precautionary measures
taken on prescribed burning, there were 36 escape fires that burned
3,075 acres (1, 244 ha.) in this Forest District in 1974 (1). The
inherent dangers of summer slash burning (Figure 4), and public
pressures aroused by smoke pollution and personal losses incurred,
indicate the desirability of investigating alternative methods such
as mechanical site preparation.
In answer to this rapidly growing need, British Columbia
Forest Service, during the summer of 1974, instituted Experimental
Project 740--Silvicultural Mechanical Site Preparation (S.M.S.P.).
The author of this report worked on the project, and during the
summer of 1975, re-visited ce.rtain of the treated areas in order to
assess the results achieved.
The following is an account of the machine trials, with related
cost and production data. Conclusive results of related seedling
growth success will not be known for a few years. However,
recommendations are made herein, on the basis of evidence
Figure 3. Drag scarifier used on Lodgepole pine flats.
I
Figure 4. Slashburn tiescapel? at Mile 19 on the Bowron RiverForest Road.
7
obtained during S. M. S. P., during previous studies of a similar
nature, and alternatively or in conjunction with other management
practices which are currently being tested, and which indicate
promising results.
II. OBJECTIVES
The aim of the Silvicultural Mechanical Site Preparation pro-
ject has been to examine available site preparation equipment to
select the more promising machinery for field trials, and to
assess their performance in obtaining a given standard of work, at
an acceptable cost level, under varying site conditions.
The following S.M.S. P. standards were established:
Trafficability
A general improvement of site conditions should beachieved which will allow unimpeded planter movementbetween planting spots. T rafficability improvement shouldreduce unproductive and often arduous walking time, thusimproving working conditions, and permitting mc reasedplanter production.
Plantability
Improvement of planting spots for planting should beaccomplished by disturbing, mixing or breaking up theduff-grass-litter layer, and by eliminating upper rootsof competing vegetation. Plantability improvementshould also stimulate growth, and increase survival rateof planted seedlings.
Spacing
Resulting planting spot distribution of not less than 450spots per acre (0.4 ha.) should be attained with generallyan 8 foot by 8 foot (2. 5 m. by 2. 5 m.) spacing.
Fire Risk
Fire hazard abatement should result from the elimina-tion and rearrangement of logging slash fuel.
E. Environment
Environmental impact should be minimized by elimina-tion of surface scalping, downhill ditching, and othererodible and undesirable site conditions.
10
III. STUDY DESCRIPTION
Treatment Areas
11
In June of 1974, B. C. Forest Service operational and support
personnel made an inspection tour of cut-over areas in the Naver,
Big Valley, and Purden Forests, to the south and east of Prince
George (Appendix A).
The following is a description of the areas selected for
scarification trials, in the order in which treatment was initiated.
The sequence and success of operations was unavoidably modified by
local site, weather, and machine supply constraints. Heavy rains
in July drenched low-lying areas, and washed out an access road
bridge crossing. Completion of a wood residue chipping operation
signalled the start-up for scarification in another area; while machine
availability from suppliers, dictated timing, location, and duration
of certain of the machine trials.
Despite the above obstacles to a complete and systematic
analysis of all systems, the trials generally proceeded toward
increasingly difficult operation conditibns. Thus the range of machine
capabilities was evaluated on the basis of recorded data, and visual
observations, as well as by judgement of optimum performance
limits, based on trials where comparison was feasible.
13
divided almost evenly between Class 1, or up to 2,500 eubic feet
peracre (29 m3/ha), and Class 2, between 2,500 and 5,000 cubic
feet per acre (29 to 58 m3/ha.). The above condition slowed machine
progress during trials, and also contributed to hang-ups, upsetting,
and equipment breakage. The major portion of the machine trials
were carried out in Block A.
Annual plants had become re-established within a month of
treatment in August 1974 (Figure 6). A heavy ground cover over-
shadowed many of the white spruce (Picea glauca ssp. glauca) seed-
lings planted in June 1975, when the area was re-visited in August
of that year. However, growth of the seedlings appeared vigorous
despite the abundance .of competitive vegetation.
Bateman Road- -Block 2 (Appendix A, Figure 7)
This was a 306 acre (124 ha.) clear-cutblock, logged in 1972-
73 and located at Mile 26 on the Bateman Road, three miles (4. 8 km.)
south of the Highway 16 crossing of the Bowron River. It comprised
Unit seven, of Cutting Permit "A", in Timber Sale Harvesting
License A04098. The area, lying between 2,600 feet (800 m.) and
3, 100 feet (945 m.) elevation, had a general southerly aspect, with
slopes ranging from zero to 30 percent. The drier glacial till ridges
had supported a lodgepole pine-aspen (Pinus contorta latifolia-
Populus tremuloides) stand. Very sparse ground vegetation,
light logging slash, and thin duff were present in these conditions.
Between the ridges in the wet spruce-alpine fir-cottonwood (Picea
glauca ssp. glauca-Abie s lasiocarpa-Populus trichocarpa) types,
heavy slash and deep organic matter were encountered. These
wet areas delayed treatment, and even during the dry period in
August 1974 they were subject to deep rutting by crawler tractors
pulling scarifiers, as the ground surface had been during logging by
rubber-tired skidders (Figure 8).
Vama Vama Creek-Block C (Appendix A)
This was a generally flat to rolling 220 acre (89 ha.) clear-cut
block located five miles (8 km.) north of Highway 16 between the
Willow and Bowron Rivers. It comprised Unit two, of Timber Sale
Harvesting License AO5 321. The dry, glacial drumlin ridges were
separated by swampy bottomlands covered by a deep organic layer.
The area was logged by a Northwood Mills Ltd. contractor during
the winter 1973-74. Considerable loss of timber in the form of
broken and buried trees resulted from heavy snowfall conditions dur-
ing logging. This situation was improved by salvage logging and
chipping of residues by the licensee with a Morbark Chiparvestor,
prior to scarification trials. The wet, heavy clay soil was subject
to deep rutting by rubber-tired skidders and crawler tractors. A
15
Figure 7. Baternan RoadBlock. T.S.H.L. A04098, C.P. !AT?,
Unit 7.
Figure 8. Swampy section in Bateman Road Block.
16
notable exception was the low ground pressure Trakmac, the only
machine used for site preparation on this area (Figure 9).
Tumuch Lake-Block D (Appendix A)
This 320 acre (130 ha.) clear-cut block, constituting Unit 20,
Cutting Permit 221, in Timber Sale Harvesting License A01846 was
located at mile 18 on the South Tumuch Road. It was a generally flat
area, with several swampy sections in the central and northern
portions, and a 20 to 30 percent slope along the south-eastern timber
boundary. Five seed blocks, each some three to four acres (1.2 to
1. 6 ha.) in size had been severely windthrown, and consequently
were salvage logged during the summer of 1974. The block was
operationally scarified during September and October 1974, with
only one acre (0.4 ha.) treated for Experimental Project 741.
Consequently, as no time studies were made on Block D, it is
only considered in this report because of its inclusion in the overall
project.
Tumuch Lake-Block E(Appendix A)
This area was located at Mile 19 on the Tumuch South Road.
The 273 acre (110 ha.) flat to rolling clear-cut block, comprising
Unit 1A of Cutting Permit 223, in T. S. H. L. A01846, had been winter
logged in 1973-74. Stumps and heavy slash (Figure 10) were
17
Figure 9. Trakmac crossing swamp between drumlin ridgesin Vama Vama Creek Block.
Figure 10. C. P. 223, Unit 1A at Mile 19 on Tumuch SouthRoad.
.
I
18
19
the result of deep snowfall conditions during harvesting.
This area was deleted from the scarification trials in order
to avoid excessive machinery breakage. Subsequently, Block E was
salvage logged, and broadcast burned. For this reason it is not
included in the appendices.
Tumuch Lake-Block F (Appendix A)
This was a 246 acre (140 ha.) clear-cut block. Comprising
Unit 14 of Cutting Permit 221, in T.S.H.L. A01846, it had been
winter logged in 1972-73. The six seedblocks left on this area had
not produced a significant level of natural regeneration. They had
suffered the same wind damage effects as those in Block D above,
and were therefore salvage logged during the summer of 1974.
Limited machine trials were carried out in this area, with the major
portion of the block being operationally scarified by brush blade
Hungary Creek West-Block G (Appendix A)
Located just north of Yellowhead Highway 16, the Hungary
Creek area was selected, along with Block A above, for limited
winter trials of the HD-16 backhoe. The results obtained in this
block, in December 1974, serve to illustrate the impracticality of
forest soil scarification in two to three feet (one meter) depth of
snow (Appendix B).
Testing Procedure
Block Subdivision
Each "block" was subdivided into "test areasit of approximately
30 to 40 acres (12 to 16 ha.) in size. The boundaries of these test
areas were roads, creeks, ridgelines, swamps and timber boundaries.
One small test area of about five acres (2 ha.) was reserved within
each block for control purposes, and received no site preparation
treatment (Appendix A).
Each "test area!? was subdivided into iwork sections?! of between
one and five acres (0.4 and 2. 0 ha.). These were usually marked at
the corners with plastic flagging tape. They were homogeneous as
to slash intensity, degree of slope, and soil type. On flat ground,
work sections were usually established 150 to 200 feet (45 to 50 m.)
wide, by 600 to 1,000 feet (180 to 400 m.) long, as most site
preparation machines worked more efficiently in long strips which
minimized turning time (see Appendix A, Figure A. 3, illustrating
research design).
Site Assessment
A site assessment plot was randomly located in each "work
section", and measurements were taken prior to site preparation
treatment. Data recorded on the Forest Site Assessment Sheet
20
(Appendix C) included measurements of slash, stumps, residual
trees, soil type, slope, aspect, etc. (Figure 11).
Work Studies
During scarification of each work section, either a) motion
economy study, or b) time study was carried out.
Motion economy was continuous timing to minute accuracy,
used while familiarizing operators with new equipment,
alternative work patterns etc. , to establish an efficiency
factor.
Time study was continuous timing with stopwatch of
components of the work cycle, e.g., working, backing up,
hang-up of equipment, turning around, etc. Work Study
Data Sheet was used for recording purposes (Appendix C).
Area Survey
Following scarification, a staff compass and tape survey was
run of the perimeter of each work section. The traverse was plotted
and planimetered to determine the area of treatment.
Photography
Aerial high level control photography for mapping purposes
was made of each block, before and after equipment trials. In
21
23
addition, low level photography, using a helicopter and 70 mm
double cameras, was made for photoanalysis of logging slash condi-
tions. Typical "before and after" results can be seen in Appendix A.
Experimental Project (E. P.) 741
Within each of Experimental Project 740 Blocks A, B and D, a
typical test area was subdivided into work sections, and treated by
all scarifiers as they became available. These areas were planted
in June 1975 as part of a joint study project with the Canadian Forestry
Service. Planting trials a.re reported on page 59. Subsequent growth
studies will determine the biological effectiveness of the various
site preparation treatments. This was a separate program from the
Silvicultural Mechanical Site Preparation (E. p. 740) project.
Equipment Trials
Testing of equipment was mainly carried out from early July
until late August, with a few trials proceeding in the Fall, and final
testing in December 1974. Scarification was done as the attachments
became available from the various suppliers. Large operational
areas were scarified by brush blade when inclement weather, machine
breakdown or modification of attachments, forced curtailment of
production studies. The equipment was either owned by B. C. Forest
Service, or on rental, or loan from private operators.
24
Availability figures reflect paid machine time on the operation,
including unavoidable delays such as machine movement, adjustments,
human delays, etc. Efficiency figures represent the percentage of
available time that individual machines and attachments were actually
working.
Machine Specifications, Comparisons andPerformance
Prime Movers (crawler)
Caterpillar D7E Tractor. For the majority of the scarification
trials, two model 48A tractors driven by Prince George owner-
operators served to power, and move the push, drag, or tow-type
scarifiers. Although rubber-tired skidders are often used for this
purpose, the generally heavy slash and wimdfall conditions experi-
enced in these trials required a slow-moving (0 to 2. 2 miles per
hour in first gear), powerful (180 H. P. ) crawler machine, with
reasonable ground clearance of 15 inches (38 cm. ).
The major disadvantages of this type of machine as a power
source are::
slow travel speed of six m. p. h.(l0km./ha.)ivhile moving
on roads between test areas,
relatively high ground pressure of 10 p. s. i. (0.7 kg. 1cm.2)
on 22 inch (56 cm. ) tracks, which may cause undesirable
25
compaction on some planting sites, as a result of its
23 ton (20,866 kg.) weight.
The 1962 tractor, equipped with 22 inch (56 cm.) width track
shoes, appeared more productive than the 1966 machine equipped
with 24 inch (61 cm.) tracks. As the machines never operated side
by side in identical conditions during the trials, the apparent dif-
ference in productivity is attributed to individual operator experience,
with some slight advantage in maneuverability between stumps with
the narrower tracks. Both machines were equipped with Hyster
winches, which occasionally were used to extricate the tractors from
mudholes, or as a more convenient attachment point than the low-
slung drawbar height of 18 inches (46 cm.).
During the 1956 to 1959 scarification trials in the Prince
George Forest District, Decie and Fraser (3) reported on a compara-
tive study made on one timber sale area between three tractor sizes.
The distribution of desirable seedbeds, as measured by the propor-
tion of milacre (2m2) plots bearing one square foot (900 cm) of
mineral soil was higher (85%) for the Caterpillar P7, than for either
the smaller International TD9 (75%) or the TD6 (70%). Despite
reasonable uniformity of stand and ground conditions, and regardless
of machine size, scarification time remained constant at 1. 5 hours
per acre. Costs, therefore, were appreciably lower per seedbed
for those prepared by the smallest tractor- -6. 2 seedbeds per dollar
26
expended, versus 3. 8 seedbeds per dollar expended by the largest
tractor.
Users, faced with a choice of tractor size are recommended to
consider:
Stump density- -heavy density will favour small tractorblade width.
Degree of slash and windfall--heavy density will favourlarge tractors.
Operator--discomfort and slowing action of jolting andpitching over even light slash is experienced with smalltractors.
Wet ground--long tracks are more suitable as they donot become mired as shorter tracks, which tend to digin.
Break-down time--less with larger tractors.
Cost- -generally much lower with smaller machines.
Horsepower--except in heavy slash, horsepower is nota limiting factor.
Considered most critical, were items three and four above,
A cautionary note is added to use only tractors in good mechanical
condition, particularly with regards to the tracks which are con-
stantly turning and workizg at changing angles. This latter observa-
tion was substantiated during E. p. 74Q An old model crawler
tractor on operational scarification in the Kenneth Creek block,
spent most of the summer broken down.
FM.C. Model 200 CA (choker arch). This 197 flywheel
27
horsepower, power shift tracked skidder was rented from Cypress
Equipment Co. Ltd. in Prince George. It was used during limited
trials in Blocks B and F, as a towing unit for the Sharkfin and Bracke
Cultivator. The unit is equipped with an hydraulic-tilt apron-arch,
winch, hydraulic bulldozer blade, and enclosed operator's cab. Its
weight of 13 tons(ll,794 kg.) provides a low ground pressure of 5.1
p. s. i. (0. 4 kg. /cm. 2) on its 22 inch (56 cm.) tracks (unloaded). It
has an excellent ground clearance of 19 inches (48 cm.) for its solid
plate underchassis.
Mounted on torsion-bar sprung rubber cushioned steel wheels,
the F.M. C, can attain speeds from 0 to 15 m. p. h. (0-24 km. Ihr.)
in forvard and reverse drive. Traction and maneuverability, under
variable ground conditions, are maintained by tilting the loaded arch
forward onto the machine deck, thus increasing the track to ground
pressure.
Although tested for only a brief period, the machine appeared
well adapted to wet spruce-balsam conditions. Longitudinal rocking
occurred as a result of loading of the apron-arch by the scarification
attachment. To alleviate this situation, it is recommended that the
winch line be re-positioned to run through a fair lead to an under-
wrap winch mounted below the deck.
Since the S. M. S. P. trials, it is understood that the F.M. C.
skidder has undergone extensive strengthening modifications,
particularly to its tracks and undercarriage.
Self-Propelled Site Preparation Machines
Two machines in this category were used during the S. M. S. P,,
program. They consisted of attachments suitable for site prepara-
tion, mounted on multi-purpose tracked prime movers.
Allis Chalmers HD 16 Tractor-John Deere 410 Backhoe. This
unit, similar to that of the U. S. Forest Service in Montana, con-
sisted of a hydraulic backhoe, with the operatort s canopy and tilting
deck mounted in-line behind the tractor fuel tank, on a power take-
off bracket.
The operation of the ackhoe required full throttle operation
of the tractor, causing it to travel too rapidly. This created a
rough ride for the backhoe operator, and uneven spacing of planting
spots which were tscreefedt? with the backhoe bucket.
This was the only unit operated under both summer and winter
conditions. The wide seasonal difference in production and cost
figures is reflected in the following data (Table 1), a result of the
three feet of snow which obscured stumps and other obstacles,
causing numerous hang-ups.
This Forest Service-owned tractor was a 185 horsepower,
power shift Allis Chalmers HD-16, equipped with hydraulic-tilt,
28
angle bulldozer blade, and auxiliary hydraulic pump to serve the
backhoe attachment. Total weight, including backhoe, was 25 tons
(22, 680 kg.), which created a ground pressure of 12 p.s. i. (0. 8
kg. /cm. 2) on the 22 inch (56 cm.) tracks. Ground clearance of this
machine was 13 inches (33 cm.). Range of travel speeds was up to
five m. p. h. (8 km. /hr.) in forward, and four m. p. h. (6 km. /hr.)
in reverse.
The model 410 John Deere had a 16 inch (41 cm.) wide backhoe
bucket, of 3. 6 cubic foot (0. 1 m. 3) capacity; it could reach 18 feet
(5. 5 m.) and was mounted on a boom with 180 degrees horizontal
swing, as well as minus 11 feet (3..4 m.), and plus 16 feet (4.9 m.)
digging depth.
Table 1. ED 16 Backhoe Production and Cost Data.
Cost per acre $ 32.00 $110.00
(Cost per hectare $ 12. 95 $ 44. 52)
Trakmac. The Washington Iron Works model TM-72 Trakmac
rented from Northwood Properties Ltd. , was an articulated
29
Acres treated per hour 1. 4 0. 4
(Hectares treated per hour 0. 6 0. 2)
Summer Winter
Hourly rental rate (1974) $ 45.00 $ 45.00Availability 44% 83%
Efficiency 88% 40%
30
soft-track vehicle, with independent hydrostatic drives on the front
and rear modules. Its exceptional maneuverability and low ground
pressures of 3.00 p.s. i. (0. 2 kg. 1cm. 2) on rear, and 375
(0. 3 kg. 1cm. 2) on front, enabled movement on wet, swampy sites
with minimum site impact. The hydraulic boom had a swing of eight
feet (2. 4 rn.) center to center of a 36 inch (0. 9 m.) diameter cutter,
or optional site preparation wheel. This machine had a 130 H P.
diesel engine, and shipping weight of 14,000 pounds (6350 kg)
(Figure 12).
Production rate, as might be expected, will not match that of
the larger crawler tractors in normal conditions (Table 2). How-
ever, the quality of its planter access trails, and planting spots
(Figure 13) combined with its minimal environmental impact, appear
attractive for highly productive, wet, or steep sites.
Considerable downtime occurred as a result of frequent
hydraulic failures during the initial trial period. The piston of one
of the swing cylinders dismantled. This was followed by failure of
the hydraulic hose to the replacement cylinder. Three other hoses
controlling the cutterwheel tilt, the cutter motor control valve, and
the return swing also failed; the former of these as the result of a
piece of wood jamming in the cutter-head. Hydraulic oil leakage
also occurred around the reservoir.
Early trials were made with the 36 inch (91 cm.) cutter-wheel
Figure 12. Washington Iron Works, model TM 72 Trakmac inKenneth Creek Block.
4--- -
-d- ' 1- -
Figure 13. Trakmac planting spots at Kenneth Creek.
31
32
which was soon replaced by the site preparation wheel. Cutting
through the duff could only be accomplished with the wheel at the high
speed setting of 640 r.pm. The straight blades of the site prepara-
tion wheel tended to centrifugally throw, rather than mix the
nutrient-rich duff with the underlying mineral soil. These blades
were soon worn round on the edges, and outer corners, and had to
be rebuilt Shrouding around the cutter-head would likely eliminate
this centrifugal waste of planting site material. Lateral tilt, and
cab-controlled speed selection of the cutter-head are other
recommended improvements
Site Preparation Attachments
Since the FMC 200 CA trials were of a very limited extent,
the comments and data below pertain to operations where the
Caterpillar D7E tractors served as prime movers for the various
scarification attachments.
Table 2. TM-72 Production and Cost Data.
Rental rate per hour (1974) $24. 00
Availability 62%
Efficiency 52%
Acres treated per hour 0. 36
(Hectares treated per hour 0. 15)
Cost per acre $67.00
(Cost per hectare $27. 11)
33.
Brush Blades. Both tractors were equipped with brush blades.
These blades were 11 feet 8 inches (3. 5 m.) long, and three feet
seven inches (1. 1 m.) high. The 1962 tractor had a Beales blade
with six 18 inch (46 cm.) long shanks which curved forward sharply
below the moldboard, producing an under-shoe effect. The Beales
brush blade rides over obstacles easily, and is well suited for site
preparation work (Figure 14). The 1966 tractor was equipped with
a Panko blade with six 24 inch (61 cm.) 1ong shanks which are only
slightly curved forward below the moldboard. The Panko brush blaae
hooks obstacles, scalps the surface, and is better adapted to slash-
piling, and land cleaning operations. In addition to test areas
completed. by brush blade (Table 3), large tioperationalli areas were
also treated in this manner. The brush blade was also found to be
necessary for removal of heavy slash while using the tow-type
scarifiers. There is considerable variance in brush blade design..
The "idealt' design might incorporate a slight V configuration, with
smooth moldboard for side-casting, as well as the shoe tooth
configuration to reduce root snagging. Brush blading results
generally in well cleared strips, sometimes scalped too deeply,
with large intervening windrow accumulations of slash (Figure 15).
Table 3. Brush Blade Production and Cost Data.
(combined for Beales and Panko blades)
35
Ripper V-Plow (Figure 16). This blade designed, built by, and
on loan from Northwood Pulp and Timber Ltd. in Prince George,
was of very massive construction. It was fabricated from two, four
foot (1.2 m.) by eight foot (2.4 m.) steel sheets welded into a
V-shaped frame, forming a 12 foot 8 inch (3. 9 m.) wide moldboard.
Vertical box frames, welded to either end of the V-frame, enclosed
heavy, depth adjustable, 24 inch (61 cm.) steel shanks with the bottom
hooked forward, stinger-like, to accomodate an .in -turned plowshare.
A third fixed stub-shank was located at the V apex of the blade. This
unit was designed to fit on the C frame of a Caterpillar D7E tractor
Maximum clearance under the blade at full lift was only 12 inches
(30 cm.).
Larger material was side-cast into windrows. Short logs
and chunks, however, were usually caught by the corner mounted
Rental rate per hour(including prime mover)
$29. 00
Availability 83%
Efficiency 64%
Acres treated per hour 0. 58
(Hectares treated per hour 0. 23)
Cost per acre $50. 00
(Cost per hectare $20. 24)
36
plowshares, and drawn inward under the crawler track. The result-
ing roughness made it difficult to maintain a constant working depth.
The plowshare lead also, on striking rooted obstructions, pulled the
entire machine with a twisting motion downward, and further into
the obstruction, causing the opposite corner of the blade to lift
completely clear of the ground. The resulting treatment effect was
one of alternate gouging with some good furrowing in between (Figure
17). The massive blade obstructed the operators view, and limited
the air flow to the engine causing overheating of both machine and
operator. The only mechanical failure was breakage of one plow-
share cutting edge. The following table shows production and cost
data obtained with the Northwood Ripper V-Plow.
Sharkfin Drag Scarifier (Figure 18). For application in the
S. M. S. P. trials, the sharkfin was combined with other equally
simple componejits which can be readily interchanged, and attached
Table 4. V-Plow Production and Cost Data.
Rental rate per hour (1974)(including prime mover)
$32.00
Availability 92%
Efficiency 66%
Acres treated per hour 1. 16
(Hectares treated per hour 0. 47)
Cost per acre $27.50
(Cost per hectare $11. 13)
I
Figure 16. V-plow moving heavy logging slash in KennethCreek Block.
Figure 17. V-plow planting spots at Kenneth Creek.
37
singly or in multiples to either winch line or drawbar of a suitable
prime mover.
Components by assembly sequence:
Boat: An eight foot (2. 4 m.) triangular shaped, one foot(0. 3 m.) deep steel towing yoke, designed by B. C.Forest Service. Attached to the leading apex was a sixfoot (1. 8 m.) long section of one and three quarter inch(4. 5 cm.) diameter tow chain This allowed the scarifierlateral flexibility to move around stumps, while permittingthe tractor to back up, and maneuver .around obstacles.Welded on the rear vertical plate were four equally-spaced attachment brackets.
Scarifier Chain: Two nine foot (2. 7 m.) long, or eightlink sections, of 30 pound (13.5 kg.) link, of two and onehalf inch (6. 4 cm.) diameter anchor chain. Ten inch(25 cm.) grouser bars extended laterally from each link.These cross pieces in Hteetl formation tended to align thelighter slash, while ripping into the duff.
Sharkfin: This drag scarifier was originally designed bythe Ontario Department of Lands and Forests. In itsS. M1 S. P. configuration it consisted of two drums, eachfour feet (1. 2 m.) long by two feet (0. 6 m.) diameter,and fabricated of one half inch (13 mm.) plate. Eachdrum had four rows of opposing spirally aligned cutterblades or fins, six inch (15 cm.) deep, six and one halfinch (16.5 cm.) top, and eight inch (20 cm.) bottomdimensions, on the longitudinal axis of the drums. Whentowed, the blades forced the drums to rotate slowly,shearing and mixing the soil surface layers in two shallowfurrows. Best rotation and results were achieved withthe drums each ballas ted with sixty gallons (227 liters)of water, through filling plugs in the rear of the drums.Partial water load caused the drums to ??nose in" and dragrather than rotating. Occasionally, the drums flippedover each other, on a stump, or while turning at the endof a strip.
Stabilizer Pads: Two, three foot (0. 9 m.) long sectionsof one and one half inch (3. 8 cm.) diameter chain,complete with swivels, served to attach and prevent
38
39
rotation of the last components. These consisted of two,three foot (0. 9 m.) lengths of discarded 24 inch (61 cm.)track from a Caterpillar D 8 size tractor. The latterserved to stabilize, and prevent the drums from bouncingabout, while also mixing the soil in the furrows cut bythe fins
This scarifier, while of simple design, produced a high
standard of performance (Table 5). Trafficability in the strips
'was adequate, and a consistent planting pattern was provided by the
furrows. The latter were five to six feet (1. 5 to 1.8 m.) apart,
but could be increased by use of a wide boat (Figure 19).
On sidehill operation, the drums tend to move laterally down-
hill. Results were generally better with the drag attached to the
tractor drawbar, maintaining boat and anchor chain in closer sur-
face contact. However, on soft ground, attaching the drag to the
winch line permitted the operator to tidrop?? the scarifier, move
ahead and winch in, as a skidder operator does on soft ground to
prevent bogging down. The only mechanical failure was breakage
of a tow chain link, when a sharkfin drum became wedged between
two large stumps on a turn.
=
.
Figure 18. Sharkfin drag scarifier at Kenneth Creek.
.
Figure 19, Sharkfin planting spots and planter access trailat Kenneth Creek.
40
Finnish Disc Trencher--Model TTS 35 (Figure 20). This
machine weighs 4,000 pounds(1814 kg.), is seven and one half
feet (2. 3 m.) long, ten feet (3 m.) wide. It consists of a V-shaped
ballast tank supported on two, three and one half foot (1. 1 m.
diameter friction motivated, toothed cutter discs.
The unit was rented from Eurocan Limited's operations
near Burns Lake, west of Prince George. It reportedly had operated
satisfactorily on site preparation in the light slash of a lodgepole
pine (Pinus contorta latifolia) cut-over. The trencher's box frame
was dented from contact with the butt plate of the rubber-tired
skidder towing nit The machine, however, is equipped with lift
hooks for the purpose of raising it with a high fairlead winch line.
This practice would prevent damage and excessive drag, while
backing up, maneuvering around stumps, turning at the end of
strips, and moving the trencher between treatment areas.
Table 5. Sharkfin Production and Cost Data.
4 1
Rental rate per hour (1974)(including prime mover)
$32.00
Availability 89%
Efficiency 78%
Acres treated per hour 1. 52
(Hectares treated per hour 0. 62)
Cost per acre $21.00
(Cost per hectare $ 8. 50)
The initial S. M. S. P. trial lasted only one hour. The ring
hitch attached to the tractor drawbar pin failed, as the trencher
rotated in the opposite direction to the tractor. This occurred
while passing around and over stumps. Replacement by a large
swivel ring proved to be an expedient but temporary improvement.
A double swivel hitch similar to a scraper hitch would have been
preferable, as excessive wear to the tractor drawbar and ring
resulted from the loose fit of the two components. During the last
trials in August 1974, the upper tongue of the tractor drawbar broke
off at the pin, due to this pounding action (Figure 21).
The trenching angle of the discs, which can be adjusted
mechanically to five different widths, was left at the second setting
in order to minimize drag, and possible damage to the machine.
The wider settings could be experimented with in lighter slash condi-
tions. The effectiveness of adding weights to create deeper furrows,
as the design permits, could also have been tested underless severe
conditions. In light slash conditions, the trencher is capable of
producing furrows to a maximum 12 inch (30 cm.) depth, 24 to 36
inch (61 to 91 cm.) width, spaced five feet (1.5 m.) apart.
Limited additional trials carried out in the fall of 1974
provided the production and cost figures shown in Table 6.
42
Figure 20. Finnish T. T. S model 35 Disc Trencher.
Figure 21. Disc Trencher at Kenneth Creek Block.
43
44
Swedish Bracke Cultivator (Figure 22). This is a sturdy pull-
type machine with a two-wheel suspension and drive "bogiet1, designed
for wheeled skidder winch line towing. The geared-down rotation of
two, four-spade mattock wheels, independently suspended and chain
driven from the bogie wheels, produced a grid-patterned, digging
and lifting scarification. This machine weighs 7300 pounds (3300 kg.).
The Swedish Bracke Cultivator was purchased by B. C. Forest
Service directly from Sweden where it is normally towed behind a
wheeler skidder. On EP 740, it was attached directly to the tractor
drawbar with a modified hitch plate. Frequent hang-ups of the
Bracke and towing tractor resulted from the low ground clearance
of 10. 5 inches (37 cm.). An early modification was the addition of
a small roller at the front end of the pole hitch, to prevent excessive
wear by the towing chain, or winch line, which subsequently replaced
it. Cross chains, and a separator bar, between the mattock wheels
Table 6. Finnish Disc Trencher Production and Cost Data.
Rental rate per hour (1974) $35.00(Including prime mover)
Availability 78%
Efficiency 72%
Acres treated per hour 1. 35
(Hectares treated per hour 0. 55)
Cost per acre $26.00
(Cost per hectare $10. 52)
45
were other modifications to facilitate road transport. Grease
nipples were added to the mattock wheel guide cylinders and pro-
vided temporary relief to lessen impact on the support pins. These
also had to be replaced with hard steel pins, supported by welded
brackets, as the ariginal pins bent during early trials.
To provide adequate ground clearance, and the recommended
pole height of 40 inches (102 cm.), a "gooseneck" hitch was fabri-
cated. However, this hitch and two drawbar pins broke during later
trials, attesting to the severe nature of site preparation work, or
perhaps, the excessive power of the towing unit. Mattock wheel
support rods bent, as trees and heavy slash fell across them, and
were replaced by wire slings which have the necessary flexibility to
escape damage.
The mattock pattern of planting spots was often interrupted,
as heavy slash interfered with the normal pattern of the four mattocks
on each wheel. The ideal pattern is a seven foot by seven foot (2. 1 m.
by w. 1 m.) spacing of holes, three to four feet (0.9 to 1.2 m.) long
and, one foot (0. 3 m.) wide, by nine to twelve inches (23 to 30 cm.)
deep (Figure 23). Production and cost data obtained with the
Bracke Cultivator are shown in Table 7.
46
Table 7. Swedish Bracke Cultivator Production and Cost Data.
Rental rate per hour (1974) $35.00(Including prime mover)
Availability 78%
Efficiency 66%
Acres treated per hour 0.81
(Hectares treated per hour 0. 33)
Cost per acre $43. 00
(Cost per hectare $17. 40)
Figure 22. Swedish Bracke Cultivatorin Bateman Road Block.
Figure 23. Bracke Cultivator planting spots and planteraccess trail at Kenneth Creek.
S
47
Caterpillar D7E
The Caterpillar D7E (180 h.p.) crawler tractor was considered
to be the optimum size for purposes of the S. M. S. P. trials. There
is now considerable evidence to indicate the need of a critical review
IV. SUMMARY OF RESULTS
Major changes to machine design, such as turbocharged engines
and planetary final drives, have taken place during the past two
decades. Nevertheless, striking similarities exist in results achieved
on mechanical forest scarification trials over this period of time.
Earlier models were less powerful, as noted below, lacking such
refinements as today's commonplace power shift transmission.
Design features of brush blades, as well as the mattock wheels of
the Bracke, and earlier Swedish cultivator, and Imsett plough (3, 5)
do bear direct comparison. Likewise the forests of northwestern
Ontario are reasonably similar to those of central and northern
British Columbia.
For purposes of comparison, results of trials as reported by
Holt, Swan and Weetman (5) in Ontario, and Decie and Fraser (3) in
the Prince George Forest District of British Columbia, are referred
to below.
Prime Movers
48
49
of prime movers. The following machine characteristics should be
examined.
Power. On a number of occasions, breakage occurred
to attachments, and even to the heavy duty tractor drawbar. This
indicates excessive power of the towing unit for this application.
Flotation. On wet sites the D7E tractor often either
bogged down, or hung up on a stump, with visible rutting of the
forest floor. While wide tracks are used on smaller tractors for
specialized operations, such as ski hill maintenance, and Arctic
transport units, their use is precluded in logged areas by the pres-
ence of track-damaging stumps, boulders, and heavy slash.
Size and Type. A comparative brush blading trial by
Decie and Fraser (3) in 1956 produced constant time-per-acre of
1.5 hours for the three tractor sizes utilized, Caterpillar D7 (115
h.p.), International T..D.9 (65 h.p.), and T. D. 6(50 h.p.).
On the 1954-55 Ontario trials, Caterpillar D4 (60 h.p.), D6
(80 h. p.), and International T. D. 14 (80 h. p.) tractors were used
as prime movers. However, the shorter tracks of the smaller
tractors often caused them to dig in on wet ground (5).
Intensity of slash, which is largely controllable by management
practices, necessarily exercises a major influence on the selection
of prime mover size and type (15). Nevertheless, the Caterpillar
D7E is considered by the writer as oversized and overpowered for
the purpose of towing site preparation attachments
FMC 200 CA
50
This tractor depends on weight-loading of the apron-arch for
optimum balance and traction. Towing capability, and machine
stability could be improved by running the winch line through a fair-
lead mounted below the deck to an under-wrap winch drum, to
minimize longitudinal rocking of the tractor.
The F.M.C. blade assembly is not strong enough for regular
blading duties, but could be strengthened for slash moving, in con-
junction with tow-type scarifiers.
Although of limited duration, S. M. S. P. trials with the F. M. C.
proved its suitability to the wet white spruce-alpine fir (Picea glauca
ssp. glauca-Abies lasiocarpa) site types. The long track, with its
low ground pressure, and torsion bar suspension create minimum
ground disturbance.
Rubber-Tired Skidders
Wheel skiddrs are used extensively in Scandinavia, and in
northwestern Ontario for the purpose of towing site preparation
attachments. They are also used in the Ootsa Lake area of British
Columbia to pull the Finnish Disc Trencher, as reported herein.
51
These applications are on generally dry site conditions.
Due to high ground pressures, with resulting environmental
impact, these machines would not be suitable as site preparation
prime movers on the wet site conditions encountered during S. M. S. P.
trials (4).
Self-Propelled Scarifiers
Allis Chalmers HD-16--John Deere 410 Backhoe
The concept of two operators attempting to perform different
functions on the same machine, while operating over rough ground
conditions is not considered practical. This was borne out during
the S.M.S.P. trials.
Trakmac
The Washington Iron Works model TM-72 Trakmac is a rela-
tively slow, costly producer of planting spots, which show no superi.-
ority to those produced by less sophisticated scarifiers. Because of
its low ground pressure, this machine operates well on very wet
sites. However, the dish-shaped planting holes, which would be
subject to flooding, are undesirable in wet locations.
Site Preparation Attachments
Brush Blades
52
The Beales brush blade, with its seven forward-curving shanks
which ride over obstacles, was better suited for site preparation
work than the Panko blade. S. M. S. P. results, however, as with the
earlier Prince George, and Ontario trials, showed brush blading to
be costlier and less effective than other scarification methods. Pro-
duction was about half that of tow-type scarifiers; with resulting
mountainous accumulations of slash and duff piled between the
scalped planter access trails. By the next rotation the otherwise flat
forest floor, which is normally ideal for mechanical harvesting, may
well have developed a gently rolling surface. This was the case with
the pit-and-mound ground relief that developed (8) in formerly wind
thrown forests of New Brunswick. Certainly, the removal of duff
from growing sites as reported earlier (3) in the Prince George area,
resulted in slower growth of tree seedlings.
Ripper V-Plow
Although it achieved reasonable operating costs, the effective
work pattern produced by the V-Plow was very sporadic. The V
configuration does have merit for incorporation in a brush blade
design, because of its sideward deflection of slash. Such a blade,
53
mounted on a suitable prime mover, could be used in conjunction
with tow-type scarifiers.
In the writer's considered opinion based on observations, the
use of a push-type ripper to produce regularly spaced planting spots
is not a practical means of forest scarification.
Sharkfin Drag Scarifier
The sharkfin achieved the lowest operating costs during the
S. M S. P. trials It produced a continuous "planting spottt in the
form of a shallow trough, thus allowing flexibility of planting site
selection. Minimal mixing action took place between the duff and
mineral soil layers. Improved configuration, e. g. three rows of
fins on the drums instead of four, might provide better mixing action.
Finnish Disc Trencher
The model T. T. S. 35 Disc Trencher, like the Rome and the
Athens disc ploughs reported in the earlier trials (3, 5), achieved
low cost performance, while producing a good.quality continuous
"planting spot11. In all of these trials, trenching was impeded by
slash not removed by the tractor blade. Soil mixing could be
improved through the addition of small floating moldboards or discs9
mounted in the rear so as to return the cutter disc excavations back
into the furrows, thus affecting a deeply cultivated windrow
Swedish Bracke Cultivator
This refined model of the earlier Swedish Cultivator, and the
imset Scarifier, did not match this latter's low cost position in its
Ontario trials (5). Nor, does production reflect that obtained in
Sweden of 2. 5 acres per hour (1. 0 ha. per hour). However, due to
its mixing action, it is reasonable to expect the same biologically
superior results with the Bracke cultivator, as were proven with
the Imset scarifier.
Tie preparation of only the necessary planting spots, thereby
eliminating unnecessary ground disturbance, is a sound concept.
Availability figures for this machine reflect excessive down-
time for towing hitch modifications. The unit is sturdy; if provided
with a suitable hitch, and the design changes already incorporated,
it should prove to be a satisfactory scarification implement.
Work Specification Comparison
From a comparison shown In Appendix B, of work done by
five scarifiers tested during July and August 1975, the following
observations and deductions have been reached.
Strip Length
Generally, long strips permit higher speeds, and greater
54.
55
production, as turn-around time is more or less constant for each
strip. A strip length of some 700 feet (215 m.) is most suitable for
machines and planters.
Strip Width
The Sharkfin achieved the most consistent spacing with an
average strip width of 17 feet (5 m.). The Bracke also attained 17
feet (5 m.) spacing with a wider range of widths, probably due to the
heavy vegetation and slash in which it operated.
The V-Plow and the Trakmac produced inconsistent strip
widths which corroborate the planters' comments on the circuitous
path of the Trakmac. This m.chine and the brush blade both prepared
strips wider than the desired eight feet (3. 4 m.) seedling spacing.
Travel Speed
The Sharkfin had the fastest travel speed, operating at over
100 feet (30 m.) per minute on some work sections. A substantial
difference in operating speed was detected between the two Caterpillar
D7E tractors. The older tractor, which attained the greater produc-
tion, was equipped with narrower tracks, and had a more experienced
operator. The V-Plow also operated at high speed, but produced a
very erratic work pattern. The 66 feet (20 m.) per minute averaged
by the Bracke cultivator was considered as a good rate of speed
Machine Minutes per Acre
V-Plow 31
Sharkfin (Operator 1) 30
Sharkfin (Operator 2) 39
Bracke 41
Brush Blade 76
Trakmac 97
56
considering the heavy brush, slash and large stump conditions on
which it operated.
The Trakmac at 21 feet (6.4 m.) per minute had the lowest
travel speed. This is understandable, as it must stop to cut planting
spots. The brush blade at 27 feet (8. 2m.) per minute was the second
slowest scarifier tested.
Turn-around time at the end of each strip is included in all
cases. However, because of the great bulk of the Sharkfin, neces-
sitating some 35 feet (11 m.) of turning radius, its turn-around time
was timed separately and found to be 0.86 minutes, and 1.31 minutes
respectively for the two tractors.
Production- -Minutes per Acre
Table 8 shows average production rates in descending order
of productivity for the work sections sampled.
Table 8. Machine Production in Minutes Per Acre Treated.
57
These figures indicate relative rates of productivity of the
machines tested. The very real difference which may occur between
operators using the same scarifier is also evident from the above
production figures. These, incidentally, correspond with other
noted production differences. They are believed to be mainly a func-
tion of degree of operator experience.
Planting Spots
Thequality of planting spots is covered elsewhere in this
report. The following then is a production study of the discrete plant-
ing spots produced by the Trakmac.
On several work sections sampled the longitudinal spacing
averaged ten feet (3 m.) centre to centre of the planting micro-sites;
lateral or cross -spacing averaged nine feet (2.7 m.).
Cycle time for the cutter head to swing and produce two micro-
sites was 40 seconds.
Work section one containing 1. 78 acres (0. 72 ha.), consisted
of five 750 foot (230 m.) long strips, and was treated in 197 minutes;
750 micro-sites were produced during this time, or just in excess
of three per minute. This production figure compares favorably
with that of the swing cycles timed above. The number of planting
spots produced per acre (0. 4 ha.) on this work section was 421.
B - Before; A - After.
The Sharkfin scarifier made the most significant improvement
in site condition and planting productivity ratings. It also more than
doubled the number of available planting spots per acre.
Site and Planting Productivity Rating
From Site Assessment measurements taken by Reforestation
Division personnel at Kenneth Creek, prior to and after site prepara-
tion, the following ratings of site condition, and planting difficulty
were determined. These were then used by the Division to establish
anticipated planting performance standards (18).
Table 9. Anticipated Planting Production.
58
SiteCondition
Rating
PlantingProduction
Rating
PlantingSpots
Per Acre
AnticipatedPlanting
ProductionPer Day
- BC ontrol 7 11 383 842-A ---BBrush Blade -A
75
1310
327427
842994
-BV-Plow -A97
1412
180355
831940
-B 11 16 181 788Sharkfin -A 5 10 373 972
-BB racke -A87
1412
300422
799886
-BT rackmac 9 14 305 799-A 5 10 310 983
59
The anticipated daily planter production for all treatments,
however, was not attained as shown in planting trials discussed in
the following section. Furthermore, the writer does not believe that
the anticipated production is attainable, under the conditions
expe rienced.
Planting Trials
From May 22 to June 9, 1975, planting trials using 2 + 0 bare-
root white spruce (Picea glauca ssp. glauca) seedings were carried
out in the test areas of Kenneth Creek Block, in an effort to evaluate
the various scarification treatments.
The stated preference of the planters was for the brush-bladed
Test Area 1, for two reasons: 1) a continuous path of mineral soil,
and 2) straight alighnment of planter access trails.
Their second choice was for Test Area 2, treated by the Bracke
Cultivator. The winter backhoe-treated Test Area 8 was not as well
prepared as Test Area 7, treated in the Fall. Both areas had some
natural regeneration, with the result that lower daily crew produc-
tion was achieved. The zig-zag pattern of the Trakmac planting
holes was criticized by the planters.
No significant correlation is feasible from the data obtained.
Time studies, of a very limited nature, showed an average of 12 to
13 seedlings planted in a five minute period, regardless of treatment,
60
and likewise on the heavily-brushed untreated control area. The
latter point is incomprehensible, and casts doubt on the veracity of
the data. Daily production for each of the planters averaged approxi-
mately 500 trees during a seven hour planting period.
During an August 1975 visit to the area, all seedlings displayed
vigorous growth despite the abundance of competitive vegetation.
A separate study will compare tree seedling growth with site prepara-
tion treatment, over a period of several years.
V. HYDROLOGIC IMPLICATIONS
No evidence of environmental impact resulting from site pre-
paration methods was present on the S. M. S. P. Blocks, up to the
most recent inspection visit in August 1975.
It is expected that any significant hydrologic event caused by
mechanical site preparation would be the result of:
Vegetation and Litter Removal
- complete removal of the slash and duff layers withthe brush blade.
Mechanical Equipment Passage
- passage of heavy tractors over exposed mineral soil.
Topography
- site preparation work perpendicular to the contourson sloping ground.
- benching on steeper slopes.
Vegetation and Litter Removal
On aspen (Populus tremuloides) sites in northern Utah, Marston
(9) found that summer storms overland flow and soil erosion were
slight where vegetation and litter covered 65 percent or more of the
soil surface. Also Lowdemilk (7), as early as 1928, studied the
effects of forest litter on run off and erosion. Beneficial effects of
litter cover were found to be due to the protection offered to soil
61
62
from the destructive action of raindrops, rather than its water-.
absorbing capacity.
The only S. M. S. P. equipment which might create these
deleterious effects was the brush blade, with its generally excessive
scalping action. Its use should be restricted to the removal of
heavier slash in preparing planter access trails by tow-type
scarifiers.
Mechanical Equipment Passage
It has been shown by Steinbrenner (17) and others, that the
use of tractors for logging creates a soil disturbance. This may take
the form of soil displacement by blading of skid trails, of deep soil
puddling (Figure 24) under saturated conditions, and compaction of
surface layers even under dry conditions. Further tests showed that
four trips with a tractor reduced macroscopic pore space by half,
and infiltration rate by over 80 percent, while dry soil conditions
prevailed. A single trip had the same adverse effects under moist
soil conditions.
The soil disturbance on skid roads reduced stocking of natural
regeneration by nearly 50 percent. Also seedlings were of poorer
quality, and showed less height growth. Site restoration was per-
formed with a Caterpillar D6 tractor equipped with a land clearing
blade containing seven 18 inch teeth, and dragging a 24 inch heavy
63
farm disc. The blade teeth broke up the compacted and puddled soil,
while the disc broke the large clods, and covered the tractor tracks.
The disc produced a well aerated mineral soil seed bed suitable for
planting.
Froehlich (4) points out that static rear-wheel ground pressures
of rubber-tired skidders of up to 28 p. s. 1., or more than double that
of crawler tractors, may be further. increased by the bouncing action
of the machine in motion (Figure 25).
Proper selection of equipment and timing of use may drastically
reducesoil disturbance and compaction.
Topography
Slope characteristics, i.e., the length and degree .of a slope,
as well as its aspect, are all significant factors, in determining the
amount of runoff and erosion. For this reason, a contour pattern
was followed on side slopes during S. M. S.. P. trials.
It is imperative that the formation of drainage channels
perpendicularto contours be avoided. The Bracke cultivator's
interrupted scarification pattern is a definite advantage, in this regard.
The sharkfin drums had a tendency to roll downhill, when operated
parallel to the contours.
The practice of benching on steeper slopes is to be avoided in site pre -
parationwork, as it isduring logging; in order to minimize Soil movement.
Figure 24 Rubber-tired skidder trail in salvage cutover atVama Vama Creek. August 1974.
I
Figure 25. Skidder tracks in Bateman Road Block.
S
.1
64
VI. ALTERNATIVE MANAGEMENT PRACTICES
This section will deal briefly with certain practices which must
be considered, either as alternatives, or as adjuncts to mechanical
site preparation, during the preparation of a sound forest management
plan. Under certain conditions, the use of one system may either
negate, or enchance the value of another management tool.
Residue Logging
During the 1974 summer season, Northwood Mills Ltd, carried
out salvage logging in areas adjacent to, or included in S. M. S. P.
trials. Residue wood materials were chipped using a Morbark
Chiparvestor (Figure 26). Loaded chip vans were hauled from land-
ings on Kenneth Creek and Vama Vama Creek to the pulpmill at
Prince George. Production of residue materials, including deciduous
trees, was in excess of 1200 cubic feet per acre (84 m3/ha.), as
reported by Northwood production personnel on the site.
A fairly recent Canadian development to inventory slash fuels
is the use of 70 mm low-level photography. Muraro (10) reports that
volumes calculated by this method are as reliable as those obtained
from ground sampling surveys. This technique was used during the
S. M. S. P. pa?oject (Appendix A), and shows promise in planning for
residue logging or site preparation activities.
Figure Z6. Morbark Chiparvestor on Northwood logging showat Vama Vama Creek.
Figure 27, Logging residue at Tumuch Lake,,
S
66
67
Increased wood fibre yield may produce the additional benefits
of slash disposal reduction measures for fire abatement, and reduc-
tion of site preparation treatment to ensure successful regeneration
(Figure 27).
Slashburnin
During the 1974 season, industry in the Prince George Forest
District broadcast and windrow burned some 20, 000 acres (8, 100 ha.),
and Forest Service an additional 1, 300 acres (525 ha.). Even with
the increased vigilance, and precautionary measure exercised on pre-
scribed burning operations, there were 36 escape fires that burned
a total of 3, 075 acres (1, 245 ha.). Continued use of prescribed
burning as a suitable site preparation method is anticipated for some
12,750 acres (5, 160 ha.) (Appendix).
Studies by McMinn (11), in the Prince George Forest District,
show improved growth of seedlings on heavily burned patches. This
suggests that on appropriate sites, burning during periods when sur-
face organic horizons can be significantly reduced, may justify the
increased fire control. measures required.
Chemical Treatment
Effective site preparation includes control of competing
68
vegetation, and manipulation of the soil for better survival and growth
of the newly planted trees.
Mechanical site preparation, and prescribed burning may
achieve the objective of inhibiting, or delaying the growth of compet-
ing vegetation. They also tend to alter or remove the surface
organic layers. Herbicide treatment (12) inhibits competing vegeta-
tion without disturbing these horizons. The aim of the S. M. S. P.
trials, however, was to create disturbance of the duff layer.
McMinn (11) reports on 197 1-72 trials in this Forest District
to assess the value of herbicides for site preparation, and to deter-
mine the significance of removing competitive vegetation, with or
without removal of surface organic horizons. Results of these
exploratory trials showed that herbicide treatment was less effec-
tive for site preparation than even blade scarification (11).
VII. CONCLUSIONS AND RECOMMENDATIONS
The following conclusions and recommendations are made in
the same chronological order that they would occur during the nor-
mal course of forest operations:
Pres carification
69
This practice was used in past years with only limited success,
when natural regeneration was the silvicultural aim. It would be of
even less value for site preparation of white spruce (Picea glauca
ssp. glauca) seedlings planted following harvesting, as many of the
planting spots produced would be covered with logging slash.
Logging
The generally wet ground conditions of the white spruce-alpine
fir (Picea glauca ssp. glauca-Abies lasiocarpa) forest types have
necessitated winter logging of approximately 60 percent of the 100, 000
acres (40, 470 ha.) whic1 is clear-cut harvested annually in the Prince
George Forest District.
Skidding on the snowpack, while undoubtedly essential in some
areas, creates two undesirable site conditions:
Duff on the forest floor is left undisturbed, thus necessitating
site preparation work.
70
Broken and lost logs are left under the snow to be retrieved
and chipped when feasible, during summer salvage logging,
at additional cost.
It is recommended that a low ground pressure crawler tractor,
such as the FMC 200, be used in the Prince George Forest District
to substantially increase the volume of timber produced during the
summer and fall seasons. This practice would undoubtedly alleviate,
if not entirely eliminate, the conditions of undisturbed forest floor,
and need for salvage residue logging, which result from winter
operations.
Site Preparation
It is recommended that, where economically and ecologically
acceptable, mechanical site preparation in white spruce-alpine fir
(Picea glauca ssp. glauca-Abies lasiocarpa) cut-over be carried out
in the following manner:
Prime Mover
Use a modified FMC 200 CA, or equivalent low ground pres-
sure crawler tractor, equipped with V-shaped brush blade, winch
and suitable towing arrangement.
Site Preparation Attachment
Use a Bracke Cultivator, as modified during S.M.S.P. trials,
and equipped with suitable towing hitch for mounting. behind the FMC
type tractor.
Cost Benefit Consideration
71
In all areas of forest management, costs of programs such as
Silvicultural Mechanical Site Preparation must be weig1ed against
benefits to be achieved, or at least anticipated. Some forest sites
are more highly productive than others; consequently greater
expenditures are justified for their rehabilitation, in view of econ-
omic returns.
A guideline expenditure (13) for the combined cost of site
preparation and establishing regeneration should not exceed $1.00 per
cubic foot (0. 03 m3.) of mean annual increment. For productivity
class one, 100 cubic feet per acre per year (7 m. per ha.), a maxi-
mum expenditure of $100, 00, divided equally between site prepara-
tion, and planting costs is justified.
It would appear from S. M. S. P. results that mechanical site
preparation costs may be kept within the established guidelines, at
least for productivity class one.
It is recommended that site productivity be given prime consi-
deration when a decision on site rehabilitation is required.
BIBLIOGRAPHY
Annual Report Prince George Forest District, B. C. ForestService. 1974.
Crossley, D. I. Mechanical scarification and strip clear-cutting to induce lodgepole pine regeneration. CanadaDepartment of Northern Affairs and National Resources.For. Res. Div. Tech. Note No. 34, 14 pp. 1956.
Decie, T. P. and A. R. Fraser. Miscellaneous notes onscarification trials Prince George Forest District 1956 to1959. B. C. Forest Service. Res. Note No. 36. 22 pp.1960.
Froehlich, H. A. Impact of even-age forest management onphysical properties of soils. Even-Age Management Sym.Proc. 0. 5. U. Paper 848. 23 pp. 1973.
Holt, L., H. S. D. Swan, and G. F. Weetman. Forest soilScarification. Pulp and Paper Research Institute of Canada.50 pp. 1956.
Illi.ngworth, K. and J. W. C. Arlidge. Interim report onsome forest site types in lodgepole pine and spruce-alpinefir stands. B. C. Forest Service. Res. Not No. 35. 44pp. 1960.
Lowdermilk, W. C. Influence of forest litter on runoff,percolation and erosion. Journal Forestry 28: 474-491.1930.
Lyford, W. H. and D. W. MacLean. Mound and pit micro-relief in relation to soil disturbance and tree distribution inNew Brunswick, Canada. Dept. Fish.8z Forest. Can. For.Serv. 17 pp.
Marston, R. B. Ground cover requirements for summerstorm runoff control on aspen sites in northern Utah.Journal Forestry 50: 303-307. 1952.
72
Muraro, S. J. Slashfuel inventories from 70 mm. lowlevel photography. Dept. Fish. & Forest. Can. For.Serv. Pub.. No. 1268. 12 pp. jllus.
McMinn, R. G. Unpublished experiment 70-F4. Pac. For.Res. Centre. Environment Canada.
Newton, M. (ed.) Herbicides in vegetation management inforests, ranges, and non-ciop lands. Syn. Proc. 0. 5. U.School of Forestry, 356 pp. 1967.
Revel, J. The need for mechanized silviculture and reforest-ation systems. B. C. Forest Service. 5 pp. 1974.
Rieche, K. W. A preliminary study of the economic useof crawler, tractor equipment for scarification. B. C.Forest Service. Eng. Div. 1961
Forest soil scarification in the Interiox ofBritish Cohimbia. B. C. Forest Service, Eng. Div. 81pp. 1963.
Project outline EP 740. B. C. ForestService Res. Div. 26 pp. 1974.
Steinbrenner, E. C. Effect of repeated tractor trips onthe physical properties of forest soils. N. W Sd. 29:155-159. 1955.
Vyse, A. H. How to calculate planting performancestandards. B. C. Forest Service Res. Div. 1974.
73
74
APPENDIX A
Maps of Forest Districts, Study Area, and Blocks
Figures Page
A. 1 British Columbia Forest Districts 75
A.2 S.M.S.P. StudyAreas (Blocks Ato G) 76
A. 3 Kenneth Creek- -Block A 77
A. 4 Bateman Road- -Block B 78
A. 5 Vama Va.ma Creek- - Block C 79
A..6 Tumuch Lake--BlockD 80
A.7 Tumuch Lake--Block F 81
A.8 HungaryCreekWest--BlockG 82
A. 9 Aerial Photographs (before and after treatment) 83
APPENDICES
Ii. PiERT
,,.,., ;.--
S. .4 - -
I -r. I.... -I .J.- -AS.-'-
-''CIOBI'-.
Figure A. 1. British Colubja Forest Districts.
L
\' \-
4)
'-._S"..'
-I /
C;O'(. -1
75
ly.
,.:i .
:i)-
..Hc"
.,'-;
Ope
rAtiO
fl.A
refl
Trc
tQd
*
't;
-\ b
z\.:'
r'...'
. !..
t-.
rt'
-1')
P1
:
."-:
12.:.
'A'C
'L '_
tj_--
----
4--'i
' ':.
.--z
.tV
t.-
')';
N--
' .'
'-
J#:
:,
\r_
\\
CI
.11
,('I
__/
d-
% t'
'\ t/.
4--'
i1\.
/ N\G
i\..
1k
E.P
.74
O A
reas
Tre
ated
E.P
. #71
1 A
rcaS
Tre
ated
Are
as N
ot T
reat
ed
Scal
e:to
4tiqI
c4?
I4
crr
:ç/'
'.'i$
3 L
-c:.
r".
I
.,r'-z
....
/ .-\
-":
..
-L'
'
KE
Y\P
1tur
tV
echa
z1C
al s
ite p
repa
ratio
r.
__%
___
..
-I_
--\
----
.J,.
A
:-11
.L"
t-'\'
\-j "
t:.'-
-''
:
'L®
L
-'LJ
(-r-
:',-
C..
Ni'(
-';.l'
J'r)
Y \c
1_-.
."'
th\c
e'ç
F 0
ftS
r-c
.'.S
.'-'
PA
.''
V
-'-z
. :--
;-:
-
-\:.r
..--,
'--.
..--)
.:2
f.. ..
-__r
.'--
\''
''t
'Y
V
r rnoz
C)
mm
H
7-I
0
\_ \ - _-- _tt\ / \... I\ / AREA ill.OPERAflONAL- TEST
!AREA 6
.11
I 1ES1 AREA 41
-._.--.-.iTEST AREA L I,
I". iI (I 1II
I (TEST .11
OPERATIONAL I AREA 3 I1Ep1741. ill.
_.____I
. n-__.1I. I gL
-IL
-
DAYS
Sr.. Wnh 1.7110,. )4.chI,.
TEST AREA
TEST)\J
I AREA'!
j/I\\\\ OPERATIONAL
OPER IOIAL
I I
TEST AREA 2
I,'..h 46.47
uI370.00
6,,.h 77.8., 1,4,6*,V.77 7' .5..., 0.rIh,Oh., III., 77.0, Mr _2.!
010.01
Figure A. 3. IKenneth Crecl--I31ockA.
-iw327.07
77
J.i, ip...... ILEGENDSIANCO 00009IL 0*114 SCC!6$ 00*0SIOICTIOO C 78007.7L)T *771* b0UND*KL.
r 5.. 7 4 r. tI..r 4 72 Ar.. 0.6. y..7e4
30.37 23.61 J.lp 1171
33.23 24.37 A...0 2474
17.11 22.00 J.Iy 2470
37.32 23,40 l74
I).', 7.42 kI.6.OMr
10.24 30.6) I..plr II'S30.22 7.23 1.p '8,'
I." 2.10 Mor 0r 1114
331 J.Iy I.pr.'.' I
0(1I
.1
TA4-
T&'2/j, "s._._.1 0
if I
!f j
II /+'ir51 \
t&3
TA' hi1L
lcoIToD 1TA1 I
Estimated I
Plaritable Area Tree-
Ocres)
8.24 Jul.7.88 Jul.8.74 Aug.4.97 Sept4.58 Oct..83 Dec.
P1OVLNCE OF BTISH COWMBIA - DEPARTMENT OF LANDS,FORESTS AND WATER RESOURCES FOREST. SERVICE, VJCTOA
ENGINEERING DIVISION
18.00 Aug.
LEN
A
7.00 July
60.24
8RANCI( ROADSDIRE CTIOF4 OF WORKTEST AREA BOUUOARY -
LL N3.
78
SCALE: I" 20 C
Test Area
64 J
0
achine AreaNetTreated
(Acres)
Work Sections
1 Control Plot No treatment2 12 Brush Blade 13.743 14 racke Cultivator 15.754 12 Sharkfirlsh fin 20.805 5 FMC 20O-Bracle 9.946 7 .Backhoe 18.327 2 Backhoe 3.32
Operational Brush Blade 30.00
EP 741 B.Blade,Backhoe,Trencher ,Bracke,Sharkfin,Trakmac
15.00
126.87
BATEMAN ROAD1BLOCK B Figure A. 4.
Test Area
VAMA VAMA CREEKBLOCK C
EJ'
' /I(
4,-I, ) /WI TEST AREA
4,
0
Figure A.. 5.
Net Area EstimatedTreated Plantable Area
Work Sections Machine (Acres) (Acres)
F'ROVNCE OF IRITlSH COIUMI3IA - DEPAREMENT 01- LANDS,IORESTS AND V/ATER RESOURCES FOREST SERVICE, VICTORIA
ENGINEERING DIVISION
LEGEND= C.
13RANCH ROADSDIRECTION OF WOR}<TEST AREA ROUNOARY -.
79
1'
Date Treated
1 7 . Trakmac 9.95 5.97 August/74
lilt NO. LI
SCALE: !' 20 CH.
TUMUCH LAKEBLOCK D Figure A. 6.
PROVINCE OF BRIUSH COLUMBIA - DEPARTMENT OF LANDS,FORESTS AND WATER RESOURCES FOREST SERVICE, VICTORIA
ENGINEERING DIVISION
LEGEUD
BRANCH ROADSDIRECTION OF V0RKTEST AREA DOUUOARY
I IL UO.
SCALE: t" 20 CH.
po
NetArea Treated
EstimatedPlantable Area
Test Area Machine (Acres) (Acres) Date Treited
Operatioual Brush blade 484 290.40 Sept.-Oct./74
EP 741 SharkfinBracke
1 00 50 Sept.-Oct./74
485.00 290.90
Test Area
1
2
Oporationel
''/_p .-.- -Ia
TEST AREA2 'a\\ F
SI-i
IrILJ-
'7-1TEST 0AREA II
OPERATIONALi
0
-\\0\
Work Sections Machine
7 Brncke Culti'ator22 Shnrkfin
Brush blade
II
EstimatedPlant able
Net Area Area DateTreated (Acres) (Acres) Tredm
12.73 6.37 Sept59.24 21.88 Se3t120.00 72.00 Sept
PROVINCE OF BRITISH COLUMBIA - DEPARTMENT OF LANDS,FORESTS AND WATER RESOURCES FOREST SERVICE, VICTORIA
ENGINEERING DIVISION
TEST AREA BOUNDARY -liLt NO.
SCALE: I 20 CF
PLO)'
LEGEND
BRANCI ROADS
81
= = -C- .0 = =
TUMUCH LAKEBLOCK F Figure A. 7.
191.D7 103.25
Test Area
1
Work Sections
5
LLO
Net Estimated
Area Treated Plantable Area
Machine (Acres) (Acres)
PROVINCE OF BRITISH COWMBIA - DEPARTMENT OF LtNDS,FORESTS AND WATER RESOURCES FOREST SERVICE, VICTORIA
ENGINEERING DIVISION
HUNGARY CREEK WESTBLOCK G Figure A.8.
LEGENDBRANCH ROADSDIRECTION OF WOR<TEST AREA BOUNDARY
82
Scale: =20 c
Date Treated
December/74
IU NO.
SCALE: I " 20 C
Backhoe 7.36 1.84
(Before
Scarification)
1:;-.-: £-.Z
Mter ScarificationbyD7 and Sharkfifl
L
After Scarification
by Tra0
Figure A. 9. Aerial Photographs (before and aftertreat me nt.
83
After Scarification After Scarification
by Bracke Cultivator by D7 and Brush Blade
APPENDIX B
Forest District and S. M. S. P. Production Tables
Tables
B.l Anticipated Acreage Logged Annually- - PrinceGeorge Forest District (197 1-1980). 85
B.2 1974 Site Preparation Activities Prince GeorgeForest District. 86
B. 3 5. M. S. P. Summary of Area Treatment. 87
B. 4 5. M. S. P. Summary of Production and Costs. 88
B. 5 Machine Comparison- -Speed of Travel vs.Production 89
B. 6 B. C. Forest Service - Reforestation Division SiteCharacteristics Chart for Rating Planting Difficulty. 90
B. 7 B. C. Forest Service - Reforestation Division SiteCharacteristics Chart for Rating Planting Difficulty. 91
84
Page
Table B. 1. Anticipated Acreage Logged Annually--Prince George Forest District (1971-1980)(By Forest Type, and Post Logging Treatment)*.
*Assume close utilization, salvage of dead and down material, and summer logging wherepractical.
Source: !ISite Preparation Requirementst' by J. Revel, B. C. Forest Service.
85
Forest TypeDenuded
(Ac.)Required
(Ac.)Possible(Ac.)
PortableSpotMech.(Ac.)
PrescribedBurning(Ac.)
PlantingRequired
(Ac.)
1. Spruce-balsam(overmature)(spruce, balsamspruce) 50,000 41,000 27,500 3,500 10,000 35,000
2. Cedar-hemlock(overmature)(cedar-spruce-balsam, hemlock) 2,000 2,000 1,000 1,000 2,000
3 Spruce-pine(thrifty mature) 10,000 5,000 3,000 500 1,500 2,000
4. Pine (pine-spruce,pine-Douglas-fir) 35,000 10,000 9,500 250 250 2,000
(mistletoe)(control)
5. Douglas-fir(Douglas-fir-pine) 3,000 1,500 1,500 1,000
Subtotal Type Nos. 1-3 62,000 48,000 31,500 4,000 12,500 39,000
Subtotal Type Nos. 4-5 38,000 11,500 11,000 250 250 3,000
TOTALALLTYPES 100,000 59,500 42,500 4,250 12,750 42,000
Table B. 2. 1974 Site Preparation Activities Prince George Forest District.
*Public Sustained Yield Unit
Source: Reforestation Division, 1974 Annual Report.
86
P.S.Y.U.*
Site Preparation (Acres)
BroadcastBurning
WindrowBurning M.S.P.
ScarificationTotalBlade Drag
Big Valley 1,885 605 - 423 1,233 4,146Blueberry 325 - 65 390Canoe 372 430 - - 100 902
Carp 2,569 912 - 17 842 4,340Crooked River 1,404 187 - 1,591Fort Nelson - - - 60 - 60Finlay 1,183 3,126 461 288 2,396 7,454Land - - - - -Longw orth 937 655 1, 710 - 3,302Moberly 405 70 147 - 72 694Monkman 1,147 - 1,170 - 2,317Naver 1,893 130 - 219 2,242Nechako 899 150 50 - 1,304 2,403Parsnip 1,378 247 330 390 2,345Peace 172 997 - 25 1,194Purden 630 477 258 1,365Robson 641 250 - - 891
Stuart Lake 994 1,025 76 1,201 3,296Takla 341 105 - - 230 676Wapiti 65 167 15 279 526Westlake - 497 343 705 1,545Willow River 330 310 375 122 1,137T.F.L. 30 820 65 3,381 143 - 4,409Unregulated 124 233 - 1,848 2,205
TOTAL 18,390 10,342 7,992 2,130 10,576 49,430
Table B. 3. S. M. S. P. Summary of Area Treatment,
87
Block(Acres)
AreaTreated(Acres)
Area E.P.Untreated 740
(Acres) (Acres)
E.P.741
(Acres)Operational
(Acres)
Block A(Kenneth Creek)
Cedex
Mile 16
Block B(Batemai Rd.)
Block C(Vama Vama)
Block D(Tuinuch)
Block E(Twnuch)
Block F(Twnuch)
Block G(Hungary Creek)
TOTALS
809
50
220
306
10
281
346
7
2, 029
610
50
220
127
10
246
192
7
1, 462
199 219
-
179 82
10
35
"Relogged and burned
154 72
7
567 390
21
15
2
38 1,
370
50
220
30
244
120
034
Table B. 4. S. M. S. P. Summary of Production and Costs.
88
Machine
RateI-li.
$
Available Efficiency Acres/Hr.
Cost,Acres $
Brush Blade 29.00 83. 3 63.9 0.58 49.58
V-Plow 32.00 92.3 65.8 1.16 27.51
Shark Fin 32.00 88. 7 77. 7 1.52 21. 10
Finnish Trencher 35.00 77.5 71, 8 1. 35 25.97
Swedish Bracke 35.00 77.9 65.8 0.81 43.23
Tralanac 24.00 61.7 51.7 0.36 66.52
H.P. 16 and Backhoe(Summer) 45.00 43.5 82.6 1.40 32.07
H. D. 16 and Backhoe(Winter) 45.00 87.8 39.7 0.41 110.52
FMC 200 and S.F. andBRK 38.00 60. 1 30. 8 1.09 32. 71
Table B. 5. Machine Comparison- -Speed of Travel vs. Production (Block A - Kenneth Creek).
Average AverageT. A. No. W. S. No. Strip Strip Speed Production(Machine) No. Strips Width Length (ft. 1mm.) mm. /ac.
89
1 2 10 24 200 28 70(Blade) 4 8 22 620 33 64
6 10 26 395 24 7411 8 22 205 25 8212 9 19 290 27 90
Average 27 76
2 4 10 17 720 84 32
(Bracke) 10 6 23 370 49 4011 9 12 590 70 5513 7 19 600 63 36
Average 66 41
3 4 6 15 740 95 34(V-Plow 6 7 26 700 74 22
7 9 19 490 68 36
Average 79 31
4 1 8 19 400 86 30
(Sharkfin) 3 9 16 640 96 33
5 6 17 650
Average 95 30
12 6 19 700 58 3716 9 14 720 70 4618 8 15 750 84 35
Average 71 39
5 1 5 22 750 19 110(Trakmac 3 6 28 400 21 80
4 7 21 400 23 100
Average 21 97
Table B. 6. B. C. Forest Service - Reforestation Division Site Characteristics Chart for RatingPlanting Difficulty.
Characteristics
- Stoniness(Factor 3)
Vegetation(Factor 2)
Coarse debris(Factor 1)
Fine debris(Factor 1)
Unplantableareas(Factor 3)
Duff(Factor4
Compaction Loose(Factor 4)
Slope (Factor 5) 10 - 35%
Infrequent stonesor boulders
Infrequent grass,herbs and lowshrubs
Scattered logs
Scatteredbranches and tops
Infrequent patchesof surface water,bedrock, etc.
Frequent stozies,boulders or coarsegravel
Frequent grasspatches, herbs, lowshrubs, infrequentnatural trees.
Frequent logs, somegrouped and crossed< 3' high
Grouped branches andtops, < 3' high, loosearrangement
Frequent patches< 1/2 acre
Occasional compactareas, e. g. Landings
0 - 10% or35 - 65%
Continuous stone,layer and/or frequentboulders, gravel
Continuous grass orother vegetation,naturals, planted trees
Frequent logs, groupedcrossed > 3' high.
Piled braiohes and tops> 3' or in a contiiuousmat
Frequent patches> 1/2 acre
Definite hardpanor compact layerthroughout.
Over 65Y0
90
<2" 2 - 8" >8"
Table B. 7. B.C. Forest Service - Reforestation Division Site Characteristics Chart for RatingPlanting Difficulty.
20 points
91
DifficultyRating
SmallB/R
Mattock
RegularB/R
Mattock
LargeTranspsShovel
LargeTranspsMattock
Styro2
Dibble
5"
MP
Dibble
7"
MPDibble
Easy 1000- 800- 700- 600- 1600- 1400- 1200-
10 points 800 650 550 450 1300 1100 950
Moderate 800- 650- 550- 450- 1300- 1100- 950-10-15 600 450 400 300 1000 800 700
Difficult 600- 450- 400- 300- 1000- 800- 700-16-20 400 300 250 200 700 600 500
Severe 400 300 250 200 700 600 500
92
APPENDIX C
British Columbia Forest Service Forms
Figures Page
C, 1 Forest Site Assessment Sheet 93
C.2 Physical Factors--Classes and Symbols 94
C. 3 Work Study Data Sheet 95
93
FS 602
BRITISH COLUMBIA FOREST SERVICEFOREST SITE ASSESSMLNT SHEET
Figure C. 1. Forest Site Assessment Sheet.
PROJECT NAME: No: FIELD SAMPLE No: DATE:12 3 4 I 6JJi I
I. R/W SITE PREPARATIONSpI. Ch.O.jSonpI. Cp. E, T.T. Ch End SM LATITUDE LONGITUDEOUMS S DDMMSS
2ojcI IT, N. TI. CHG.BIGIN
I :2. NATURAL L.ND SITE PIEPARATION
SEc BLock .. IT.1.1. ACRES OLOCK ACRES
I I I I I I I I I I I III!!,LATITUDE LONGITUDEo o u M s s o uI I I
u $ s 6ItS311r
I 1 1 I
2 17 2O22 2321.25.Qhfl.
31 3? 3 34 S36'73S 40 1 L2 L3 4L46 52 554S5 565758 S9O 61162IN
t on
24Count
So
$ S IOFAN INCH
S 5!iI578!_!162.65I,3
I
Lend
Ilui.A.p
FI LendFcoI'jr,.
UN.!
IIIUM.2
) 14
uuiuui aaiuu uu uuiiu2S 2730311233 3L 356 3743 41 2 431.6 47 1.849 50
INDIVIDUAL TREE DETAILS (D.B.H MEASURED TO THE NEAREST 0thcc.e 0.8.14 4ht ISpcic DON H,9ht .ec 08.14 1gt 0.0K
iMAIUUIIIIIuIII1NISiI3Hei9flt Spe 0.8,1 Ment iS--"U. 16MUUIIINMIIUINMUIilUMUIM.I.Mu'up.InuII.JINUSIUN ___NMUlNlUIIIN IIUUIUD
21MUIMMUi .&-i RIUNLI-i--i22MUMUUIU 23
DNIUS1UUUUNUSUIMIlURNIiii 2.I 25
I
UN 4-u.26
27
STUMP AND SLASH DETAIL.S I DIAMETER MEASUREDRN
TO NEAREST
lintat $ht tilt reou,rbdHE C K ,1 q i---
NCII ) :29-XNNUUINNNU
STUMPSI:TL1t]E1Ni1riu-iL1I
IIIIMIUIM
LIII7 l-. I E'O 014.I_n9Ih
D DIA. (NO DIA.
4-4
0IA LnIfl 3D
awiuluiuuuuNMuiihuu 2
431
4 I32
MI ININN I 33
u'.uu ii
MEASUREMENTSNNMNIIUNau._.u.hh1
FOR D.B.H hEGlT
I
I
I
4- +-3S
CURVESUUl
(D.BH-NEAREST_________ :E:K
0th OFANINCH HEIGHT- NEAREST FOOT) .381
2-4 001 COUNT Soce DON 1aiQht 0DM Heqht 08.H HegM 0 8.11 Hiht 0 O.M HQht 0 B K 1PI 39___
-l--4 -4 f-4- 4-4 I -4-- I- -
. I +-T.II II4L.._44
........
SHOWN.
I
..... +- F----
III-+-
II
.4
- -
44
45
-I--I-F- F-_..I_......._.._t_.._I_I
1-4
4 It IIREMARKS
STATEMENT OF SAMPLING DONE 9Y
. PARTY CIflEF
ME AT THE PLACECCRTIFIED
SIGN
THAT
HERC
THIS ISA TRUE
B
U
B
U
LAND FORMSO - OLACIAL
OP BASAL TILLGPM Pendant Ground MoraineGPP Till PI.,r
GM A8LATION DEPOSITSGMA Ahistion Ground Moraine0MM Marginal Moro,..
OF OLACIO-FLUVIALGFK Kome Terrac.GFE E5Iter TrOutOFT GIaea- Floolnl TarroceOFF Outwash Plain
F- FLU VIALFP FLOOD PLAIN
FPC Cocered TypeFPL BorMeonder Type
FT RIVER TERRACEFF FLU VIAL FANPD DELTA
FED Fan DeltaC- COLLU VIAL
CT TALUS AND SCREECTC Can.
CL SLIDE DEBRISCLS SoIl Creep CIR Reck SlideCLE Earth Slide
CF COLLUVIO- FLUVIALCF F Col IaOieI Fon
CR SHALLOW COLLIJVIAL MATERIAL WITH SOLID ROCK%- ORGANIC
$G SWAMP ASSOCIATED WlItl GLACIAL TERRAIN02K Swamp filled k.tII.s00 F Swofltp I1II.d meltwatnr channel,
OF SWAMP ASSOCIAIEO WITH FLU VIAL DEPOSITSOFF Swamp en flood PlainaOF S Filled 0,00w LeOne end BecImai,r ChennileSWAMPS ASSOCIATED WITH SIDE HILl. SEEPAGE
ØM MARINE SWAMPS AND TIDE FLATSL- LACUST RICE
LB Lobe BedL 0 Bench or Strand Lrne
W WIND DEPOSITSWD Done.WL Lee.,
V- VOLCANICVL Leve FlewVA Volcanic Ash DepositsVC Volcanic Cinder Cane
R - BED ROCK, £.pa..d or Clot. to Sorfan.
HEIGHT CURVESTh. numb., unsanuend should be I... then 20 height, parspecie pen timber type in even - aged and young hand.. Old.,end rand, with teverdi level, OF Crowns requite t,erethan 20 rnading. .uI should not e.cned 50 needIng,.
Tree height readIng, take distributed as fallow.
PHYSICAL FACTORS-CLASSES AND SYMBOLS
DOUBLE PLOTTINGlAl Length IIIdnd W(dth(I( or Radiue(II viad ter LARGE PLOT
Ltngth(2I - (21 - 12) SMALL PLOTDON LIMIT must bOon ODD INIERGER < IS
(B) If area has betA prenouely logged USE length (I(.tC. forSTANOING TREES and/or STUMPS.USE length (21 etc far SLASH. Cit diffirent tree, lenglb (I))
DBH LIMIT MUST BE LEFT BLANK.
NOTE: Peiet the alpheb.ttc Choroclers" I aad 0 ff1.1, tadr,tInguIsh frees the number, I and 0
ROUGHNESS 1% indIcate, portIon at urea affected II. 0-10% 4. 40-60%2.IO-25% 5. 60%.3.25400/
ASPECTI.. NORTH. NN
NORTH-east NEEAST a E ESOUTH- ear a SESOUTH 0 SSSOUTH-w.st.5W
Ti WESTCWWB. NORTH-w..I.NW9. FLAT 5 NA
MAJOR LAND FEATURESFPL Flood Plain USI Upper Slap,BFL Bench Flata MSL Middle Slop.VFR Volley Flaor ILD blandLSL Lower Slope
GRANULAR SOILS WITH LITTLE FINES (410% FINES)GRAVELGRAVEL and SANDSANDGRANULAR SOILS WITH SIGNIFICANT FINES (10-55% FINES)SILTY GRAVELCLAYEYSILTY SANDFINE - GRAINED SOILS (>35 0/, FINES)SILT.CLAYORGANIC SOILS (DEPTH 2 FEET C
SOIL MATERIALlOO SOLID ROCK200 BOULDERS B ROCK FRAGMENTS3-00-10-20-30
4-00-10-20-30
5-00-1020
600
VOIL MOISTURE.D VERY DRY
DR DRYcR FRESH
94
(Mg MOISTWE WETVW VERY WET
STABILITYI-HIGH STABILITY 2-NORMALLY STABLE 3-UNSTABLE
MATURITY II-MATURE 2-IMMATURE
STUMP STATE
2-MEDIUM,EFFECT5 WALKIRG3-HEAVY, DIFFICULT WALKING AND EFFECTS WORK4-VERY HEAVY,VERY DIFFICULT AND INFLUENCES WORK GREATLY
BRA NC HIN ES SI-BRANCHES COVERING < /3 OF STEM2- BRANCHES COVEOIIIdG 1/3 TO 2/3 OF STEM3-BRANCHES CC'.ERING 2/3 OF STEM
WINDFALl.0- NO WINDFALLI-RSTTEN (mI/S OF TREE DECAYEOI2-'iOUND (-I/3 OF TREE DECAYEDI
0 PL AND ALL DECIDUOUS TREES ARE MATuRE >80 TEARSOT-IER CONIFEROUS TREES MAIURE>120 YEARS
SLASH Of TAILSRECORD SLASH IF LENGTH 4FT. AND LARGE TIAMETER S
STUMP DETAILSRECORD STUMPS IS" DIAMETER
UMI,UH2 AND PENETRATIONMEASURED 10 NEAREST 1/10 FOrTI
2 - 4_ COUNT.INCLUDES ALL TREES WITH A 0 SN of I.1 - 5.0
T.T. AND BLOCK ACRESRECORDED 10 THE NEAREST ACRE.
Figure C. 2. Physical Factors - Classes and Symbols.
SPECIESFl -CE -
FIRCEDAR
LA -CO -
LARCHCOT ION WOOD
1 lINEN> 5O°/, OF ALL STUMPS ABOVE IS "DIA. ARE IS YEARSOLD OR OLDER
2-OTHER THAN CLASS IHE - HEMLOCK AL - ALDERBA BALSAM MA MAPLE AREA STATESP -CY -PW -
SPRUCECYPRESSWHITE PINE
52 -AS -WF -
BIRCHASPEN -WINDFALL
I-NATURAL 3-BURNED AND LOGGED2-LOGGED 4-BURNED
PL - L000EPOLE PINE SN - SNAG UNDERGROWTHPY - YELLOW PINE I- LIGHT, DOES NOT EFFECT WALKING
DOMINANT (Mee.ure 1/41
CO-DOMINANT (Ueo.ure 2/41
UNDERSTORY (H 1/4)
SUPPRESSED (Do not nseaaur,)
GPO Dru,nllnlaed TillGPR Rack DrumlIn Aria
GIlL Lateral HeroIneGUK Kame-Kettle Topog.
GFV VeIl.1 TealaOFF Olacla-Fluolal FenO FO Olecla-Flunlal Delta
F PV Natural L.n,e,FPB Braid.d Type
Figure C. 3. Work Study Data Sheet.
95
ENGINEERING SERVICES DIVISION ES. 114RCV.DCC.I#54_ 0
WORK STUDYDATA SHEET
Type of study Pige NoProject Sta to St - Acres
Timer Midline unitBegin Time r.na l'h..*e To.1
?.Tca,uremrnt er,rk -(DC;crjptjøfl 01 condiiionc. acilviluc,, etc.)
i
Sb. Time
H
IL IUiuu.jU II
U
au.uiur: :::iII
i
V
psccltEl.ifllc