Project Overview BQE Water worked with the mine owner to design, construct and commission a SART plant in a ght nine month schedule to allow this acve gold mine to process all its ore and avoid stockpiling high-grade ore with copper mineralizaon. Elevated cyanide-soluble copper in the ore interfered with efficient and cost-effecve gold recovery, and cyanide destrucon prior to discharge into tailings pond that presented a challenge for cyanide limits. The SART plant treats barren leach soluon (BLS) containing up to 1,500 mg/L of dissolved copper. On average, 87% of the copper is recovered and up to 80% of the cyanide regenerated. The copper is recovered from the BLS as a commercial grade concentrate, generang an incremental revenue stream, and the regenerated cyanide is recycled to the leach operaon, reducing overall cyanide consumpon. Cyanide discharge limits in the tailings pond are also met and copper interference in the adsorpon/desorpon (ADR) circuit is minimized, resulng in improved gold doré purity. Process Flowsheet Objective Reduce metallurgical interference of copper to improve gold doré purity and comply with cyanide levels in tailings technOlOgY SART plant capacitY 2,880 m 3 /day lOcatiOn Gümüşhane, Turkey bQe WateR scOpe Process design, HAZOP, equipment specificaons and sizing, construcon review, commissioning, plant opmizaon, operator training, operaon manuals and standard operang procedures, on-going technical support Mastra Mine, Koza Gold MAS2020030CD Suite 250 – 900 Howe Street Vancouver BC Canada V6Z 2M4 www.bqewater.com Contact our water treatment experts to find out how we can help you. 1 800 537 3073 or bbaker@bqewater.com SART Detox CIP CCD CIC Leach Communion NaCN make-up Cyanide Recycle ORE Tailings Cu 2 S product

Upload: others

Post on 05-Jun-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Mastra Mine, Koza Gold - BQE Water · Mastra Mine, Koza Gold MAS2020030CD Suite 250 – 900 Howe Street Vancouver BC Canada V6Z 2M4 Contact our water treatment experts to find out

Project OverviewBQE Water worked with the mine owner to design, construct and commission a SART plant in a tight nine month schedule to allow this active gold mine to process all its ore and avoid stockpiling high-grade ore with copper mineralization.

Elevated cyanide-soluble copper in the ore interfered with efficient and cost-effective gold recovery, and cyanide destruction prior to discharge into tailings pond that presented a challenge for cyanide limits.

The SART plant treats barren leach solution (BLS) containing up to 1,500 mg/L of dissolved copper. On average, 87% of the copper is recovered and up to 80% of the cyanide regenerated. The copper is recovered from the BLS as a commercial grade concentrate, generating an incremental revenue stream, and the regenerated cyanide is recycled to the leach operation, reducing overall cyanide consumption.

Cyanide discharge limits in the tailings pond are also met and copper interference in the adsorption/desorption (ADR) circuit is minimized, resulting in improved gold doré purity.

Process Flowsheet

ObjectiveReduce metallurgical interference of copper to improve gold doré purity and comply with cyanide levels in tailings

technOlOgYSART

plant capacitY2,880 m3/day

lOcatiOnGümüşhane, Turkey

bQe WateR scOpeProcess design, HAZOP, equipment specifications and sizing, construction review, commissioning, plant optimization, operator training, operation manuals and standard operating procedures, on-going technical support

Mastra Mine, Koza Gold

MAS2020030CD

Suite 250 – 900 Howe StreetVancouver BC Canada V6Z 2M4

www.bqewater.com

Contact our water treatment experts to find out how we can help you.1 800 537 3073 or [email protected]

SART Detox

CIP

CCD CICLeachCommunition

NaCN make-up Cyanide Recycle

ORE Tailings

Cu2S product