matthew+meas+-+long+paper.docx
TRANSCRIPT
Electricity in South Africa – A Chronological Assessment
Matthew R. Meas
I. Introduction
Electricity is undoubtedly the lifeblood of industry. While numerous models exist for the
structuring of an electricity supply industry, failure in the structure will always lead to dire social and
economic consequences for that country. Although the government is not calling it one, many
people believe that South Africa’s electricity supply industry is in crisis. This paper reviews the
history of the electricity supply industry in South Africa, focusing in particular on the transformation
during the political revolution, and the consequent lack of policy coherence that led to the 2008 load
shedding and the persistent lack of supply capacity thereafter. The current supply situation is
outlined in the context of the measures taken to ameliorate the supply shortages and opportunities
not realised. Additional short-term solutions are considered, including the accelerated introduction
of private generators employing renewable energy, and the long term prospects evaluated for the
improvement of the industry.
II. History of the South African electricity industry (Eberhard, 2007)
In 1897 the Rand Central Electric Works built the first commercial central power station in South
Africa. The foremost purpose of the plant was to supply the gold mines around Johannesburg. As the
country became more industrialised, the government assumed an increasing role in the electricity
supply industry (ESI), gradually acquiring private electricity supply operations, whose existence it
considered to be suboptimal for development. These events culminated in the passing of the
Electricity Act, No 42 of 1922, which created The Electricity Supply Commission, controlled by
commissioners appointed by the Minister, and the Electricity Control Board. ESCOM was given the
legislative authority to establish operations for the generation and distribution of electricity. The
commission repaid its early loans from government and had to raise capital through the issuing of
bonds thereafter. ESCOM was exempt from corporate income tax and was to supply electricity at the
lowest possible cost, making neither a profit nor a loss. Although electricity supply undertakings in
other municipalities did not require a license from the ECB, the Provincial Administrator was
required to launch an enquiry to ESCOM on whether its operations would be more cost-effective. As
a result, the jurisdiction of ESCOM extended to Durban, Cape Town, and other towns. In 1948
ESCOM secured control over the majority of the power stations as well as the high-voltage
transmission lines, when it purchased the largest private producer, the Victoria Falls Power
Company. By 1973, the transmission grid had been interconnected and was nationally controlled. So
the structure of the South African power sector came resemble that of many other countries in the
early 20th century, with ESCOM the unchallenged organisation integrating the complete value chain
from generation through distribution.
In order to meet the rapidly growing demand for electricity, new power stations were built,
mostly concentrated in the north-east of the country, and situated immediately adjacent to privately
owned coal mines which entered into long-term supply contracts with ESCOM. The growth in
demand was exacerbated by the oil shocks of the 1970s, as the economy was progressively
electrified, resulting in reserve margins as low as 11% in 1975. Furthermore, the unprecedented
engineering challenges encountered in increasing the scale of boiler designs and the effective use of
low-grade coal, compounded the concerns of power shortages amongst the planners at ESCOM,
causing them to order even more power stations (Eberhard, 2007). However, financing new assets
was becoming increasingly unaffordable, and the Electricity Act was consequently amended in 1971
to allow ESCOM to accumulate a Capital Development Fund from increased retained earnings
approved by the State President. Substantial price increases ensued, which troubled the
stakeholders and eventually led to a government enquiry by the De Villiers Commission, in 1983. The
Commission criticised the management, planning, and bookkeeping at ESCOM. Following the
recommendations of the Commission, the Electricity Act was amended in 1985, and replaced by a
new Act in 1987. ESCOM was renamed Eskom in accordance with the new Eskom Act of 1987 and
the Capital Development Fund replaced with standard business accounting practices. The previous
governance structure was replaced with a new two-tier corporate structure, which would require a
permanent executive management board to report to an Electricity Council representing major
electricity consumers, government, and municipal distributors. The Act replaced Eskom’s previous
mandate with the directive to “provide the system by which the electricity needs of the consumer
may be satisfied in the most cost-effective manner, subject to resource constraints and the national
interest.” and effectively transferred responsibility of regulating tariffs from the ECB to the
consumer-dominated Electricity Council (Eberhard, 2007).
To reduce the impact of the impending excess capacity due to their over-planning, Eskom
cancelled plans for new power stations, delayed the construction of others, and decommissioned or
mothballed older plant. Eskom lowered previous demand growth projections of 7% and promoted
load growth, offering low-cost electricity contracts to energy-intensive users, particularly those in
the in the beneficiation of aluminium and Ferro-chrome for export. Many vertically-integrated
electricity monopolies experienced similar cyclical overbuild and contraction during the 1970s and
1980s. While expansion projects presented little risk to investors or managers of state owned
enterprises, as debt was guaranteed by the state and the costs were borne by electricity consumers,
investments were infrequent and had long lead-times. They were often discontinued when
projected growth rates were not realised, requiring an arduous balance between mitigating short
term overcapacity and planning for future demand. When need for new capacity arose, higher
electricity prices would inevitably be necessary to finance the investment, yet consumers would
have grown accustomed to low tariffs based on the value of the previous generation of capital that
had largely depreciated. New investment frameworks were thus explored, and the government
commissioned the first privatisation study of the utility, which Eskom conducted in 1988. The state
was reviewing the performance of state owned enterprises at the time, and it had identified a need
to attract foreign direct investment. The study analysed several options and concluded that it would
be possible, and indeed preferable to privatise Eskom in its entirety, without introducing
competition, though the proposals were quietly abandoned in light of the uncertain political
circumstances at the time. The democratic revolution of 1994 unexpectedly renewed interests in the
liberalisation of the state-owned enterprises, and several were either privatised, or subjected to
corporate shareholder performance contracts. Throughout the world, outmoded state-owned,
vertically-integrated electricity supply industries were being restructured into unbundled,
competitive industries (Eberhard, 2007). Awareness was increasing amongst shareholders and the
focus would eventually return to Eskom. In the words of Eberhard (2007) “Change was becoming
inevitable.”
III. Primary precursors to the load shedding of 2008
When the ANC came into power, the desire of the new government to articulate their
position concerning energy led to the writing of the 1998 White Paper on Energy, which served as
the official proposal for the restructuring of the ESI. A major concern at the beginning of the 1990s
had been inequality of access to electricity and the plethora of small, financially inviable municipal
distributors (Eberhard, 2007). To address these issues, Section 7.1.3.3 proposed the formation of
Regional electricity distributors, stating that “Government will consolidate the electricity distribution
industry into the maximum number of financially viable independent regional electricity distributors
(REDs).” Section 7.1.4.4 of the 1998 White Paper proposed the establishment of the National
Electrification Fund, at the recommendation of the EDRC, stating that “Government will establish a
National Electrification Fund to provide electrification subsidies.” Section 7.1.5.8 called for the
facilitation of non-utility generation, stating that “The entry of multiple players into the generation
market will be encouraged” (Department of Energy, 1998).
The 1998 White Paper effectively set the stage for subsequent legislature designed to
facilitate practical, methodical restructuring of the ESI. To this effect, several bureaucrats and
representatives from Eskom and the NER assembled at a Ministerial Workshop in April 2000 and
agreed upon a draft policy paper outlining the restructuring the ESI. Eskom’s management were
initially alarmed at the extent of the proposals, which sought to reduce Eskom’s share in generation
market to 35%. However, in March 2002, broad consensus was reached on the next steps of the
“managed liberalisation process” approved by Cabinet in May 2001. The process would require
Eskom to retain no less than 70% of the existing electricity generation market. The remainder was to
be privatised and an initial 10% transferred to black economic ownership by 2003. An independent,
state-owned Transmission Company was to be established to vertically unbundle the industry and
ensure equal access to the transmission lines. Moreover, a new electricity market framework was to
be established based on multiple market models in order better distribute both physical and
financial risk, by diverse platforms for transactions between generators, traders and buyers, such as
bilateral contracts and power exchange. The power exchange was to be supported by a transparent
and independent governance mechanism, with a regulatory framework for ensuring the
participation of Independent Power Producers (IPPs) and the use of a range of primary energy
sources (Eberhard, 2007). In 2007 the Department of Energy announced their intention to table a bill
during the 2012 Parliamentary session to establish an Independent System and Market Operator
(ISMO). Eskom would cede transmission and distribution of electricity to the ISMO, who would enter
into purchase agreements with generators and supply agreements with municipalities according to a
rationalised tariff structure (Lloyd, 2012). While these reform steps were confirmed in March 2004,
the target dates were also significantly delayed, with a partial divestment Eskom’s generation assets
that had been scheduled for 2003 deferred around 2007 (Eberhard, 2007). Discussions relating to
the ISMO bill were continuously stalled, prior to its official withdrawal at the 2015 annual ANC
lekgotla (Paton, 2015).
The National Electrification Forum (NELF) advocated the accelerated electrification
programme which increased the proportion of households with access to electricity from one third
in 1993, to nearly 70% in 2000 (Marquard, 2006). A fundamental concern of stakeholders
represented in the NELF was the restructuring of the electricity distribution industry (EDI) to make
distribution financially viable and ensure that the EDI would be able to facilitate their ambitious
national electrification programme (Eberhard, 2007). While the unions shared these concerns, larger
urban governments that had reaped financial benefits from electricity sales did not, and feared
losing the additional revenue. The Board of the NER weighed rationalisation of the EDI through its
licensing process against further legislation from government and decided on the latter. After a
longwinded and controversial development, revision and relaying process their proposal, which
suggested consolidation of the EDI into an optimal number of financially viable and independent
Regional Electricity Distributors, or REDs, was approved by Cabinet in May 1997. In June 1999,
Cabinet agreed that six REDs were optimal, and that a publicly-owned, national EDI Holdings
Company should be founded to facilitate their creation. Defining the boundaries of the REDs proved
problematic, which led to the appointment of a consortium led PriceWaterhouseCoopers (PwC) in
early 2000. The group produced an exhaustive list of working papers, yet the EDI Holdings Company
formed more than a year after the decision, and the REDs had still not been created by
2007(Eberhard, 2007). Unsuccessful attempts to form the REDs were abandoned after 15 years,
during which they claimed a total R1.2 billion in consultants, summits, committees. A Cabinet
decision in 2010 confirmed that the REDS are dead, and Eberhard (2012) suggests that the reason is
clear. Electricity distribution is constitutionally described as a local government function and
although numerous municipalities initially cooperated in restructuring of the EDI, they objected
when ultimately instructed to cede their lucrative operations. The proposed amendment which
would have allowed their functions to be transferred to national government was soon withdrawn
when it became apparent that it would not be passed in the National Assembly, yet the Cabinet
decision to abandon the REDs model suggested no alternative. The National Planning Commission
subsequently proposed a plan to control the seemingly unmanageable scale and complexity of the
challenges facing the EDI could be mitigated using the Pareto principle, allowing 80 per cent of
municipal distribution to be improved with 20 per cent effort directed at our twelve cities. The
valuable plans made by EDI Holdings should be swiftly resurrected and the transferral of assets
considered in the few anomalous situations where Eskom still supplies city customers. Conversely,
the small rural municipalities that have difficulty providing a sustainable electricity service would
very likely enter into service delivery agreements with either Eskom or neighbouring metropoles, but
this requires definitive support from government (Eberhard, 2012).
The call for private generators to enter the supply did not proceed as envisioned, as could
have been anticipated considering the frequent disagreement and rescheduling of the “managed
liberalisation process.” With no contractual assurance of reasonable return on investment, private
industry simply could not rival Eskom’s cost and capacity, lest tariffs rise to international levels
(Lloyd, 2012). In addition to the proposed unbundling of Eskom, Cabinet issued a mandate in April
2001 explicitly stating that “Eskom [would] not [be] allowed to invest in new generation in the
domestic market… to ensure meaningful participation of the private sector in electricity in the
medium term” (DME Cabinet Memorandum April 2001, as cited in MAPS 2014). This effectively
transferred decisions regarding new build from Eskom to government, and despite projections that
new capacity would be necessary by 2007, Eskom was not permitted to build the capacity to meet it
(Marquard, 2006).
A public alert was issued in July 2004 warning of potential load shedding. Load shedding is
strategically applied by Eskom to prevent total collapse of the national grid in times when the
available generation capacity cannot safely meet the demand for electricity. However, it is the last of
several ancillary measures, which includes the National Control Centre calling upon the demand
market participation customers to reduce their loads by prearranged contractual amounts. If the
reduction is insufficient, supply to customers on interruptible tariffs may be interrupted for a limited
duration. Once these options have been exhausted, the National Control Centre will then assess the
shortfall and request Eskom Regional Control Centres to temporarily terminate supply to
predetermined loads such that the balance is restored to the national grid. A Southern African
Power Pool emergency is also declared, so that partners with spare capacity can assist in limiting the
extent of the disruptions (NERSA, 2008). No independent power producers had been contracted by
2004 and Eskom was still prohibited from investing in new capacity. Since Eskom had shut down the
department responsible for building new power stations, lead times on large stations were
anticipated to be longer, at around 9 years and low reserve margins would complicate supply-
demand balancing. Cabinet consequently lifted the decree that had excluded Eskom from investing
in the new-build programme in October 2004, and tasked Eskom with leading the procurement of
new generation capacity. Moreover, it was clear that unless demand growth was considerably lower
than expected, the new build would mitigate, but not prevent the upcoming supply shortages
(MAPS, 2014). In 2008, Minister Trevor Manuel explained that previous public expenditure had
predominantly subsidized the extension of supply, as opposed to financing the utility (Public
Protector, 2008). However, the electrification programme cannot be used to excuse the lack of
capacity, as it has since been shown that it was in fact inflicted by incoherent policy. Bearing in mind
that the largest consumers of electricity are not residential, industrial users, most forecasting of
industrial loads alone would have, and had indeed, signalled the impending supply shortage
(Eberhard, 2007).
The 2008 investigation of the National Energy Regulator of South Africa (NERSA) into the
load shedding of 2008 revealed that maintenance scheduled for January 2008 exceeded that allowed
by the operating reserve requirement by approximately 2000MW. Moreover, the actual unplanned
outages were abnormally high, and regularly exceeded 4000MW in January 2008, often requiring
pre-emptive load shedding to preserve the integrity of the power system. The opportunities
available to shutdown plant for planned maintenance meant that Eskom’s usual maintenance
procedures could not be effectively applied. Eskom adopted the 90/7/3 (Capacity balance Installed =
Available/in planned maintenance/in unplanned maintenance) operating philosophy in the early
1990s, when the reserve margin was comparatively large. Since then there has been an increase in
frequency and severity of unplanned outages, mostly due to boiler tube leaks, which occurred more
frequently when was operated at emergency generation levels and the quality of coal was poor. The
boiler tube leaks accounted for over 20 percent of the unplanned capacity loss during the inquiry
period. While gas turbines were inoperative on seven occasions due to lack of fuel, this had
relatively low effect on the rate of unplanned outages. However, more fuel oil was used during the
inquiry period than would otherwise be used in a calendar year. The increasing rate of planned
outages despite a decreasing reserve margin was predominantly caused by longer outages needed
for the comprehensive mid-life refurbishment of older plant, including Arnot. Yet, the investigation
identified a lack of coordination between the financial, resource and operational plans necessary for
effective maintenance procedures, and a tendency for Eskom to treat symptoms through minimum-
time maintenance instead of addressing the underlying causes through effective, maximum-benefit
maintenance. It was found that Eskom exported 765MW more power to neighbouring countries
during the load shedding period than was obligated by firm contractual requirements. Imports
totalled 850MW, whereas exports exceeded imports by 469MW during the period under
consideration. The NERSA (2008) investigation also revealed that inconsistent coal quality and wet
coal led to uncontrollable combustion, increased component wear, and coal handling problems
which caused load losses as great as 3000MW. As a result of low coal stockpile and high rainfall
coupled with the large number of unplanned generator trips and high planned maintenance, the
System Operator had no realistic alternative to load shedding.
IV. Managing the electricity supply shortage
Research conducted at the University of Cape Town indicates that the tendency for developing
countries to follow industrialised countries in unbundling their electricity supply industries with the
objective of establishing a structure resembling the standard market model often resulted in
incomplete restructuring and the emergence of a hybrid market model. The hybrid model is
characterised by coexistence of independent power producers, operating under long-term contracts,
a large state-owned utility, continuing to hold a significant-to-dominant share in the market (Nel,
2012). It is this hybrid market model which best describes the current electricity supply situation in
South Africa. On 24 January 2008, Eskom sent a letter to their customers requesting them to reduce
their load. The subsequent shutdown in the mining industry attracted much publicity to the fact that
Eskom could not guarantee supply (NERSA, 2008). However, the economic recession and the
corresponding demand decline initially helped to create space for a recovery. Eskom has since
rebuilt coal stockpiles and brought additional emergency capacity online. Demand Side Management
programme has also been implemented which has achieved energy savings and capacity from
Independent Power Producers and Renewable Energy Independent Power Producers has been
connected to the grid (Joffe, 2012). Eskom has twenty four operational power stations, of which
fourteen are large coal fired stations and made the decision to build the 4,800MW Medupi in 2005,
and were granted a license from NERSA in 2006. The construction of a further base-load station,
Kusile, started in 2008 and the first unit was expected on line in 2014 (Lloyd, 2012). However, these
have been delayed and while one unit of Medupi has been commissioned, construction on Kusile is
set to continue for a long time yet, as is the Ingula Pumped Storage Scheme (Creamer, 2015).
Reasons given for the delay in the construction of new generation capacity include difficulties in
completing environmental impact assessments on tribal land (Eskom, 2014). Unrest after a fatal
accident at the Ingula construction site caused significant delays (Eskom, 2014). Most of the coal
fired fleet is located on the site of coal mines with which they have long-term coal contracts. Eskom
also owns and operates the only nuclear power station in Africa, located at Koeberg, approximately
30 kilometres north of Cape Town, as well as three hydroelectric plants and two pumped storage
schemes used to meet peak demand and maintain control and balance of the system. Small,
municipal power stations and back-up gas turbines constitute approximately 5 per cent of the
national generation capacity with the approximately 2 percent remainder representing private
generators (Eskom, 2015). South Africa exports approximately 5.5 per cent of the total net electricity
produced to Botswana, Lesotho, Mozambique, Namibia, Swaziland and Zimbabwe. Approximately
3.6 per cent of the total electricity produced in South Africa takes the form of imports,
predominantly from the Mozambique Cahora Bassa hydro-electric station, the Democratic Republic
of Congo, and Zambia (Stats SA, 2014). Most of Eskom’s bulk electrical power is sold to large mining
and industrial customers, and to municipalities, accounting for more than 80 per cent of its revenue
and electricity sales, and a further 5.1 per cent consists of retail distribution services directly to
residential customers (Eskom, 2014).
In response to the 2008 load shedding, Government declared an electricity emergency and
formed the Government National Electricity Emergency Programme (GNEEP) led by a National
Electricity Response Team (NERT), to alleviate the crisis by drawing upon the collective efforts of
various industry stakeholders (NERSA, 2008). The NERSA, uncertain of their role in relation to the
NERT, put forth their recommendations to Eskom in their report from the investigation into the 2008
load shedding. The NERSA directed Eskom to monitor the match between the coal delivered and
burned and to continuously secure adequate stock levels to fuel power stations through periods of
copious rainfall and unforeseen events. However, Eskom failed to address the shortcomings in their
coal protocol. In their commentary on the NERSA report (2008), Eskom denied complacency in their
procurement of coal, and yet reported delivery of the incorrect grade of coal (Eskom, 2014).
The impact of the electricity supply shortages can be further ameliorated by the increased use of
renewable energy as supplemental capacity during periods of peak demand. While Eskom has
improved their maintenance procedures in the years following the 2008 load shedding incidents,
doing so has been difficult with reduced reserve margins (NERSA, 2008). If anything, the additional
capacity from renewable energy technologies should also substitute the capacity taken out of
service during maintenance procedures. Renewable energy technologies have shorter lead times
and significantly lower construction costs compared to conventional technologies (Lovins, 1976).
Furthermore, there is no fuel cost associated with fuelling renewable energy technologies. However,
the targets of the Eskom Renewable Energy Independent Power Producer Procurement Programme
(REIPPPP) are currently not being met (Eskom, 2014). The 2013/2014 target for total independent
power producer purchases was set at 4152 GWh, of which 3671 GWh was successfully secured
(Eskom, 2014). The current programme requires each application to be reviewed by the Minister of
Energy, in accordance with the Electricity Regulations on New Generation Capacity (Department of
Energy, 2011). This subjection of each application to ministerial judgement is ineffective, and hinders
a critical procedure which should be expedited in light of our current supply situation. The mandate
and decision-making procedure should be clarified and revised, such that the authority to make
informed decisions regarding applications through the independent power producer programme can
be extended to the commissioners appointed by the minister. NERSA should furthermore be
mandated to regulate tariffs with renewed intent and should hold all entities in the ESI and EDI
responsible to their contractual agreements. Additionally, partnerships with generators in Namibia,
Botswana and Mozambique will undoubtedly improve the outlook for the South African ESI in the
coming years, and we can learn from Europe’s experience that the introduction of renewable energy
is fostered by connections between regions (Lloyd, 2012).
Another untapped potential for reducing the impact of the electricity supply shortages is
cogeneration. The cost of rooftop photovoltaic panels continues to drop and commercial consumers
in major cities are investing in the technology despite the effective silence of South African electricity
policy regarding the topics of cogeneration and the wheeling of power into the grid. If cogeneration
were to be facilitated at attractive rates, private investigation in generation capacity may improve
more rapidly, and the increase in capacity would be favourable for consumers and the integrity of
the grid (Burkhardt, 2015).
V. Prospects for the electricity supply industry
The foremost short-term priority for the South African ESI industry should undoubtedly be
the establishment of an adequate reserve margin. Thereafter, additional prospects should be
considered to avoid the pitfalls of the past. In his Roadmap to a thriving Electricity Supply Industry in
South Africa (2012), Doug Kuni, MD of the South African Independent Power Producers Association
suggests renewed attempts at allowing private generators into the market, as these may help
alleviate funding problems that may arise during capacity expansions. Kuni continues,
recommending that municipalities be put under pressure to return all of their distribution
equipment to serviceable order, and that tariffs be regulated within affordable ranges to address the
backlog and facilitate this initiative. Acknowledging the large expenses involved in grid maintenance,
Kuni suggests that the Department of Energy Renewable Energy Independent Power Producer
Procurement Programme be merged with an accelerated off-grid programme in remote
communities. Lastly, Kuni laments the intricacy of the current ESI and calls upon Government to
establish a Permanent Electricity Commission (PEC) of professionals from international ranks, with
experience in successful power sector reforms, to be tasked with restructuring the regulatory
process. To this end, Kuni suggests that the PEC be tasked with producing future independent power
producers, immediate revision of the complete suite of legislative and regulatory documents to
achieve sufficient coherence that can facilitate participation from independent power producers,
and advising Government on future policy.
Though there exists no evidence to suggest that competitive market structure is necessarily
better than a monopolised, or hybrid market structure, the former may indeed be the better option
for South Africa. Many of Eskom’s power stations will be reaching the end of their lives, and will
have to secure funding for new generation capacity. However, it is anticipated that the utility will
have difficulty securing funding beyond what it receives from the National Treasury, as its long-term
credit BB+ rating was reduced to BBB- and eventually to sub-investment, or “junk” status in March
2015 (SAPA, 2015). This development could significantly limit the prospects for the development of
the South African ESI. While the precise position of a single network operator and its relation to
Eskom has been the source of much debate, the creation of an ISMO may become a necessity in the
future. As an alternative to Eskom agreeing to increasing debt to finance their new generation
capacity, the introduction of independent power producers should be better incentivised and the
purchasing of capacity staggered to compensate that taken off the grid from the decommissioning of
the current Eskom fleet. This would effectively change Eskom’s role from that of primary generation
supplier to that of owner and operator of the transmission- and some distribution infrastructure. As
operating the transmission lines in an equitable fashion is one of the functions of the ISMO, it
follows that there is a possibility that the ISMO could be established out of Eskom (Minister of
Energy, 2011). Should this come to pass, the power stations most recently added to the Eskom fleet
could then be privatised, and the proceeds of the sale invested into further reinforcement of the
transmission and distribution networks.
The recurring theme amongst the wealth of proposals for the future of the South African ESI
are a need for clear direction, adequate, stable supply and a grid that is robust and adaptable. Unless
the failing EDI is repaired, the market structure of the ESI is of little consequence. Similarly,
insufficient supply to meet the demands of the system would be detrimental to a well-functioning
grid. Therefore, the EDI and generation capacity should ideally grow concurrently, and not
independently, as it has and continues to today.
VI. Conclusion
The electricity supply industry in South Africa experienced much the same issues of overbuild and
subsequent contraction prior to 1994 and surplus generation remained after the political revolution.
In accordance with the 1998 White Paper on Energy, unbundling of Eskom was attempted through
the encouragement of private sector participation and restructuring of the electricity distribution
industry into six regional electricity distributors. The REDs failed, and the private sector did not
respond as anticipated. A temporary decree which prohibited Eskom from expanding supply capacity
caused a delay in the procurement of new capacity, which led to load shedding in 2008. The
recovery has not been without problems. The vast array of legislature and organisations set up to
enforce them and deal with the issue illustrates how the shortage is not a purely technical problem,
and that legislation alone is insufficient to address it. Much socio-political pressure is needed to
induce any substantial action, and a champion for the cause as well as a coherent suite of policy is
desperately needed. Better communication of information to the public is also needed to adequately
explain how the need for load shedding arises, and the measures that are implemented before
resorting load shedding. Recommendations have been made for ameliorating the supply shortages,
including the amendment of policy to allow for expedited introduction of REIPPPs and cogeneration.
While no evidence exists to suggest that competition is necessarily better, the need for restructuring
and re-appropriation of power in the ESI is apparent. Several power stations in Eskom’s existing fleet
will be nearing the end of their lives soon, and with their long-term credit rating recently reduced to
“junk-status,” Eskom will find it difficult to secure funding for new generation capacity. With the use
of appealing tariffs and tax incentives, it would likely be easier to attract private investors to finance
their own generation operations. To this end, it has been suggested that Eskom’s role be
transformed from that of the primary generation supplier to that of owner and operator of the
transmission system, with the additional responsibility of assisting struggling municipal distributors
to become financially viable. We hope that society can apply the political pressure as peacefully as it
has in the past. While competition may well be beneficial a unique solution is needed for the unique
problems that face the South African Electricity Supply Industry.
REFERENCES
BURKHARDT, P. (2015). SA mulls giving credit for rooftop solar electricity. [Online] Available from: http://www.moneyweb.co.za/uncategorized/sa-mulls-giving-credits-for-rooftop-solar-electric/. (Accessed: 28 March 2015).
CREAMER, T. (2015). Eskom confirms Kusile, Ingula schedule slippages. [Online]. Available from: http://www.engineeringnews.co.za/article/eskom-confirms-kusile-ingula-schedule-slippages-2015-01-30. (Accessed: 28 March 2015).
DEPARTMENT OF ENERGY. (2011). Electricity Regulations for New Generation Capacity. [Online]. Available from: http://new.nersa.org.za/SiteResources/documents/Electricity%20Regulations%20on%20new%20generation%20capacity.pdf. (Accessed: 18 March 2015).
EBERHARD, A. (2007). The Political Economy of Power Sector Reform in South Africa. The Political Economy of Power Sector Reform. Cambridge University Press, Cambridge.
EBERHARD, A. (2012). The REDs are dead. [Online] Available from: http://www.gsb.uct.ac.za/files/TheRedsaredead.pdf. (Accessed: 21 March 2015).
ESKOM. (2015). Power Stations and Pumped Storage Schemes. [Online] Available from: http://www.eskom.co.za/Whatweredoing/ElectricityGeneration/PowerStations/Pages/Power_Stations_And_Pumped_Storage_Schemes.aspx. (Accessed: 21 March 2015).
ESKOM. (2014). Integrated report. [Online] Available from: http://integratedreport.eskom.co.za/dow-pdf.php. (Accessed: 21 March 2015).
DEPARTMENT OF MINERALS AND ENERGY. (1998). White Paper on the Energy Policy of the Republic of South Africa. [Online] Available from: http://mfma.treasury.gov.za/MFMA/Guidelines/whitepaper.pdf. (Accessed: 18 March 2015).
JOFFE, H. (2012). Challenges for South Africa’s Electricity Supply Industry. Focus. 64.
KUNI, D. (2012). Roadmap to a thriving Electricity Supply Industry in South Africa. Focus. 64.
NATIONAL ENERGY REGULATOR OF SOUTH AFRICA. (2008). Inquiry into the National Electricity Supply Shortage and Load Shedding. [Online] Available from: http://www.ameu.co.za/Portals/16/Documents/Elec%20Supply/NERSA%20Report%20on%20supply%20shortage%20and%20load%20shedding%20-12May2008.pdf. (Accessed: 18 March 2015).
LLOYD, P. (2012). Restructuring South Africa’s Electricity Supply Industry. Focus. 64.
LOVINS, A. B. (1976) Energy Strategy: The Road Not Taken? Foreign Affairs. 55(1).
MARQUARD, A. (2006). The origins and development of South African energy policy. (Doctoral dissertation, University of Cape Town).
MINISTER OF ENERGY. (2011). Independent System and Market Operator Bill. Government gazette.34289
NEL, S. (2012). Transforming the Energy Supply Industry. Focus. 64.
PATON, C. (2015). ANC opts to keep Eskom in one piece. [Online] Available from: http://www.bdlive.co.za/business/energy/2015/02/02/anc-opts-to-keep-eskom-in-one-piece. (Accessed: 24 March 2015).
PUBLIC PROTECTOR SOUTH AFRICA. (2008). Report on a preliminary investigation relating to electricity load shedding implemented by Eskom Holdings Limited. [Online] Available from: http://www.pprotect.org/library/investigation_report/Load%20shedding%20Report.pdf. (Accessed: 18 March 2015).
SOUTH AFRICAN PRESS ASSOCIATION. (2015). Eskom downgraded to junk: S&P. [Online] Available from: http://businesstech.co.za/news/general/82943/eskom-credit-rating-downgrade-to-bb-sp/. (Accessed: 28 March 2015).
STATISTICS SOUTH AFRICA. (2015). Electricity generated and available for distribution (Preliminary). [Online] Available from: http://www.statssa.gov.za/publications/P4141/P4141December2014.pdf. (Accessed: 20 March 2015).
TROLLIP, H., BUTLER, A., BURTON, J., CAETANO, T., GODINHO, C (2014) Energy Security in South Africa. Cape Town, MAPS.