MaxCell First order Installation Reports
MTNL Mumbai
Amit DubeyMaxCell Market Manager - India
Date: 13th May 2010End User: MTNL MumbaiInstaller: MillikenVenue: MTNL, Chembur, MumbaiClassification: Overlay
Amit DubeyMaxCell Market Manager - India
Chembur, MTNL Mumbai
Before After MaxCell installation
Section Conduit ID, mm
Existing Cable or sub duct OD mm
Pull Length
M
Sweeps, degrees
MaxCell Installations Cable Installation Final Fill
RatioStyle Time, min
Tension, kgs
OD, mm Time, min
Tension, kgs
1 100 empty 223 Straight 3 x 5621-3 25 4 Man
Hand Pull
4 x 12 & 2 x 14mm
45 4 Man HP
9.7%
2 100 Empty 223 Straight 3 x 5621-3 25 4 Man
Hand Pull
2 x 14 & 2 x
18mm
50 4 Man HP 10.4 %
3 100 Empty 223 Straight 3 x 5621-3 25 4 Man
Hand Pull
2 x 12mm
25 4 Man HP 2.9 %
Remarks:-
-This was the first order installation of MaxCell in Chembur, MTNL Mumbai through contractors.
- There were four 110-100mm empty conduit and have to installed 27 nos. of cables (combination of 12 & 18mm).
-There were an hand hole in between manhole. it is 89m from one and 134m from other manhole. Contractor first installed rope in all four conduit.
- Successfully installed 3 nos. of EM 5621-3 three cell MaxCell in three of 110-100mm conduit while fourth conduit left out for future use.
-Deployed 6 cables (2 x 14mm & 4 x 12mm) in two EM5621-3 MaxCell in first 110-100mm conduit. 4 cables (2x 18mm & 2 x 14mm) in second 110-100mm conduit. And 2 x 12mm cables in third 110-100 conduit.. Fourth for future use.
-
Date: 13th May 2010End User: MTNL MumbaiInstaller: MillikenVenue: MTNL, Chembur, MumbaiClassification: Overlay
Amit DubeyMaxCell Market Manager - India
Installation Results:
Date: 13th May 2010End User: MTNL MumbaiInstaller: MillikenVenue: MTNL, Chembur, MumbaiClassification: Overlay
MaxCell praparation
Successful installing cables
Amit DubeyMaxCell Market Manager - India
Cable Pulling
Date: 14th May 2010End User: MTNL MumbaiInstaller: MillikenVenue: MTNL Kandiwali Exchange, MumbaiClassification: Overlay
Amit DubeyMaxCell Market Manager - India
Kandiwali, MTNL Mumbai
Before After MaxCell installation
Section Conduit ID, mm
Existing Cable or sub duct OD mm
Pull Length
M
Sweeps, degrees
MaxCell Installations Cable Installation Final Fill
RatioStyle Time, min
Tension, kgs
OD, mm Time, min
Tension, kgs
1 100 empty 130 Straight 3 x 5621-3 35 1 Man
Hand Pull
1 x 18 15 2 Man HP
3.2 %
Remarks:-
-In this starch only one 110-100mm conduit was available while apart from two manhole there were 12 & 24 nos. of 110-100mm conduit available.
- 50m of this stretch was along with bridge while remaining was under the foot path.
- We installed 3 nos. of EM 5621-3 MaxCell and further deploy one 18mm cable in one of the cell successfully.
-Now there are provision of 8 nos of cable to installed in future.
Date: 14th May 2010End User: MTNL MumbaiInstaller: MillikenVenue: MTNL, Kandiwali Telephone Exchange, MumbaiClassification: Overlay
Amit DubeyMaxCell Market Manager - India
Installation Results:
Date: 14th May 2010End User: MTNL MumbaiInstaller: MillikenVenue: MTNL, Kandiwali Telephone Exchange, MumbaiClassification: Overlay
MaxCell getting enter
Amit DubeyMaxCell Market Manager - India
Passing through handhole
Successful Installed