may 4, 2005

37
Robert G. Ethier, Ph.D. Director, Market Monitoring May 4, 2005 ISO New England State of the Market Report 2004

Upload: marcus

Post on 17-Jan-2016

47 views

Category:

Documents


0 download

DESCRIPTION

ISO New England State of the Market Report 2004. May 4, 2005. Robert G. Ethier, Ph.D. Director, Market Monitoring. Overview of 2004. The New England markets continued to be competitive in 2004, operating as designed with no evidence of significant exercise of market power Low summer loads - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: May 4, 2005

Robert G. Ethier, Ph.D.

Director, Market Monitoring

May 4, 2005

ISO New England State of the Market Report 2004

Page 2: May 4, 2005

2

Overview of 2004

• The New England markets continued to be competitive in 2004,

operating as designed with no evidence of significant exercise

of market power

• Low summer loads– Summer peak was 2.3% lower than 2003

– Annual total load was 1.3% higher than 2003

• Surplus of generation region-wide

• Regional surplus consistent with:– Competitive market results

– Uneconomic environment for new investment

Page 3: May 4, 2005

3

2004 Is 5th Full Year of Market Operations

• Over that time, some important improvements:– 9,480 MW of new, clean, generation

– Average heat rate of oil and gas units has declined by 5.6%

– Unit availability has increased from 81% to 88%

– Fuel Adjusted spot prices have decreased 5.7%

– Improved regulation performance has decreased requirements by 29%

• Market enhancements led to efficiencies– SMD in 2003

– Biggest change in 2004 was introduction of Forward Reserve Market

• Resource Adequacy solution (LICAP) still needed

Page 4: May 4, 2005

4

Biggest Test for Markets in 2004: January Cold Snap

• Stressed New England energy infrastructure– Markets generally operated well

• Analysis of period led to numerous improvements– Improved information exchange between the ISO, gas pipelines and

electricity market participants

– Additional dual-fuel operating flexibility

– Revised market timing under extreme conditions

• On-going work• LMPs need to consistently reflect marginal needed resources

– 2005 results much improved

• Need increased availability incentives

Page 5: May 4, 2005

5

Biggest Challenges Ahead: Out-of-Market Payments

• Daily out-of-merit operations due to voltage and 2nd

contingency coverage– Transmission upgrades needed

– Unit flexibility

• Mainly have units with high economic minimums/ long run times

• Need additional quick start units in constrained areas

• Large increase in Reliability Agreements– 2,200 MW under agreements, 4,625 MW additional seeking treatment

– Approximately 20% of system capacity

– Need long-term resource adequacy solution

– Reliability Agreements do not send signals for most existing generators

and do not provide incentives for new entry

Page 6: May 4, 2005

6

Fuel Prices and Energy Prices

• Fuel-Adjusted prices lower than previous years

• Electricity prices were driven by high fuel prices, the largest

component of generators’ marginal costs– Natural gas prices were 5% percent higher than 2003 on average, and

82% higher than 2002

– Nearly half of New England capacity is gas-fired or gas capable

– These units were marginal in approximately 86% of pricing intervals

• Electricity prices peaked in January as natural gas prices rose

Page 7: May 4, 2005

7

Daily Average Real-Time System Price of Energy vs.Variable Production Costs*

$0

$25

$50

$75

$100

$125

$150

$/M

Wh

Variable Cost Gas Plant

Variable Cost Oil Plant

System RT Energy Price

*System Energy Prices and Variable Cost of Gas Plant exceeded $150 on J anuary 14 and 15.

Page 8: May 4, 2005

8

Actual and Fuel-Adjusted Average Real-Time Electric Energy Prices, 2000 - 2004

$43.03

$37.52

$53.40 $54.44

$48.60$46.65

$43.51$45.95 $45.95

$43.33

$0

$10

$20

$30

$40

$50

$60

2000 2001 2002 2003 2004

$/M

Wh

Actual Load-Weighted Electric Energy Price

Load-Weighted Electric Energy Price Normalized to Year 2000 Fuel Price Levels

Page 9: May 4, 2005

9

Marginal Input Fuels in Real-T ime, 2004

Per

cent

of

Tim

e

0%

10%

20%

30%

40%

50%

60%

Page 10: May 4, 2005

10

Energy Prices in 2004

• Next slides show real-time price duration curves for 2001 to 2004– Percentage of hours when load-weighted price for New England is greater than

each given price level

• 2004 price levels generally similar to 2003

• More price spikes than in 2003, and fewer than in 2002 and 2001:– Real-time prices exceeded $500 in 3 hours, compared to 1 hour in 2003, 4

hours in 2002 and 15 hours in 2001

– Infrequent price spikes primarily due to milder summer weather and relatively

robust capacity margins

• Scarcity pricing provisions not triggered

• Day-Ahead Hub prices $1.59/MWh higher than Real-Time prices

Page 11: May 4, 2005

11

System Price Duration Curves, Prices < $2002001-2004

$0

$25

$50

$75

$100

$125

$150

$175

$200

Percent of Hours

En

erg

y P

rice

($/

MW

h)

2001

2002

2003

2004

System Price is single Energy-Clearing Price for Interim Market Period ending Feb. 28, 2003, and load-weighted Real-Time Energy Market LMPs for Mar. 2003 - Dec. 2004.

Page 12: May 4, 2005

12

System Price Duration Curves, Prices in Most Expensive 5% of Hours

2001-2004

$0

$100

$200

$300

$400

$500

$600

$700

$800

$900

$1,000

$1,100

0% 1% 2% 3% 4% 5%

Percent of Hours

En

erg

y P

rice

($/

MW

h)

2001

2002

2003

2004

System Price is single Energy-Clearing Price for Interim Market Period ending Feb. 28, 2003, and load-weighted Real-Time Energy Market LMPs for Mar. 2003 - Dec. 2004.

Page 13: May 4, 2005

13

Daily Average Hub LMPJanuary - December 2004

DA Hub LMP RT Hub LMP

$/M

W

$0

$50

$100

$150

$200

$250

$300

$350

Date

01/0

1/20

0402

/01/

2004

03/0

1/20

0404

/01/

2004

05/0

1/20

0406

/01/

2004

07/0

1/20

0408

/01/

2004

09/0

1/20

0410

/01/

2004

11/0

1/20

0412

/01/

2004

01/0

1/20

05

Page 14: May 4, 2005

14

2004 Average Nodal Prices, $/MWh Day-Ahead

Real-Time

Page 15: May 4, 2005

15

All-in Energy Prices

• Following slides shows “all-in” prices – Cost of energy, ancillary services, capacity, and uplift costs

• Energy is load-weighted average of locational real-time prices

• Ancillary services include reserves and regulation prior to SMD,

regulation in 2003, and regulation and forward reserves in 2004

• All-in prices rose slightly in 2004– Energy costs similar in 2003 and 2004

– Uplift and ancillary services costs higher in 2004• Introduction of the Forward Reserve Market and an increase in VAR tariff

reliability payments

– Capacity costs very small in 2004

Page 16: May 4, 2005

16

New England Wholesale Electricity Market Cost Metric:Energy*, Capacity, Ancillary Services, and Uplift Costs: $/MWh

2001, 2002, 2003, and 2004

$0

$10

$20

$30

$40

$50

$60

2001 2002 2003 2004

Energy Uplift Capacity Ancillary Services

*Energy: Interim Markets period = ECP * System Load, SMD period = RT Load Oblig * RT LMP.

Page 17: May 4, 2005

17

New England All-In Price Metric ($/MWh)

$/ MWh 2003 % of Tot. 2004 % of Tot.Energy $53.08 95.9% $54.75 96.0%Uplift $0.71 1.3% $1.27 2.2%Capacity $0.97 1.8% $0.06 0.1%Ancillary Services $0.60 1.1% $0.96 1.7%Total $55.36 100.0% $57.05 100.0%

Page 18: May 4, 2005

18

Capacity Auction Clearing PricesApril 2003 - December 2004

$0

$50

$100

$150

$200

$250

$300

$350

$400

$450

Obligation M onth

$/M

W-M

on

th

Supply Auction Clearing Price

Demand Auction Clearing Price

Page 19: May 4, 2005

19

Uplift Payments by Quarter, 1999 - 2004

$0

$10,000,000

$20,000,000

$30,000,000

$40,000,000

$50,000,000

$60,000,000

$70,000,000

$80,000,000

$90,000,000

1999

Q2

1999

Q3

1999

Q4

2000

Q1

2000

Q2

2000

Q3

2000

Q4

2001

Q1

2001

Q2

2001

Q3

2001

Q4

2002

Q1

2002

Q2

2002

Q3

2002

Q4

2003

Q1

2003

Q2

2003

Q3

2003

Q4

2004

Q1

2004

Q2

2004

Q3

2004

Q4

RMR ORC

Economic ORC

NCPC

Energy Uplift

Congestion Uplift Costs

Page 20: May 4, 2005

20

Load Profile

• Next slides show annual load duration curves for New England– Percentage of hours in which the load is greater than the level

indicated on the vertical axis

• Mild summer weather in 2004 – Peak days had far less impact on average prices than year with normal

weather due to absence of severe price spikes • 2003 had a similar pattern

• Only 2 hours when actual loads exceeded 24,000 MW– Compared to 19 hours in 2003 and 34 hours in 2002

• There were 177 hours when loads exceeded 21,000 MW – Compared to 200 hours in 2003 and 263 hours in 2002

Page 21: May 4, 2005

21

New England Hourly Load-Duration Curves2001, 2002, 2003, 2004

8,000

10,000

12,000

14,000

16,000

18,000

20,000

22,000

24,000

26,000

Percent of Hours

Sys

tem

Lo

ad (

MW

)

2004

2003

2002

2001

Page 22: May 4, 2005

22

New England Hourly Load-Duration Curves, Top 5% of Hours2001, 2002, 2003, 2004

8,000

10,000

12,000

14,000

16,000

18,000

20,000

22,000

24,000

26,000

0% 1% 2% 3% 4%

Percent of Hours

Sys

tem

Lo

ad (

MW

)

2004

2003

2002

2001

Page 23: May 4, 2005

23

Demand Response

• New England offers range of price and reliability-based

response programs

• Total enrollment around 350 MW at end of 2004

• Total hours of curtailment increased in 2004 due to increased

number of events– Many in winter months due to high gas prices

– 4,223 MWh in 2003

– 13,475 MWh in 2004

• Program enrollment roughly constant from 2003 to 2004– Need much greater levels of demand response in the long run

Page 24: May 4, 2005

24

Demand Response ParticipationTotal MW Enrolled in Demand Response Programs

0

50

100

150

200

250

300

350

400

450

MW

Page 25: May 4, 2005

25

Major Market Changes: Forward Reserve Market

• What is the Forward Reserve Market?– Advanced purchase of fast-start capacity– 10-minute non-spin and 30-minute non-spin– Units must offer above a strike price based on natural gas

costs– Liquidated damages incent delivery

• Market experienced adequate participation and reasonable outcomes

Page 26: May 4, 2005

26

Forward Reserve Market: Results and Observations

• Purchased approximately 1,900 MW each auction

• Clearing prices of $4.08 to $4.50/KW-Mo.

• Auction worked

– Unit availability good

– “Right” resources won

– Participants responded to incentives by adding dual-fuel

capability, buying firm gas, and offering a less efficient

combined-cycle as 2 peaking units

Page 27: May 4, 2005

27

Economic Incentives for New Investment

• In long-run equilibrium, market should support the entry of new generation – Need sufficient net revenues (revenue in excess of production costs) to

finance new entry

• We calculated the net revenue the markets would have provided to different types of units in 2004– A gas-fired combined-cycle “CC” (heat rate= 7,000)– A gas-fired combustion turbine “GT” (heat rate=10,500)

• Combustion-turbines units that participated in the Forward Reserve Market had increased revenues over 2003

Page 28: May 4, 2005

28

Economic Incentives for New Investment (Continued)

• Net revenue for gas-fired combined-cycle units lower than

2003 and 2002, despite higher Energy and All-In prices in 2004– Due to gas price increases

– Also due to new capacity added in 2002 and 2003

• Indicates insufficient net revenue from market to support

investment in new GT or CC units– GT would only recover 66% - 88% of estimated 2004 annual fixed

costs

– CC would only recover 50% -64% of estimated 2003 annual fixed costs

• Existing units also financially stressed– Consistent with surge in Reliability Agreements

Page 29: May 4, 2005

29

Net Revenue Metric 2004

Energy revenues are calculated as the revenue per MW of a hypothetical unit assumed to be dispatched during each hour when the market clearing price equals or exceeds the unit's marginal cost, adjusted for a 5% forced outage rate. Revenues are calculated based on the real-time Hub LMP. Capacity sales revenue is based on ISO ICAP Supply Auction clearing prices.Ancillary services revenue is Regulation for combined-cycle, and Regulation and Forward Reserves for combustion-turbine. Forward Reserve revenues equal auction revenues minus average penalties.

Combined Cycle

Combustion Turbine

Year CT Energy Capacity Ancillary CT Total CT Run Hours High Low2002 $22,387 $12,000 $1,781 $36,168 1825 $80,000 $60,0002003 $11,293 $1,972 $1,767 $15,032 773 $80,000 $60,0002004 $8,058 $360 $44,466 $52,884 620 $80,000 $60,000

Estimated Annual Fixed Cost Range

Year CC Energy Capacity Ancillary CC Total CC Run Hours High Low2002 $79,006 $12,000 $1,781 $92,787 7115 $125,000 $100,0002003 $72,739 $1,972 $1,767 $76,478 5741 $125,000 $100,0002004 $62,697 $360 $1,350 $64,407 5420 $125,000 $100,000

Estimated Annual Fixed Cost Range

Page 30: May 4, 2005

30

MW Covered by Reliability Agreements

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

2002 2003 2004 2005 1st Qtr 2005, includingpending

MW

Page 31: May 4, 2005

31

Forced Outages• Next slide presents trends in forced outage rates from the

beginning of the New England Markets– Forced outage rate is percentage of time capacity is unavailable due to

full or partial forced outages– The decrease in availability 1996-1998 was due to the extended outages

of several nuclear units

• Total outage rates have declined substantially following implementation of markets in New England– Consistent with deregulated market incentives to maximize availability– Previous analysis suggests initial high outage rates in new combined-

cycle units • New England has many new combined-cycle units • Improvements in outage rates may be expected as these units mature

Page 32: May 4, 2005

32

Average Generator Outages as a Percentage of Total System Generating Capacity

0%

5%

10%

15%

20%

25%

1996 1997 1998 1999 2000 2001 2002 2003 2004

% o

f C

ap

ac

ity

Planned Outages as a % of Capacity Unplanned Outages as a % of Capacity

Page 33: May 4, 2005

33

Congestion and Marginal Loss Costs

• Following slide shows average hourly differences between

LMPs at Hub vs. each load zone – Differences reflect impact of congestion and marginal losses on LMPs

• Maine had negative congestion – Due to export constraints and negative marginal losses

• Connecticut had significant positive congestion– Periodically import constrained

• Note that these numbers understate congestion costs– Exclude significant out-of-merit local operating reserve costs

Page 34: May 4, 2005

34

Average Hourly LMP Difference from Hub2004

ME NH SEMA RINEMA WCMA VT CT

$/M

Wh

$-6.00

$-5.00

$-4.00

$-3.00

$-2.00

$-1.00

$0.00

$1.00

Day-Ahead Real-Time

Page 35: May 4, 2005

35

Competitive Benchmark Analysis

• Evaluated actual energy clearing price and cumulative bid-in

capacity – Ascending price (“aggregate bid-intercept”) vs marginal cost-based

simulated dispatch

• Simulated dispatch designed to produce estimate of perfectly

competitive market outcome– Estimate is subject to an unknown error

• Metric is % increase over “perfect” market outcome – “Quantity-weighted Lerner Index”

• Market continues to function well – Modest differences from competitive baseline

Page 36: May 4, 2005

36

Competitive Benchmark Results: 2003 vs. 2004

Quantity-Weighted Lerner I ndex Price Measure

2004 Price

($/ MWh) 2003 2004

Competitive Benchmark Price $54.49

Real-Time Hub Price $48.95 9% 3%

Aggregate Bid-Intercept Price $52.13 -4% -6%

Page 37: May 4, 2005

37

Conclusions

• 2004 characterized by low summer loads and ample generation

• The New England markets continued to perform competitively– No evidence of significant economic or physical withholding

• Cold Snap experience led to important market improvements

• Little incentive to add capacity, even in constrained areas– Participants responded to Forward Reserve Market signals

• Out-of-market payments require on-going attention– LICAP solution needed

• Additional Demand Response needed