mccook main tunnel system connection to tarp mainstream tunnel on right chicago tunneling overview...

69
CHICAGO TUNNELING OVERVIEW & RESERVOIRS CONNECTING TUNNELS Faruk Oksuz, P.E. & Cary Hirner, P.E. McCook Main Tunnel System connection to TARP Mainstream Tunnel on right

Upload: phungkiet

Post on 19-Aug-2018

231 views

Category:

Documents


1 download

TRANSCRIPT

CHICAGO TUNNELING OVERVIEW & RESERVOIRS CONNECTING TUNNELS

Faruk Oksuz, P.E. & Cary Hirner, P.E.

McCook Main Tunnel System connection to TARP Mainstream Tunnel on right

Welcome to Chicago

• Windy City

• Lake Front Attractions

• Museum Campus - Art Institute

• Navy Pier

• Maggie Daley Park / Grant Park

• Michigan Avenue

• Cubs Game

• Choose CTA Blue Line into the City, and CTA Red Line to Wrigley Field

• McCook Reservoir & Tunnel Project Visit on Thursday, August 17

Chicago Tunneling Overview

• A True Tunneling Town

• Tunneling Geology

• Tunneling Aspects Unique to Chicago

• TARP McCook Reservoir Connection

• TARP Thornton Composite Reservoir Thorn Creek Diversion Tunnel Connection

• Q & A

Chicago has more tunnels than most other cities in the world. Flat topography and favorable ground conditions inspired tunnels to be built and utilized since 1866 with Lake Michigan Water Intake. In 1899, the Illinois Telephone and Telegraph Company secretly built the first utility and railway tunnel (Chicago Tribune).

Chicago Tunnels

• 1899 to 1933 - Nearly 60 miles of freight/utility tunnels - about 45 miles is still in use for utilities -power, gas, cable, fiber optic, data, etc.

• City of Chicago, Water Tunnels since 1866

• CTA’s transit tunnels

• 550 miles of MWRD interceptors with tunnels

• 1972 to 2006 – 110 miles of tunnels for TARP, ranging from 8 to 33-ft in diameter

• Miles & miles of more other raw water and sewer, stormwater tunnels

Over 300 miles of large (>8-ft) diameter tunnels in and around the City

MWRD Thorn Creek Diversion Tunnel , a 22-foot, unlined hard rock TBM tunnel excavated by Jay Dee for flood water diversions into Thornton Transitional Reservoir in early 2000, and later lined with concrete by Walsh in 2014.

Tunnels are Long-Term & Sustainable Solutions

• Tunnels have been serving Chicagoland with a 100-year plus service life

• Benefits of shortest distance to get from point A to B, and without interfering with rivers, roadways, railways, and utilities

• Gravity conveyance benefits are maximized -no pumping or energy needed to operate except terminus pump stations

• Chicago’s below ground and “forgotten” marvels until the famous Chicago Tunnel Flood in 1992

Tunnels are very integral part of the water supply and environmental protection for Chicagoland’s 14 million population, including residential, commercial, and industrial users.

There are so many tunnels in Chicago

• Over the past 130 years, tunnels were built for water, coal freight, railways, utilities, river/railroad/roadway crossings, sewer, combined sewer overflows and flood management

• Tunnels have been a significant, and surely the most reliable and sustainable fabric of “Chicago’s Urban Living”

• Flat topography and ground conditions favorable for tunneling – hardpan/blue clay soils and Silurian Dolomite

• Water/wastewater infrastructure, Lake Michigan, and environmental protection - nowhere for water to run

• Dense and compact urban setting

• Maybe the Windy City folks are seeking shelter from cold weather, too

Chicago Tribune, Tempo, August 2, 2007 – P. T. Reardon

1860 1870 1880 1890 1900 1910 1920 1930 1940 1950 1960 1970 1980 1990 2000 2010 2020

Chicago Discovered and Built Tunnels Since 1860s…

All resulted in best tunnel engineering and construction experience / projects

1866Lake Michigan Water Intake

1869River Crossings

1906Freight Tunnels

1943Subways

2004FermiLab Physics Tunnels

1985 - 2006TARP Phase I

2006 - 2017TARP Phase II(Reservoir Connections)

1899Utility/Railway Tunnels

1950Interceptors

2020 2025 2030 2035 …. ….

Future is also Looking Bright for Tunnels in Chicago

Tunnels continue to prove to be the most effective urban solutions, particularly for flood and CSO management

2020 – 2025 ?Downtown - O’Hare Airport Hyperloop Tunnel ?

2018 -MWRD, City of Chicago, Evanston - Water, Flood Management, CSO Tunnels

2020 - ?FermiLab Accelerator Physics Tunnels

2025 - ?Rail Tunnel Upgrades & New Ones

Tunneling Geology of Chicago Area

9

General Stratigraphy of the Chicago Area

William H.B., Geology of the Chicago Area, ISGS, 1971. 10

Major Geologic Formations Tunneling Aspects

Glacial Till Freight tunnels, rail tunnels, water and sewer tunnels, utility tunnels

Silurian Limestone/ Dolomite

TARP tunnels, water and sewer and utility crossing tunnels.

Maquoketa Shale Not used - limited underground aggregate mining and physics tunnels penetrate through

Galena Dolomite Underground aggregate mining

St. Peter Sandstone No tunnels or mining

Chicago’s Tunneling Geology

• Glacial Till – hardpan/blue clay, silt, sand, cobbles and boulders

• Silurian Dolomite - Joints and faults are vertical to near vertical, trending prominently N50oW to N50oE, mostly filled with clay/silt

• Silurian Dolomite - Bedding planes are tight, intermittent inflows are through open joints and faults, and bleeds as groundwater levels are drawn down

11

System Series Group or Formation

Thickness (ft) Lithology

Quaternary Pleistocene 0-125 Till, sand, gravel, clay, Silurian

NiagaranRacine 0-300 LimestoneSugar Run Dolomite

Alexandrian Joliet

Kankakee Dolomite with thin shale layers

ElmwoodWilhelmi

Ordovician Cincinnatian Maquoketa 160 – 200 ShaleChamplain Galena 120 - 180 Dolomite/Limestone

DunleithPlatteville DolomiteSt. Peter Sandstone

Favorable geology & ground for tunnels and reservoirs - record-breaking TBM performances

Existing Tunnels and Deep Quarries Provide Excellent Data Source for Rock Tunnels

• Abundance of existing data

• Historic reversal of rivers and construction of the Illinois-Michigan Canal

• Deep surface quarries and underground aggregate mines

• Previous tunnels

• Foundations for tall buildings, bridges, and roadways

• Predictable Ground Conditions

• Geotechnical drilling and testing needs are far less than other locations due to already existing data, uniformity of ground, and past tunneling experience

• GBRs are kind of “optional” as there is an overwhelming tunneling experience available to tunnel constructors

• Groundwater – mostly dealt by dewatering (panning and pumping) and lowered water table in rock

12

Tunneling Aspects Unique to Chicago Area

13

Design Completion4 to 8 months6 to 8 months3 to 6 Mos.Design Start

Hydraulics

Operations & Maintenance

Compliance

Easements/Permits

Geotechnical

Environmental

Traffic/Community

Tunnels & Shafts

Pump Stations

Gates & Valves

Diversion Works

Cost Estimates

Preliminary Schedule

Procurement

TUNNEL DESIGN PROCESS

ConfirmFacility Plans

Basis of DesignFinal DesignPlans-Specs GBR*/GDR

AdvertiseContract

Pre-design / VE Workshops

Design Validation Process

Plans & Specs Development

COST AND CONSTRUCTABILITY

RISK MANAGEMENT

Preliminary Engineering

Typical Tunnel Design Process

Tunnels Risk Management Process

Conveyance Tunnel Design Details

• Systems Operations

• Hydraulic sizing and alignment selection

• Geologic conditions

• Environmental conditions

• Groundwater conditions

• In-situ rock stresses and initial ground support

• Tunneling and permanent lining – typically two pass tunneling method

• Post-lining and grouting

• Surface connections, commissioning and startup

Plans, profile, specifications, reports, etc.

Tunnel Sizing and Alignment Selection

• System Hydraulics & Operational Flexibility

• Horizontal/Vertical Alignment Evaluation:

• Risks (technical, political, and contractual)

• Shaft locations

• Easements

• Capital and operating costs

• Geotechnical considerations

• Community impacts

• Proximity to sensitive structures

• Tunneling under rivers, wetlands, etc.

• Permits

• Constructability issues

Tunnel alignment and shaft location selections can benefit from innovative tools and solutions in a virtual reality environment.

Tunnel Cost Analysis

Benchmarking to Recent Chicago Tunnels:

• Des Plaines Inflow ~ $125M (bid)

• Albany Park ~ $62M (bid)

• McCook Main Tunnel ~ $132M (bid)

• Cost of diversion works, gates, pump stations, etc. can be substantial and skew per foot/diaestimates.

Diversion Works and Drop Shafts Designs

Vortex Drop Shaft (Milwaukee)Plunge Drop Shaft (Chicago)

CSO to Tunnel

River

CSO Outfall

Storage Tunnel

Drop Shafts

Consolidation Sewer

Regulators

Wet

Weather

Deep Tunnel Pump Station to WWTP

Working Shaft

Combined SewerTo WWTP

WWTP

CSO to Tunnel

Combined Flow

to WWTP and

Tunnel

BEDROCK

SOILS

Understanding of How Deep Tunnel Systems WorkCombined Sewers Overflow (CSO) Management Tunnels

Chicago TARP – Tunnel and Reservoir Plan

• Largest combined sewer overflow and flood management system

• Services Chicago downtown and 123 suburban communities

• 110 miles of rock tunnels, 8 to 33-ft dia., 170 to 300-ft deep

• 3 mega reservoirs – two excavated in rock

Chicago’s largest infrastructure undertaking for nearly four decades

21

McCook Reservoir

Thornton Reservoir

Chicago Tunnel and Reservoir Plan - TARP

Operation Cycle

1. Dry Weather

2. Wet Weather

3. Interceptors and Tunnels Full

4. Reservoir Full

5. Store, Pump out, Treat, and Discharge

How did MWRD build TARP ?

• Storage and gravity conveyance system

• Tunnel Boring Machines (TBM)

• Excavated 150 to 300 ft below ground, through limestone rock

• Lined with concrete

• Unique inlet/drop shaft layout

• Self cleaning systems

Mainstream Tunnel system was the largest (30-ft dia.) and the longest (40.5 miles) TBM tunnel in the U.S.

when completed in 1985.

Little Calumet Tunnel - TBM & Cutter Head

Open-face, hard-rock gripper TBMs

Silurian dolomite (~ 15 to 25 kpsi)

Record-breaking advance rates and continuous tunnel drives

Minimal groundwater or gas problems

Hard rock TBM assembly

(for illustration, typically done in underground)

Chicago Area Hard Rock Tunneling Experience Runs Deep

Drop shafts, diversions, pumping stations

• Plunge Drop or Chicago style drop shafts

• 250 + across TARP

• Up to 300 ft deep and

4 to 17-ft dia.

• 600 plus diversion structures

• 3 pumping stations

• 550 miles of interceptor sewers

26

McCook Reservoir

McCook Reservoir and Tunnel Systems

Distribution Tunnels &

Chamber

Main Tunnel &

Gates

Courtesy of USACE

Flow from Chicagoland

Outlet to Reservoir

Outlet to Stickney

Air Vent

Isometric Schematic No Scale

TARP Mainstream Tunnel (in service)

To McCook Reservoir

Main Gates

McCook Reservoir - Main Tunnel SystemFrom Mainstream Tunnel (Chicago)

To Mainstream Pump Station & Stickney Treatment Plant

Flow in both directions

McCook Main Tunnel System Layout

29

To MS Pump Station & Stickney WRP

McCook Reservoir

From Mainstream TARP

Gates

Concrete Bulkhead

ConnectionGate / Construction Access ShaftPortal / Energy

Dissipation

Reservoir Region

Bifurcation & Transition Region

TAPR / Mainstream TunnelConnection Region

Concrete Bulkhead

McCook Main Tunnel System – Plan & Profile

Main Tunnel System - Gate Chamber Layout

Numerical Modeling Using UDEC (Universal Distinct Element Code)• Applicable for tunnels and shafts with circular

and horseshoe shape geometries

• Incorporates existing tunnel lining and support details

• Two dimensional numerical program based on the distinct element method for discontinuummodeling. UDEC simulates the response of soils and discontinuous rock mass subjected to either static or dynamic loading

• Influence of water pressure

• Cohesion and friction of intact soil/rock and discontinuities.

• Shear strength of planar and rough surfaces, filled joints, faults, etc.

Successfully performed for the Chicago area tunnels. 32

Unique Features - Connection to Existing TARP Mainstream Tunnel

• Optimized for hydraulics to manage large flows (30,000 cfs) and velocities (up to 35 fps)

• Live connection while TARP tunnel is kept in service

• 16.5 ft radius sides allows smooth transition to cross-section of 33 ft diameter Mainstream Tunnel

• Flat top maximizes the height of the profile across the connection section and flow from Mainstream Tunnel is forced downwards

• Reducing the height, but increasing the width results in a flare for a smoother turning of the flow into the Main Tunnel and Reservoir

33

Horizontal sweep radius = 7.5ft

Horizontal sweep radius = 30ft

Horizontal sweep radius = 5ft

33.6ft 34.5ft 35.8ft 37.6ft

31.375ft

29.75ft

28.125ft

26.5ft

33ft

Section A-A Section B-B Section C-C Section D-D Section E-E

Section F-F

Joint smoothed to 1.5ft radius

Sides = 16.5ft radius

Corners = 4ft radius

General Detail for Sections B-B to E-E

A

A

B

B

E

E

C

C

D

D

Elevation

Plan

F

F24ft 24ft12ft 12ft

Mainstream Tunnel Connection - Elliptical Mitre

Velocity on central plane

Region with sub-atmospheric pressure

Maximum velocity = 48 fpsMinimum absolute pressure = 0.6atm

Note separation of flow at connection

High Head Wheel Gates for Tunnels

35

Large gates allow for hydraulic controls in tunnels, systems operations and storage optimization, and maintenance of reservoirs and tunnels

Factory Acceptance Tests for gates for McCook

McCook Main Gates Design - Computational Fluid Dynamics (CFD) Modeling

• High head wheel gates for tunnels are unique to Chicago (three gate systems installed, fourth is under construction)

• McCook Gates - total of six (6) 29-ft high x 14.5-ft wide wheel gates inside 88-ft diashaft and bifurcated tunnel

• Operates under up to 300 psi pressure

• Separate design, fabrication, and installation contracts

MCCOOK MAIN TUNNEL SYSTEM CONSTRUCTION

• Connects the Mainstream Tunnel to McCook Reservoir

• 1,600-ft long, 33-ft finished diameter tunnel

• 6 mega gates underground to manage the flow in and out of reservoir

• Sequential (or NATM) excavations using drill & blast

• Construction complete in 2017

DROP Structures – BIM & 3D CONSTRUCTION RENDERINGs

39Construction Shaft and Site Layout

40Gate Chamber and tunnel heading excavation

41Excavated tunnel and reinforcement (concrete forms in the background)

42Concrete form work

Bifurcation Steel Liner

43

DRILL & BLAST PLAN

• Sequential (or NATM) excavation included top heading (upper half of tunnel) removal followed with lower bench excavation

• One unique drill & blast excavation layout included a single round full 36-dia face and 15-feet long section prior to connection to Mainstream Tunnel

44

45

Lined sections of the tunnel and gates bifurcation area

Bifurcation Steel Liner

• 3.5 million lbs of fabricated steel

• 32 Fabricated Sections

• Welding

• Shop Welds

• 5,300lf Full Penetration Weld

• 22,000lf fillet welds

• Field Welds

• 5,000lf Full Penetration Weld

• Shipments

• By Fabricator – 48 Permit loads (Missoula to Chicago)

• Average shipment size 16ft Wide x 35ft Long x 13.5ft Tall

47

Steel liner installation around gate openings with tolerance less than ½-inch over 60-ft height

48Gate chamber concrete placement

Mainstream Connection - Top Heading and Construction Platform in TARP tunnel

Mainstream Connection – Upstream Cofferdam in Tunnel and Lining Work

Mainstream Connection – Completed.

52Working together, site visits and inspections

Partnering

• Bi-monthly partnering meetings facilitated by Kiewit

• Discussion of outstanding issues, resolutions, and action items

• Participants include USACE, MWRD, Kiewit and Black & Veatch

• Followed by site visits as needed.

Thornton Reservoir Creek Tunnel • Tunnel structural integrity modeling – predictive

approach

• Geology and geotechnical (existing borings, tunnel construction data)

• Supplemental soil borings, wells, piezometers, falling head and pump tests, and dye testing to characterize ground conditions and permeability of soils/rock

• Evaluate any signs of movements/ground losses in vicinity of shafts and tunnels

• Instrumentation and monitoring plan during dewatering

• Emergency Response Plan

54

MWRD’s Thorn Creek Tunnel – Example of an unlined rock tunnel. B&V designed and implemented concrete lining and contact grouting program for this 3,800 feet long tunnel rehab.

Thornton Composite Reservoir

• Serves TARP Calumet System and also designed

to capture Thorn Creek over-the-bank flood

waters when Transitional Reservoir is

decommissioned

• Key components - groundwater protection

system, connecting tunnels and gates to TARP

system and a roller-compacted concrete (RCC)

dam

• Dewaters to Calumet Pump Station and Water

Reclamation Plant

Thornton Composite Reservoir received the 2016 Project of the Year Recognition and Award by the American Public Works Association (APWA)

Thornton Composite Reservoir and Thorn Creek Diversion Tunnel in foreground, TARP tunnels, drop shafts & Calumet WRP in background

Thornton Composite Reservoir

• 7.8 BG Reservoir (24,100 acre-feet)

• Allocation: 4.8 BG CSOs and 3.0 BG Thorn Creek storm water

(courtesy MWRDGC)

Thornton Composite Reservoir

• Completion of aggregate mining

• Perimeter Grout Curtain

• Roller-Compacted-Concrete (RCC)

Dam

• TARP Indiana Avenue Tunnel

Connection and Main Gates

• Thorn Creek Tunnel Connection

and Reservoir Preparations

North Lobe

Existing Mainstream Tunnel

Existing Dewatering Tunnel

Existing Diversion Tunnel

Gates

Connecting Tunnel

Grout Curtain

Drainage Adit

Tunnel PlugTunnel Plug

Thorn Creek Tunnel

Visitor Parking & Working Pad

Quarry Plugs

Tollway Grout Curtain

Tollway Dam

Thorn Creek Diversion Tunnel Connection to Thornton Composite Reservoir

Thorn Creek Connection Tunnel

• 1,075-ft long, 20-ft dia, concrete-lined tunnel

• 3,870 ft concrete lining of existing diversion tunnel (20-ft dia)

• Drop shaft with deaeration chamber and vent shaft, small energy dissipation apron at

tunnel outlet

Thorn Creek Connection Tunnel

3D-View

Perimeter Grout Curtain

• Inclined - double row

• Primary, Secondary, and

Tertiary boreholes

• Maximum depth of 500 ft

• Balanced-stabilized grout

mixes

• Automated grout control

systems

Grout Curtain Installation

Comparison of Water Pressure Testing vs. Pressure Grouting

Pressure GroutingDownhole Geophysics

Grout Takes

Water Takes

Drainage Adit Conversion

• Reinforced concrete tunnel plugs at both ends

• Drain holes to increase effectiveness

• Drilled upward at 30-ft intervals along aditcrown

• Inclined 30o from vertical to better intercept joints

• 10-ft dia access shaft and connection tunnel

• To access drainage adit

• Potential back-up for dewatering adit

January 13, 2010B&V -

Drainage Adit Conversion

Reduce seepage from Reservoir passing to Main Lobe and minimize potential instability of Tollway Dam

Thornton Reservoir and Tunnels – APWA 2016 Project of the Year Award

Chicago River Front - many fish species have returned, now a regular place for the Annual Bass Fishing Tournament !

Acknowledgements

U.S. Army Corps of Engineers

CHICAGO DISTRICT

F.H. Paschen

Thank you - Questions & Answers

69

[email protected]@bv.com