MDOT ACTT Workshop. Structures I-94 From I-96 to East of Connor Participants Steve Stroh, URS Corp Vijay Chandra, Parson Brinckerhoff Raj Ailaney, FHWA Gary Jakovich, FHWA Jon Nekritz, FHWA Phil Grotenhuis, MDOT Matt Chynoweth, MDOT Terry Lavoy, MDOT Wesley King, MDOT. - PowerPoint PPT PresentationTRANSCRIPT
MDOT ACTT Workshop
StructuresI-94 From I-96 to East of Connor
Participants• Steve Stroh, URS Corp• Vijay Chandra, Parson Brinckerhoff• Raj Ailaney, FHWA• Gary Jakovich, FHWA• Jon Nekritz, FHWA• Phil Grotenhuis, MDOT• Matt Chynoweth, MDOT• Terry Lavoy, MDOT• Wesley King, MDOT
Shallow Structure Types• Channel Bridge• Cable-Stayed Bridge with slab superstructure• Tied-Arch Bridge with slab superstructure• “Conventional beam bridge with integral
supports”• Segmental voided slab
Pre-fabrication• Segmental Concrete Superstructure• Pre-cast piers• Pre-cast abutments• Pre-cast deck panels• Pre-cast bridge barrier• Temporary Bridges Bailey/Acrow
ElementsSystems
ElementsSystems
High Performance Materials• Polymer Asphalt• High Performance concrete• High Performance steel• Self-Consolidating Concrete• High Strength Concrete• Initial Overlays
Retaining Walls• Remove retaining walls, purchase additional
Right of Way (ROW), Lay slope back at 3:1 • Soldier Pile, Soil Nailed or Secant Walls
Service Drive Expansion• Near Wayne State University (WSU)
parking garage expand service drive over slope.
Foundations for Interchanges• Single/mono shaft• Large diameter closed in steel pipe pile• Post grouted shaft
Railway Crossings• Construct temporary railroad bridges as
necessary• Diverge rail traffic onto one bridge in areas
with multiple tracks• Roll in pre-fabricated bridge over short
closure period• Edge girder floor beam system
Interchange Construction Staging• Build new ramps before eliminating
movements• Construction Planner
• Manage sequence of construction for whole interchange
• Ramp Bridges• Segmental Box• Steel Box/Plate
• Temporary Structures to move traffic
Advanced Contracting• Identify bridges for early
construction/replacement due to poor condition• Advanced relocation of utilities
Design to Minimize Future Maintenance• Eliminating expansion joints, design for
continuity• Minimize number of bearings
Erection Methods• Self Propelled Modular Transport (SPMT) • Roll In• High capacity cranes• Erection Gantry