measure a semi-annual report - meeting portal
TRANSCRIPT
Measure A Semi-Annual ReportPeriod Ending June 30, 2020
October 2020 Advisory Committees
• VTA and BART reached a major milestone on March 2, 2020 when BART appointed a Rail Acceptance Officer to take responsibility for the transition of the BART Berryessa Extension Project from a VTA construction project to an operating element of the BART system.
• After resolution of critical discrepancies, BART resumed Phase 3 operations and maintenance testing on March 12, 2020.
• The CPUC approved the System Safety Certification on June 3, 2020.
• A ribbon cutting ceremony was held on June 12, 2020 that included a small group of dignitaries and project participants. Members of the public were invited to livestream the event to maintain a small crowd and adhere to social distancing requirements.
• The SVBX project entered Revenue Service on June 13, 2020.
2
BART Silicon Valley Berryessa Extension (SVBX)
• The contractor for the new Component Repair Shop within the Hayward Maintenance Complex (HMC) was granted Substantial Completion for the entire facility on February 13, 2020.
• BART assigned its 40th new revenue vehicle to VTA in January 2020, thus completing VTA’s obligation under the SVBX Full Funding Grant Agreement. VTA is procuring 20 additional vehicles as part of its BART Core Systems commitment.
• The prefabricated steel bridge sections for the Montague Pedestrian Overcrossing were delivered to the site in June 2020. Field work on the sections continued in preparation for their July 2020 installation over Montague Expressway.
3
BART Silicon Valley Berryessa Extension (SVBX)
4
$ Millions – Year of Expenditure
SVBX: Cost Summary
$'s millions
Cost by FTA Standard Cost Category
FFGA
Budget
A
Incurred Costs
as of 30-Jun-20
Forecast Cost at
Completion
(FAC)
B
Variance
(A - B)*
10 Guideway and Track Elements $ 416.1 $ 327.6 $ 327.8 88.3
20 Stations, Stops, Terminals, & Intermodal $ 250.3 $ 227.3 $ 229.6 20.7
30 Support Facilities: Yards, Shops, Admin. Bldgs $ 46.5 $ 28.0 $ 32.4 14.1
40 Sitework & Special Conditions $ 220.1 $ 223.3 $ 251.3 (31.2)
50 Systems $ 260.7 $ 281.7 $ 317.8 (57.1)
60 ROW, Land and Existing Improvements $ 261.0 $ 164.4 $ 168.0 93.0
70 Vehicles $ 174.3 $ 38.2 $ 109.7 64.6
80 Professional Services $ 548.3 $ 655.7 $ 698.2 (149.9)
90 Unallocated Contingency $ 40.2 $ - $ 44.7 (4.5)
100 Finance Charges $ 112.5 $ 150.6 $ 150.6 (38.1)
Concurrent Non-Project Activities $ 91.3 $ 89.6 $ 91.3 0.0
Total Project Cost $ 2,421.3 $ 2,186.3 $ 2,421.3 0.0
*Numbers in green reflect that the forecast is better than the budget
Silicon Valley Berryessa Extension Project
Budget-Cost Analysis
SVBX: Ribbon Cutting Ceremony & Inaugural Train RideJune 12, 2020
5
Montague Pedestrian Overcrossing Bridge SectionDelivered to Site
6
•On April 17, 2020 a special VTA Board of Directors meeting was held for members to be briefed on two special
concept studies underway to address BART’s operational and safety concerns with the single bore configuration
that was included in the project’s June 2018 Record of Decision from the Federal Transit Administration (FTA).
These concept studies maintain, at a minimum, a Single Bore stacked configuration under Santa Clara Street (50’
below surface) between 13th Street and Stockton Avenue to minimize street-level impacts and business
disruptions in the San Jose downtown core during construction.
•At VTA’s June 19, 2020 Board of Directors meeting, staff provided an overview of the funding application to be
submitted to the Federal Transit Administration (FTA) for the Expedited Project Delivery (EPD) Pilot Program. This
presentation included details on the project scope, cost estimate, schedule, contract plan, and funding plan.
•Following the presentation to the Board of Directors, staff met with FTA Region IX on June 25, 2020 to provide a
similar overview of the project. On July 17, 2020, staff met with FTA Headquarters and Region IX staff to review
VTA’s EPD application readiness to formally submit for federal funding. General details of the application were
discussed with a focus on elements satisfying the requirements of the EPD program. VTA was also informed that a
Project Management Oversight Consultant (PMOC) has been assigned for project oversight and risk assessment.7
BART Silicon Valley Phase II Extension
8
Map of BART Silicon Valley Phase II Extension
BART Silicon Valley Phase II Extension
9
Artist’s Rendering of the Downtown San Jose BART Station Interior
BART Silicon Valley Phase II Extension
10
BART Silicon Valley Phase II ExtensionProject Schedule
Completed Projects on Capitol Expressway
• 2012 Pedestrian Improvements (sidewalk, lighting and trees)
• 2015 Eastridge Transit Center expansion
and reconfiguration
• 2017 Bus Rapid Transit (BRT) to the
Eastridge Transit Center
• 2018 Pedestrian Access Improvements
across Capitol Expressway to the Eastridge Transit Center
11
Extend Light Rail From Downtown San Jose to the East Valley
Eastridge to BART Regional Connector (EBRC) Project
12
• Extends light rail from the Alum Rock Station on
Capitol Avenue to the Eastridge Transit Station
• 2.4 miles long with two stations (Story Road and
Eastridge)
• Located in the median of Capitol Expressway with
side running through Tully Road to the Eastridge
Transit Station
• Elevated structure to avoid conflicts with pedestrian
or vehicular traffic at grade crossings. This is the
fastest and safest operation along the expressway.
Extend Light Rail From Downtown San Jose to the East Valley
13
EBRC Guideway Profile
Guideway Profile
Sto
ry R
d
Cap
ito
lAve
Tully
Rd
LRT Station
Oca
la A
ve
Cu
nn
ingh
am A
ve
EastridgeAlum Rock
Extend Light Rail From Downtown San Jose to the East Valley
14
EBRC Project Activities
Property acquisition
Utility Relocation
Construction
Engineering
We are here
Advertisement and Award
February 2021
Extend Light Rail From Downtown San Jose to the East Valley
15
EBRC Construction Cost and Funding
Measure A $314 Million
Regional Measure 3 Funds $130 Million
Other (LCTOP) $ 15 Million
Senate Bill (SB) 1 $ 9 Million
Total Estimated Cost of the Project $468 Million
Extend Light Rail From Downtown San Jose to the East Valley
EBRC Property Acquisition
• All offers made
• Settled or have Use Agreement on most
• Court hearings for others in October 2020
• Reaching agreement with Valley Water
• FAA coordination continues
16
Extend Light Rail From Downtown San Jose to the East Valley
EBRC Utility Relocation
• PG&E Electrical Transmission Line in
early 2021
• Water line relocation in early 2021
• Other utilities in spring to summer 2021
17
Extend Light Rail From Downtown San Jose to the East Valley
EBRC Other Activities
• Construction industry review
• Stakeholder Working Group (SWG)
• Artwork integration
• Field office
18
Extend Light Rail From Downtown San Jose to the East Valley
EBRC Photo Simulations and Renderings
19
Extend Light Rail From Downtown San Jose to the East Valley
20
North End Retaining Wall
Photo simulation Capitol Avenue south of Capitol Expressway
(looking west)
Extend Light Rail From Downtown San Jose to the East Valley
21
Elevated Story Station
Photo simulation Capitol Expressway at Story Road (looking east)
Extend Light Rail From Downtown San Jose to the East Valley
22
Elevated Story Station
Photo simulation Story Road (looking east)
Extend Light Rail From Downtown San Jose to the East Valley
23
Eastridge StationExtend Light Rail From Downtown San Jose to the East Valley
EBRC Stakeholder Working Group
24
• Goal to minimize construction inconvenience
• Solution to minimizing inconvenience in one
area may cause impact in another area
• Adding restrictions to minimize
inconvenience results in more cost and
maybe more time
• Need to understand what constraints have the most overall value to implement
Extend Light Rail From Downtown San Jose to the East Valley
25
Structure Construction
Different work happening concurrently along the expressway
Extend Light Rail From Downtown San Jose to the East Valley
EBRC VTA Community Outreach
• Stakeholder Working Group
• VTA EBRC Policy Advisory Board
• Presentations to neighborhood groups and organizations
• VTA hosted events
• Field Office & Door/Door
• Newsletters/Mailed Notices
• Next Door & Stakeholder Email
• Partner postings (EBRC-CELR PAB, Councilmember/Supervisor)
• Construction signage
• Changeable message boards
• Apple & Google Maps
26
Extend Light Rail From Downtown San Jose to the East Valley
• 65% design deliverables for modifications to the Chaboya
Yard received in July 2020. Design expected to be
complete by end 2020.
• Alum Rock Santa Clara BRT in revenue service.
• Bus stop improvements associated with Stevens Creek
Rapid 523 is complete.
• Design scope for the bus stop improvements on El Camino
Real Rapid corridor is being finalized.
27
Improve Bus Service in Major Bus Corridors