measure a semi-annual report - meeting portal

27
Measure A Semi-Annual Report Period Ending June 30, 2020 October 2020 Advisory Committees

Upload: others

Post on 24-Jan-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Measure A Semi-Annual Report - Meeting Portal

Measure A Semi-Annual ReportPeriod Ending June 30, 2020

October 2020 Advisory Committees

Page 2: Measure A Semi-Annual Report - Meeting Portal

• VTA and BART reached a major milestone on March 2, 2020 when BART appointed a Rail Acceptance Officer to take responsibility for the transition of the BART Berryessa Extension Project from a VTA construction project to an operating element of the BART system.

• After resolution of critical discrepancies, BART resumed Phase 3 operations and maintenance testing on March 12, 2020.

• The CPUC approved the System Safety Certification on June 3, 2020.

• A ribbon cutting ceremony was held on June 12, 2020 that included a small group of dignitaries and project participants. Members of the public were invited to livestream the event to maintain a small crowd and adhere to social distancing requirements.

• The SVBX project entered Revenue Service on June 13, 2020.

2

BART Silicon Valley Berryessa Extension (SVBX)

Page 3: Measure A Semi-Annual Report - Meeting Portal

• The contractor for the new Component Repair Shop within the Hayward Maintenance Complex (HMC) was granted Substantial Completion for the entire facility on February 13, 2020.

• BART assigned its 40th new revenue vehicle to VTA in January 2020, thus completing VTA’s obligation under the SVBX Full Funding Grant Agreement. VTA is procuring 20 additional vehicles as part of its BART Core Systems commitment.

• The prefabricated steel bridge sections for the Montague Pedestrian Overcrossing were delivered to the site in June 2020. Field work on the sections continued in preparation for their July 2020 installation over Montague Expressway.

3

BART Silicon Valley Berryessa Extension (SVBX)

Page 4: Measure A Semi-Annual Report - Meeting Portal

4

$ Millions – Year of Expenditure

SVBX: Cost Summary

$'s millions

Cost by FTA Standard Cost Category

FFGA

Budget

A

Incurred Costs

as of 30-Jun-20

Forecast Cost at

Completion

(FAC)

B

Variance

(A - B)*

10 Guideway and Track Elements $ 416.1 $ 327.6 $ 327.8 88.3

20 Stations, Stops, Terminals, & Intermodal $ 250.3 $ 227.3 $ 229.6 20.7

30 Support Facilities: Yards, Shops, Admin. Bldgs $ 46.5 $ 28.0 $ 32.4 14.1

40 Sitework & Special Conditions $ 220.1 $ 223.3 $ 251.3 (31.2)

50 Systems $ 260.7 $ 281.7 $ 317.8 (57.1)

60 ROW, Land and Existing Improvements $ 261.0 $ 164.4 $ 168.0 93.0

70 Vehicles $ 174.3 $ 38.2 $ 109.7 64.6

80 Professional Services $ 548.3 $ 655.7 $ 698.2 (149.9)

90 Unallocated Contingency $ 40.2 $ - $ 44.7 (4.5)

100 Finance Charges $ 112.5 $ 150.6 $ 150.6 (38.1)

Concurrent Non-Project Activities $ 91.3 $ 89.6 $ 91.3 0.0

Total Project Cost $ 2,421.3 $ 2,186.3 $ 2,421.3 0.0

*Numbers in green reflect that the forecast is better than the budget

Silicon Valley Berryessa Extension Project

Budget-Cost Analysis

Page 5: Measure A Semi-Annual Report - Meeting Portal

SVBX: Ribbon Cutting Ceremony & Inaugural Train RideJune 12, 2020

5

Page 6: Measure A Semi-Annual Report - Meeting Portal

Montague Pedestrian Overcrossing Bridge SectionDelivered to Site

6

Page 7: Measure A Semi-Annual Report - Meeting Portal

•On April 17, 2020 a special VTA Board of Directors meeting was held for members to be briefed on two special

concept studies underway to address BART’s operational and safety concerns with the single bore configuration

that was included in the project’s June 2018 Record of Decision from the Federal Transit Administration (FTA).

These concept studies maintain, at a minimum, a Single Bore stacked configuration under Santa Clara Street (50’

below surface) between 13th Street and Stockton Avenue to minimize street-level impacts and business

disruptions in the San Jose downtown core during construction.

•At VTA’s June 19, 2020 Board of Directors meeting, staff provided an overview of the funding application to be

submitted to the Federal Transit Administration (FTA) for the Expedited Project Delivery (EPD) Pilot Program. This

presentation included details on the project scope, cost estimate, schedule, contract plan, and funding plan.

•Following the presentation to the Board of Directors, staff met with FTA Region IX on June 25, 2020 to provide a

similar overview of the project. On July 17, 2020, staff met with FTA Headquarters and Region IX staff to review

VTA’s EPD application readiness to formally submit for federal funding. General details of the application were

discussed with a focus on elements satisfying the requirements of the EPD program. VTA was also informed that a

Project Management Oversight Consultant (PMOC) has been assigned for project oversight and risk assessment.7

BART Silicon Valley Phase II Extension

Page 8: Measure A Semi-Annual Report - Meeting Portal

8

Map of BART Silicon Valley Phase II Extension

BART Silicon Valley Phase II Extension

Page 9: Measure A Semi-Annual Report - Meeting Portal

9

Artist’s Rendering of the Downtown San Jose BART Station Interior

BART Silicon Valley Phase II Extension

Page 10: Measure A Semi-Annual Report - Meeting Portal

10

BART Silicon Valley Phase II ExtensionProject Schedule

Page 11: Measure A Semi-Annual Report - Meeting Portal

Completed Projects on Capitol Expressway

• 2012 Pedestrian Improvements (sidewalk, lighting and trees)

• 2015 Eastridge Transit Center expansion

and reconfiguration

• 2017 Bus Rapid Transit (BRT) to the

Eastridge Transit Center

• 2018 Pedestrian Access Improvements

across Capitol Expressway to the Eastridge Transit Center

11

Extend Light Rail From Downtown San Jose to the East Valley

Page 12: Measure A Semi-Annual Report - Meeting Portal

Eastridge to BART Regional Connector (EBRC) Project

12

• Extends light rail from the Alum Rock Station on

Capitol Avenue to the Eastridge Transit Station

• 2.4 miles long with two stations (Story Road and

Eastridge)

• Located in the median of Capitol Expressway with

side running through Tully Road to the Eastridge

Transit Station

• Elevated structure to avoid conflicts with pedestrian

or vehicular traffic at grade crossings. This is the

fastest and safest operation along the expressway.

Extend Light Rail From Downtown San Jose to the East Valley

Page 13: Measure A Semi-Annual Report - Meeting Portal

13

EBRC Guideway Profile

Guideway Profile

Sto

ry R

d

Cap

ito

lAve

Tully

Rd

LRT Station

Oca

la A

ve

Cu

nn

ingh

am A

ve

EastridgeAlum Rock

Extend Light Rail From Downtown San Jose to the East Valley

Page 14: Measure A Semi-Annual Report - Meeting Portal

14

EBRC Project Activities

Property acquisition

Utility Relocation

Construction

Engineering

We are here

Advertisement and Award

February 2021

Extend Light Rail From Downtown San Jose to the East Valley

Page 15: Measure A Semi-Annual Report - Meeting Portal

15

EBRC Construction Cost and Funding

Measure A $314 Million

Regional Measure 3 Funds $130 Million

Other (LCTOP) $ 15 Million

Senate Bill (SB) 1 $ 9 Million

Total Estimated Cost of the Project $468 Million

Extend Light Rail From Downtown San Jose to the East Valley

Page 16: Measure A Semi-Annual Report - Meeting Portal

EBRC Property Acquisition

• All offers made

• Settled or have Use Agreement on most

• Court hearings for others in October 2020

• Reaching agreement with Valley Water

• FAA coordination continues

16

Extend Light Rail From Downtown San Jose to the East Valley

Page 17: Measure A Semi-Annual Report - Meeting Portal

EBRC Utility Relocation

• PG&E Electrical Transmission Line in

early 2021

• Water line relocation in early 2021

• Other utilities in spring to summer 2021

17

Extend Light Rail From Downtown San Jose to the East Valley

Page 18: Measure A Semi-Annual Report - Meeting Portal

EBRC Other Activities

• Construction industry review

• Stakeholder Working Group (SWG)

• Artwork integration

• Field office

18

Extend Light Rail From Downtown San Jose to the East Valley

Page 19: Measure A Semi-Annual Report - Meeting Portal

EBRC Photo Simulations and Renderings

19

Extend Light Rail From Downtown San Jose to the East Valley

Page 20: Measure A Semi-Annual Report - Meeting Portal

20

North End Retaining Wall

Photo simulation Capitol Avenue south of Capitol Expressway

(looking west)

Extend Light Rail From Downtown San Jose to the East Valley

Page 21: Measure A Semi-Annual Report - Meeting Portal

21

Elevated Story Station

Photo simulation Capitol Expressway at Story Road (looking east)

Extend Light Rail From Downtown San Jose to the East Valley

Page 22: Measure A Semi-Annual Report - Meeting Portal

22

Elevated Story Station

Photo simulation Story Road (looking east)

Extend Light Rail From Downtown San Jose to the East Valley

Page 23: Measure A Semi-Annual Report - Meeting Portal

23

Eastridge StationExtend Light Rail From Downtown San Jose to the East Valley

Page 24: Measure A Semi-Annual Report - Meeting Portal

EBRC Stakeholder Working Group

24

• Goal to minimize construction inconvenience

• Solution to minimizing inconvenience in one

area may cause impact in another area

• Adding restrictions to minimize

inconvenience results in more cost and

maybe more time

• Need to understand what constraints have the most overall value to implement

Extend Light Rail From Downtown San Jose to the East Valley

Page 25: Measure A Semi-Annual Report - Meeting Portal

25

Structure Construction

Different work happening concurrently along the expressway

Extend Light Rail From Downtown San Jose to the East Valley

Page 26: Measure A Semi-Annual Report - Meeting Portal

EBRC VTA Community Outreach

• Stakeholder Working Group

• VTA EBRC Policy Advisory Board

• Presentations to neighborhood groups and organizations

• VTA hosted events

• Field Office & Door/Door

• Newsletters/Mailed Notices

• Next Door & Stakeholder Email

• Partner postings (EBRC-CELR PAB, Councilmember/Supervisor)

• Construction signage

• Changeable message boards

• Apple & Google Maps

26

Extend Light Rail From Downtown San Jose to the East Valley

Page 27: Measure A Semi-Annual Report - Meeting Portal

• 65% design deliverables for modifications to the Chaboya

Yard received in July 2020. Design expected to be

complete by end 2020.

• Alum Rock Santa Clara BRT in revenue service.

• Bus stop improvements associated with Stevens Creek

Rapid 523 is complete.

• Design scope for the bus stop improvements on El Camino

Real Rapid corridor is being finalized.

27

Improve Bus Service in Major Bus Corridors