measure l bond update - berryessa union school district l... · •awaiting final quote from vendor...

13
MEASURE L BOND UPDATE February 27, 2018

Upload: others

Post on 14-Aug-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MEASURE L BOND UPDATE - Berryessa Union School District L... · •Awaiting final quote from vendor •Furniture delivery April 2018 •FIS Furniture ‐Laneview & Majestic Way •Furniture

MEASURE L BOND UPDATEFebruary 27, 2018

Page 2: MEASURE L BOND UPDATE - Berryessa Union School District L... · •Awaiting final quote from vendor •Furniture delivery April 2018 •FIS Furniture ‐Laneview & Majestic Way •Furniture

• Phase 2 Project Update• Phase 3 Project Update• Phase 4 Project Update• FIS and Classroom Furniture Update• Program Schedule Review

Measure L – Overview

Page 3: MEASURE L BOND UPDATE - Berryessa Union School District L... · •Awaiting final quote from vendor •Furniture delivery April 2018 •FIS Furniture ‐Laneview & Majestic Way •Furniture

• Vinci Park FIS Project  (Phase 1)– Project is on schedule to be completed in March  

Main FIS space

Measure L – Phase 2 Projects

Page 4: MEASURE L BOND UPDATE - Berryessa Union School District L... · •Awaiting final quote from vendor •Furniture delivery April 2018 •FIS Furniture ‐Laneview & Majestic Way •Furniture

• Pavement Rehabilitation – Piedmont Middle School• Project approved by DSA• Receive bids March 2018• Construction starts June 2018

• Vinci Park Elementary School ‐ FIS  • Phase 2 ‐ Exterior Canopy and Site work

• CGS (California Geological Survey) has approved the project• Meeting with DSA in early March for Canopy approval• Procurement/installation of exterior canopy and site related work completed by May 1, 2018

Measure L – Phase 2 Projects

Page 5: MEASURE L BOND UPDATE - Berryessa Union School District L... · •Awaiting final quote from vendor •Furniture delivery April 2018 •FIS Furniture ‐Laneview & Majestic Way •Furniture

Laneview FIS Project – Project to be completed by March 5, 2018

Main FIS space

Measure L – Phase 3 Projects

Page 6: MEASURE L BOND UPDATE - Berryessa Union School District L... · •Awaiting final quote from vendor •Furniture delivery April 2018 •FIS Furniture ‐Laneview & Majestic Way •Furniture

Laneview FIS Project

Small group space

Measure L – Phase 3 Projects

Page 7: MEASURE L BOND UPDATE - Berryessa Union School District L... · •Awaiting final quote from vendor •Furniture delivery April 2018 •FIS Furniture ‐Laneview & Majestic Way •Furniture

Laneview FIS Project

Fencing between and Main building and Kindergarten

Measure L – Phase 3 Projects

Page 8: MEASURE L BOND UPDATE - Berryessa Union School District L... · •Awaiting final quote from vendor •Furniture delivery April 2018 •FIS Furniture ‐Laneview & Majestic Way •Furniture

Majestic Way FIS Project – Project to be completed on March 12, 2018

Main FIS space

Measure L – Phase 3 Projects

Page 9: MEASURE L BOND UPDATE - Berryessa Union School District L... · •Awaiting final quote from vendor •Furniture delivery April 2018 •FIS Furniture ‐Laneview & Majestic Way •Furniture

Majestic Way FIS Project

FIS sink area 

Measure L – Phase 3 Projects

Page 10: MEASURE L BOND UPDATE - Berryessa Union School District L... · •Awaiting final quote from vendor •Furniture delivery April 2018 •FIS Furniture ‐Laneview & Majestic Way •Furniture

• FIS Furniture ‐ Vinci Park• Awaiting final quote from vendor• Furniture delivery April 2018

• FIS Furniture ‐ Laneview & Majestic Way• Furniture delivery on March 2, 2018

• FIS Furniture ‐ 2018 Project• Meeting with Principal in March 2018

• Classroom Furniture ‐ 2018 Projects• Submitting order to vendor for quote in February 2018

Measure L – Furniture

Page 11: MEASURE L BOND UPDATE - Berryessa Union School District L... · •Awaiting final quote from vendor •Furniture delivery April 2018 •FIS Furniture ‐Laneview & Majestic Way •Furniture

• Modernization Projects• Ruskin Elementary School ‐ FIS

• Receive bids in March 2018

• Piedmont Middle School ‐ FIS • Receive bids in March 2018

• Brooktree Elementary School • Receive bids in April 2018

• Cherrywood Elementary School • Interior Painting Package ‐Receive bids March 2018• Mod/FIS Package – Awaiting structural comments from DSA• Meeting with DSA in March to review wheelchair lift option

• Toyon Elementary School  • Interior/Exterior Painting Package – Receive bids March 2018• FIS 

• Submit to DSA early May 2018• Construction to begin in Fall of 2018

• Morrill Middle School • Receive bids in April 2018

Measure L – Phase 4 Projects

Page 12: MEASURE L BOND UPDATE - Berryessa Union School District L... · •Awaiting final quote from vendor •Furniture delivery April 2018 •FIS Furniture ‐Laneview & Majestic Way •Furniture

Measure L – Program Schedule

Design Preconstruction Furniture Order Finalized Furniture OrderedDSA Review Construction Quote Pric ing Lead TimeBid Start of School PO Generated Furniture Received and PlacedAward Punch List

Construction Projects

1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 5

Vinci Park FIS

Vinci Park FIS - Exterior Canopy

Laneview - FIS

Majestic Way - FIS

Brooktree - Modernization

Brooktree - FIS

Morrill - Modernization

Morrill - FIS

Cherrywood - Interior Painting

Cherrywood - Modernization

Cherrywood - FIS

Toyon - Interior/Exterior Painting

Toyon - Modernization

Toyon - FIS

Ruskin - FIS

Piedmont - FIS

Piedmont Drop off

Furniture Projects

FIS Furniture - Vinci Park

FIS Furniture - LV & MW

FIS Furniture - Phase 4

Furniture

DecemberWeek

2018

2018 Construction & Furniture Projects

FebruaryWeek

April May June July August SeptemberMarchWeek Week

Furniture LegendConstruction Legend

WeekOctober November

Week Week Week Week Week Week

Page 13: MEASURE L BOND UPDATE - Berryessa Union School District L... · •Awaiting final quote from vendor •Furniture delivery April 2018 •FIS Furniture ‐Laneview & Majestic Way •Furniture

Thank You