media

4
Client: Bloor Homes Main Contractor: Sanctus Ltd & Hanson Quarries Geotechnical Consultant: Clarke Bond Project Type: Residential Size: 700,000m3 Ground Profile: Placed Clays & Blasted Rock Fill Requirement: 1m TLW HEIC (14 tonne 5 Sided) Verification: Discovery CE & Clarke Bond IGI: None TWP: None TLW: Engineered 1m TLWs for 30m deep platform Duration: June 2013 to October 2014 CIR: Yes CIS: Yes It was proposed to develop the “Phase 5 - void”, within the southern Quarry boundary, by constructing an engineered platform of site-won and imported fills, up to 700,000m3. The quarry is approximately 32 metres deep (coincident with the central and northern end of the development platform) with steep walls to the north, east and west. Once complete the platform will be approximately 210m long, generally 20m to 26m deep (with one location up to 30m deep) and will be used for residential development containing approximately 120 units, with associated access and infrastructure. LANDPAC started HEIC works on 700,000m3 on Barnhill Quarry in Chipping Sodbury in June 2013. The project required HEIC to improve placed clay & blasted rock materials, in 1m thick layers for total average engineered platform depth of 30m. HEIC was adopted as part of Sanctus's overall design on providing an engineered platform for residential housing support, comprising a finished 4 Hectare area, once complete. Placed Clays and blasted rack materials varied. Existing natural materials and fills within the quarry were re-used and additional infill material was derived from a number of sources adjacent to Barnhill (e.g. Southfields Tip & Hanson Quarry) : Granular Made Ground deposits Cohesive Made Ground deposits Triassic Cohesive Deposits (Possible Rhaetic Deposits) Lower Cromhall Sandstone and Carboniferous Limestone were excavated/quarried The materials used in the earthworks were required to meet the classes of acceptable earthworks material as set out in the Specification for Highway Works Series 600 Earthworks (SHW). LANDPAC adopted it’s Zone Load Testing equipment (2m x 2m x 100m steel plate & calibrated pencil 1-2 tonne steel weights) to test each third HEIC’d layer for 100kN/m2 for < 20mm, as per BS1377, for the full depth of the engineered platform, once complete (total ZLTs expected 20 No). LANDPAC Ground Engineering LTD Intelligent Ground Improvement ® CASE STUDY – LP1193 BARNHILL QUARRY, CHIPPING SODBURY, ENGLAND RESIDENTIAL / HOUSING DEVELOPMENT TWP Temporary Working Platforms Tel: +44 8455005533 Web: www.landpac.co.uk E-mail: [email protected] IGI In-Situ Ground Improvement TLW Thick Layer Works

Upload: yen-ling-ng

Post on 18-Jul-2016

3 views

Category:

Documents


0 download

DESCRIPTION

journal

TRANSCRIPT

Page 1: Media

Client: Bloor HomesMain Contractor: Sanctus Ltd & Hanson QuarriesGeotechnical Consultant: Clarke BondProject Type: ResidentialSize: 700,000m3Ground Profile: Placed Clays & Blasted Rock Fill

Requirement: 1m TLW HEIC (14 tonne 5 Sided)Verification: Discovery CE & Clarke BondIGI: NoneTWP: NoneTLW: Engineered 1m TLWs for 30m deep platformDuration: June 2013 to October 2014CIR: Yes CIS: Yes

It was proposed to develop the “Phase 5 - void”, within thesouthern Quarry boundary, by constructing an engineeredplatform of site-won and imported fills, up to 700,000m3.

The quarry is approximately 32 metres deep (coincidentwith the central and northern end of the developmentplatform) with steep walls to the north, east and west.

Once complete the platform will be approximately 210mlong, generally 20m to 26m deep (with one location up to30m deep) and will be used for residential developmentcontaining approximately 120 units, with associatedaccess and infrastructure.

LANDPAC started HEIC works on 700,000m3 on BarnhillQuarry in Chipping Sodbury in June 2013. The projectrequired HEIC to improve placed clay & blasted rockmaterials, in 1m thick layers for total average engineeredplatform depth of 30m. HEIC was adopted as part ofSanctus's overall design on providing an engineeredplatform for residential housing support, comprising afinished 4 Hectare area, once complete.

Placed Clays and blasted rack materials varied. Existingnatural materials and fills within the quarry were re-usedand additional infill material was derived from a number ofsources adjacent to Barnhill (e.g. Southfields Tip &Hanson Quarry) :• Granular Made Ground deposits• Cohesive Made Ground deposits• Triassic Cohesive Deposits (Possible Rhaetic

Deposits)• Lower Cromhall Sandstone and Carboniferous

Limestone were excavated/quarried

The materials used in the earthworks were required tomeet the classes of acceptable earthworks material as setout in the Specification for Highway Works Series 600Earthworks (SHW).

LANDPAC adopted it’s Zone Load Testing equipment (2mx 2m x 100m steel plate & calibrated pencil 1-2 tonne steelweights) to test each third HEIC’d layer for 100kN/m2 for <20mm, as per BS1377, for the full depth of the engineeredplatform, once complete (total ZLTs expected 20 No).

LANDPAC Ground Engineering LTDIntelligent Ground Improvement

® CASE STUDY – LP1193BARNHILL QUARRY, CHIPPING SODBURY, ENGLAND

RESIDENTIAL / HOUSING DEVELOPMENT

TWPTemporary Working Platforms

Tel: +44 8455005533 Web: www.landpac.co.uk E-mail: [email protected]

IGIIn-Situ Ground Improvement

TLWThick Layer Works

Page 2: Media

LANDPAC Definitions:HEIC - High Energy Impact Compaction - Intelligent Ground Improvement ApplicationCIR - Continuous Impact Response - Intelligent Stiffness Profile MonitoringCIS - Continuous Induced Settlement - Intelligent Differential Settlement MonitoringZLT – Zone Load Testing – 2m x 2m x 100mm steel plate loaded from 35kN/m2 up to 125kN/m2 (Fact Sheet attached)

TLWThick Layer Works

LANDPAC Ground Engineering LTDIntelligent Ground Improvement

®

TWPTemporary Working Platforms

Tel: +44 8455005533 Web: www.landpac.co.uk E-mail: [email protected]

IGIIn-Situ Ground Improvement

CIR Map per 1m thick layer being HEIC’d

CASE STUDY – LP1193BARNHILL QUARRY, CHIPPING SODBURY, ENGLAND

RESIDENTIAL / HOUSING DEVELOPMENT

Page 3: Media

Base Plate: 2m x 2m square 100mm thick pre-fabricated Steel Plate, or similar

Kentledge: 2m x 0.2m x 0.2m Calibrated Steel Blocks, or similar

Control Datum's: 2 x 1m long steel pins, or similar, to construct levelling datum's, placed > 6m from ZLT plate

Monitoring Surveying Equipment: Zeiss Dini Digital Precise Level and staff accurate to 0.1mm, or similar

Zone Load Test (ZLT) loading and unloading is carried out in

general, accordance with BS1377: Part 9, Section 4.2,

“Methods of test for Soils for Civil Engineering purposes – In-

situ Teats”.

The ZLT load is applied through the use of calibrated steel

“blocks" of known weight. The “blocks” are lifted into place

using certified chains and certified lifting lugs attached to the

“blocks. The load/”blocks” are applied to the plate in a

symmetrical fashion to ensure an even application. The most

appropriate combination of “blocks” is used to match the

required load increment.

The maximum ZLT load that can be applied safely is

120kN/m2, on a 2m x 2m base plate

The general loading criterion is defined below.

Before HEIC: Settlement for a 120kN/m2 load on un-

improved soils (2m x 2m base plate) was typically measured

as 26mm over a 15 day period.

After HEIC: Settlement for a 120kN/m2 load on HEIC

improved soil (2m x 2m base plate) was typically measured

as 5.5mm over a 6 day period (i.e. < 0.1mm for last 24

hours), confirming that the drained stiffness modulus

specification had been met for that project.

This ZLT method covers the determination of the settlement

characteristics of soil in-situ by a test in which a constant load

is applied to the ground for a period of several days through a

steel pad placed on the surface. The ZLT is suitable for

estimating the settlement caused by loads placed on filled

ground. The ZLT makes it possible to estimate the

settlement that will occur due to an applied load. The ZLT is

solely confined to providing an indication of the magnitude of

settlement of the ground immediately beneath the test pad.

LANDPAC Ground Engineering LTD

Intelligent Ground Improvement

®

FACT SHEET – ZLT

ZONE LOAD TEST (ZLT)

Tel: +44 8455005533 Web: www.landpac.co.uk E-mail: [email protected]

2 x Typical 120kN/m2 Zone Load Tests (ZLTs) set-ups

ZLT data “before” and “after” full HEIC application

Page 4: Media

Apparatus: Rigid square steel base plate of suitable

dimensions and known mass. The larger dimension (B1) and

the smaller dimension (B2) of the square pad shall be such

that B2/B1 = 1. B1 or B2 shall be not smaller than 2m. The

pad shall be fitted with four levelling stations at its periphery

equidistant from the centre of the pad and from each other.

The levelling stations shall be accessible when the pad is

loaded. In general the ground to a depth of not more than

1.5B1 or 1.5B2 will be affected by the loading test and the

properties of the ground at greater depths will have little

influence on the test results.

Kentledge, in the form of calibrated steel “blocks”, of known

mass sufficient to provide the required bearing pressure.

Levelling equipment: Surveyor’s level with tripod and staff

capable of measuring to a resolution of at least 0.1mm. The

levelling equipment shall be maintained in adjustment

according to the manufacturer’s instructions.

Levelling datum stations which shall not move more than

0.5mm during the course of the ZLT.

Procedure ; Levelling datum stations. Establish two levelling

datum stations for the load test at a distance from each other

of at least 3B1 or 3B2. Locate the levelling datum stations at

a distance of at least 3B1 or 3B2 from the centre of the load

test.

Preparation of test area: Excavate the area of the load test

to remove obvious surface soft materials and prepare a level

surface. The prepared area shall be sufficiently large to make

possible the installation of the loading pad but no larger.

Installation of pad: The pad shall be prefabricated, in the

form of a 2m x 2m square steel base plate 100mm thick.

Place a layer of sand, nowhere exceeding 100mm in

thickness, and with a level surface, on the prepared soil

surface. Bed the prefabricated steel base plate onto the

sand.

Loading sequence: Apply the load so that it is evenly

distributed over the pad. Where the load is mobilised above

the pad, and prior to its application, ensure that it is kept

stable sufficiently far from the test position so as to reduce

the influence on the results to a tolerable level. Apply the

load in a number of equal increments. Measure the

settlement of the pad immediately following the application of

each load increment. Record the time at which each load

increment is applied and each set of levels is taken.

Intermediate increments of load need be maintained only for

the period corresponding to the immediate settlement.

Maintained load test: When the final load increment has

been applied and the immediate settlement has been

measured, take further measurements of settlement at

suitable intervals of time, or until <0.1mm settlement is

recorded for last 24 hours.

Unloading: Remove the load in equal decrements

corresponding to the incremental application of load.

Immediately following each load decrement measure the

vertical movement of the pad.

Apply data through relevant calculations.

LANDPAC Ground Engineering LTD

Intelligent Ground Improvement

®

Tel: +44 8455005533 Web: www.landpac.co.uk E-mail: [email protected]

FACT SHEET – ZLT

ZONE LOAD TEST (ZLT)

Dynamically applied load

10km/hr - Three Sided HEIC

(Up to 70 surface coverages)

Bedded

ZLT Base Plate

Placed

Calibrated

Steel Blocks

Statically applied Load, up to 120kN/m2

(Depending on Specification)D

rain

ed S

tiff

ness M

odulu

s

Dra

ined S

tiff

ness M

odulu

s

Typical HEIC depth of influence down to 3m bgl - Typical ZLT bulb of pressure down 3m bgl