Project Status and Update
Mega Expansion Project KFSH& RC, Jeddah
Bismilllah ar–Rahman ar-Rahim
View on the Oncology Building
Follow this link to KFSH&RC-J Website: http://ig.kfshrc.edu.sa/wps/portal/
Monthly Report No. 23 April 2015
Areal view on the Oncology Building
Page 2 Mega-Expansion Project
UPCOMING ACTION ITEMS
APRIL SITE ACTIVITIES
General
Piling Phase II underway 52 of 344 Piles completed (288 Remaining)
27 cranes are now erected across the site
Oncology
First section of LINAC Vault walls cast successfully
Core 9 elevator walls cast up to level 1; Core walls cast to level 2
Tower level 3 part slab cast
Tower level 2 slab under construction
Block walls to the perimeter of the building and internal walls proceeding
Medical Areas
Raft sections being cast in ACC, D&T and Pediatrics Tunnel
High level raft sections in all areas being cast
Scaffold and slab decking for Tunnel roof underway in ACC and Pediatrics
Scaffold and slab decking to level 2 slab underway in all areas
Academic/Administration/Research complex
Columns up to level 1 in Research & Administration Buildings
Fist section of level 2 slab in Admin cast and underway in Research Building
Waterproofing & rebar to Academic Building raft slab underway
Central Utility Plant (CUP)/Kitchen & Laundry area
Walls in Water Tank under construction
CUP columns and walls cast
Casting Kitchen & Laundry raft strips
Casting CUP & Medical Powerhouses columns
Follow this link to KFSH&RC-J Website: http://ig.kfshrc.edu.sa/wps/portal/
Page 3 Mega-Expansion Project
APRIL SITE PHOTOGRAPHS
Follow this link to KFSH&RC-J Website: http://ig.kfshrc.edu.sa/wps/portal/
Oncology: Core 10 Elevator & Stair 30 walls level 1 to level 2
Oncology Tunnel: Core 9 Elevator walls rebar & closing shutters ready to cast
Page 4 Mega-Expansion Project
APRIL SITE PHOTOGRAPHS
Follow this link to KFSH&RC-J Website: http://ig.kfshrc.edu.sa/wps/portal/
ACC Tunnel: Rebar to walls; waterproofing & backfilling outside the tunnel
ACC Tunnel: Decking to the Tunnel roof slab
Page 5 Mega-Expansion Project
APRIL SITE PHOTOGRAPHS
Follow this link to KFSH&RC-J Website: http://ig.kfshrc.edu.sa/wps/portal/
Administration Building: First section of level 2 slab cast
ICU Tunnel: Puddle flanged sleeves through the Water Tank
Page 6 Mega-Expansion Project
APRIL SITE PHOTOGRAPHS
Follow this link to KFSH&RC-J Website: http://ig.kfshrc.edu.sa/wps/portal/
CUP: View looking NE of CUP slab and columns cast
Inpatients North: Construction works around Core 1 Elevators