meghraj capital advisors private limited
DESCRIPTION
Meghraj Capital Advisors Private Limited. Infrastructure Advisory I Mergers & Acquisitions I Syndication I Capital Markets. MYT-Features and Status of Implementation. Nagpur- 25 th February 2011. Vivek Mishra. Structure. Introduction to MYT - PowerPoint PPT PresentationTRANSCRIPT
Meghraj Capital Advisors Private Limited
MYT-Features and Status of ImplementationNagpur- 25th February 2011
Infrastructure Advisory I Mergers & Acquisitions I Syndication I Capital Markets
Vivek Mishra
Structure
I. Introduction to MYT Conventional Tariff Setting Process and its Limitations
Concept of MYT
Rationale and Benefits
II. Framework and Options Legal and Policy Framework
Current Status – India and International
Key Elements of MYT Framework Design
Options for MYT Framework Design
III. MYT Options in Detail Cost plus Regulation
Targeted Incentive Regulation
Performance based Regulation – Price and Revenue Cap
Risk and Return Framework of various Options
IV. MYT Options and Regulatory Objectives 2
3
I. Introduction to Multi Year TariffsI. Introduction to Multi Year TariffsI. Introduction to Multi Year Tariffs
4
I. Introduction to Multi Year TariffsI. Introduction to Multi Year Tariffs
● Till recently, most of the State Electricity Regulatory Commission in India have followed the annual process of tariff determination
● The mechanism involves: Establishing of Prudent costs each year by the Regulator Limited but assured return allowed in cost estimates (Concept Cost Plus
Regulation) Cost variations (above or below the approved figures) eligible for true-up at the
end of each year Limited or no incentive to outperform regulatory awards
Conventional Process of Tariff Setting
Key Limitations of Conventional Tariff Setting Process
• Mechanism is not sufficiently stable to provide the certainty required to
undertake long term investments
Principles are not clearly set and tendency to pad up costs
Annual evaluation and determination of “reasonable” costs
Possibility of change in regulatory principles from year to year
• The annual framework does not provide the requisite incentive
Any savings on account of better performance taken away next year
Any cost on account of under-performance is subject to regulatory discretion,
bringing in uncertainty
• Process is very long leading to high cost of regulation
5
MYT is an answer to make the tariff setting exercise more predictable, and to ensure that costs are recovered in a more mechanistic manner
MYT – The Concept
“ A new system where the tariff setting exercise is done for a
multiple years in one go, is termed as MYT”
• Concept of MYT can mean several things: Prescribing values/numbers on a multi-year basis for various elements of
cost/ARR
Adherence to prescribed benchmarks
Instead of prescribing numbers/values principles governing the input costs
and output prices for the multi year period can be done
6
Key Benefits of MYT
• Predictability
Leads to regulatory certainty
Simplification of regulatory process
• Innovation and Cost Reduction
Encourages utility to find innovative ways to reduce costs and improve
efficiency
Accompanied by a transparent and stable system of incentives
• Improvement in Customer service and satisfaction
There is a provision of reward/penalty to encourage achievement of the
prescribed customer service and satisfaction levels
• Risk allocation Determines the best entity to bear a particular risk
7
II. Multi Year Tariffs – Framework and Options
8
Legal and Policy Framework
• As of 31st March 2009, 14 states have notified
MYT regulations
Of the above 8 of them have issued one or
more tariff orders
A no. of other SERCs are in process of
development of MYT regulations
• Internationally, MYT has been implemented in
several countries
Latin America – Chile, Argentina, Brazil
Europe – UK, Spain
USA
Asia – Pakistan, Vietnam (in process), India
State MYT Regulations
MYT Orders
Andhra Pradesh √ √
Assam √ ×
Bihar √ ×
Chhattisgarh √ ×
Delhi √ √
Gujarat √ √
Himachal Pradesh √ √
Jharkhand √ ×
Karnataka √ √
Kerala √ ×
Madhya Pradesh √ √
Maharashtra √ √
Rajasthan √ √
Tamil Nadu √ ×
9
● Section 61(f) of the Electricity Act, 2003 requires the Appropriate Commission to be guided by the principles of MYT in tariff determination
● The National Tariff Policy notified by the Govt. of India in 2006 also provides for development of MYT framework by the States
Key Elements of MYT Framework Design
10
Measurability Materiality Controllability Predictability
Measurability of the element
around which incentivization
will be planned is important for design and
correct implementation
Risk Mitigation mechanisms
become necessary around those elements that have the potential to significantly impact the
performance of the utility
Measurability of the element
around which incentivization
will be planned is important for design and
correct implementation
The element will need to be
controllable to the utility to
enable them to beat regulatory
targets
The element will need to be predictable because the
ability to determine a
prudent level of regulatory target is crucial for the incentivization
process
Options in MYT Regulatory Framework Design
11
• Prudent costs established by Regulator
• Limited but assured return allowed in cost estimates
• Cost variations eligible for true-up
• Limited or no incentive to outperform regulatory awards
• Also called “Benchmark Regulation”
• Works on the basic cost plus framework but overlays incentives on cost plus
• Identifies cost pass through and risk mitigation elements clearly
• Having elements of TI and PBR (few elements on Multi-year basis)
• Uses the basic PBR and TI concepts
• Incentivizes better metering and loss reduction
Cost PlusRegulation
Targeted Incentive
Hybrid option
• Regulates by outcome and not by cost behaviour
• Utility at liberty to
manage costs and
enhance profits
• Initial rate setting
based on cost of
service
• Two basic variants -
price cap and
revenue cap
Performance Based Regulation
Choice of framework will depend on implementation capabilities of the sector entities
Conventional Options for MYT Framework
III. MYT Framework Design – Options in Detail
12
Cost Plus Regulation or Rate of Return
• Is the traditional form of US regulation and has been extensively used in
India
In India, the approved costs are reviewed every year against the historic costs
• Prices are set to allow the recovery of allowed costs and the required rate
of return
• Perceived as relatively less risky, the capital costs of the company is lower
than under other approaches
• Regulation becomes intrusive:
costs are assessed for their prudency
investments are assessed as to their ‘used-and-useful’ status
• Company has the incentive to Gold-Plate Investments and has no
compulsion to achieve efficiency savings
• Profit volatility should be minimized but price and revenue volatility may be
high
13
Targeted Incentive based Regulation
• Specific targets set for some important operating elements for the
duration of the control period
Losses
Collection Efficiency
Operating Expenditure
Quality of Service parameters etc
• All other cost elements subject to normal cost-plus regulation
• Improvements over and above the targets to the account of utility or
shared with consumers and vice-versa
• Most of the SERCs in India have adopted the Targeted Incentive
approach
14
Performance Based Regulation (PBR)
• Under PBR, rules of the road are better known up front
Reduced risk of prudence disallowance and greater flexibility for utilities, utilities prefer
such regulatory structure
The frequency of rate cases is reduced and there are reduced administrative costs
• Helps in reduction of overall cost of service to the customers and improve
system reliability and quality of service to customers
• In order to achieve public policy goals, the Regulator can set specific
goals for utility management to focus on, such as promoting Demand Side
Management, and supply diversity
• Characterised by RPI-X+Y formula
Base cost set at beginning of control period based on historical cost data
Efficiency gains/losses to account of utility
Pass through of external costs (Y) allowed
• Variants of PBR include “Price Cap” and “Revenue Cap”
15
Price-Cap
• Price path established for a set price control period (in the extreme, to the end of the useful life of the asset, but normally for 3 to 5 years)
Price path is based on forecast of operating and capital costs
• Provides the company with an opportunity, if it outperforms the forecasts, of earning a rate of return higher than required
• Incentives are, however, linked with a higher required return, owing to the greater risk faced by the company
• Regulation is, in theory, less intrusive and the more detailed price review only happens once every 3 to 5 years
• Company has the incentive to game - especially by under estimating demand
• No price volatility but revenue and profits may be volatile
• Has been used in England, Chile, Brazil, Australia
16
Revenue-Cap
• Rather than setting a price-path, revenue-cap regulation establishes a fixed revenue profile
Removes incentive to under-forecast demand
Limits the upside potential to the company to those cost aspects actually under the
control of the company
• Most useful for industries where the fixed costs dominate the cost base
• Requires a correction factor in the formula so that any under or over-recovery of revenue can be corrected within the life of the price control
• Can lead to moderate price and profit volatility
• Has been used in Spain, Norway, Netherlands, Denmark
17
Risk and Return Framework of various Options
FeatureAnnual CoS
Regulation
Targeted Incentive / Benchmark Regulation
Performance Based Regulation
Risk Mitigation High Moderate to High Moderate to High
Regulatory Involvement
High Moderate to High Low
Incentive Low Moderate to High High
Benefit sharing To Consumers Shared To Utilities
Information Requirement
Moderate Moderate High
Measurement Requirement
High Moderate Low
18
Choice largely depends on the level of data availability, stability in the current regulatory framework, socio-economic and political considerations etc. An option
could also be to gradually move from Annual CoS Regulation to more advance form of Performance based Regulation
III. Building blocks of MYT
19
Control Period
• Implies the period for which the principles for determination of allowable revenue and the applicable norms remain unchanged
Provides regulatory certainty
Length of the control period determines the incentives available as the surplus available
consequent to superior performance can be retained for the length of the control period
Converse is also true as losses too have to be retained for the control period
• Several aspects need to be considered while deciding the length of the control period
Should be sufficiently long so that utilities have the incentive to investment as the probability
for costs recovery is higher. Also the benefits accrue for a longer period
Should not be very long as this would result in inflexible MYT framework
Could lead to excess profits or losses for the utilities
20
Control Period contd..
• Commission determines the control period by taking into account: licensees proposal
data regime in the state
preparedness of the licensees to implement the proposed changes
• Involves periodic reviews by Regulator from time to time, and
• Review at the end of the control period to factor in the “learning” for the next control period
21
22
MYT Control Period duration across states in India
States Control Period First Year of Control Period
Andhra Pradesh First control period = 3 years and subsequent control period = 5 years
FY 2006-07
Assam Generation = First control period, 5 years from 1st April 2006; Transmission = First control period, 3 years from 1st April 2006; Distribution = First control period, 3 years from 1st April 2006
FY 2006-07
Delhi First control period = 4 years and subsequent control period = 5 years
FY 2007-08
Jharkhand First control period = 3 years and subsequent control period = 5 years
Not specified
Kerala First control period = 3 years and subsequent control period = 5 years
FY 2007-08
Madhya Pradesh First control period = 3 years FY 2006-07
Maharashtra First control period = 3 years and subsequent control period = 5 years
FY 2006-07
West Bengal First control period = 1 year; Second control period = 3 years; Subsequent control periods = 5 years
FY 2007-08
22
To start with the control period may be on the shorter side
Controllable Elements
• Sales
• System Losses – Transmission and Distribution
• Power Purchase Cost (except variation in fuel cost & GCV)
• Operating Parameters
• Debt Equity Ratio
• Operating Expenditure
Employee Cost
Administrative and General Expenses
Repair and Maintenance Expenses
• Working Capital Requirement
• Interest Cost and Interest Rate
• Capital Expenditure
• Quality of Supply
• Collection Efficiency
• Bad Debts
23
There are divergent views on Sales & Transmission losses some consider these to be uncontrollable
Un-Controllable Elements
• Price of Fuel – Coal or Oil
• Gross Calorific Value of Coal/Oil
• Terminal benefits of the employees
• Force Majeure Events
• Changes in law, judicial pronouncements and orders of the Central and State Government or the Commission
• Economy-wide fluctuations like changes in inflation rates, market rates, taxes and statutory levies etc.
24
Elements of cost and other parameters which are beyond the reasonable control of the Utility are considered uncontrollable
IV. Prerequisites for implementing MYT
25
Implementation Pre-requisites
• Good baseline data for reasonable estimation of future costs and performance (and hence efficiency gains)
System losses, power demand, power purchase costs, operating expenditures, un-metered
consumption etc.
All the should be estimated through actual measurement or scientific studies
• Nevertheless, Regulatory process should not wait for perfect information to be first available
Process and mechanism can be introduced that improve the data regime in due course
However, reliable and timely information is an imperative, and all steps should be taken to
achieve this
• Strong and robust measurement and monitoring mechanisms through the control period For approval of incentive/disincentive linked to actual performance
For incorporating the feedback in the subsequent control period
26
27
Key Imperatives for MYT Implementation (Prior to the control period)
27
Load Forecasting Study
Generation Planning (Supply Side Analysis)
System and Network Planning Study
Study for estimation of un-metered
consumption`
Determination of Power Purchase Requirement
and Optimization
Opex Efficiency Targets and Verification Framework
Collection Efficiency
Assessment
ARR Projections
Development of Regulations (Including
incentive and monitoring framework)
Study on Actual Loss Estimation
Realistic Capex Estimation and
Evaluation Framework
Tariff Determination and Rationalization
Preparation of Business Plans/Account Separation
Dissemination Workshops for Stakeholders
Plan for Meaningful Consumer Participation
Revenue and Billing Analysis
Monitoring and Verification Framework
28
Key Imperatives for MYT Implementation (During the control period)
28
Establishment of Robust MIS
System
Monitoring of Controllable parameters
Capex Monitoring
Regular monitoring
and generation of
reports
Data collection process and system audit
Assessment of Performance & Validation of
Computations
Monitoring of uncontrollable
parameters
Compliance of Directions
Corrective Actions –
Implementation timelines
Overall System Audit
Thank You