mersey gateway bridge project · 2014. 10. 22. · mer-cjv-rep-tmp-02-510117 3 22 october 2014...

17
MERSEY GATEWAY BRIDGE PROJECT MERSEYLINK CONSTRUCTION METHOD REPORT SECTION 2 WIDNES LOOPS JUNCTION OCTOBER 2014 MER-CJV-REP-TMP-02-510117

Upload: others

Post on 27-Jan-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

  • MERSEY GATEWAY BRIDGE PROJECT

    MERSEYLINK CONSTRUCTION METHOD REPORT SECTION 2 WIDNES LOOPS JUNCTION OCTOBER 2014

    MER-CJV-REP-TMP-02-510117

  • Construction Method Report Section 02 – Widnes Loops

    DARESBURY OFFICE

    Document Control Sheet Rev. Status Revision History Date By Check Approved

    0 PD For Planning Discharge 22/10/14 JR SM SG

    Merseylink CJV 7400 Daresbury Park Daresbury Warrington Cheshire WA4 4BS Tel: +44 (0)1928 785700

  • Construction Method Report Section 02 – Widnes Loops

    DARESBURY OFFICE

    TABLE OF CONTENTS

    1 Introduction ............................................................................................................. 1

    1.1 Introduction ....................................................................................................... 1

    2 Construction ............................................................................................................ 5

    2.1 Site Access ....................................................................................................... 5

    2.2 Site Clearance & Demolition ............................................................................. 5

    2.3 Construction Methods ....................................................................................... 6

    2.4 Services Diversion/Protection ........................................................................... 8

    3 Construction Vehicles And Numbers .................................................................... 9

    4 Site Compound ........................................................................................................ 9

    5 Traffic Management Issues .................................................................................. 10

    6 Environmental Issues ........................................................................................... 11

    6.1 Construction Environmental Management Plan .............................................. 11

    6.2 Waste Estimates ............................................................................................. 12

    7 Appendix A - Supporting Documents .................................................................. 13

  • Construction Method Report Section 02 – Widnes Loops

    MER-CJV-REP-TMP-02-510117 1 22 OCTOBER 2014

    1 INTRODUCTION

    1.1 Introduction

    1.1.1 This Construction Method Report (CMR) outlines the extent and sequence of work

    required to construct the permanent highway works at Widnes Loops - Section 2 of the

    Mersey Gateway Project.

    1.1.2 This document develops the information about the construction of Victoria Widnes Viaduct

    contained in the CMR reference: MER-CJV-REP-TPL-00-5100011, for the entire Project

    Works, partially approved by the local planning authority in February 2014.

    1.1.3 Section 2 comprises the works between the Freight line and St Helens Canal. Section 2

    also includes links to the A577 Widnes eastern bypass that connects with junction 7 of the

    M62 to the north. See Figure 1 as an extract from drawing ref - MER-DJV-DRA-HWY-02-

    301052.

    Figure 1 Extent of Section 2

    1.1.4 The main line will remain elevated between the Freightline Bridge and St Helens Canal.

    The Widnes Loops junction roundabout will be constructed at the lower level at the

    intersection with Widnes Eastern Bypass. This will form a grade separated junction giving

    access to and from the Mersey Gateway to the south from the A577 Widnes Eastern

    Bypass.

  • Construction Method Report Section 02 – Widnes Loops

    MER-CJV-REP-TMP-02-510117 2 22 OCTOBER 2014

    1.1.5 The Garston to Timperley Rail Freightline structure will comprise of a precast Opti Cadre

    (closed cell box culvert to minimise bearing pressure on the underlying soil) system

    installed on a piled foundation.

    1.1.6 The elevated section of carriageway between the Freightline bridge and the Victoria and

    Widnes Viaduct will be constructed as an embankment from the Freightline to the edge of

    Victoria Road, where the Viaduct abutment will be constructed.

    Freight Line Railway Structure.

    1.1.7 The proposed design for the Freightline comprises a precast concrete portal (Opti Cadre)

    supported on a piled foundation. Wing walls will be of reinforced earth, which will further

    reduce the site work alongside the Garston Timperley Line. This proposal results in a

    quicker and more efficient construction sequence highly suited to the railway environment.

    The transport and erection of the large precast units will require the use of large mobile

    cranes. See Figure 2 as an extract from drawing ref MER-DJV-STR-02-342102.

    Figure 2 Elevation of Freightliner Bridge

    1.1.8 The ground that will support the abutments will be improved by use of dry soil mixing to

    form a cement stabilised soil column. These ground improvement works will be carried

    out by specialist rigs that sink an auger into the ground and then mix dry cement with the

    existing soil as the auger is withdrawn forming a column of cement stabilised soil.

  • Construction Method Report Section 02 – Widnes Loops

    MER-CJV-REP-TMP-02-510117 3 22 OCTOBER 2014

    Victoria- Widnes Loops Viaduct

    1.1.9 East of the Freightline structure will be an embankment leading to the south of the Victoria

    and Widnes Viaduct. In areas of the new embankment, the ground that will support the

    abutments will also be improved by dry soil mixing.

    1.1.10 The new viaduct integrates the Victoria and Widnes bridges into one continuous structure

    and therefore eliminates the need for abutments and earthwork structures between

    Victoria road and Widnes Loops. This is deemed to be the most efficient and effective

    design solution.

    1.1.11 The Viaduct will be a 7 span structure terminating on a large abutment to the east of

    Victoria Widnes Loops. The bridge deck is constructed with pre-cast pre-stressed “W”

    beams with an in-situ concrete deck slab. The deck is supported on reinforced concrete

    abutments and piers. The piers are founded on precast piles. The abutment will comprise

    piled foundations, pile caps, abutment walls and reinforced earth wing walls. See Figure 3

    as an extract from drawing ref MER-DJV-STR-02-343101.

    Figure 3 Elevation of Widnes Loops Viaduct

    Test Piles

    1.1.12 As part of the initial construction works a series of sacrificial test piles will be

    implemented. The location of these test piles are adjacent to the permanent pile

    foundations as follows:

    Widnes Loops

    Pier G8, Pier G4 (within Catalyst Park) and Pier G1 (rear of Spraycraft premises on

    Hutchinson Street) as indicated in Figure 4

  • Construction Method Report Section 02 – Widnes Loops

    MER-CJV-REP-TMP-02-510117 4 22 OCTOBER 2014

    Figure 4 Location of Test Piles at Widnes Loops Viaduct

    Freightline Bridge

    East abutment (Former Fallons yard) and West abutment (former Sammy Evans yard) as

    indicated in Figure 5.

    Figure 5 Location of Test Piles at Freightliner Bridge

  • Construction Method Report Section 02 – Widnes Loops

    MER-CJV-REP-TMP-02-510117 5 22 OCTOBER 2014

    1.1.13 The method for undertaking these works will be the same as for the test piles in other

    parts of the Mersey Gateway Project previously agreed by the local planning authority

    (LPA) to be permitted development.

    1.1.14 The piling risk assessment for these test piles will be included as an appendix in the

    Contamination Management Plan within the COPE / CEMP.

    2 Construction

    2.1 Site Access

    2.1.1 Access to the Freightline structure is expected to be via haul roads from Victoria Road to

    the south and Ditton Road to the north. Alternatively, we will use existing roads or hard

    standings. The access to the rail side will be gained following liaison with Network Rail.

    Rail possessions will be required for constructing the Opti Cadre structure and for

    installing various infrastructure protection measures to enable construction activity

    adjacent to the live railway.

    2.1.2 Access to Victoria & Widnes Viaduct shall be via Victoria Road and Hutchinson Street,

    with signage in place warning road users of the entrances into site. Access Point 2A into

    the Catalyst compound is already established and are details included in the approved

    compounds submission to the LPA.

    2.1.3 Access to Widnes Loops and the embankments between Victoria and Widnes Viaduct

    and St Helens Canal shall be via the existing Catalyst Park entrance. Abnormal load

    access is available via Widnes Eastern Bypass using the existing emergency access to

    Spike Island.

    2.2 Site Clearance & Demolition

    2.2.1 The new carriageway crosses the Victoria Road area at a height of approximately 10m

    above current road level. The area will be cleared of the existing brick structures and the

    arisings re-engineered and utilised for fill or capping materials in the same area. Existing

    services will be isolated or diverted accordingly.

  • Construction Method Report Section 02 – Widnes Loops

    MER-CJV-REP-TMP-02-510117 6 22 OCTOBER 2014

    2.2.2 The light industrial units within the Catalyst area, will be dismantled and materials

    recycled. All existing services will be isolated or diverted accordingly.

    2.2.3 The ground below the Catalyst area is known to contain high levels of contamination.

    Remediation was carried out as advanced work in this area with on-going monitoring

    being carried out by the Project team. All excavation in this area will be kept to a

    minimum.

    2.2.4 All site won materials (engineered if required) will be re-used in the Project where

    reasonably practicable.

    2.3 Construction Methods

    Freightline Bridge

    2.3.1 The Freightline bridge structure comprises the installation of a precast reinforced concrete

    portal, supported on precast pile foundations.

    2.3.2 Following the site clearance, a piling platform will be formed along the length of the

    structure on both sides of the track within adjacent compounds (Compound C4 - MER-

    CJV-DRA-WAF-01-501065 and Compound C6a - MER-CJV-DRA-WAF-02-501068

    rev01).

    2.3.3 This piling platform will be utilised for both the installation of the temporary sheet piles and

    the installation of the permanent precast piles.

    2.3.4 Once the temporary sheet piles have been installed to allow excavation landward side of

    the running line, and the ground subsequently reduced, the installation of the precast piles

    will commence.

    2.3.5 The temporary sheet piles will work twofold, initially to retain the ground and secondly, if

    left, the piles 2m above AOD can be utilised as the temporary site boundary/fence line.

    This will mean that all works landward side of the sheet pile would be within the scheme

    boundary and therefore outside of any possession of Network Rail land. This will make

    the works more controllable and therefore programme efficient.

    2.3.6 Once the permanent piles have been installed the pile cap area will be excavated. The

    arising’s are likely to be contaminated, which will result in the material being treated prior

    to re-use in the earthworks. The method of construction of the portal frame will require the

    use of mobile cranes of various capabilities.

  • Construction Method Report Section 02 – Widnes Loops

    MER-CJV-REP-TMP-02-510117 7 22 OCTOBER 2014

    Freightline Bridge Retaining Wall

    2.3.7 The retaining wall comprises of a short structure to avoid the impacts of the road

    embankment on an existing building known as Todds Building.

    2.3.8 The structure will comprise a reinforced ‘L’ shaped concrete wall with plain concrete

    finish. The wall will be constructed on an ‘improved ground’ area of excavation. The

    maximum height of the wall will be 4.4m with sloping sides that correspond to the angle of

    slope of the proposed embankment with a permeable drainage layer provided on the rear

    face.

    2.3.9 A timber post and 4 rail fence constructed to standard details will be provided at the top of

    the wall for pedestrian safety.

    Victoria-Widnes Viaduct

    2.3.10 The sequence of the construction of Victoria Widnes loops is best shown on the extract

    below from drawing MER-DJV-STR-02-343105 as Figure 6. This extract clearly shows the

    construction of the viaduct will progress from Pier G8 in the east, to Pier G1 in the west.

    2.3.11 The ground supporting the main line embankment from the Victoria & Widnes Viaduct to

    the north approach structures will be improved by dry soil mixing.

  • Construction Method Report Section 02 – Widnes Loops

    MER-CJV-REP-TMP-02-510117 8 22 OCTOBER 2014

    Figure 6 Victoria-Widnes Loops Viaduct Construction Sequence

    2.4 Services Diversion/Protection

    2.4.1 Discussions about the impact of the works on utilities have been held with United Utilities,

    National Grid, BT and Scottish Power.

    2.4.2 There are also continuing discussions with United Utilities with respect to the location and

    monitoring of the existing 1050 sewer during the proposed works. The abutment piers

    have been designed such that they will miss this sewer.

    2.4.3 There is an existing manhole which is located in the future Widnes Loops access road. It

    has been agreed with the utility company that this will be capped off and abandoned.

    2.4.4 There is also a proposed attenuation pond that has been redesigned to maintain access

    to an existing manhole for United Utilities operatives.

    2.4.5 National Grid (Medium and Low pressure) and Scottish Power have been engaged to

    disconnect existing services to the buildings still due for demolition. These redundant

    services will be removed to suit the construction programme.

  • Construction Method Report Section 02 – Widnes Loops

    MER-CJV-REP-TMP-02-510117 9 22 OCTOBER 2014

    3 Construction Vehicles and Numbers

    3.1.1 Site Clearance along Victoria Road and at the Catalyst will require approximately 100

    HGV movements to remove the arising’s from the demolition of the existing buildings. The

    existing embankment will be removed by approximately 800 HGV movements, with the

    material being used in the remodelling of the new embankment. The concrete beams from

    the 2 existing bridges and the reinforced concrete superstructures will be broken up and

    the steel recycled and the concrete debris may be incorporated into the landscaping

    embankment areas.

    3.1.2 The proposed construction of the integrated Victoria and Widnes Viaduct has resulted in

    the reduction of approximately 100 HGV movements in respect of the ground

    improvement and embankments no longer required. The number of concrete HGV

    movements will also be considerably reduced with the introduction of an onsite concrete

    plant in the Catalyst area.

    3.1.3 Other plant proposed for this element of the works are: specialist piling rigs, mobile

    cranes, dozers, rollers, pavers and general excavation plant. The construction of the

    bridges in the area will involve the delivery of materials that will include, scaffolding,

    formwork and falsework, reinforcement, concrete pumps and aggregate HGV’s.

    4 Site Compound

    4.1.1 The site welfare facilities for the works associated with Victoria and Widnes Viaduct will

    be established within the newly refurbished Viking House Compound (C4), which is

    located along Ditton Road.

    4.1.2 This work will require a workforce of approximately 50 operatives with office, car parking,

    welfare and messing facilities being accommodated at this compound. All operatives will

    use a site mini bus service to be transported to their place of work.

    4.1.3 The proposed layout is as indicated on drawing: MER-CJV-DRA-WAF-01-501065. Site

    access to the compound will be from Ditton Road and via the existing access point. Local

    signage will be provided giving advance warning of site access as indicated on drawing:

    Site Access 1A - MER-CJV-DRA-TMP-01-501092.

    4.1.4 The perimeter of the compound is bounded by a combination of fencing and walling which

    will be retained. Additional block and mesh fencing will be provided for our facilities, as

    necessary.

  • Construction Method Report Section 02 – Widnes Loops

    MER-CJV-REP-TMP-02-510117 10 22 OCTOBER 2014

    4.1.5 All services are currently live into Viking House. These services will be utilised and

    extended for the additional site accommodation, which will be brought into the compound

    area to service the workforce.

    4.1.6 Flood lights will be fitted to the external perimeter of the temporary buildings and

    maintained and extended to illuminate the compound areas. There are no residential

    occupiers in the vicinity likely to be disturbed by the lighting.

    4.1.7 On-site car parking for a minimum of 137 people has been identified for staff and

    construction operatives using the facilities. This will be provided at the compound (C2), as

    indicated on drawing: MER-CJV-DRA-WAF-01-501154. As mentioned above, a mini bus

    service will be established to take operatives to site.

    4.1.8 Wheel cleaning facilities will be available depending on the volume of site traffic using the

    compound and exiting onto the local roads system. As a minimum a hand operated power

    jet wash system will be utilised to clean wheels. However, in periods of peak traffic flows

    from site a self-contained wheel wash will be located adjacent to the site entrance and

    prior to the exit. This will be suitable for all site vehicles.

    4.1.9 Fuel storage will be located adjacent to the main offices. This will consist of a double

    bunded tank facility located on a concrete hard-standing with drip trays and spill kits also

    being available. The storage tank is located away from any existing drainage system in

    order to minimise spillage risks.

    5 Traffic Management Issues

    5.1.1 Key to the northern landside section of the Project and completion of the northern

    approach to the main crossing will be ensuring the traffic management phasing facilitates

    the earthworks strategy. To construct the embankments for the approach through Ditton

    and Widnes Loops, the earthworks material in the existing embankments will need to be

    excavated and re-used in the new embankments.

    5.1.2 At this stage there are no major Traffic Management layouts planned in Phase 1, we are

    currently developing the Phasing strategy for Phases 2 and 3 which start later in the

    programme. These plans will be agreed through the LPA process within the agreed

    timescales.

  • Construction Method Report Section 02 – Widnes Loops

    MER-CJV-REP-TMP-02-510117 11 22 OCTOBER 2014

    5.1.3 Some incidental localised Traffic Management may be required as the works progress in

    Phase 1, for such works as service diversions. These TM layouts will be agreed with HBC

    highway authority. All notice periods will be adhered to for the approval of such works.

    5.1.4 All pedestrian routes around the area will be maintained throughout the construction

    phases although minor diversions may be required in specific locations as the works

    progress. These, too, will be agreed with HBC highways authority in advance.

    Construction plant and pedestrians will be segregated at all times and warning signage

    displayed at all crossing points.

    6 Environmental Issues

    6.1 Construction Environmental Management Plan

    6.1.1 Environmental issues relating to the work in Section 2 is outlined in the CEMP cover

    report document MER-CJV-PMP-ENV-00-510904 rev 3. This document outlines the

    environmental issues relating to the works envisaged and explains how the following

    Management Plans will be implemented;

    Pollution Prevention including Traffic Management and Water Quality

    Waste

    Biodiversity

    Noise and Vibration

    Air Quality

    Contamination

    Archaeology

    6.1.2 The CEMP cover document includes environmental issues relating to Section 1, 2 and 9.

    An earlier version was submitted for works in Section 1 and has now been updated to

    cover the works outline in this report.

    6.1.3 This CEMP cover report and the associated core environmental documents have been

    agreed, with the LPA, to remain as a ‘live’ submission under planning reference

    14/00484/MGCON to 14/00487/MGCON. This CMR report should therefore be read in

    conjunction with the most current ‘live’ submission.

  • Construction Method Report Section 02 – Widnes Loops

    MER-CJV-REP-TMP-02-510117 12 22 OCTOBER 2014

    6.2 Waste Estimates

    6.2.1 It is estimated that site clearance will generate approximately 20m3 of green waste and

    vegetation.

    6.2.2 The demolition of the existing industrial buildings along Hutchinson Street and within the

    Catalyst Park compound will generate approximately 5000m3 of building waste

    comprising, brick, concrete, reinforcement and steel sections.

    6.2.3 The excavation of the existing Widnes eastern bypass carriageway will generate

    approximately 9000 m3 of waste road construction materials.

    6.2.4 Pile arising’s from the construction of the foundations of the new Freightline structure,

    Victoria and Widnes Viaduct, East Bridges and St Helens Canal bridge are estimated to

    comprise of 9700m3 of contaminated material. We propose to treat and re-use this

    material in the construction of the works.

    6.2.5 The construction of the new structures will generate approximately 750m3 of waste

    construction materials, comprising timber formwork, reinforcement, concrete and empty

    drums and containers.

    6.2.6 The new carriageway drainage will involve the excavation of contaminated materials. We

    estimate that approximately 2500m3 of this material will either be treated and re-used in

    the works or removed off site to an appropriate licenced facility for further treatment or

    disposal.

    6.2.7 All these materials will be stored and treated in accordance with the Waste Management

    Plan (MER-CJV-PMP-ENV-00-510034 rev 01) within the Construction Environmental

    Management Plan cover report (MER-CJV-PMP-ENV-00-510904).

  • Construction Method Report Section 02 – Widnes Loops

    MER-CJV-REP-TMP-02-510117 13 22 OCTOBER 2014

    8 APPENDIX A - Supporting Documents

    Victoria-Widnes Loops Viaduct

    General arrangement sheet 1 of 2 - MER-DJV-DRA-STR-02-343101_iss5_rev03

    General arrangement sheet 2 of 2 - MER-DJV-DRA-STR-02-343102_iss5_rev03

    Construction Sequence - MER-DJV-DRA-STR-02-343105_iss2_rev01

    Abutment G1 Pile Layout - MER-DJV-DRA-STR-02-343201_iss2_rev01

    Piers G2-G7 Pile Layout - MER-DJV-DRA-STR-02-343202_iss3_rev02

    Abutment G8 Pile Layout - MER-DJV-DRA-STR-02-343203_iss2_rev03

    Abutment G1 dimensions - MER-DJV-DRA-STR-02-343310_iss2_rev01

    Pier G2 dimensions sheet 1 of 2 - MER-DJV-DRA-STR-02-343320_iss1_rev-

    Pier G2 dimensions sheet 2 of 2 - MER-DJV-DRA-STR-02-343321_iss1_rev-

    Piers G3-7 dimensions - MER-DJV-DRA-STR-02-343330_iss2_rev01

    Abutment G8 dimensions - MER-DJV-DRA-STR-02-343380_iss1_rev-

    Deck dimensions sheet 1 - MER-DJV-DRA-STR-02-343410_iss2_rev-

    Freightline Bridge

    Freightline Bridge General Arrangement sheet 1 of 3 - MER-DJV-DRA-STR-02-342101_iss1_rev-

    Freightline Bridge General Arrangement sheet 2 of 3 - MER-DJV-DRA-STR-02-342102_iss1_rev-

    Freightline Bridge General Arrangement sheet 3 of 3 - MER-DJV-DRA-STR-02-342103_iss1_rev-

    Freightline Bridge Construction Sequence - MER-DJV-DRA-STR-02-342104_iss1_rev-

    Freightline Bridge Pile and Pile Cap Details - MER-DJV-DRA-STR-02-342201_iss1_rev-

    Freightline Bridge Retaining Wall

    Freightline Bridge Retaining Wall GA - MER-DJV-DRA-STR-02-466160_iss4_rev03

    Freightline Bridge Retaining Wall Plan & Profile - MER-DJV-DRA-STR-02-466161_iss4_rev03

    Freightline Bridge Retaining Wall Cross Sections - MER-DJV-DRA-STR-02-466163_iss4_rev03

  • Construction Method Report Section 02 – Widnes Loops

    MER-CJV-REP-TMP-02-510117 14 22 OCTOBER 2014

    Freightline Bridge Retaining Wall Details - MER-DJV-DRA-STR-02-466167_iss4_rev03

    Site Access and Compounds

    Site Access 1A - MER-CJV-DRA-TMP-01-501092 rev-

    Compound C2 Parking - MER-CJV-DRA-WAF-01-501154_iss2_rev01

    Compound C4 - MER-CJV-DRA-WAF-01-501065 rev-

    Compound C6a - MER-CJV-DRA-WAF-02-501068 rev01