    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    METHOD OF STATEMENT

    BOX UP AND PIPE SLEEVE

    FOR

    INSTALLATION

  • 8/14/2019 Method Box and Sleeve 3

    2/28

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    : TPOLY-MOS-30-100-00

    : 00

    : Box up and pipe sleeve installation

    Effective Date Issue No.

    Name: Name: Name:

    Prepared By: Reviewed By: Approved By:

    THAI POLYCONS PUBLIC COMPANY LIMITED

    CHEVRON THAILAND AVIATION CONSOLIDATION PROJECT

    TPOLY DOCUMENT NO.

    REVISION

    TITLE

    AUTHORISATION

    Mr.Chaiya W. Mr.Chawalit M. Mr.Chanwit Chaleoiad

    Signature: Signature: Signature:

    Date: Date: Date:

    NOTE : A CONTROLLED copy is valid only if stamped "C" in red,

    Uncontrolled copy will Not be updated or amended.

    Please refer to a controlled copy or check for amendments before use.

    AMENDMENT / RELEASE RECORD

    M&E Project Manager Project ManagerM&E Project Engineer

  • 8/14/2019 Method Box and Sleeve 3

    3/28

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    Subject Page No.

    1. General 12. Material 1

    3. Equipment & Tool 2

    4. Box up and pipe sleeve installation procedures 3

    5. Quality Assurance 4

    6. Appendix 5

    6.1 Flow chart 6

    6.2 Illustation. 8

    CONTENT

    .3 Details drawing of Box up and sleeve installation 9

    6.4 Schedule 11

    6.5 Resources 15

    6.5.1 Equipment schedule 16

    6.5.2 Man Power schedule 19

    6.6 Inspection and Test Plan 22

    6.7 Check list of Work 24

  • 8/14/2019 Method Box and Sleeve 3

    4/28

    METHOD STATEMENT

    FOR

    COLD WATER PIPE INSTALLATION AND TESTING

    1. General

    This method statement is to describe the intended work method and control measures for the

    pipe sleeve installation which is carried out for this project.

    2. Material

    2.1 Material of Pipe Sleeve

    Item Description

    1 Black steel pipe

    2 Black iron wire

    3 Rebar 2-db mm.

    2.2 Material of Box Up

    Item Description

    1 Ply wood minimum of thickness is 5/16 (8 mm)

    2 Nail

    3 Black iron wire

    4 REBAR 2-DB MM.

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

  • 8/14/2019 Method Box and Sleeve 3

    5/28

    Project: Chevron Thailand Aviation Consolidation Owner: Chevron

    Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    4. Box up and pipe sleeve installation Procedure

    4.1Setting out Survey

    4.1.1 From the survey, the issued drawings will be marked up detailing all containment location and

    proposed materials and equipment to be installed for approval. Actual commencement of the

    installation works would be agreed with the client and main parties, which would also depend on the

    working areas being made available. The installation system will be installed in accordance with the

    safety policy using plan and equipment to suit the application.

    4.2 Check Location of working areas.

    4.2.1 The working area will be cleared and being made available.

    4.3 Installation

    4.3.1 Project specification, all works/operations will be carried out in accordance with all proven methods

    and industry standards.

    4.3.2 On completion of the installation, all of the location and position will be followed in the referential

    drawing

    4.4 Inspection

    4.4.1 Materials shall supply to the Consulting Engineer's for his approval certificates from the

    manufacturer, showing that the materials have been tested according to the relevant specification or

    standard.

    4.4.2 The Project Engineer and supervisor will make the visual inspection of the location and position also

    others. Then request to the Consulting Engineer's inspector to inspected and approved. TheInspection must continuity in accordance with Approved M&E inspection check list to ensure that all

    sleeves or box up were immovable. And work properly.

    4.4.3 If inspection or tests show defects, such defective work or material shall be replaced and

    Inspection and tests shall be repeated.

  • 8/14/2019 Method Box and Sleeve 3

    6/28

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    3.Equipment and ToolBasic equipment for the mark will be as follows.

    Item

    1

    2

    3

    4

    5

    Hammer

    Saw

    Equipment / Tool

    Cutter

    Pincers

    Cut off machine for 14" cutting discs

  • 8/14/2019 Method Box and Sleeve 3

    7/28

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    5. Quality Assurance

    All works will conform to the standards set out. Material on site approval by DEC. the work proced

    corresponds with visual method of statement. The proposed inspection and test plans (ITP) are shown

    in the appendix.The proposed Inspection and Test Plans (ITP) are shown in the Appendix.

  • 8/14/2019 Method Box and Sleeve 3

    8/28

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    6. APPENDIX

  • 8/14/2019 Method Box and Sleeve 3

    9/28

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    6.1 FLOW CHART

  • 8/14/2019 Method Box and Sleeve 3

    10/28

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    FLOW CHART FOR BOX AND SLEEVE INSTALLATION

  • 8/14/2019 Method Box and Sleeve 3

    11/28

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    6.2 ILLUSTRATION

  • 8/14/2019 Method Box and Sleeve 3

    12/28

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    6.3 DETAILS DRAWING OF

    BOX UP AND SLEEVE INSTALLATION

  • 8/14/2019 Method Box and Sleeve 3

    13/28

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

  • 8/14/2019 Method Box and Sleeve 3

    14/28

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    6.4 SCHEDULE

  • 8/14/2019 Method Box and Sleeve 3

    15/28

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    Box up and Sleeve (Work Schedule)

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

    1 Water Treatment Plant (Pump Room) 3 days 2/11/09 4/11/09

    1.1 Setting out survey 1 day 2/11/09 2/11/09

    1.2 Check Location of working areas 1 day 2/11/09 2/11/09

    1.3 Installation 1 day 3/11/09 4/11/09

    1.4 Inspection 1 day 4/11/09 4/11/09

    Item Description Duration Start Finish

    Box up and sleeve schedule

    For November 2009

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

    2 S,W,V System ground floor 3 days 3/1/10 5/1/10

    2.1 Setting out survey

    2.2 Check Location of working areas

    2.3 Installation

    2.4 Inspection

    3 Cold Water Supply System ground floor 3 days 10/1/10 12/1/10

    3.1 Setting out survey

    3.2 Check Location of working areas

    3.3 Installation

    3.4 Inspection

    Description Duration StartItem Finish

    Box up and sleeve schedule

    For January 2010

    Page 12

  • 8/14/2019 Method Box and Sleeve 3

    16/28

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    Box up and Sleeve (Work Schedule)

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

    4 S,W,V System second floor 3 days 10/1/10 12/1/10

    4.1 Setting out survey

    4.2 Check Location of working areas

    4.3 Installation

    4.4 Inspection

    5 Fire protection ground floor work 3 days 10/1/10 12/1/10

    Item Description Duration Start Finish

    Box up and sleeve schedule

    For January 2010

    5.1 Setting out survey

    5.2 Check Location of working areas

    5.3 Installation

    5.4 Inspection

    6 Air conditioning system ground floor 3 days 10/1/10 12/1/10

    6.1 Setting out survey

    6.2 Check Location of working areas

    6.3 Installation

    6.4 Inspection

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

    7 Fire protection ground floor work (Pump Room) 3 days 6/2/10 8/2/10

    7.1 Setting out survey

    7.2 Check Location of working areas

    7.3 Installation

    7.4 Inspection

    Item Description Duration Start Finish

    Box up and sleeve schedule

    For Febuary 2010

    Page 13

  • 8/14/2019 Method Box and Sleeve 3

    17/28

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    Box up and Sleeve (Work Schedule)

    Item Description Duration Start Finish

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

    8 Fire protection second floor work 3 days 10/2/10 12/2/10

    8.1 Setting out survey

    8.2 Check Location of working areas

    8.3 Installation

    8.4 Inspection

    Box up and sleeve schedule

    Item Description Duration Start Finish

    Box up and sleeve schedule

    For Febuary 2010

    9 Cold Water Sypply System second floor 3 days 10/2/10 12/2/10

    9.1 Setting out survey

    9.2Check Location of working areas

    9.3 Installation

    9.4 Inspection

    10 Air conditioning system second floor 3 days 25/1/10 27/1/10

    10.1 Setting out survey

    10.2 Check Location of working areas

    10.3 Installation

    10.4Inspection

    11 ir conditioning system roof floor 2 days 1/2/10 2/2/10

    11.1 Setting out survey

    11.2 Check Location of working areas

    11.3 Installation

    11.4 Inspection

    Page 14

  • 8/14/2019 Method Box and Sleeve 3

    18/28

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    6.5 RESOURCES

    Project: Chevron Thailand Aviation Consolidation

    O Ch Th il d E l i d P d i Li i d

  • 8/14/2019 Method Box and Sleeve 3

    19/28

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    6.5 RESOURCES

    6.5.1 Equipment Schedule

    Location 1. Water Treatment Plant (Pump Room) (1 Place)

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

    a Cutter 1 1 1

    b Pincers 3 3 3

    c Cut Off Machine for 14" Cutting Discs 1 1 1

    d Hammer 1 1 1

    e Fishing Line 1 1 1

    f Steel tape 3 3 3

    Saw 1 1 1

    Item Description

    Box up and sleeve schedule

    For November 2009

    Page 16

    Total 11 11 11

    Location 2. Cold Water Supply System ground floor

    3. S,W,V System second floor4 .Fire protection ground floor work

    5. Air conditioning system ground floor (4 Places)

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

    a Cutter 4 4 4

    b Pincers 12 12 12

    c Cut Off Machine for 14" Cutting Discs 1 1 1

    d Hammer 4 4 4

    e Fishing Line 4 4 4

    f Steel tape 12 12 12

    g Saw 2 2 2

    39 39 39

    Item Description

    Box up and sleeve schedule

    For December 2009

    Page 16Page 16

  • 8/14/2019 Method Box and Sleeve 3

    20/28

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    7.1 RESOURCES

    6.5.1 Equipment Schedule (cont.)

    Location 6. S,W,V System ground floor (1Place)

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

    a Cutter 1 1 1

    b Pincers 3 3 3

    c Cut Off Machine for 14" Cutting Discs 1 1 1

    d Hammer 1 1 1

    Fishin Line 1 1 1

    Item Description

    Box up and sleeve schedule

    For January 2010

    Page 17

    f Steel tape 3 3 3

    g Saw 1 1 1

    11 11 11

    Location 7. Fire protection ground floor work (Pump Room) (1 Place)

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

    a Cutter 1 1 1

    b Pincers 3 3 3c Cut Off Machine for 14" Cutting Discs 1 1 1

    d Hammer 1 1 1

    e Fishing Line 1 1 1

    f Steel tape 3 3 3

    g Saw 1 1 1

    11 11 11

    Box up and sleeve schedule

    For Febuary 2010Item Description

    Page 17

  • 8/14/2019 Method Box and Sleeve 3

    21/28

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    6.5 RESOURCES

    6.5.1 Equipment Schedule (cont.)

    Location 8. Fire protection second floor work

    9. Cold Water Sypply System second floor

    10. Air conditioning system second floor (3 Places)

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

    a Cutter 3 3 3

    b Pincers 9 9 9

    c Cut Off Machine for 14" Cutting Discs 1 1 1

    d Hammer 3 3 3

    Item Description

    Box up and sleeve schedule

    For Febuary 2010

    Page 18

    e

    f Steel tape 9 9 9

    g Saw 2 2 2

    30 30 30

    Location 11.Air conditioning system roof floor (1 place)

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

    a Cutter 1 1

    b Pincers 3 3

    c Cut Off Machine for 14" Cutting Discs 1 1

    d Hammer 1 1

    e Fishing Line 1 1

    f Steel tape 3 3

    g Saw 1 1

    10 10

    Item Description

    Box up and sleeve schedule

    For Febuary 2010

    Page 18

    Project: Chevron Thailand Aviation Consolidation

    O Ch Th il d E l ti d P d ti Li it d

  • 8/14/2019 Method Box and Sleeve 3

    22/28

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    6.5 RESOURCES (Cont.)

    6.5.2 Man Power Schedule

    Location 1. Water Treatment Plant (Pump Room) (1 Place)

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

    Manpower

    a Project Engineer 1 1 1

    b M&E Super Visor 1 1 1

    c Headman 1 1 1

    d General labour 3 3 3

    e Safety Officer 1 1 1

    Item Description

    Box up and sleeve schedule

    For November 2009

    Page 19

    Total 7 7 7

    Location 2. Cold Water Supply System ground floor

    3. S,W,V System second floor

    4 .Fire protection ground floor work

    5. Air conditioning system ground floor (4 Places)

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

    a Project Engineer 1 1 1

    b M&E Super Visor 1 1 1

    c Headman 2 2 2

    d General labour 12 12 12

    e Safety Officer 1 1 1

    17 17 17

    Item Description

    Box up and sleeve schedule

    For December 2009

    Page 19

  • 8/14/2019 Method Box and Sleeve 3

    23/28

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    6.5 RESOURCES (Cont.)

    6.5.2 Manpower Schedule (cont.)

    Location 6. S,W,V System ground floor (1Place)

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

    Manpower

    a Project Engineer 1 1 1

    b M&E Super Visor 1 1 1

    c Headman 1 1 1

    Item Description

    Box up and sleeve schedule

    For January 2010

    Page 20

    d General labour 3 3 3

    e Safety Officer 1 1 1

    7 7 7

    Location 7. Fire protection ground floor work (Pump Room) (1 Place)

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

    a Project Engineer 1 1 1

    b M&E Super Visor 1 1 1c Headman 1 1 1

    d General labour 3 3 3

    e Safety Officer 1 1 1

    7 7 7

    Item Description

    Box up and sleeve schedule

    For Febuary 2010

    Page 20

    j C i A i i C i i

  • 8/14/2019 Method Box and Sleeve 3

    24/28

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    7.1 RESOURCES (Cont.)

    7.1.2 Manpower Schedule

    Location 8. Fire protection second floor work

    9. Cold Water Sypply System second floor

    10. Air conditioning system second floor (3 Places)

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

    a Project Engineer 1 1 1

    b M&E Super Visor 1 1 1

    Item Description

    Box up and sleeve schedule

    For Febuary 2010

    Page 21

    c Headman 1 1 1

    d General labour 9 9 9

    e Safety Officer 1 1 1

    13 13 13

    Location 11.Air conditioning system roof floor (1 place)

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

    aProject Engineer 1 1

    b M&E Super Visor 3 3

    c Headman 1 1

    d General labour 1 1

    e Safety Officer 1 1

    7 7

    Item Description

    Box up and sleeve schedule

    For Febuary 2010

    Page 21

  • 8/14/2019 Method Box and Sleeve 3

    25/28

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    6.6 INSPECTION AND TEST PLAN

  • 8/14/2019 Method Box and Sleeve 3

    26/28

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    6.7 CHECK LIST OF WORK

    Project: Chevron Thailand Aviation ConsolidationOwner: Chevron Thailand Exploration and Production LimitedConsultant: Dynamic Engineering Consultant

  • 8/14/2019 Method Box and Sleeve 3

    27/28

    Consultant: Dynamic Engineering ConsultantContractor: Thai Polycons Public Company Limited

    Check List for Box Up and Pipe Sleeve Installation Doc No.: TPOLY-CHV-M&E-0001-00

    : :

    : :

    :

    Purpose Of Inspection :

    Electrical and Communication System Air Conditioning and Ventilation System

    Plumbing System Compressed Air Supply System

    Fire Protection System Others

    Not Acceptable

    #1 #2

    1 Approved brand/make of material used

    2 Location

    3 Size And Dimension

    4 All sleeves or box up is immovable.

    5 Housekeeping

    Item

    Location Specific Location

    Date Attach Drawing No.

    Check List Serial No.

    Visual

    Item CheckCriteria /

    Chk. Methood

    No. of InspectionRemark

    Acceptable

    Signature

    Visual

    Visual

    Measure

    Measure

    Above installation is acceptable

    Above installation is not acceptable

    Note :

    Project: Chevron Thailand Aviation Consolidation

    Owner: Chevron Thailand Exploration and Production Limited

    Consultant: Dynamic Engineering Consultant

  • 8/14/2019 Method Box and Sleeve 3

    28/28

    Consultant: Dynamic Engineering Consultant

    Contractor: Thai Polycons Public Company Limited

    Quality record

    Form No.

    Test method Frequency Standard Specification

    M&E

    Box Up And Sleeve Installation

    -Material : Black Steel PipeManufacture'S

    Certificate

    -Approved Before

    Use -Every

    Delivery

    TIS N/A As Specification N/A N/A I I

    Technical Specifications for the

    Aviation

    Consolidation Project

    Doc.No.5T0142/RFP/0066/MP/BKK

    INSPECTION AND TEST PLAN FOR CHEVRON THAILAND AVIATION CONSOLIDATION PROJECT

    Item Description

    Inspection and test required ReferenceAcceptance

    Criteria

    Inspection and Test plan

    Vender Subcon TPOLY ERA

    Page 23

    -Install Box Up And Sleeve Measurement EverytimeMethod

    VisualChapter 7,8,19 N/A SI I I TPOLY-CHV-M&E-0001-00

    Symbol Symbol

    H D

    W/O SI

    W I

    S R

    Legend Legend

    Mandatory Hold Point - Hold Unit Approved Document or Record Required

    Witness Point - Optional Subcontractor Inspection

    Witness Point Inspection

    Surveillance Point - Random / Each Quantity Review Point

    Page 23