method box and sleeve 3
TRANSCRIPT
-
8/14/2019 Method Box and Sleeve 3
1/28
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
METHOD OF STATEMENT
BOX UP AND PIPE SLEEVE
FOR
INSTALLATION
-
8/14/2019 Method Box and Sleeve 3
2/28
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
: TPOLY-MOS-30-100-00
: 00
: Box up and pipe sleeve installation
Effective Date Issue No.
Name: Name: Name:
Prepared By: Reviewed By: Approved By:
THAI POLYCONS PUBLIC COMPANY LIMITED
CHEVRON THAILAND AVIATION CONSOLIDATION PROJECT
TPOLY DOCUMENT NO.
REVISION
TITLE
AUTHORISATION
Mr.Chaiya W. Mr.Chawalit M. Mr.Chanwit Chaleoiad
Signature: Signature: Signature:
Date: Date: Date:
NOTE : A CONTROLLED copy is valid only if stamped "C" in red,
Uncontrolled copy will Not be updated or amended.
Please refer to a controlled copy or check for amendments before use.
AMENDMENT / RELEASE RECORD
M&E Project Manager Project ManagerM&E Project Engineer
-
8/14/2019 Method Box and Sleeve 3
3/28
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
Subject Page No.
1. General 12. Material 1
3. Equipment & Tool 2
4. Box up and pipe sleeve installation procedures 3
5. Quality Assurance 4
6. Appendix 5
6.1 Flow chart 6
6.2 Illustation. 8
CONTENT
.3 Details drawing of Box up and sleeve installation 9
6.4 Schedule 11
6.5 Resources 15
6.5.1 Equipment schedule 16
6.5.2 Man Power schedule 19
6.6 Inspection and Test Plan 22
6.7 Check list of Work 24
-
8/14/2019 Method Box and Sleeve 3
4/28
METHOD STATEMENT
FOR
COLD WATER PIPE INSTALLATION AND TESTING
1. General
This method statement is to describe the intended work method and control measures for the
pipe sleeve installation which is carried out for this project.
2. Material
2.1 Material of Pipe Sleeve
Item Description
1 Black steel pipe
2 Black iron wire
3 Rebar 2-db mm.
2.2 Material of Box Up
Item Description
1 Ply wood minimum of thickness is 5/16 (8 mm)
2 Nail
3 Black iron wire
4 REBAR 2-DB MM.
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
-
8/14/2019 Method Box and Sleeve 3
5/28
Project: Chevron Thailand Aviation Consolidation Owner: Chevron
Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
4. Box up and pipe sleeve installation Procedure
4.1Setting out Survey
4.1.1 From the survey, the issued drawings will be marked up detailing all containment location and
proposed materials and equipment to be installed for approval. Actual commencement of the
installation works would be agreed with the client and main parties, which would also depend on the
working areas being made available. The installation system will be installed in accordance with the
safety policy using plan and equipment to suit the application.
4.2 Check Location of working areas.
4.2.1 The working area will be cleared and being made available.
4.3 Installation
4.3.1 Project specification, all works/operations will be carried out in accordance with all proven methods
and industry standards.
4.3.2 On completion of the installation, all of the location and position will be followed in the referential
drawing
4.4 Inspection
4.4.1 Materials shall supply to the Consulting Engineer's for his approval certificates from the
manufacturer, showing that the materials have been tested according to the relevant specification or
standard.
4.4.2 The Project Engineer and supervisor will make the visual inspection of the location and position also
others. Then request to the Consulting Engineer's inspector to inspected and approved. TheInspection must continuity in accordance with Approved M&E inspection check list to ensure that all
sleeves or box up were immovable. And work properly.
4.4.3 If inspection or tests show defects, such defective work or material shall be replaced and
Inspection and tests shall be repeated.
-
8/14/2019 Method Box and Sleeve 3
6/28
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
3.Equipment and ToolBasic equipment for the mark will be as follows.
Item
1
2
3
4
5
Hammer
Saw
Equipment / Tool
Cutter
Pincers
Cut off machine for 14" cutting discs
-
8/14/2019 Method Box and Sleeve 3
7/28
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
5. Quality Assurance
All works will conform to the standards set out. Material on site approval by DEC. the work proced
corresponds with visual method of statement. The proposed inspection and test plans (ITP) are shown
in the appendix.The proposed Inspection and Test Plans (ITP) are shown in the Appendix.
-
8/14/2019 Method Box and Sleeve 3
8/28
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
6. APPENDIX
-
8/14/2019 Method Box and Sleeve 3
9/28
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
6.1 FLOW CHART
-
8/14/2019 Method Box and Sleeve 3
10/28
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
FLOW CHART FOR BOX AND SLEEVE INSTALLATION
-
8/14/2019 Method Box and Sleeve 3
11/28
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
6.2 ILLUSTRATION
-
8/14/2019 Method Box and Sleeve 3
12/28
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
6.3 DETAILS DRAWING OF
BOX UP AND SLEEVE INSTALLATION
-
8/14/2019 Method Box and Sleeve 3
13/28
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
-
8/14/2019 Method Box and Sleeve 3
14/28
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
6.4 SCHEDULE
-
8/14/2019 Method Box and Sleeve 3
15/28
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
Box up and Sleeve (Work Schedule)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
1 Water Treatment Plant (Pump Room) 3 days 2/11/09 4/11/09
1.1 Setting out survey 1 day 2/11/09 2/11/09
1.2 Check Location of working areas 1 day 2/11/09 2/11/09
1.3 Installation 1 day 3/11/09 4/11/09
1.4 Inspection 1 day 4/11/09 4/11/09
Item Description Duration Start Finish
Box up and sleeve schedule
For November 2009
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
2 S,W,V System ground floor 3 days 3/1/10 5/1/10
2.1 Setting out survey
2.2 Check Location of working areas
2.3 Installation
2.4 Inspection
3 Cold Water Supply System ground floor 3 days 10/1/10 12/1/10
3.1 Setting out survey
3.2 Check Location of working areas
3.3 Installation
3.4 Inspection
Description Duration StartItem Finish
Box up and sleeve schedule
For January 2010
Page 12
-
8/14/2019 Method Box and Sleeve 3
16/28
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
Box up and Sleeve (Work Schedule)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
4 S,W,V System second floor 3 days 10/1/10 12/1/10
4.1 Setting out survey
4.2 Check Location of working areas
4.3 Installation
4.4 Inspection
5 Fire protection ground floor work 3 days 10/1/10 12/1/10
Item Description Duration Start Finish
Box up and sleeve schedule
For January 2010
5.1 Setting out survey
5.2 Check Location of working areas
5.3 Installation
5.4 Inspection
6 Air conditioning system ground floor 3 days 10/1/10 12/1/10
6.1 Setting out survey
6.2 Check Location of working areas
6.3 Installation
6.4 Inspection
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
7 Fire protection ground floor work (Pump Room) 3 days 6/2/10 8/2/10
7.1 Setting out survey
7.2 Check Location of working areas
7.3 Installation
7.4 Inspection
Item Description Duration Start Finish
Box up and sleeve schedule
For Febuary 2010
Page 13
-
8/14/2019 Method Box and Sleeve 3
17/28
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
Box up and Sleeve (Work Schedule)
Item Description Duration Start Finish
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
8 Fire protection second floor work 3 days 10/2/10 12/2/10
8.1 Setting out survey
8.2 Check Location of working areas
8.3 Installation
8.4 Inspection
Box up and sleeve schedule
Item Description Duration Start Finish
Box up and sleeve schedule
For Febuary 2010
9 Cold Water Sypply System second floor 3 days 10/2/10 12/2/10
9.1 Setting out survey
9.2Check Location of working areas
9.3 Installation
9.4 Inspection
10 Air conditioning system second floor 3 days 25/1/10 27/1/10
10.1 Setting out survey
10.2 Check Location of working areas
10.3 Installation
10.4Inspection
11 ir conditioning system roof floor 2 days 1/2/10 2/2/10
11.1 Setting out survey
11.2 Check Location of working areas
11.3 Installation
11.4 Inspection
Page 14
-
8/14/2019 Method Box and Sleeve 3
18/28
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
6.5 RESOURCES
Project: Chevron Thailand Aviation Consolidation
O Ch Th il d E l i d P d i Li i d
-
8/14/2019 Method Box and Sleeve 3
19/28
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
6.5 RESOURCES
6.5.1 Equipment Schedule
Location 1. Water Treatment Plant (Pump Room) (1 Place)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
a Cutter 1 1 1
b Pincers 3 3 3
c Cut Off Machine for 14" Cutting Discs 1 1 1
d Hammer 1 1 1
e Fishing Line 1 1 1
f Steel tape 3 3 3
Saw 1 1 1
Item Description
Box up and sleeve schedule
For November 2009
Page 16
Total 11 11 11
Location 2. Cold Water Supply System ground floor
3. S,W,V System second floor4 .Fire protection ground floor work
5. Air conditioning system ground floor (4 Places)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
a Cutter 4 4 4
b Pincers 12 12 12
c Cut Off Machine for 14" Cutting Discs 1 1 1
d Hammer 4 4 4
e Fishing Line 4 4 4
f Steel tape 12 12 12
g Saw 2 2 2
39 39 39
Item Description
Box up and sleeve schedule
For December 2009
Page 16Page 16
-
8/14/2019 Method Box and Sleeve 3
20/28
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
7.1 RESOURCES
6.5.1 Equipment Schedule (cont.)
Location 6. S,W,V System ground floor (1Place)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
a Cutter 1 1 1
b Pincers 3 3 3
c Cut Off Machine for 14" Cutting Discs 1 1 1
d Hammer 1 1 1
Fishin Line 1 1 1
Item Description
Box up and sleeve schedule
For January 2010
Page 17
f Steel tape 3 3 3
g Saw 1 1 1
11 11 11
Location 7. Fire protection ground floor work (Pump Room) (1 Place)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
a Cutter 1 1 1
b Pincers 3 3 3c Cut Off Machine for 14" Cutting Discs 1 1 1
d Hammer 1 1 1
e Fishing Line 1 1 1
f Steel tape 3 3 3
g Saw 1 1 1
11 11 11
Box up and sleeve schedule
For Febuary 2010Item Description
Page 17
-
8/14/2019 Method Box and Sleeve 3
21/28
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
6.5 RESOURCES
6.5.1 Equipment Schedule (cont.)
Location 8. Fire protection second floor work
9. Cold Water Sypply System second floor
10. Air conditioning system second floor (3 Places)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
a Cutter 3 3 3
b Pincers 9 9 9
c Cut Off Machine for 14" Cutting Discs 1 1 1
d Hammer 3 3 3
Item Description
Box up and sleeve schedule
For Febuary 2010
Page 18
e
f Steel tape 9 9 9
g Saw 2 2 2
30 30 30
Location 11.Air conditioning system roof floor (1 place)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
a Cutter 1 1
b Pincers 3 3
c Cut Off Machine for 14" Cutting Discs 1 1
d Hammer 1 1
e Fishing Line 1 1
f Steel tape 3 3
g Saw 1 1
10 10
Item Description
Box up and sleeve schedule
For Febuary 2010
Page 18
Project: Chevron Thailand Aviation Consolidation
O Ch Th il d E l ti d P d ti Li it d
-
8/14/2019 Method Box and Sleeve 3
22/28
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
6.5 RESOURCES (Cont.)
6.5.2 Man Power Schedule
Location 1. Water Treatment Plant (Pump Room) (1 Place)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Manpower
a Project Engineer 1 1 1
b M&E Super Visor 1 1 1
c Headman 1 1 1
d General labour 3 3 3
e Safety Officer 1 1 1
Item Description
Box up and sleeve schedule
For November 2009
Page 19
Total 7 7 7
Location 2. Cold Water Supply System ground floor
3. S,W,V System second floor
4 .Fire protection ground floor work
5. Air conditioning system ground floor (4 Places)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
a Project Engineer 1 1 1
b M&E Super Visor 1 1 1
c Headman 2 2 2
d General labour 12 12 12
e Safety Officer 1 1 1
17 17 17
Item Description
Box up and sleeve schedule
For December 2009
Page 19
-
8/14/2019 Method Box and Sleeve 3
23/28
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
6.5 RESOURCES (Cont.)
6.5.2 Manpower Schedule (cont.)
Location 6. S,W,V System ground floor (1Place)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Manpower
a Project Engineer 1 1 1
b M&E Super Visor 1 1 1
c Headman 1 1 1
Item Description
Box up and sleeve schedule
For January 2010
Page 20
d General labour 3 3 3
e Safety Officer 1 1 1
7 7 7
Location 7. Fire protection ground floor work (Pump Room) (1 Place)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
a Project Engineer 1 1 1
b M&E Super Visor 1 1 1c Headman 1 1 1
d General labour 3 3 3
e Safety Officer 1 1 1
7 7 7
Item Description
Box up and sleeve schedule
For Febuary 2010
Page 20
j C i A i i C i i
-
8/14/2019 Method Box and Sleeve 3
24/28
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
7.1 RESOURCES (Cont.)
7.1.2 Manpower Schedule
Location 8. Fire protection second floor work
9. Cold Water Sypply System second floor
10. Air conditioning system second floor (3 Places)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
a Project Engineer 1 1 1
b M&E Super Visor 1 1 1
Item Description
Box up and sleeve schedule
For Febuary 2010
Page 21
c Headman 1 1 1
d General labour 9 9 9
e Safety Officer 1 1 1
13 13 13
Location 11.Air conditioning system roof floor (1 place)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
aProject Engineer 1 1
b M&E Super Visor 3 3
c Headman 1 1
d General labour 1 1
e Safety Officer 1 1
7 7
Item Description
Box up and sleeve schedule
For Febuary 2010
Page 21
-
8/14/2019 Method Box and Sleeve 3
25/28
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
6.6 INSPECTION AND TEST PLAN
-
8/14/2019 Method Box and Sleeve 3
26/28
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
6.7 CHECK LIST OF WORK
Project: Chevron Thailand Aviation ConsolidationOwner: Chevron Thailand Exploration and Production LimitedConsultant: Dynamic Engineering Consultant
-
8/14/2019 Method Box and Sleeve 3
27/28
Consultant: Dynamic Engineering ConsultantContractor: Thai Polycons Public Company Limited
Check List for Box Up and Pipe Sleeve Installation Doc No.: TPOLY-CHV-M&E-0001-00
: :
: :
:
Purpose Of Inspection :
Electrical and Communication System Air Conditioning and Ventilation System
Plumbing System Compressed Air Supply System
Fire Protection System Others
Not Acceptable
#1 #2
1 Approved brand/make of material used
2 Location
3 Size And Dimension
4 All sleeves or box up is immovable.
5 Housekeeping
Item
Location Specific Location
Date Attach Drawing No.
Check List Serial No.
Visual
Item CheckCriteria /
Chk. Methood
No. of InspectionRemark
Acceptable
Signature
Visual
Visual
Measure
Measure
Above installation is acceptable
Above installation is not acceptable
Note :
Project: Chevron Thailand Aviation Consolidation
Owner: Chevron Thailand Exploration and Production Limited
Consultant: Dynamic Engineering Consultant
-
8/14/2019 Method Box and Sleeve 3
28/28
Consultant: Dynamic Engineering Consultant
Contractor: Thai Polycons Public Company Limited
Quality record
Form No.
Test method Frequency Standard Specification
M&E
Box Up And Sleeve Installation
-Material : Black Steel PipeManufacture'S
Certificate
-Approved Before
Use -Every
Delivery
TIS N/A As Specification N/A N/A I I
Technical Specifications for the
Aviation
Consolidation Project
Doc.No.5T0142/RFP/0066/MP/BKK
INSPECTION AND TEST PLAN FOR CHEVRON THAILAND AVIATION CONSOLIDATION PROJECT
Item Description
Inspection and test required ReferenceAcceptance
Criteria
Inspection and Test plan
Vender Subcon TPOLY ERA
Page 23
-Install Box Up And Sleeve Measurement EverytimeMethod
VisualChapter 7,8,19 N/A SI I I TPOLY-CHV-M&E-0001-00
Symbol Symbol
H D
W/O SI
W I
S R
Legend Legend
Mandatory Hold Point - Hold Unit Approved Document or Record Required
Witness Point - Optional Subcontractor Inspection
Witness Point Inspection
Surveillance Point - Random / Each Quantity Review Point
Page 23