methow valley irrigation district alternatives evaluation

34
Methow Valley Irrigation District Alternatives Evaluation Presented by Bob Montgomery, P.E. and David Rice, P.E. January 31, 2013

Upload: kirkan

Post on 23-Feb-2016

34 views

Category:

Documents


0 download

DESCRIPTION

Methow Valley Irrigation District Alternatives Evaluation. Presented by Bob Montgomery, P.E. and David Rice, P.E. January 31, 2013. Alternatives Evaluation Report (AER) Scope. Coordination meetings Meetings with project team MVID board of directors and shareholders - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Methow  Valley Irrigation District Alternatives Evaluation

Methow Valley Irrigation DistrictAlternatives Evaluation

Presented byBob Montgomery, P.E. and David Rice, P.E.

January 31, 2013

Page 2: Methow  Valley Irrigation District Alternatives Evaluation

Alternatives Evaluation Report (AER) Scope• Coordination meetings

– Meetings with project team– MVID board of directors and shareholders

• Hydrologic feasibility analysis– Groundwater well testing– Evaluation of individual well option

• Development of AER– Evaluation of 4 alternatives– Hydraulic analyses, cost analyses, concept

drawings– Draft and final reports

Page 3: Methow  Valley Irrigation District Alternatives Evaluation

Groundwater Investigation

• Potential well sites identified• Test well drilling plan developed

– Description and specifications for drilling work• Test well drilling – 8 inch exploration wells

– MVID beaver pond property– Jumars property– Eileen property

Page 4: Methow  Valley Irrigation District Alternatives Evaluation

Summary of Drilling at MVID Beaver Pond Property• Well drilled to 90 ft below ground surface

(bgs)• Static water level was 10 ft bgs• Encountered bedrock at 80 ft bgs• We are not recommending this site be

used for production wells

Page 5: Methow  Valley Irrigation District Alternatives Evaluation

Summary of Drilling at Jumars Property

• Well drilled to 180 ft bgs• Static water level was 69 ft bgs• Good formations of sand and gravel were

found• Pump test not performed because of

freezing weather

Page 6: Methow  Valley Irrigation District Alternatives Evaluation
Page 7: Methow  Valley Irrigation District Alternatives Evaluation
Page 8: Methow  Valley Irrigation District Alternatives Evaluation

Summary of Drilling at Eileen Property

• Well drilled to 156 ft bgs• Static water level was 8 ft bgs• Good formations of sand and gravel were

found• Higher withdrawals likely available at this

site• Pump test not yet performed

Page 9: Methow  Valley Irrigation District Alternatives Evaluation
Page 10: Methow  Valley Irrigation District Alternatives Evaluation

Summary of Alternatives

• Alternative 1– West canal replaced with pressurized pipe system– Supplied by pump station on Methow River

• Alternative 2– West canal replaced with pressurized pipe system– Supplied by wells in connection with Methow

River• Alternative 3

– West canal replaced with two pressurized pipe systems

– Supplied by wells in connection with Methow River

Page 11: Methow  Valley Irrigation District Alternatives Evaluation

Summary of Alternatives (Cont.)

• Alternative 4– Convert to individual well systems, where

possible– Reduced West system – Upper West Side users

– Pressure pipe system– Supplied by well (or river pump station)– Users likely still within a reduced MVID

– Reduced East system – Lateral E1 replacement– Pressure pipe system– Supplied by well– System operated as part of a reduced MVID, or

through agreement with Town of Twisp

Page 12: Methow  Valley Irrigation District Alternatives Evaluation

Alternative 1

Page 13: Methow  Valley Irrigation District Alternatives Evaluation

Alternative 1 – Detailed Summary

• Supply– Methow River pump station

– 2.4 cfs (125 HP) pumping to users upstream– 8.6 cfs (200 HP) pumping to users

downstream• Pressurized PVC pipe system

– Main line – approx. 47,800 feet, 8” to 18” diam.– Laterals – approx. 29,600 feet, 3” to 8” diam.

• Storage (optional)– 132,000 gallons (upstream of pump station)– 476,000 gallons (downstream of pump station)

Page 14: Methow  Valley Irrigation District Alternatives Evaluation

Alternative 1 – Implementation Costs

• Probable construction cost– $6 to $7 million (2013 dollars)

• Additional implementation costs– Land acquisition, engineering, permitting,

administrative

Page 15: Methow  Valley Irrigation District Alternatives Evaluation

Alternative 1 – Life Cycle Costs

• Probable annual life cycle costs– Power: $30K to $35K (2013

dollars)– O&M: $140K to $160K (2013

dollars)– Replacement fund: $55K to $65K (2013

dollars)–Probable annual assessment

– $155 to $165 per acre for power + O&M– $50 to $60 per acre for replacement fund

– Analysis assumes– Okanogan PUD irrigation rate schedule– 3% annual inflation and 3% annual interest

Page 16: Methow  Valley Irrigation District Alternatives Evaluation

Alternative 2

Page 17: Methow  Valley Irrigation District Alternatives Evaluation

Alternative 2 – Detailed Summary

• Groundwater well supply– Total 11.0 cfs supply– Multiple large production wells

• Booster pump station– 2.4 cfs (75 HP) pump station to users upstream

of Roach Spill

Page 18: Methow  Valley Irrigation District Alternatives Evaluation

Alternative 2 – Detailed Summary (Cont.)

• Pressurized PVC pipe system– Main line – approx. 47,800 feet, 8” to 18” diam.– Laterals – approx. 29,700 feet, 3” to 8” diam.

• Storage (optional)– 132,000 gallons (upstream of pump station)– 476,000 gallons (downstream of pump station)

Page 19: Methow  Valley Irrigation District Alternatives Evaluation

Alternative 2 – Implementation Costs

• Probable construction cost– $6.5 to $7.5 million (2013 dollars)

• Additional implementation costs– Land acquisition, permitting, administrative

Page 20: Methow  Valley Irrigation District Alternatives Evaluation

Alternative 2 – Life Cycle Costs

• Probable annual life cycle costs– Power: $40K to $45K (2013

dollars)– O&M: $145K to $165K (2013

dollars)– Replacement fund: $60K to $70K (2013

dollars)–Probable annual assessment

– $160 to $170 per acre for power + O&M– $50 to $60 per acre for replacement fund

– Analysis assumes– Okanogan PUD irrigation rate schedule– 3% annual inflation and 3% annual interest

Page 21: Methow  Valley Irrigation District Alternatives Evaluation

Alternative 3

Page 22: Methow  Valley Irrigation District Alternatives Evaluation

Alternative 3 – Detailed Summary

• Groundwater well supply– Upper middle system - total 5.1 cfs supply– Lower system - total 5.9 cfs supply– Multiple large production wells

• Booster pump station– 2.4 cfs (75 HP) pump station in upper/middle

system to users upstream of Roach spill

Page 23: Methow  Valley Irrigation District Alternatives Evaluation

Alternative 3 – Detailed Summary (Cont.)

• Pressurized PVC pipe system– Main line – approx. 41,100 feet, 8” to 15” diam.– Laterals – approx. 29,700 feet, 3” to 8” diam.

• Storage (optional)– Upper/middle system

– 132,000 gallons (upstream of pump station)– 158,000 gallons (downstream of pump

station)– Lower system

– 317,000 gallons

Page 24: Methow  Valley Irrigation District Alternatives Evaluation

Alternative 3 – Implementation Costs

• Probable construction cost– $5.5 to $6.5 million (2013 dollars)

• Additional implementation costs– Land acquisition, permitting, administrative

Page 25: Methow  Valley Irrigation District Alternatives Evaluation

Alternative 3 – Life Cycle Costs

• Probable life cycle costs– Power: $40K to $45K (2013

dollars)– O&M: $145K to $165K (2013

dollars)– Replacement fund: $60K to $70K (2013

dollars)–Probable assessment

– $165 to $175 per acre for power + O&M– $50 to $60 per acre for replacement fund

– Analysis assumes– Okanogan PUD irrigation rate schedule– 3% annual inflation and 3% annual interest

Page 26: Methow  Valley Irrigation District Alternatives Evaluation

Alternative 4

Page 27: Methow  Valley Irrigation District Alternatives Evaluation

Alternative 4 – Detailed Summary• Combination of individual well systems

and pressurized pipe system where wells are not feasible

• Individual well systems– For parcels outside town of twisp – Groundwater likely available in valley and

margins in unconsolidated sediment formation– Recommend drilling deeper and using screens

for higher capacity wells

Page 28: Methow  Valley Irrigation District Alternatives Evaluation

Alternative 4 – Detailed Summary• Reduced Upper West system

– Groundwater well supply – 2.5 cfs– Pressurized PVC pipe system

– Approx. 21,100 feet, 3” to 12” diam.– Storage (optional)

– 132,000 gallons

Page 29: Methow  Valley Irrigation District Alternatives Evaluation

Alternative 4 – Detailed Summary (Cont.)

• Reduced Upper East System– Groundwater well supply – 2.5 cfs– Pressurized PVC pipe system

– Approx. 6,100 feet, 4” to 10” diam.– No storage– Operation

– Part of reduced MVID, or– Served through agreement with Town of

Twisp with separate irrigation meter

Page 30: Methow  Valley Irrigation District Alternatives Evaluation

Alternative 4 – Implementation Costs

• Probable construction cost for reduced MVID system (Upper West and Upper East systems)– $2.1 to $2.6 million total (2013 dollars)

– $1.5 to $1.8 million for upper west (2013 dollars)

– $600K to $800K for upper east (2013 dollars)

• Additional implementation costs– Land acquisition, permitting, administrative

Page 31: Methow  Valley Irrigation District Alternatives Evaluation

Alternative 4 – Life Cycle Costs

• Probable life cycle costs for reduced MVID (upper west and upper east systems)– Power: $12K to $16K (2013

dollars)– O&M: $20K to $30K (2013 dollars)– Replacement fund: $27K to $32K (2013

dollars)–Probable assessment

– $180 to $190 per acre for power + O&M– $120 to $130 per acre for replacement fund

– Analysis assumes– Okanogan PUD irrigation rate schedule– 3% annual inflation and 3% annual interest

Page 32: Methow  Valley Irrigation District Alternatives Evaluation

Comparison of AlternativesFactor Alternativ

e 1Alternative 2 Alternative 3 Alternative 4

Capital Cost(funded by Ecology)

$6-7 million $6.5-7.5 million $5.5-6.5 million

$2.1-2.6 million

Annual Costs (power, O&M, replacement)

$225-260,000

$245-280,000 $245-280,000 $99-118,000

Estimated Annual Assessment (Power

+ O&M per acre)

$155-$165 $160-170 $165-$175 $180-$190

Additional Assessment for

Replacement Fund

$50-60 $50-$60 $50-$60 $120-$130

Water Supply River Pump Station

Groundwater Wells

Groundwater Wells

Groundwater Wells

Other Features Pressurized pipe

Two Zones

Pressurized pipe

Two Zones

Pressurized pipe

Two Systems, Two Zones in Upper System

Individual Well Systems,

MVID Reduced to Upper West and Upper East

Systems

Page 33: Methow  Valley Irrigation District Alternatives Evaluation

Next Steps

• Completion of AER• MVID selection of preferred alternative• Selection criteria

– Cost (construction cost, land acquisition, O&M, replacement, impact to shareholder assessment)

– Water supply (impact to groundwater, surface water, and continuity with methow river)

– Property impacts– Social and political feasibility– Ease of permitting– Constructability, ease of operation

Page 34: Methow  Valley Irrigation District Alternatives Evaluation

Questions and Comments

• To be collected at tables for each alternative

• For more information:– See www.mvid.org– Talk with MVID Directors and Staff– Visit the Trout Unlimited office in Twisp

(115 S. Glover St.) – Email questions and comments to:

[email protected]