TUGAS AKHIR MANAJEMEN
PELAKSANAAN
PEMBANGUNAN JALAN TOL
MOJOKERTO – KERTOSONO STA. 5+350 – STA. 10+350 DENGAN MENGGUNAKAN PERKERASAN KAKU
DI KABUPATEN MOJOKERTO PROVINSI JAWA
TIMUR
ZULFIKAR JAUHARI
NRP. 3110040601
PROGRAM STUDI DIPLOMA 4 TEKNIK SIPIL
![Page 2: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/2.jpg)
Fakultas Teknik Sipil dan Perencanaan
Institut Teknologi Sepuluh Nopember
Surabaya 2012
![Page 3: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/3.jpg)
STA 10 +350 STA 5 +350
![Page 4: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/4.jpg)
BAGAN ALUR
METODELOGI
![Page 5: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/5.jpg)
GI
LANJUTAN
METODELO
![Page 6: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/6.jpg)
PETA LOKASI QUARRY
![Page 7: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/7.jpg)
PETA LOKASI QUARRY
JARAK LOKASI PROYEK DENGAN LOKASI QUARRY ADALAH 32, 4 KM
![Page 8: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/8.jpg)
PEKERJAAN TANAH
![Page 9: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/9.jpg)
Pekerjaan Tanah
• Pembersihan dan Pembongkaran
• Galian Konstruksi 0 - 2 m
• Pekerjaan Timbunan
• Lapisan Geotextile
• Penyiapan Badan Jalan
![Page 10: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/10.jpg)
PEMBERSIHAN & PEMBONGKARAN
1. Pembongkaran dilakukan pada daerah milik jalan yang telah ditentukan dan atas petunjuk direksi.
2. Harus dilakukan dengan hati-hati berkaitan dengan banyaknya utilitas existing bawah tanah.
2. Hasil pembongkaran dibuang diluar lokasi pekerjaan atau lokasi yang telah ditentukan oleh direksi .
![Page 11: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/11.jpg)
PEMBERSIHAN & PEMBONGKARAN
PEMBERSIHAN/PENGUPASAN TOP SOIL, PENGANGKUTAN DAN PERATAAN
1. Pembersihan permukaan tanah dengan Bulldozer 2. Loading hasil streping ke Dump truck dengan Excavator
3. Galian tanah permukaan + 50 cm dengan Bulldozer 4. Loading hasil galian dengan excavator ke dump truck untuk dibuang ke disposal area
50 cm
![Page 12: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/12.jpg)
PEKERJAAN DRAINASE
![Page 13: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/13.jpg)
PEKERJAAN GALIAN SALURAN TEPI
CONTOH TYPE SALURAN
GALIAN SALURAN
TEPI 1
GALIAN SALURAN TEPI 2
![Page 14: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/14.jpg)
PEKERJAAN GALIAN SALURAN TEPI
PERSIAPAN
Rencanakan urutan penggalian, urutan pekerjaan
U-Ditch, tempat penimbunan tanah hasil galian
sementara sebelum diangkut keluar dari site.
PEMBUATAN GALIAN
Rencana Galian Pondasi
Galian untuk Pondasi
1. Siapkan alat-alat yang diperlukan. 2. Menggali tanah dengan ukuran lebar sama
dengan lebar bagian bawah dengan kedalaman
yang disyaratkan. 3. Menggali sisi-sisi miringnya, sehingga
diperoleh sudut kemiringan yang tepat. 4. Buang tanah sisa galian ketempat yang telah
ditentukan. 5. Cek posisi, lebar, kedalaman dan kerapianya,
sesuai dengan rencana.
Papan Bouwplank
Bekas Galian
Tiang Bouwplank
![Page 15: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/15.jpg)
PEKERJAAN PEMADATAN
![Page 16: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/16.jpg)
Dump truck 11 ton Material timbuanan (Sirtu)
Bulldozer 150 HP Motor Grader 3.1 m3
Vibrator roller 12 ton Truck tanki air (6000 m3)
Timbunan lapis 2 Timbunan lapis 3
Timbunan lapis 1
Muka tanah asli
![Page 17: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/17.jpg)
PENYIAPAN BADAN JALAN
1. Pekerjaan pembentukan badan jalan dan perapihan serta perataan menggunakan motor grader sehingga membentuk kemiringan sesuai design
2. - Vibrator Roller memadatkan permukaan yang telah diratakan oleh motor grader dgn diberi air secukupnya
- Sekelompok pekerja akan membantu meratakan badan jalan dengan alat bantu
![Page 18: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/18.jpg)
PEKERJAAN TIMBUNAN TANAH BIASA
1. EXCAVATOR MEMUAT MATERIAL TIMBUNAN KEDALAM DUMP TRUCK DI BORROW AREA KE MUDIAN DIANGKUT KELOKASI PEKERJAAN
2. TIBA DILOKASI PEKERJAAN MATERIAL DIDUMPING DARI DUMP TRUCK KEMUDIAN DILAKUKAN PENG HAMPARAN
3. PENGHAMPARAN TANAH TIMBUNAN MENGGUNAKAN MOTOR GRADER
4. –HAMPARAN MATERIAL DISIRAM AIR SEBELUM DI PADATKAN
-PEMADATAN MATERIAL DILAKUKAN DENGAN MENG GUNAKAN ALAT VIBRATOR ROLLER
WATER TANK TRUCK
![Page 19: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/19.jpg)
PEKERJAAN TIMBUNAN PILIHAN
1. EXCAVATOR MEMUAT MATERIAL TIMBUNAN PILIHAN KEDALAM DUMP TRUCK DI BORROW AREA KE MUDIAN DIANGKUT KELOKASI PEKERJAAN
2. TIBA DILOKASI PEKERJAAN MATERIAL DIDUMPING DARI DUMP TRUCK KEMUDIAN DILAKUKAN PENG HAMPARAN
3. PENGHAMPARAN TIMBUNAN PILIHAN MENGGUNAKAN MOTOR GRADER
4. –HAMPARAN TIMBUNAN PILIHAN DISIRAM AIR SEBELUM DI PADATKAN
-PEMADATAN MATERIAL DILAKUKAN DENGAN MENG GUNAKAN ALAT VIBRATOR ROLLER
WATER TANK TRUCK
![Page 20: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/20.jpg)
PEKERJAAN PERKERASAN BERBUTIR
1. Pendatangan material timbunan dari luar dengan menggunakan Dump Truck
2. Material di hampar dengan Motor Grader
3. Proses pemadatan hasil peghamparan dengan menggunakan Vibrator Roller
4. Prosess pemadatan diikuti pembasahan dengan Water Tank Truck
![Page 21: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/21.jpg)
PEKERJAAN PERKERASAN BETON
![Page 22: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/22.jpg)
Rigid Pavement
PERSYARATAN TEKNIS
a. Beton • Lantai Kendaraan, mutu beton K-400 (umur 28 hari) • Lantai Kerja, Mutu beton harus setara dengan beton K-125 (umur 28 hari)
b. Baja Tulangan • Diameter > 13 mm : U-39 (ulir) • Diameter < 13 mm : U-32 (polos)
![Page 23: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/23.jpg)
KONSTRUKSI PEKERJAAN PERKERASAN BETON
FLOWCHART PEKERJAAN K - 40
START
MATERIAL KLAS B = 20 CM BY MOTOR GRADER/VIBRO ROLLER/TANKI AIR
LEAN CONCRETE thick = 5 cm BY TRUCK MIXER
CONCRETE PAVEMENT
LEAN CONCRETE t=5
CONCRETE PAVEMENT thick = 27 cm BY TRUCK MIXER
FINISH
CONCRETE PAVEMENT
![Page 24: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/24.jpg)
KONSTRUKSI PEKERJAAN PERKERASAN BETON
PELAKSANAAN PEKERJAAN SLAB K-400
1. Pekerjaan Persiapan
Pekerjaan persiapan yang dilakukan untuk perkerasan beton yaitu penentuan elevasi lean concrete yang akan di cor. Pemasangan bekisting pada sisi jalan untuk pengecoran lean concrete pekerjaan pengecoran lean concrete
2. Pekerjaan pengecoran lean concrete
3. Pemasangan bekisting sisi jalan yang juga berfungsi sebagai rel dari concrete paver. Pemasangan pelastik dan kayu yang berfungsi sebagai crack inducer
4. Pembuatan Dowel, Tie Bar dan Wire Mesh
Pembuatan dowel, tie bar dan pemasangan wire mesh, dilakukan sebelum pekerjaan pengecoran dimulai.
![Page 25: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/25.jpg)
PEKERJAAN PERKERASAN BETON KONSTRUKSI
Mulai
Penyiapan Alat Paver
Pemasangan Rel
Pemasangan Plastik, crack inducer, Dowel &
Tie Bar
PERSIAPAN
Pemasangan Wire Mesh
Perkuatan
Selesai
![Page 26: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/26.jpg)
PEKERJAAN PERKERASAN BETON
Pengukuran/Penentuan Elevasi Lean Concrete
Pembuatan Dowell dan Tie bar
![Page 27: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/27.jpg)
26 METODE PELAKSANAAN PEKERJAAN RIGID PAVEMENT
1. Buat Patokan Lean Concrete
10 Cm
2. Pengecoran Lapisan Lean Concrete
Papan Pijakan Pekerja
10 Cm
![Page 28: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/28.jpg)
PEKERJAAN PERKERASAN BETON KONSTRUKSI
Persiapan
Membuat Alur
Pengecoran
Compound
Menggelar & Meratakan
Pembasahan Beton
Pemadatan Pemotongan
Joint
Meratakan Permukaan
Pengisian Joint Sealant
Finish
![Page 29: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/29.jpg)
+
+
+
+
++
++
++
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
ALUR PENGECORAN CONCRETE
Oleh karena lebar Jalan 7 m Maka lebar penghamparan dibuat dua kali masing masing Dengan lebar hampar 3.5 m
2
3 4 1
3.50 m
![Page 30: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/30.jpg)
++
+
3.50 m
3.50 m 3.50 m
![Page 31: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/31.jpg)
PEKERJAAN PERKERASAN BETON KONSTRUKSI
1 2
Pengecoran Penyebaran & Pemadatan
3 4 5
![Page 32: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/32.jpg)
Meratakan Permukaan Pembuatan Alur Curing Compound
![Page 33: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/33.jpg)
PEKERJAAN PERKERASAN BETON KONSTRUKSI
6 7 8
Pembasahan Beton Pemotongan Joint Pengisian Joint Sealant
9
10
![Page 34: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/34.jpg)
Perlindungan dengan Tenda Hasil RIGID PAVEMENT
![Page 35: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/35.jpg)
Manajemen
• Untuk mengetahui bagaimana manajemen yang dipakai, saya menggunakan bantuan program MS Project untuk memfasilitasi pengaturan Biaya, Waktu, dan Mutu
![Page 36: Metode jalan beton](https://reader031.vdocuments.net/reader031/viewer/2022012309/587a449c1a28ab00148b5041/html5/thumbnails/36.jpg)
32