OBRA CONSTRUCCION DE PARQUE INFANTILACARI - CARAVELI - AREQUIPAAGOSTO DEL 2008
UNID. CANTIDAD PRECIO PARCIAL
1.00 OBRAS PROVISIONALES 1,818.65
1.01 CONSTRUCCION DE ALMACEN, CASETA DE GUARDIANIA m2 9.00 80.10 720.90
1.02 AGUA PARA LA CONSTRUCCION mes 1.00 150.00 150.00
1.03 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 m u 1.00 947.75 947.75
2 OBRAS PRELIMINARES 758.36
2.01 TRAZO Y REPLANTEO m2 236.25 1.63 385.09
2.02 LIMPIEZA DE TERRENO MANUAL m2 236.25 1.58 373.28
3 MOVIMIENTO DE TIERRAS 10,056.37
3.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 33.54 23.55 789.87
3.02 CORTE O RELLENO DE TERRENO HASTA 0.20 m m2 47.25 9.29 438.95
3.03 ELIMINACION DE MATERIAL EXCEDENTE A MAQUINA m3 38.26 28.76 1100.36
3.04 AFIRMADO COMPACATADO DE 4" PISOS Y VEREDAS m2 226.05 9.95 2249.20
3.05 DEMOLICIÓN DE STRUCTURA EXISTENTE m2 249.00 22.00 5478.00
4 OBRAS DE CONCRETO SIMPLE 19,980.39
4.01 CONCRETO 1:10 +30% P.G. PARA CIMIENTOS CORRIDOS m3 20.00 155.21 3104.20
4.02 ENCOFRADO Y DESENCOFRADO m2 93.00 34.44 3202.92
4.03 FALSO PISO DE 4" DE CONCRETO 1:8 m2 51.05 19.88 1014.87
4.04 VEREDA DE CONCRETO DE 4" m2 280.00 43.89 12289.20
4.05 JUNTAS DE DILATACION m 52.00 7.10 369.20
5 OBRAS DE CONCRETO ARMADO
5.01 CONCRETO ARMADO PARA MURO 7,543.84
05.01.01 CONCRETO f 'c=210 kg/cm2 m3 8.00 321.24 2569.92
05.01.02 ENCOFRADO Y DESENCOFRADO m2 98.17 34.44 3380.97
05.01.03 ACERO fy=4200 kg/cm2 kg 231.87 6.87 1592.95
5.02 SARDINELES 3,575.47
05.02.01 ENCOFRADO Y DESENCOFRADO h=0.20 m (CARAVISTA) m2 38.40 43.32 1663.49
05.02.02 CONCRETO f 'c=210 kg/cm2 PARA SARDINELES m3 2.88 321.24 925.17
05.02.03 ACERO fy=4200 kg/cm2 kg 143.64 6.87 986.81
6 REVOQUES ENLUCIDOS Y MOLDURAS 3,200.06
6.01 TARRAJEO DE SUPERFICIE DE CONCRETO m2 166.41 19.23 3200.06
7 PISOS Y PAVIMENTOS 2,193.62
7.01 BLOQUES DE CONCRETO DE COLORES m2 51.05 42.97 2193.62
8 PINTURA 1,353.01
8.01 PINTURA VINILICA EN MUROS EXTERIORES 2 MANOS m2 203.46 6.65 1353.01
9 CARPINTERIA DE MADERA 2,000.00
9.01 PORTADA DE MADERA glb 1.00 2000.00 2000.00
10 CARPINTERIA METALICA 16,794.71
10.01 PAPELERA DE FIERRO LAMINADO u 4.00 250.00 1000.00
10.02 RUEDA GIRATORIA u 1.00 3500.00 3500.00
10.03 COLUMPIO PARA CUATRO PERSONAS u 1.00 1700.00 1700.00
10.04 JUEGO MULTIPLE u 1.00 4500.00 4500.00
10.05 CASTILLO u 1.00 1550.00 1550.00
10.06 BALANZA u 1.00 2000.00 2000.00
10.07 BARRAS PARALELAS u 1.00 650.00 650.00
10.08 PASAMANOS u 1.00 450.00 450.00
10.09 BANCAS DE CONCRETO CON APOYO DE TUBO FºGº 1-1/2" m 3.00 481.57 1444.71
11 INSTALACIONES ELECTRICAS 3,650.73
11.01 SALIDA DE TECHO CON CABLE AWG TW 2.5 mm (14) + D PVC SEL 16 mm (5/8) pto 5.00 91.92 459.60
11.02 TABLERO ELECTRICO u 1.00 513.49 513.49
![Page 2: Metrados Parque Acari](https://reader036.vdocuments.net/reader036/viewer/2022082506/563dbb4e550346aa9aac0d28/html5/thumbnails/2.jpg)
11.03 TUBERIAS PVC SAP (ELECTRICAS) D=1" m 85.00 11.59 985.15
11.04 ARTEFACTO FLUORECENTE 1/18W u 5.00 78.19 390.95
11.05 CABLE ELECTRICO NYY 3 X 4 mm2 m 118.00 11.03 1301.54
12 JARDINERIA 4644.36
12.01 SEMBRADO DE GRAS m2 180.00 23.51 4231.80
12.02 PLANTONES u 9.00 20.00 180.00
12.03 SEMBRADO DE FLORES m2 18.00 12.92 232.56
13 VARIOS 350.00
13.01 FLETE TERRESTRE glb 1.00 0.00 0.00
13.02 PINTURA DE JUEGO DE DAMAS Y MUNDO glb 1.00 350.00 350.00
SUB TOTAL 77,919.58
GASTOS GENERALES 10% 7,791.96
TOTAL 85,711.54
SON : OCHENTICINCO MIL SETECIENTOS SETENTIUN Y 54/100 NUEVOS SOLES
![Page 3: Metrados Parque Acari](https://reader036.vdocuments.net/reader036/viewer/2022082506/563dbb4e550346aa9aac0d28/html5/thumbnails/3.jpg)
CUADRO DE METRADOS
OBRA CONSTRUCCION DE LA PLAZUELA Y PARQUE INFANTIL ACARI
UBICACIÓN SECTOR : NUEVO ACARI PROVINCIA : CARAVELI
DISTRITO : ACARI DEPARTAMENTO: AREQUIPA
FECHA JULIO DEL 2009
ITEM DESCRIPCION UND Nº VECES LARGO ANCHO ALTO PARCIAL TOTAL
CONSTRUCCION DE PARQUE INFANTIL ACARI
01 OBRAS PROVISIONALES
01.01 CONSTRUCCION DE ALMACEN Y CASETA DE GUARDIANIA M2 1.00 6.00 3.00 18.00 18.00
01.02 AGUA PARA LA CONSTRUCCION MES 1.00 1.00 1.00
01.03 CARTEL DE IDENTIFICACION DE OBRA DE 3.60 x 2.40 m UND 1.00 1.00 1.00
02 OBRAS PRELIMINARES
02.01 TRAZO Y REPLANTEO M2 1.00 37.00 21.37 790.69 790.69
02.02 LIMPIEZA DE TERRENO MANUAL M2 1.00 37.00 21.37 790.69 790.69
03 MOVIMIENTO DE TIERRAS
03.01 EXCAVACION DE ZANJAS PARA CIMIENTOS M3 33.54MUROS 1.00 73.00 0.40 0.50 14.60
SARDINEL INTERIOR 1.00 90.00 0.30 0.30 8.10SARDINEL VEREDA 2.00 17.50 0.30 0.30 3.15
2.00 13.50 0.30 0.30 2.432.00 20.00 0.30 0.30 3.60
BANCA DE CONCRETO 3.00 0.40 0.40 0.65 0.31FAROL DE PIE 14.00 0.40 0.40 0.60 1.34
03.02 CORTE O RELLENO DE TERRENO HASTA 0.20 mt M3 47.25area= 236.25 m2 0.20 47.25
03.03 ELIMINACION DE MATERIAL EXCEDENTE A MAQUINA M3 38.261.00 31.88 1.20 38.26
03.04 AFIRMADO COMPACTADO DE 4" EN PISOS Y VEREDAS M2 325.16EN PISO DE ADOQUIN CON CONCRETO DE PIEDRA 1.00 51.05 51.05
VEREDA INTERIOR 2.00 25.50 1.50 76.502.00 7.50 1.50 22.50
VEREDAS PERIMETRICAS 2.00 37.00 1.50 111.002.00 21.37 1.50 64.11
04 OBRAS DE CONCRETO SIMPLE
04.01 CONCRETO 1:10 +30% P.G. PARA CIMIENTOS CORRIDOS M3 13.82CIMIENTO DE MUROS DE CONCRETO 1.00 24.00 0.45 0.60 6.48
2.00 3.46 0.45 0.60 1.87
1.00 16.34 0.45 0.60 4.41
MURO PERGOLA 8.00 0.60 0.60 0.10 0.29
PEDESTAL 8.00 0.40 0.40 0.60 0.77
04.02 ENCOFRADO Y DESENCOFRADO PERGOLA M2 12.68MURO PERGOLA 8.00 2.50 0.25 5.00
PEDESTAL 8.00 1.60 0.60 7.68
04.03 FALSO PISO DE 4" DE CONCRETO 1:8 M2 51.05EN PISO PARA ADOQUIN CONCRETO DE PIEDRA AREA 51.05 51.05
![Page 4: Metrados Parque Acari](https://reader036.vdocuments.net/reader036/viewer/2022082506/563dbb4e550346aa9aac0d28/html5/thumbnails/4.jpg)
04.04 VEREDA DE CONCRETO DE 4" M2 274.11VEREDA INTERIOR 2.00 25.50 1.50 76.50
2.00 7.50 1.50 22.50VEREDAS PERIMETRICAS 2.00 37.00 1.50 111.00
2.00 21.37 1.50 64.11
04.05 JUNTAS DE DILATACION M2 52.00longitud 52.00 52.00
05 OBRAS DE CONCRETO ARMADO
05.01 CONCRETO ARMADO PARA MURO
05.01.01 CONCRETO F'C=210KG/CM2 CERCO DE PERGOLA M3 16.362.00 7.10 0.20 1.35 3.83
2.00 13.20 0.20 1.35 7.13
2.00 9.00 0.20 1.10 3.96
2.00 12.00 0.20 0.30 1.44
05.01.02 ENCOFRADO Y DESENCOFRADO M2 98.172.00 7.10 1.35 19.17
2.00 13.20 1.35 35.64
2.00 9.00 1.10 19.80
2.00 12.00 0.30 7.20
05.01.03 ACERO fy=4200 kg/cm2 KG 231.871.00 0.56 414.05 231.87
05.02 SARDINELES
05.02.01 ENCOFRADO Y DESENCOFRADO h=0.30 m CARAVISTA M2 38.40SARDINEL INTERIOR 2.00 90.00 0.30 54.00
SARDINEL VEREDA 4.00 17.50 0.30 21.004.00 13.50 0.30 16.204.00 20.00 0.30 24.00
05.02.02 CONCRETO F'C=210KG/CM2 - PARA SARDINELES M3 2.88SARDINEL INTERIOR 1.00 90.00 0.15 0.10 1.35
SARDINEL VEREDA 2.00 17.50 0.15 0.10 0.532.00 13.50 0.15 0.10 0.412.00 20.00 0.15 0.10 0.60
05.02.03 ACERO PARA SARDINELES Kg 143.641.00 0.56 256.50 143.64
06 REVOQUES ENLUCIDOS Y MOLDURAS PERGOLA
06.01 TARRAJEO DE SUPERFICIE DE CONCRETO M2 81.81MUROS 2.00 7.10 1.35 19.17
2.00 13.20 1.35 35.642.00 9.00 1.10 19.802.00 12.00 0.30 7.20
6.02 TARRAJEO DE SARDINEL DE CONCRETOSARDINEL INTERIOR 4.00 165.00 0.30 198.00
SARDINEL VEREDA 4.00 17.50 0.30 21.004.00 13.50 0.30 16.20
4.00 20.00 0.30 24.00 259.20
07 PISOS Y PAVIMENTOS07.01 BLOQUES DE CONCRETO DE COLORES M2 51.05
AREA 51.05
08 PINTURA
08.01 PINTURA VINILICA EN MUROS INTERIORES Y EXTERIORES 2 MANOS M2 81.81MUROS 2.00 7.10 1.35 19.17
2.00 13.20 1.35 35.642.00 9.00 1.10 19.802.00 12.00 0.30 7.20
8.02 PINTURA ESMALTE EN SARDINEL 2 MANOS M2SARDINEL INTERIOR 2.00 90.00 0.30 54.00
![Page 5: Metrados Parque Acari](https://reader036.vdocuments.net/reader036/viewer/2022082506/563dbb4e550346aa9aac0d28/html5/thumbnails/5.jpg)
SARDINEL VEREDA 2.00 17.50 0.30 10.502.00 13.50 0.30 8.102.00 20.00 0.30 12.00
EN COLUMNAS DE LA PERGOLA 2.00 2.95 6.28 37.05 75.75
09 CARPINTERIA DE MADERA
09.01 PERGOLA DE MADERA GLB 1.00 1.00
10 CARPINTERIA METALICA
10.01 PAPELERA DE FIERRO LAMINADO UND 6.00 6.00 6.00
10.02 RUEDA GIRATORIA UND 1.00 1.00 1.00
10.03 COLUMPIO PARA 4 PERSONAS UND 1.00 1.00 1.00
10.04 JUEGO MULTIPLE UND 1.00 1.00 1.00
10.05 CASTILLO UND 1.00 1.00 1.00
10.06 BALANZA UND 1.00 1.00 1.00
10.07 BARRAS PARALELAS UND 1.00 1.00 1.00
10.08 PASAMANOS UND 1.00 1.00 1.00
10.09 BANCAS DE METAL CON ASIENTO Y RESPALADR DE MADERA UND 16.00 1.00 16.00
10.10 POSTE PEDESTAL PROTECOTRA DE JARDIN UNID. 82.00 82.00 82.00
10.11 CADENA PROTECTORA DE JARDIN E=1" ML. 172.00 172.00 172.00
11 INSTALACIONES ELECTRICAS
11.01 SALIDA DE TECHO CON CABLE AWG 2.5 mm2 PARA CENTRO DE LUZ PTO 5.00 5.00
11.02 TABLERO ELECTRICO UND 1.00 1.00
11.03 TUBERIAS PVC SAP ELECTRICAS DE 1" ML 116.00ALIMENTACION DE POSTES 1.00 116.00
11.04 ARTEFACTO LUMINARIO 1 LAMP 18W UND 24.00 24.00
11.05 CABLE ELECTRICO NYY 3x 4mm2 ML 140.00ALIMENTACION DE POSTES 1.00 140.00
POSTES COLONIALES UNID. 8.00 8.0012 JARDINERIA
12.01 SEMBRADO DE GRASS M2POSA Nº 01 M2 2.00 27.50 55.00POSA Nº 02 M2 2.00 26.00 52.00POSA Nº 03 M2 2.00 28.73 57.46
164.46
12.02 PLANTONES FICUS UND 6.00 6.00 6.00
12.03 SEMBRADO DE FLORES M2 10.00 10.00 10.00
13 VARIOS
13.01 FLETE TERRESTRE GLB 1.00 1.00 1.00
13.02 PINTURA DE PERGOLA GLB 1.00 1.00 1.00