Tonight’s Agenda
• Project Area Discounts/Eat, Shop, Play
• Advance Utility Relocation Update and Look-Ahead
• Tree removal, replacement and landscape overview
• Design Builder Update
• Animation Video – pile installation/street decking
• Break out session Q&A
2
Section 2 New Starts Engineering phase of the FTA Capital Investment Grant Program
Under Construction Forecasted Schedule
Section 1 Section 2 Section 3
Length 3.9 Miles 2.6 Miles 2.48 Miles
New Stations Wilshire/La Brea
Wilshire/Fairfax
Wilshire/La Cienega
Wilshire/Rodeo
Century City
Westwood/UCLA
Westwood/VA
Hospital
Pre-Construction Activities Current - 2016 2017 - 2018 2025 - 2027
Construction 2015 - 2023 2019 - 2026 2027 - 2035
Operations 2023 2026 2035 3
Project Area Discounts
Project Area Discounts is a program that provides exclusive offers to local businesses in communities that are designated project areas.
Purple Line Extension currently has more than 30 businesses enrolled.
For a full list visit: http://www.metro.net/service/discounts/ple-pad/.
For information on how to participate, please contact [email protected].
4
Eat Shop Play
A new webpage will soon highlight the ways the community can Eat at local restaurants, Shop at local retail stores and Play at local destinations.
Eat, Shop, Play will provide access to exclusive offers and information about participating local businesses. The community will be asked to take a pledge to support local businesses during and after construction of the project.
5
Construction Activity Timeline Optimal Schedule Without Restrictions (Assumes extended work hours)
7
*Schedule is subject to change. Updated as of January 2015
YEAR
QUARTER Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Advanced Utility Relocations
Piling
Decking
Station Excavation/Shoring
Tunneling
Station
Testing
Revenue Service
YEAR
QUARTER Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Advanced Utility Relocations
Piling
Decking
Station Excavation/Shoring
Tunneling
Station
Testing
Revenue Service
YEAR
QUARTER Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Advanced Utility Relocations
Piling
Decking
Station Excavation/Shoring
Tunneling
Station
Testing
Revenue Service
*Subject to change without notice. Updated as of January 2015.
*Subject to change without notice. Updated as of January 2015.
LA CIENEGA STATION AREA - SECTION 1 PURPLE LINE EXTENSION PROJECT2020 2021 2022 20232014 2015 2016 2017 2018 2019
FAIRFAX STATION AREA - SECTION 1 PURPLE LINE EXTENSION PROJECT2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
2015 2016 2020 2021
*Subject to change without notice. Updated as of January 2015.
LA BREA STATION AREA - SECTION 1 PURPLE LINE EXTENSION PROJECT2014 2022 20232017 2018 2019
Below Deck
Decking Remove Deck
Below Deck
Install Deck Remove Deck
Decking Remove Deck
Testing
Testing
AUR
Tunneling
Station
Testing
AUR
Tunneling
Station
AUR
Tunneling
Station
Piling
Piling
Piling
Station Excavation/Shoring
Station Excavation/Shoring
Station Excavation/Shoring
Below Deck
West and East Segments Map
8
1
2 4
5 3
• West Segment, Mindy Lake: 1-3 1: Wilshire/La Cienega
2: Wilshire/Fairfax
• East Segment, Michael Cortez: 3-5 4: Wilshire/La Brea
5: Tie-in at Wilshire/Western Station
Tie-in at Western Station
• Ongoing: Acquiring properties on NE corner of Wilshire/Manhattan Pl
9
Properties to be Acquired on NE Corner
Wilshire/Manhattan Pl
• Summer 2016: Construction is anticipated to begin with advanced utility relocation work.
• Summer 2016: Work is anticipated to begin with advanced utility relocation
Rendering of AUR Work
Crenshaw Yard Staging Site Wilshire/Crenshaw
• Will be used throughout Section 1 utility relocation and construction
• Sound wall is complete – Installing sound wall on two gates
• Property acquired at 675 Crenshaw
• Mitigation Efforts and Maintenance: – Right Turn Only signs at Lorraine Gate
– No Metro Contractor Parking on City Street signs
– Noise awareness training
– Nightly noise readings
– Maintenance inside and outside of yard
10
Maintenance work at Crenshaw Yard Acquired property on 675 Crenshaw
Crenshaw Yard Sound Wall and Plywood Installation at the gates
La Brea Utility Relocation 1 Year
11
*Schedule is subject to change. Updated as of January 2015
2014 2015 2016 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Fiber
Power
Water
LADWP Cable Pulling
AT&T Construction
Gas
Metro Advanced Utility Relocation (AUR) Work
• Completed: – Fiber-optic cable relocation
– Electrical work (vaults/duct works)
– Waterline work (fire services, meter, duct, iron steel pipes)
– LADWP Cable Pulling
• Currently underway – February 2015: Gas anticipated to be completed
– March 2015: AT&T Cable pulling anticipated to be completed
La Brea Station Update
12
Photo of AUR work at Wilshire/La
Brea
• Acquisition of Properties
– 665 S La Brea Ave (Abatement work underway)
• Carling Way Alley Vacation
– Alley temporary reroute exit to Detroit
La Brea Station Update (continued)
13 Photos of former Lawrence of La Brea and Carling Way Alley
La Brea Station Mitigation
• Project Area Discount Program
• Business and resident advanced communications
• Night time mitigation efforts
– Torching steel plates
– Additional sound blankets
– Signage
– Louder work moved to daytime hours
14
Photos of sound blankets and torching
steel plates used during recent AUR
work at Wilshire/La Brea
Fairfax Utility Relocation 2 Years
15
*Schedule is subject to change. Updated as of January 2015
2014 2015 2016 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Fiber
AT&T Construction
Power
Water
LADWP Cable Pulling
Gas
Fairfax Station What’s Happened So Far
Metro Advanced Utility Relocation (AUR) Work
• Fiber-optic cable relocation ongoing
• Electrical work underway
• Work Hours:
16
Day work:
Monday – Friday: 9AM - 3:30PM
Saturday: 8AM - 6PM*
Night work:
Sunday – Thursday: Friday
8PM - 6AM 10PM- 8AM
*as needed
Photos of trenching for Fairfax Station
Photo of concrete installation under existing
utilities for Fairfax Station
Fairfax Station What’s Next
• Spring and Summer 2015: Water and gas relocation work anticipated to start
• Summer 2016: AUR work anticipated to be completed
Photo of contractor forming duct bank to vault for Fairfax Station
17
Fairfax Station Mitigation
• Paving work is scheduled to occur on Saturdays
• After 11pm activities are monitored and adjustments are made to the sound blankets at the source to stay below allowable noise levels
– Alternatively, the type of construction activity is changed to reduce noise levels
• Project Area Discount program
• Businesses Are Open During Construction signs
18
Photos of “Businesses Open During Construction” sign and sound blankets at Wilshire/Fairfax
La Cienega Utility Relocation 30 Months
19
*Schedule is subject to change. Updated as of January 2015
2014 2015 2016 2017
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Fiber
Water, Sewer, Storm, Drain, Power
AT&T Construction
Gas
La Cienega Station What’s Happened So Far
Metro Advanced Utility Relocation (AUR) Work
• Completed: Fiber relocation on Wilshire between Gale and San Vicente
• November 2014: Potholing work began on Wilshire and is anticipated to be completed by end of January 2015
Photos of potholing work for the La Cienega Station
20
La Cienega Station What’s Next
• January 2015: Notice to Proceed for AUR contractor has been announced.
• Late 2016: Utility relocation anticipated to be completed. This includes:
21
Photo of Staging Site at Fairfax. A similar site will be created for
the La Cienega Station
Day work:
Monday – Friday: 7AM - 4PM
Sunday: 9AM - 6PM*
*as needed
La Cienega Station Mitigation
• Businesses are Open signs
• Parking relocation program
• Project Area Discount Program
• Plate lock system utilized for sidewalk steel plates
22
Photos of sound blanket for noise mitigation and plate locks at Wilshire/La Cienega
Noise Mitigation Night time work permit: Ambient +5 Db
Crenshaw Yard Wilshire/La Brea
Wilshire/La Cienega Wilshire/Fairfax
23
Tree Removal and Relocation
• Estimate 101 trees need to be removed – 12 at Western Station Tie-in
– 37 at La Brea Station
– 52 at Fairfax Station
• Relocation can be difficult due to condition, cost, timing, size
• Metro has reached out to 30 organizations to gauge interest
– Tree People, Santa Monica Mountains Conservancy, Griffith Park
• Will relocate some trees to Crenshaw Yard
Mexican fan palms around
Wilshire/La Cienega
25
Tree Removal Process City of Los Angeles
• Metro will submit tree removal application to Urban Forestry Division (UFD)
• 30-day posting period to allow for public comment – Tree removal notification system:
http://bsspermits.lacity.org/treepostings/
• UFD will submit report to Board of Public Works for approval; public meeting held
• Trees will be removed incrementally based on construction phasing
• Anticipate first removals at La Brea in spring 2015 – Fairfax removals in summer 2016
– La Cienega removals in late 2016
Lagerstroemia around
Wilshire/Fairfax
26
Landscape Plan Overview
• Metro will replace all trees 2:1
• Design-Builder responsible for landscape plan – Will review existing plan to ensure all trees are necessary to remove
• Landscape palate dictated by existing palate and city requirements
• Miracle Mile Civic Coalition will be included in draft discussions
• Workshops will be hosted by Design-Builder for community input
• City of Los Angeles has agreed to 36” box trees and 20-25’ palms
• New irrigation, controllers and lighting for affected areas
• Furnish and install new Miracle Mile median signs Phoenix dactylifera around
Wilshire/Fairfax
27
Design-Build Update
• July 2014: Metro Board Awards Design-Build Contract
– Skanska, Traylor Bros. and J. F. Shea, a Joint Venture (STS)
• Notice To Proceed (NTP) given January 12, 2015
• Contractor first steps:
– Design Engineering Plans
– Potholing beginning February 2015
• Contractor will be present at March 2015 Community Meeting
29
Design-Builder – Major Construction
• April 1, 2015 – Detroit Parking Lot to close permanently
• Next steps:
– Undergrounding of overhead utilities in Detroit lot
– Construct temporary alley relocation, Carling Way to exit west to
Detroit at northern end of parking lot
– Demo former Metro Customer Service Center, Blockbuster,
Lawrence of La Brea
– Construct staging yard sound walls
• Late 2015 – Pile Drilling begins at La Brea
30
Future Community Meetings
• Next Community Meeting: March 19, 2015
– Anticipate Design-Builder will attend
• Community Meetings held on the 3rd Thursday of every other month
• Community Meeting location will rotate along the alignment
• Section 1 Advisory Group will meet as needed to discuss station specific issues. Meetings will be open to the public.
– Next meeting will focus on La Brea Station/Detroit Lot
• For monthly updates, look out for our newsletter!