Asset Management Metropolitan Council Environmental Services
2015 Minnesota APWA Conference
Sam Paske, P.E.
Outline
1. Background and drivers
2. Approach
3. Framework
4. Next steps
by Alexrk2 - Own work. Licensed under CC
BY 3.0
MCES Mission, Vision & Values
Mission Provide wastewater services and integrated planning to ensure
sustainable water quality and water supply for the region.
Vision Be a valued leader and partner in water sustainability.
Values Excellence
Inclusiveness
Integrity
Respect
Commitment
5
Metropolitan Council
Environmental Services
Wastewater Planning and
Treatment
Water Resources
Planning and Monitoring
Water Supply Planning
Transit Community
Development
The mission of the Metropolitan Council is to foster efficient
and economic growth for a prosperous metropolitan region.
40% lower rates than peers
7
8 treatment plants with 108
communities connected
• 370 million gallons/day
wastewater capacity
(250mgd average)
• 600 miles of pipes
• Approx. 70 lift stations
• 206 metering sites
MCES Wastewater System
Metropolitan Wastewater Plant, St. Paul
o $6 Billion infrastructure replacement cost
o $250M TOTEX Budget 2015
o $1.7 Billion in authorized or planned
capital projects (80% preservation)
8
• Regulatory Requirements
• Aging Infrastructure
• Increasing Costs
• Retiring Workforce
• Sustainability
• Environmental Leadership
Increasing Challenges
9
Aging Wastewater Interceptor Infrastructure
$100M+ per Year
Maintain Top Value
Risk
Perfor-
mance
$$$
Understanding Asset Management
Values-based Approach
Approach Value
Realistic, based on
understanding
Integrity
Respect
Continuous Improvement Excellence
Shift from individual to
collective accountability
Inclusiveness
Commitment
External
Reference
IAM structure
ISO 55000
Uptime Elements
Source: Institute of Asset Management’s Asset
Management Anatomy, based on ISO 55000:2014
Benchmarking
International Water Association
Water Services Association of Australia
Aquamark/American Water Works Association
Asset
Management
Structure
Levels of Service
A. Financial
Wastewater charges and fees are affordable, predictable and justifiable and remain below the average of our national
peers.
Our AAA Bond rating is retained.
Our five-year budget plan optimizes total expenditures to meet our customer service goals and lay the foundation for
long-term financial stability.
B. Public Health and Environmental Protection
Comply consistently with all regulatory permits.
Convey wastewater without backups or spills, except during situations beyond our control, such as extreme wet weather.
Establish and track a plan to achieve best water quality for lowest total cost (to the region) for waters receiving
wastewater effluent
C. Customer Service
Achieve sufficiently accurate wastewater flow measurement, or estimation, to ensure fair and equitable allocation of
municipal wastewater charges and to establish inflow/infiltration mitigation goals.
Be a good neighbor with respect to odors, traffic, noise, and visual aesthetics.
Provide wastewater conveyance and treatment capacity consistent with the regional wastewater system plan and
approved local comprehensive sewer plans.
Communicate with customer communities to explain wastewater financial information, planned capital projects,
and programs affecting their community, and to coordinate public infrastructure asset preservation work.
D. Leadership
Be safe
Minimize the impact on our environment
Reclaim resources from wastewater
Asset Management Policy
Asset – any physical item that has value to
MCES
Asset Management - … translates
organizational objectives into asset-related
decisions, plans and activities using a risk-
based approach
Risk – social, technical, regulatory and
environmental factors that could impact our
mission, vision or goals.
Principles 1. Defined customer service levels help us meet expectations and control costs.
2. Staff capabilities, tools and knowledge must be fostered for sound asset decisions,
informed asset plans and disciplined operation and maintenance.
3. Infrastructure investments look at all options to balance cost, risk and performance
requirements for maximum value over the whole asset life.
4. Lifecycle activities in asset plans are agreed to by operations, maintenance and
engineering before design and construction.
5. Cross functional teams develop risk-based asset plans for all facilities.
6. Individuals and teams use and improve asset plans to operate to agreed-upon design
performance, and maintain for optimal reliability and life, all at lowest possible cost.
7. New or renewed facilities are delivered ready to operate reliably and maintain
effectively.
8. Lessons learned and best practices are incorporated into design, operating and
maintenance strategy development processes for continuous improvement.
Optimization Framework
Criticality
What should an asset do?
How important is that?
A living criticality process to institutionalize
– Measure improvements over time (manage risk down)
– Legitimize daily use
Link to condition
Gives us RISK
Framework for the
Asset Management
Plan
Level-of-Service goals
established through the
collaboration of maintenance,
operations and engineering
Next steps…
1. Finalize the framework
2. Pilot criticality assessment
3. Continue pipe rehabilitation program
4. Asset plans – first 50% complete
5. Planning and Scheduling