MGM SPRINGFIELD OFF-SITE MITIGATION - 2/19/18 TO 3/2/18
WORK HOURS: 7:00 AM TO 3:30 PM
FOR CONSTRUCTION-RELATED INQUIRES PLEASE CONTACT:[email protected]
OFF-SITE MITIGATION
LOC# ZONE LOCATION DESCRIPTION DESCRIPTION OF WORK
1 A Dwight Street & I-291 Off RampInstallation of traffic signs & posts; traffic signal wiring/timing is expected. Lane shifts and/or alternating one way traffic will be required. Pedestrian access will be rerouted. Some noise, dust and vibration may result. A police detail is anticipated. Activity will proceed on an intermittent basis due to normal sequencing of work tasks, subcontractors, & coordination of work.
2 B Locust Street & Mill Street No work anticipated
3 B Main Street & East Columbus Avenue No work anticipated
4 C State Street & St. James Avenue No work anticipated
5 C State Street & Oak Street No work anticipated
6 C State Street & Federal Street No work anticipated
7 C State Street & Spring Street No work anticipated
8 D Plainfield Street & Riverside RoadInstallation of traffic signs & posts; traffic signal wiring/timing is expected. Lane shifts and/or alternating one way traffic will be required. Pedestrian access will be rerouted. Some noise, dust and vibration may result. A police detail is anticipated. Activity will proceed on an intermittent basis due to normal sequencing of work tasks, subcontractors, & coordination of work.
9 D Plainfield Street & Avocado StreetInstallation of traffic signs & posts; traffic signal wiring/timing is expected. Lane shifts and/or alternating one way traffic will be required. Pedestrian access will be rerouted. Some noise, dust and vibration may result. A police detail is anticipated. Activity will proceed on an intermittent basis due to normal sequencing of work tasks, subcontractors, & coordination of work.
10 D Plainfield Street (between Avocado Street & West Street)Installation of traffic signs & posts; traffic signal wiring/timing is expected. Lane shifts and/or alternating one way traffic will be required. Pedestrian access will be rerouted. Some noise, dust and vibration may result. A police detail is anticipated. Activity will proceed on an intermittent basis due to normal sequencing of work tasks, subcontractors, & coordination of work.
11 D Plainfield Street & John StreetInstallation of traffic signs & posts; traffic signal wiring/timing is expected. Lane shifts and/or alternating one way traffic will be required. Pedestrian access will be rerouted. Some noise, dust and vibration may result. A police detail is anticipated. Activity will proceed on an intermittent basis due to normal sequencing of work tasks, subcontractors, & coordination of work.
12 D John Street (between St. George Road & Plainfield Street) No work anticipated
13 E Main Street & Liberty Street No work anticipated
MGM SPRINGFIELD OFF-SITE MITIGATION - 2/19/18 TO 3/2/18
WORK HOURS: 7:00 AM TO 3:30 PM
FOR CONSTRUCTION-RELATED INQUIRES PLEASE CONTACT:[email protected]
OFF-SITE MITIGATION
LOC# ZONE LOCATION DESCRIPTION DESCRIPTION OF WORK
14 E Main Street & Taylor Street No work anticipated
15 E Main Street & Worthington Street No work anticipated
16 E Main Street & Bridge Street No work anticipated
17 E Main Street & Boland Way No work anticipated
18 E Main Street & Court Street No work anticipated
19 E State Street & Chestnut Street No work anticipated
20 E State Street & Dwight Street No work anticipated
21 E State Street & Main Street No work anticipated
22 E Main Street (between State Street & Union Street) No work anticipated
23 E Main Street & Union Street No work anticipated
24 E Boland Way & East Columbus AvenueInstallation of traffic signs & posts; traffic signal wiring/timing is expected. Lane shifts and/or alternating one way traffic will be required. Pedestrian access will be rerouted. Some noise, dust and vibration may result. A police detail is anticipated. Activity will proceed on an intermittent basis due to normal sequencing of work tasks, subcontractors, & coordination of work.
25 E Pynchon Street & East Columbus Avenue No work anticipated
26 E State Street (between Main Street & East Columbus Avenue ) No work anticipated
27 E State Street & MGM Way Reconstruction of sidewalks, curbing, & installation of wheelchair curb ramps. Lane shifts and/or alternating one way traffic will be required. Pedestrian access will be rerouted. Some noise, dust and vibration may result. A police detail is anticipated.
MGM SPRINGFIELD OFF-SITE MITIGATION - 2/19/18 TO 3/2/18
WORK HOURS: 7:00 AM TO 3:30 PM
FOR CONSTRUCTION-RELATED INQUIRES PLEASE CONTACT:[email protected]
OFF-SITE MITIGATION
LOC# ZONE LOCATION DESCRIPTION DESCRIPTION OF WORK
28 E Union Street (between Main Street & East Columbus Avenue)Installation of traffic signs & posts; traffic signal wiring/timing is expected. Lane shifts and/or alternating one way traffic will be required. Pedestrian access will be rerouted. Some noise, dust and vibration may result. A police detail is anticipated. Activity will proceed on an intermittent basis due to normal sequencing of work tasks, subcontractors, & coordination of work.
29 E Boland Way (between East & West Columbus Avenue) Installation of traffic signs & posts; traffic signal wiring/timing is expected. Lane shifts and/or alternating one way traffic will be required. Pedestrian access will be rerouted. Some noise, dust and vibration may result. A police detail is anticipated. Activity will proceed on an intermittent basis due to normal sequencing of work tasks, subcontractors, & coordination of work.
30 E I-91 Off Ramp to West Columbus Avenue No work anticipated
31 E Memorial Bridge & West Columbus AvenueInstallation of traffic signs & posts; traffic signal wiring/timing is expected. Lane shifts and/or alternating one way traffic will be required. Pedestrian access will be rerouted. Some noise, dust and vibration may result. A police detail is anticipated. Activity will proceed on an intermittent basis due to normal sequencing of work tasks, subcontractors, & coordination of work.
32 E State Street & East Columbus AvenueInstallation of traffic signs & posts; traffic signal wiring/timing is expected. Lane shifts and/or alternating one way traffic will be required. Pedestrian access will be rerouted. Some noise, dust and vibration may result. A police detail is anticipated. Activity will proceed on an intermittent basis due to normal sequencing of work tasks, subcontractors, & coordination of work.
33 E East Columbus Avenue (between State Street & Union Street) Installation of traffic signs & posts; traffic signal wiring/timing is expected. Lane shifts and/or alternating one way traffic will be required. Pedestrian access will be rerouted. Some noise, dust and vibration may result. A police detail is anticipated. Activity will proceed on an intermittent basis due to normal sequencing of work tasks, subcontractors, & coordination of work.
34 E Memorial Bridge Installation of traffic signs is expected. Lane shifts and/or alternating one way traffic will be required. Pedestrian access will be rerouted. Some noise, dust and vibration may result. A police detail is anticipated. Activity will proceed on an intermittent basis due to normal sequencing of work tasks, subcontractors, & coordination of work.
35 E Union Street & West Columbus AvenueInstallation of traffic signs & posts; traffic signal wiring/timing is expected. Lane shifts and/or alternating one way traffic will be required. Pedestrian access will be rerouted. Some noise, dust and vibration may result. A police detail is anticipated. Activity will proceed on an intermittent basis due to normal sequencing of work tasks, subcontractors, & coordination of work.
36 E Union Street & East Columbus AvenueInstallation of traffic signs & posts; traffic signal wiring/timing is expected. Lane shifts and/or alternating one way traffic will be required. Pedestrian access will be rerouted. Some noise, dust and vibration may result. A police detail is anticipated. Activity will proceed on an intermittent basis due to normal sequencing of work tasks, subcontractors, & coordination of work.
37 E State Street & West Columbus AvenueInstallation of traffic signs & posts; traffic signal wiring/timing is expected. Lane shifts and/or alternating one way traffic will be required. Pedestrian access will be rerouted. Some noise, dust and vibration may result. A police detail is anticipated. Activity will proceed on an intermittent basis due to normal sequencing of work tasks, subcontractors, & coordination of work.
A
D
B
E
A
C
D
B
E
SPRINGFIELD REFERENCE PLAN
C
33
35
22
26
28
4
34
10
12
1
2
3
5
6
7
9
11
8
13
14 15 16 17 18
19
20
21
232425
29
30
3136
32
27
37
LOC# LOCATION DESCRIPTION DESCRIPTION OF WORK
1 Elm Street & Route 5 No work anticipated
2 Roundabout at Route 5 and North End Bridge No work anticipated
3 Roundabout at Route 5 and Memorial Bridge No work anticipated
4 Route 5, South End Rotary and Route 57 On-Ramp No work anticipated
5 Route 57 near Intersection of Corey Street/Alexander Drive No work anticipated
MGM SPRINGFIELD OFF-SITE MITIGATION - 2/19/18-2/23/18WORK HOURS: 7:00 AM TO 3:30 PM
FOR CONSTRUCTION-RELATED INQUIRES PLEASE CONTACT: [email protected]