2
OPERATIONAL AREA
Umkhanyakude District Municipality Zululand District Municipality uThungulu District Municipality uMhlathuze Local Municipality Northern of Ilembe District Municipality
Mhlathuze Water operational area covers 4½ WSA’s in KwaZulu-Natal
3
ALIGNMENT TO DWAF STRATEGY
ACCESS TO WATER SERVICES Regional bulk supply in Mandlakazi/Hlabisa
area Provision of water and sanitation to schools
QUALITY OF PURIFIED WATER National water quality reporting system ASGISA Skills development at technical level Customer care
4
…/cont. Provision of operational and management
services to district municipalities Umkhanyakude District Municipality Gert Sibande District Municipality Service Level Agreements signed with WSA in
operational area Supply Agreements signed with all customers
ENERGY Energy supply to critical installations agreed
with supplier and these installations would not be load shedded.
5
STRATEGIC DIRECTION
To form strategic partnerships with WSA’s To establish strategic networks with all role
players To support and assist WSA’s to meet their
mandates To assist DWAF with water and sanitation
provisions
6
BUSINESS DEVELOPMENT & PARTNERSHIP OPPORTUNITIES
KZN regional bulk water supply Provincial project with DLGH. Water
supply to Mandlakazi / Hlabisa Area WfW contract with DWAF for 3 years Water and sanitation project schools
(Phase 1 = R48mil)
7
WATER QUALITY
SANAS; SABS 241 standard (2004) Physical quality – 99% compliance Bacteriological quality – 99% compliance Log data into National Water Quality
Register National Microbial analyses program for
bacteriological quality
8
INFRASTRUCTURE DEVELOPMENT
Replacement section of waste-water disposal system (R150mil)
Upgrade of water treatment plant (R112mil) Refurbishment of water transfer scheme (R5,2mil) Refurbishment budget provision for various
installations approved (R16,9 million) Assessment of pipeline integrity in progress Tariffs set for replacement and refurbishment of
infrastructure
9
REPRESENTATIVITY OF BOARD & EXECUTIVE MANAGEMENT
BO
AR
DE
XE
CU
TIV
EEQUITY
GENDER
BLACK WHITE INDIAN
8 1 1
FEMALE MALE
5 5
BLACK WHITE INDIAN
3 2 0
FEMALE MALE
0 5
EQUITY
GENDER
10
TARIFF 2008/09
Approved by National Treasury Discussions held with customers that if
electricity cost increase relevant would be passed onto customers
11
FINANCE REPORT
AUDIT ISSUES Consortium of new External Auditors, KPMG/Sizwe
Ntsaluba, appointed for the FY2006/07 audit Financial statements were prepared in accordance with
SA GAAP, Water Services Act and the PFMA. MW received a Qualified Audit opinion for the
FY2006/07 on the basis of a Special Purpose Entity, MW Lessor Trust, which was set up to finance a DWAF Emergency Transfer Scheme in 1996. The last audited financials of the Trust were in February 2005. The purpose for which the Trust was set up ended on 1July 2007 and MW is in the process of dissolving it.
12
…/cont.
There was a prior year restatement of the FY2005/06 financials in order to
• Comply with disclosure requirements• Correct seven prior year errors noted
13
INCOME STATEMENT
Operating income before finance costs increased by 3% from FY2005/06 to FY2006/07
Operating costs to Total income decreased from 76% in FY2005/06 t0 73% in FY2006/07. This is in line with the Board’s strategy to streamline and contain costs.
Net finance costs reduced by 38% from FY2005/06 to FY2006/7 due to; The redemption of loans (R45,1million) in
FY2006/07 The renegotiation of interest rates with the loan
providers. (DBSA reduced their interest rate from 16.5% to 13%) .
14
FINANCE RATIOS
Target FY2006/07 FY2005/06
Debtors’ days 45 days 90.8 days 96.8 days
Current ratio 2:1 1.6:1 1.4:1
Quick ratio 1:1 1:1 0.9:1
Debt /Equity ratio 1< 1.7 1.9
Return on Assets 10% 12.9% 14.1%
15
CAPITAL EXPENDITURE
Actuals (in R000’s) FY2006/07 FY2005/06
Richards Bay Effluent disposal
46 899 5 812
Water Schemes 4 297 2 045
CAPITAL BUDGET FY2007/08 FY2008/09 FY2009/10
Water Schemes 155 576 69 863 99 367
Connection 1 482 119 518 82 000