Page 1: MICE Coupling Coil Update Steve Virostek for Allan DeMello Lawrence Berkeley National Laboratory MICO January 23, 2013 January 23, 2013

MICE Coupling Coil MICE Coupling Coil UpdateUpdate

Steve Virostek for Allan DeMelloLawrence Berkeley National Laboratory

MICOMICO

January 23, 2013January 23, 2013

Page 2: MICE Coupling Coil Update Steve Virostek for Allan DeMello Lawrence Berkeley National Laboratory MICO January 23, 2013 January 23, 2013

MICE RFCC Module – MICE Schedule Review at RAL, UK

Page 2Derun Li - Lawrence Berkeley National Lab – May 24, 2011

MICE Coupling Coil Update – MICO

Page 2Allan DeMello- Lawrence Berkeley National Lab – January

23, 2013

Current Status of Coupling CoilCurrent Status of Coupling Coil

• Cold Mass• By-pass of cooling pipe leak installed• Pressure test of all cooling pipes complete• Vacuum check of all cooling pipes complete• Shipping to Fermilab today

• Cryostat• Drawings are complete• LBNL mechanical shop will fabricate the first cryostat• Purchase order for stainless steel placed

Page 3: MICE Coupling Coil Update Steve Virostek for Allan DeMello Lawrence Berkeley National Laboratory MICO January 23, 2013 January 23, 2013

MICE RFCC Module – MICE Schedule Review at RAL, UK

Page 3Derun Li - Lawrence Berkeley National Lab – May 24, 2011

MICE Coupling Coil Update – MICO

Page 3Allan DeMello- Lawrence Berkeley National Lab – January

23, 2013

By-pass pipe

Location of leakLocation of leak

Original pipeOriginal pipe

By-pass pipeBy-pass pipe

Helium reservoir

Section view

Section of pipe cut out

Pipe capped

Page 4: MICE Coupling Coil Update Steve Virostek for Allan DeMello Lawrence Berkeley National Laboratory MICO January 23, 2013 January 23, 2013

MICE RFCC Module – MICE Schedule Review at RAL, UK

Page 4Derun Li - Lawrence Berkeley National Lab – May 24, 2011

MICE Coupling Coil Update – MICO

Page 4Allan DeMello- Lawrence Berkeley National Lab – January

23, 2013

By-pass pipe

• Fitting location for Fermilab magnet test is same as the original pipe

Location of leakLocation of leak

Original pipeOriginal pipe

By-pass pipe

Section of pipe cut out

FermilabFermilabmagnet testmagnet testfittingfitting

Page 5: MICE Coupling Coil Update Steve Virostek for Allan DeMello Lawrence Berkeley National Laboratory MICO January 23, 2013 January 23, 2013

MICE RFCC Module – MICE Schedule Review at RAL, UK

Page 5Derun Li - Lawrence Berkeley National Lab – May 24, 2011

MICE Coupling Coil Update – MICO

Page 5Allan DeMello- Lawrence Berkeley National Lab – January

23, 2013

By-pass Cooling Pipe Pressure TestBy-pass Cooling Pipe Pressure Test

• The by-pass cooling pipe was hydrostatically tested, in steps, to a pressure of 300 psi• No leaks detected• Vacuum tight

Page 6: MICE Coupling Coil Update Steve Virostek for Allan DeMello Lawrence Berkeley National Laboratory MICO January 23, 2013 January 23, 2013

MICE RFCC Module – MICE Schedule Review at RAL, UK

Page 6Derun Li - Lawrence Berkeley National Lab – May 24, 2011

MICE Coupling Coil Update – MICO

Page 6Allan DeMello- Lawrence Berkeley National Lab – January

23, 2013

Pressure Test of Other Cooling PipesPressure Test of Other Cooling Pipes

• Other two cooling pipes were hydrostatically tested, in steps, to a pressure of 223 psi• No leaks detected• Vacuum tight

Upper cooling pipe being tested Lower cooling pipe being tested

Page 7: MICE Coupling Coil Update Steve Virostek for Allan DeMello Lawrence Berkeley National Laboratory MICO January 23, 2013 January 23, 2013

MICE RFCC Module – MICE Schedule Review at RAL, UK

Page 7Derun Li - Lawrence Berkeley National Lab – May 24, 2011

MICE Coupling Coil Update – MICO

Page 7Allan DeMello- Lawrence Berkeley National Lab – January

23, 2013

Coupling Coil Cold Mass Ready to ShipCoupling Coil Cold Mass Ready to Ship

Coupling coil cold mass wrapped for shipping

Coupling coil cold mass moved to crate

Coupling coil cold mass in crate

Page 8: MICE Coupling Coil Update Steve Virostek for Allan DeMello Lawrence Berkeley National Laboratory MICO January 23, 2013 January 23, 2013

MICE RFCC Module – MICE Schedule Review at RAL, UK

Page 8Derun Li - Lawrence Berkeley National Lab – May 24, 2011

MICE Coupling Coil Update – MICO

Page 8Allan DeMello- Lawrence Berkeley National Lab – January

23, 2013

Coupling Coil CryostatCoupling Coil Cryostat

Single Cavity Vacuum Vessel Exploded View

Page 9: MICE Coupling Coil Update Steve Virostek for Allan DeMello Lawrence Berkeley National Laboratory MICO January 23, 2013 January 23, 2013

MICE RFCC Module – MICE Schedule Review at RAL, UK

Page 9Derun Li - Lawrence Berkeley National Lab – May 24, 2011

MICE Coupling Coil Update – MICO

Page 9Allan DeMello- Lawrence Berkeley National Lab – January

23, 2013

Coupling Coil CryostatCoupling Coil Cryostat

•Cryostat design is complete•Drawings complete•LBNL mechanical shop will

fabricate the first cryostat•Purchase order for stainless

steel placed•Estimated to take 6 months to

complete fabrication•Drawings will be updated to

reflect the “as built” cryostat