microsoft project tutorial for chapters 6 & 7

33
Microsoft Project Tutorial for Chapters 6 & 7 This Tutorial explains how to: Reflect A Crashed Project in the Gan tt Chart Resource Loading Create a Resource Calendar Use MSP Auto Resource Leveling Project Status and the Earned Value Report * Click on above link to skip to that Section *clicking on the light bulb will take you directly to the software tutorial for that lesson *clicking on Home will take you directly back to the first slide

Upload: jamal

Post on 11-Jan-2016

44 views

Category:

Documents


2 download

DESCRIPTION

Microsoft Project Tutorial for Chapters 6 & 7. This Tutorial explains how to: Reflect A Crashed Project in the Gantt Chart Resource Loading Create a Resource Calendar Use MSP Auto Resource Leveling Project Status and the Earned Value Report * Click on above link to skip to that Section. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Microsoft Project Tutorial for Chapters 6 & 7

Microsoft Project Tutorial for Chapters 6 & 7

This Tutorial explains how to:

• Reflect A Crashed Project in the Gantt Chart• Resource Loading• Create a Resource Calendar• Use MSP Auto Resource Leveling• Project Status and the Earned Value Report* Click on above link to skip to that Section

*clicking on the light bulb will take you directly to the software tutorial for that lesson

*clicking on Home will take you directly back to the first slide

Page 2: Microsoft Project Tutorial for Chapters 6 & 7

Reflecting a Crashed Project in the Gantt ChartThe Gantt Chart for Table 6-1 reflects a change in working schedule to

a 7-day work week.

Page 3: Microsoft Project Tutorial for Chapters 6 & 7

Reflecting a Crashed Project in the Gantt Chart

*To do this (review): • Go to Tools• Select Change Working Time

In the Change Working Time Box:• Click on the Work Weeks Tab• Click Details• Select all seven days • Set days to specific Working

Times• Set the whole week to an 8

hour shift• Press OK

Page 4: Microsoft Project Tutorial for Chapters 6 & 7

Reflecting a Crashed Project in the Gantt ChartTo adjust the expediting of a project, simply change the duration of

the Critical Task’s duration in the Gantt table (20-day solution)By Changing the duration of task a:• The Finish Date of task a has

updated automatically• The Finish Date of the Project

and the Gantt Chart have updated accordingly:

Page 5: Microsoft Project Tutorial for Chapters 6 & 7

Reflecting a Crashed Project in the Gantt ChartTake the same approach to adjust the Project even further

(19-day solution)After Changing task a, change task f’s duration to 8 days• The Finish Date of task a has

updated automatically• The Finish Date of the Project

and the Gantt Chart have updated accordingly:

Page 6: Microsoft Project Tutorial for Chapters 6 & 7

Reflecting a Crashed Project in the Gantt ChartThe Gantt Chart will adjust automatically for all crashed adjustments

(18-day & 16-day)

Page 7: Microsoft Project Tutorial for Chapters 6 & 7

Resource Loading First, Build your Gantt Chart to resemble figure 6-10, exclude

resources for now.

Be sure to:• Mark “Scheduling Shoots” a summary task• Use the Gantt Chart Wizard to Show Finish dates of tasks &

Milestones• Add WBS Codes

Page 8: Microsoft Project Tutorial for Chapters 6 & 7

Resource Loading

Now Create a Resource list

• Go to the View Bar• Select Resource Sheet

A chart will appear:

Page 9: Microsoft Project Tutorial for Chapters 6 & 7

Resource Loading Creating a Resource list

• First, enter in each individual Resource Name from the Action Plan (figure 6-10) • Assign Each individual Resource a Unique Initial • Transfer Standard & Overtime Rates from Table 6-5 to appropriate

Resource, Table should resemble below:

Page 10: Microsoft Project Tutorial for Chapters 6 & 7

Resource Loading Assigning a Resource to a Task

• Refer back to Gantt View• Under WBS 2 (Scriptwriting), Go to Resource Names• There is now a drop down with Resource Names, select Scriptwriter

Page 11: Microsoft Project Tutorial for Chapters 6 & 7

Resource Loading Assigning Multiple Resources to a Task

• Double click anywhere on the appropriate task row (propose shoots) • The Task Information Box will appear:

• Select the Resources Tab

Page 12: Microsoft Project Tutorial for Chapters 6 & 7

Resource Loading Assigning Multiple Resources to a Task

• Under Resource Name, add each Resource Needed• Then select OK

Page 13: Microsoft Project Tutorial for Chapters 6 & 7

Resource Loading Assigning Multiple Resources to a Task

• Under Resource Name, add each Resource Needed• Then select OK

The Gantt Table should now looks as follows:

* Task 11 shooting, should include the Editor, not scriptwriter(typo)

Page 14: Microsoft Project Tutorial for Chapters 6 & 7

Resource CalendarsCreating a Resource Calendar

As mentioned in the text, some of the resources have a schedule that does not follow MSP’s Standard Calendar. We can create a resource Calendar for these Resources. (Refer to Table 6-4) • Go to Tools• Select Change Working Time…

In the Change Working Time Box, under the For calendar dropdown, notice that each Resource Name has been added. First Select Scriptwriter

Page 15: Microsoft Project Tutorial for Chapters 6 & 7

Resource CalendarsCreating a Resource Calendar

The Scriptwriter works one hour later (6: 00 p.m.) and one extra day of the week (Saturday)• Select the Work Weeks Tab • With Default Line 1 selected, click details

• Highlight all working days (Monday-Saturday)• Set Days to the Specific work

times • Change to end at 6:00 p.m.• Click OK

Page 16: Microsoft Project Tutorial for Chapters 6 & 7

Resource CalendarsCreating a Resource Calendar

A warning that the fixed-duration of tasks assigned to this resource will be changed. Click ok

Page 17: Microsoft Project Tutorial for Chapters 6 & 7

Resource CalendarsCreating a Resource Calendar

The Client works a standard schedule except for a vacation scheduled for March 13-March 26. Create a calendar for this Resource:• Go to Tools, Select Change Working Time, and select Client from

the “For Calendar” Dropdown

• Choose the Exceptions Tab • Enter in Vacation• Include Start and Finish Dates• Click OK

Page 18: Microsoft Project Tutorial for Chapters 6 & 7

Resource CalendarsCreating a Resource Calendar

A warning that the fixed-duration of tasks assigned to this resource will be changed. Click ok

Page 19: Microsoft Project Tutorial for Chapters 6 & 7

Resource CalendarsCreating a Resource Calendar

Create a calendar for the Editing Room • Under Working Weeks Tab• Set days Monday- Friday• Set Times from 9:30 a.m. – 3 p.m.• Select OK to the same

warning about changes in duration

Page 20: Microsoft Project Tutorial for Chapters 6 & 7

Resource CalendarsCreating a Resource Calendar

In the Gantt Chart View, we can see that the end date has been changed to 5/17 to accommodate for new resource calendars.

Page 21: Microsoft Project Tutorial for Chapters 6 & 7

Resource LevelingView the Resource Loading Chart

To view the Resource Loading Chart:• On the View bar click Resource Usage

Resource Loading Chart• Timescale can be

adjusted just as the Gantt Chart was.• Resources in bold are

over-allocated.

Page 22: Microsoft Project Tutorial for Chapters 6 & 7

Resource LevelingView Over-Allocated resources

To view Resources that are over-allocated:• Click on the More Views button on the View Bar• Choose Resource Allocation• Select an over-allocated resource (Scriptwriter)

Page 23: Microsoft Project Tutorial for Chapters 6 & 7

Resource LevelingView Over-Allocated resources

Filter for only Over allocated Resources• Go to Project, Filtered for:• Select Over allocated Resources

Page 24: Microsoft Project Tutorial for Chapters 6 & 7

Resource LevelingView Over-Allocated resources

Viewing Over-allocated resources graphically: • Click on Resource Graph • Adjust the Timescale for the graph as we

did with the Gantt chart

Page 25: Microsoft Project Tutorial for Chapters 6 & 7

Resource LevelingLeveling Resources

To Level Resources:• Go to Tools• Select Level Resources

This will bring up the Resource Leveling Dialogue

box

Page 26: Microsoft Project Tutorial for Chapters 6 & 7

Resource LevelingLeveling Resources

To Level Resources:• Select Automatic

Leveling Calculations • For this example, we

want to Look for over-allocations on a Day by Day basis. • Level entire project • Level only within

available slack

Page 27: Microsoft Project Tutorial for Chapters 6 & 7

Resource LevelingLeveling Resources

This particular project has been leveled for all tasks but individual tasks can also be leveled over the entire

project or over a designated time span.

Page 28: Microsoft Project Tutorial for Chapters 6 & 7

Project StatusProject Status & The Earned Value Report

Entering Actuals into our report to track project status*Before Tracking a Project’s Status, save it, this will be your

“Baseline” or snapshot or project Plan

Set Baseline: • Tools • Tracking• Set Baseline• Set Baseline to Entire Project

Page 29: Microsoft Project Tutorial for Chapters 6 & 7

Project StatusProject Status & The Earned Value Report

Entering “Actuals” into our report to track project status

Select Tracking Gantt from View Bar: • Insert the Actual & Baseline Start & Finish Columns

if needed. • Also insert Actual & Baseline Duration if needed.• Plug in Actual Start & Finish Dates, Actual Duration,

Cost, and Work should adjust accordingly.

Page 30: Microsoft Project Tutorial for Chapters 6 & 7

Project StatusProject Status & The Earned Value Report

Viewing the Earned Value Report of a Project

Click on the upper left corner of the Task Sheet so the entire project is highlighted

• Right Click • Select More Tables from the menu• Select Earned Value• Click Apply

Page 31: Microsoft Project Tutorial for Chapters 6 & 7

Project StatusProject Status & The Earned Value Report

Viewing the Earned Value Report of a Project

Your Earned Value Report can be given from your Project Status and will adjust according to the actuals

you put it.

Page 32: Microsoft Project Tutorial for Chapters 6 & 7

Project StatusThe Earned Value Report can also be exported to an Excel Graph

• Go to Report• Choose Visual Reports…

On the Visual Reports dialogue box • Select the Expected Value

Over Time Report • Click View

Page 33: Microsoft Project Tutorial for Chapters 6 & 7

Project Status

The auto-leveling and tracking options are an effective tool for Project Managers and should be explored

further.