  • MINE DEVELOPMENT ASSOCIATES

    MINE ENGINEERING SERVICES

    775-856-5700 210 South Rock Blvd.

    Reno, Nevada 89502

    FAX: 775-856-6053

    Technical Report

    Titan Project

    Ontario, Canada

    Prepared for

    November 7, 2006

    Revised February 12, 2007

    Ownership Revised February 26, 2010

    Neil Prenn, P. Eng.

  • MINE DEVELOPMENT ASSOCIATES

    MINE ENGINEERING SERVICES

    775-856-5700 210 South Rock Blvd.

    Reno, Nevada 89502

    FAX: 775-856-6053

    C O N T E N T S

    1.0 SUMMARY .................................................................................................................................... 1

    1.1 Introduction .......................................................................................................................... 1

    1.2 Geology and Mineralization ................................................................................................. 1

    1.3 Mineral Processing and Metallurgical Testing .................................................................... 2

    1.4 Mineral Resource Estimate .................................................................................................. 2

    1.5 Conclusions and Recommendations .................................................................................... 5

    2.0 INTRODUCTION AND TERMS OF REFERENCE ..................................................................... 6

    2.1 Introduction .......................................................................................................................... 6

    2.2 Terms of Reference .............................................................................................................. 6

    2.3 Definitions ............................................................................................................................ 7

    3.0 RELIANCE ON OTHER EXPERTS .............................................................................................. 8

    4.0 PROPERTY DESCRIPTION AND LOCATION ........................................................................... 9

    4.1 Location ................................................................................................................................ 9

    4.2 Land Area and Mining Property Description ....................................................................... 9

    4.3 Agreements and Encumbrances ......................................................................................... 10

    4.4 Environmental Liability ..................................................................................................... 10

    5.0 ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE AND

    PHYSIOGRAPHY ........................................................................................................................ 13

    5.1 Access ................................................................................................................................ 13

    5.2 Climate ............................................................................................................................... 13

    5.3 Local Resources and Infrastructure .................................................................................... 13

    5.4 Physiography ...................................................................................................................... 13

    6.0 HISTORY ...................................................................................................................................... 14

    6.1 Historic Resource Estimates .............................................................................................. 14

    7.0 GEOLOGIC SETTING ................................................................................................................. 16

    7.1 Regional Geology ............................................................................................................... 16

    7.2 Property Geology ............................................................................................................... 16

    8.0 DEPOSIT TYPES ......................................................................................................................... 19

  • Technical Report, Titan Project Prophecy Resource Corp. and Randsburg International Gold Corp. Page 2

    Mine Development Associates C:\Projects\Titan\43-101\43-101_2006_Titan_revised_03-04-10final.doc February 26, 2010 neil 3/4/10 5:42 PM

    9.0 MINERALIZATION ..................................................................................................................... 20

    10.0 EXPLORATION ........................................................................................................................... 21

    10.1 Historic Exploration ........................................................................................................... 21

    10.2 Randsburgs Exploration .................................................................................................... 22

    11.0 DRILLING .................................................................................................................................... 23

    12.0 SAMPLING METHOD AND APPROACH ................................................................................. 25

    13.0 SAMPLE PREPARATION, ANALYSES AND SECURITY ...................................................... 27

    13.1 Check Assays ..................................................................................................................... 27

    13.2 Sample Statistics ................................................................................................................ 28

    14.0 DATA VERIFICATION ............................................................................................................... 33

    15.0 ADJACENT PROPERTIES .......................................................................................................... 34

    16.0 MINERAL PROCESSING AND METALLURGICAL TESTING ............................................. 35

    17.0 MINERAL RESOURCE ESTIMATE .......................................................................................... 37

    17.1 Specific Gravity ................................................................................................................. 37

    17.2 Resource Estimate .............................................................................................................. 37

    18.0 OTHER RELEVANT DATA AND INFORMATION ................................................................. 43

    19.0 INTERPRETATION AND CONCLUSIONS .............................................................................. 44

    20.0 RECOMMENDATIONS .............................................................................................................. 45

    21.0 REFERENCES .............................................................................................................................. 46

    22.0 CERTIFICATE OF AUTHOR ...................................................................................................... 48

  • Technical Report, Titan Project Prophecy Resource Corp. and Randsburg International Gold Corp. Page 3

    Mine Development Associates C:\Projects\Titan\43-101\43-101_2006_Titan_revised_03-04-10final.doc February 26, 2010 neil 3/4/10 5:42 PM

    T A B L E S

    Table 1.1 Randsburg Drilling Summary .................................................................................................... 2

    Table 1.2 Titan Inferred Resource ............................................................................................................. 4

    Table 6.1 Historic Indicated and Inferred Resource Estimate ............................................................. 15

    Table 11.1 Randsburg Drilling Summary ................................................................................................. 23

    Table 11.2 Extent of Drilling ..................................................................................................................... 23

    Table 12.1 Mineralized Intervals ............................................................................................................... 25

    Table 13.1 Metallurgical Test Composite vs Drill Hole Analysis ............................................................ 27

    Table 13.2 Drill Hole Statistics ................................................................................................................. 28

    Table 16.1 Altairnano Metallurgical Test Composites .............................................................................. 35

    Table 17.1 Density Testing of Mineralized Materials ............................................................................... 37

    Table 17.2 Statistics of Materials Inside and Outside the Mineralized Zones .......................................... 39

    Table 17.3 Titan Inferred Resource ........................................................................................................... 42

    F I G U R E S

    Figure 4.1 Location of the Titan Project .................................................................................................. 11

    Figure 4.2 Claims of the Titan Property with Location of Inferred Resource ......................................... 12

    Figure 7.1 Regional Geology .............................