ministry of infrastructure the republic of rwanda · (eac) and regional organizations (eapp, egl,...
TRANSCRIPT
Ministry of Infrastructure
The Republic of Rwanda
Contents
Energy Sector Background
Energy Sector Overview
The Current Status & Planned Energy Sector Growth
Generation & Access Targets
Energy Sector Reform
Planned Generation & Tariff
National Energy Policy
Development of Interconnection
Investment Opportunities
Background
Rwanda’s economy grew at an annual average rate of 8.3%
over the past 5 years;
Current Government target is to
achieve 11.5% annual average growth over the EDPRS II period
(2013-2017);
Rwanda’s second Economic
Development and Poverty Reduction Strategy (EDPRS II)
enshrined in four thematic
areas, aims at achieving rapid
economic growth, rural development, productivity and
youth employment, and
accountable governance;
RWANDA: VITAL STATISTICS
Access to affordable and modern
sources of energy is therefore
essential to the achievement of the
above development objectives;
Energy Sector overview
Dependence on Biomass (wood energy) for fuel stands at 85%. We target to reduce this to an est. 55% by 2017 & to 50% by 2020
Current Electricity installed capacity is 160 MW. We intend to
increase To at least 563 MW by 2017/18
Current generation mix: 60.32% hydro, 32.03% thermal ,2.3%
methane & 5.42 % solar. The target is to increase generation from indigenous resources & gradually reduce over dependence on
thermal.
The Current Status & Planned Energy Sector Growth
Electricity Access
0%
50%
23.0%
4.7%
29.9% 8.6%
48.0% 22.0%
Electrification rate2014Planned 2015/16
Current access to electricity is
23%. We target to increase the access to 70% by 2017/18.
Public institutions (schools,
health facilities, administrative
offices) to be connected 100% by 2017/18
Current network length:
3,932km MV, 1,078km LV &
1,228km HV. We are expanding the network to
meet the access targets
An estimated $ 3bn of
investment capital is required to generate 563 MW & reach
70% access by 2017/18.
Generation & Access Targets
Sales of Tier 2-5 home solar systems, plus number of connections to mini-grids (not connected to the central electricity system)
Planned Generation & Tariff
10
11
12
13
14
15
2005 2010 2015 2020 2025 2030 2035
USc
/kW
h
Projected Average Tariff
Energy Sector Reform
• The Utility recently reformed
and this allows for the private
sector to actively participate
in electric power production,
transmission, distribution and
trading both within and
outside the country;
• Furthermore it simplifies
tendering procedures to
allow investors to bid for
contracts ;
• The Rwanda Utility
Regulatory Agency ( RURA)
is an independent regulator
• The Rwanda Government
through Rwanda
Development Board and
Rwanda Energy Group Ltd, is
ready for business in Energy
Sector ;
• We welcome investors with
both finance and technology;
• We have recently concluded
power deals with different
global project developers
( Ex: Contour Grobal, GigaWatt
Grobal, Hakan, Symbion Power,
etc.)
National Energy Policy Power Transmission Network
The Government of Rwanda strongly
committed to working with its neighbors
(EAC) and regional organizations (EAPP,
EGL, NELSAP) on energy development to
reach its Energy Policy Objectives
Promote the development of the
interconnected regional network and
coordinated planning of generation
expansion to minimize costs and improve
security of supply
Promotion regional power trading to
materially reduce the average cost of
power and the carbon intensity of the
grid
The Policy recommends Import Capacity
of 20% for prudent planning (Security
Purposes)
Development of Interconnection
Power Transmission Network
Development of Interconnection
Power Transmission Network
Kibuye-Gisenyi-Goma-Kigali, 200km, 220kV
double circuit
Rwanda-TZ TL 220kV double circuit 109km for Rwnda
scope
Rwanda-Ug TL, 220kV double circuit, 172km
Rwanda-Burundi, 220km single circuit,
142km to Gitega/Burundi
Kibuye-Kamanyola, 220kV,double circuit, 90km-no funding yet
Development of Interconnection
Development of Interconnection
Development of Interconnection
INVESTMENT OPPORTUNITIES
Other Small Hydro Power
Incentives: •Over 332 Micro Hydropower sites have been identified •69 Greenfield sites identified •REFIT Feed in tariff (from 100kW to 5MW) •Standard PPA for small sites •Size varies between 100kW to 5 MW Way Forward: •Feasibility studies to be carried out and put under competitive process.
Nyabarongo II Hydro Power •Nyabarongo-I completed with capacity of 28MW
Incentives: •128 MW multi-purpose project with damn and pumped power, irrigation and other uses •Phase 1: 47.5 MW ( Dam based plant) •Strategic importance: energy, water supply, irrigation, flood control •Phase 12: 80 MW ( Pumped Storage based plant) Way forward: •Completion of Feasibility Study by July 2015 • Investment as BOT
Feasibility Study On-going by Feedback Infra(Indian Firm)
Feasibility Studies Required
Value of projects: Est. USD 350-500m
Methane Power Generation Incentives: •Lake Kivu has est. 700MW over 55 years, split equally between Rwanda and DRC •3.6 MW Government owned pilot project completed and connected to Grid Nov 2008; •100MW IPP under construction in two phases; • Phase 1: 25MW pilot project COD expected before end of 2015; •Clear L. Kivu management prescriptions on safe operation and maintaining our resource established Way forward: •50 MW to start construction this year ( Symbion-IPP) •Available more than 100MW with Combined Cycle technology (Methane Gas & Steam) under-feasibility study now
Peat to Power Generation
Value of projects: Est. USD 3m per MW Incentives: •Nationwide peat assessment exists indicating around 600MW of potential and currently being updated.( by SWECO –Sweden ) •Study to be finalised July 2015; IPP to be launched thereafter. •Seeking investors in both peat mining, power generation or both
Way forward: Encouraging Developers to invest in peat to power (Combined Cycle to be considered)
Feasibility Study on going by SWECO(Swedish Firm)
Feasibility Study & Detailed Engineering Designs Required
Geothermal Power Generation
Incentives: •Geothermal Master Plan being developed, ready by Sept. 2015
Way forward: •Final ground studies underway as part of Master Plan •Resume exploration dependant on Master Plan •Once exploration proves potentials of power source, the Government will engage private sector for power production
Study On-going
Solar Power Generation
Incentives: •Largest utility scale PV plant in East Africa located in Rwanda •Solar Assessment 2013 •Looking for further utility PV power from 2017/18 at cost reflective tariff •Large off-grid potential available with results based financing program and other government incentives •Rural Electrification strategy underdevelopment • Renewable Energy Law (Draft) Way forward: •Off-grid market available with target to reach 22% House Holds (520,000 HHs) by 2018
Feasibility Study Required
Off-grid: Mini-grids Electrification
Incentives: •PPA with off-taker guarantees demand and results based finance support •Simplified Licensing for Rural Electrification in existence and to be updated before end 2015 •Sites identified where grid will not reach within 5 years •22% Electrification target by 2018 through off-grid solutions •Some feasibility studies available
Way forward: •Private Sector is key for this sector to reach the target
Feasibility Study Required
Eldoret – Kampala – Kigali Oil Pipeline Incentives: •Eldoret – Kampala feasibility study finished •Kampala–Kigali feasibility study completed August 2014 •Strong incentive to undertake project for energy security and regional integration
Way forward: •Envisage PPP/EPC models •Still looking for investors
Value of projects: Est. USD 1 bn Kampala- Kigali section
Regional Integration: Investments
Feasibility Study Completed
Feasibility Study Complete
Rusizi III & IV Hydro Power
Incentives: •International tenders for construction and transmission •Pre-feasibility study completed Way forward: •Fund mobilization for detailed study and implementation
Feasibility Study on-going 400/220kV Transmission Lines and substations
Incentives: •Feasibility studies have been finalized with the final output in Oct, 2015 options on going in the investment unit Way forward: •Budget to be mobilized • Implementation of the project by Fiscal Year 2016/17
THANK YOU