MINUTES OF TWENTIETH COORDINATION MEETING (26/05/2015)
Following issues of effective coordination for development of Mumbai were discussed on 5/5 and status of work clarified as follows:-
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
1 MMRDA CR / WR
CBE
A. Proposed construction of elevated connecter between Bandra-Kurla
complex and Eastern express highway.
1. GAD for ROB between Kurla &
Sion. 2. GAD for ROB for Chunabhatti
Railway Station. 3. GAD for ROB near Chunabhatti
Railway station. In lieu of L-xing No. 1/T.
MMRDA suggested on 23.09.2014 that proposed elevated corridor (CSTM-Panvel) may be raised at
Chunabhatti to the same level as at Kurla to enable ROB 2 & ROB 3 at Chunabhatti to remain
underneath. MRVC and Railways agreed.
MMRDA also indicated that they are not able to lower the level of the connector by 1.5 m as
requested by MRVC. This will result into keeping the PNVL - CSTM fast corridor at level of 18 to 20
meters right from SCL Road Kurla point to EE highway Chunabhatti point.
It was requested by Central Railway to add a Road
also along with Fast corridor for effective disaster Management.
i) GAD for ROB between Kurla & Sion approved on 16.01.15.
ii) Chunabhatti Station ROB GADs approved on
27.01.15. iii) Chunabhatti LC No. 1T, ROB approved on
29.01.15. Launching scheme of all the three ROBs will be
submitted by MMRDA by 15.04.15. Case cannot be submitted to CRS without
launching schemes. After this work Chunabhatti
level crossing shall be closed. No change as on 10.3.15, 24.03.2015 &
07.04.2015. PDC of 15.04.2015 will be honored. PDC shifted from 15.4.2015 to 6.5.2015.
Consultants (M/s STUP) have submitted all the 3
launching schemes. They will be submitted by MMRDA before next meeting.
Instead of launching scheme, the revised GADs with plate girders have been
submitted on 19.5.15.
2 MMRDA
CR
CBE
Mumbai -Trans Harbour sea link (MTHL)
Approval of GAD‟s of ROB‟s over Central Railway land from Sewri to Chirle
Mainland Nhava side Drg. No.
180581/142 sheets, and 2180581/ 1 to 7 sheets.
Observations regarding span arrangement over
running lines conveyed to MMRDA vide letter dated 17.07.2014.
MMRDA was to provide revised GAD of this by
07/10/14. Now target shifted to 14/10/14. Target busted again. Again PDC fixed at 30.10.14. PDC
17/11/14. Meeting held on 12/11/14. Crossings will be with 3
spans. Instead of 5 sets of piers it was decided to
submit GAD with 2 sets of piers. Final GAD from MMRDA is awaited.
PDC 01/01/2015. Revised PDC 20/1/15 PDC again shifted to 15.2.15 due to work to be
done by M/S CES ( Consultants of MMRDA) GAD is yet to be submitted by MMRDA.
PDC – 15.4.2015. No change in above PDC on
24.03.2015 & 7.4.2015.
Page 2 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
GAD submitted on 16.4.2015. Approval of DFC and
construction will be obtained by 24.4.2015. CBE will issue in-principle approval to submit final GAD
to be signed by Division and Headquarters.
Clearance of DFC awaited by CBE. In-principle approval to MMRDA will be given by 10.5.15
DFC approval given by Shri Prakash Mudliar.
IPA given to MMRDA on 10.5.15. Tracing of
this approved GAD will be given by MMRDA on 09.6.15.
39 CR
MMRDA
DRM
Connecting the existing skywalk on west
side of Ghatkopar station to the Metro
building so as to ensure seamless connectivity with railway‟s 12 meters
wide FOB.
Under process.
Details given to MMRDA on 15/10/14.Consultants
of MMRDA working on this. PDC 15.11.14. Delayed to 05/12/14.
DRM BB: Proposal has to be submitted by MMRDA. The
same has not been submitted till date. Concerned
officials not available on 16/12/14. MMRDA yet to decide whether to complete this
project or not. ITEM CLOSED.
ITEM OPENED on 10.2.15. PDC 15.4.15 No change as on 10.3.2015, 24.03.2015.
PDC of 15.04.2015 will be honored.
Detailed drawing submitted to DEN (HQ). PDC for approval – 30.4.2015.
Approval given with two corrections on 30.4.15. PDC for MMRDA for corrected detailed drawing –
08.5.15.
Corrected drawing received on 10.5.15.
Approved by DRM/BB to be given by 09.6.15.
89 CR
MMRDA
MMRDA has carried out widening of the
road between Ambernath, Vangani and Khopoli. Due to widening, some existing
110kv Railway Transmission line towers need to be shifted.
17 transmission line towers are prone to hitting by
road vehicles and cause disturbance to traction tower supply in KYN-PUNE section affecting train
movement. Joint Survey by Railways & MMRDA officials
already done in 2014. An Estimate for shifting of
these towers sent to MMRDA by BB division for depositing the money in March 2014.
Money has not been deposited by MMRDA till date.
MMRDA had apprehensions that land required for shifting has been identified by Railways or not.
They were advised that shifting has been planned in all details.
MMRDA agreed to deposit Rs.6 Crore as
Page 3 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
asked by Railways by 09.6.15 after
verification of tower nos. at site by joint visit of S/Shri M. Patil ( MMRDA) and P.K
Kataria (Rlys) on 28.5.15.
Page 4 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
5 CIDCO
CR
CBE
Proposal of crossing of Navi Mumbai
Metro line at Taloja station on Diva-Panvel railway line by DFCCIL.
It is necessary to accord approval by
Railways to the Metro Station No.10,
portion of Depot approach via duct and the pier at the edge of the railway
boundary (to facilitate the NHAI span crossing) since all these work are away
from the operational area of Diva-Panvel
line and it will expedite the execution of the Metro works held up on the Railway
land.
Meeting held between CIDCO & DRM, Central
Railway along with other railway officials on 18.09.2014.
Central Railway & DFCC came to an Agreement on
the track layout of their respective track layout at Taloja Station.
Further item was discussed with DRM/BB, CE/CIDCO and PCE with GM/CR on 07.10.2014.
Revised drawing with relocation of RUB at location
of existing LC will be given by CIDCO by 10/10/14. This will permit some more space for expansion to
C.Rly. Meeting in GM‟s Room held at 15.30 hours on 07.10.2014.
CIDCO submitted revised GAD based on the discussions by 14/10/14. PDC for Railways and
DFC 26/10/14. Rly gave feedback 22/10/14. GAD
by CIDCO to be given on 25/12/14. Central Railway agreed that the structure of
station No 10 and Depot Approach Viaduct of Navi Mumbai Metro, located away from the operational
area of Diva panel line are permitted for
construction. GM , Central Railway instructed the concerned Railway officials to release letter by
27/11/14, to commence construction. Central Railway confirmed that on formal
submission of GAD of superstructure of NM Metro crossing of operational Diva- Panvel line, the
construction of pier of NHA3 crossing stands
approved for construction. Since this is located away from the operational area of Diva- Panvel
line and at edge of Railway Boundary. CIDCO is requested to expedite submission of GAD
of through type girder. In view of delay on part of
CIDCO designer, it was decided today that maintenance agreement will be submitted by
Railway to CIDCO 15/1/15. As soon as agreements s executed by CIDCO, the
construction of Depot, station no 10 and NH
crossing can be started. Follow-up meeting was held by CAO(C)/ PCE with
CBE/CR, and CE/CIDCO on 13.1.2015 and decided that CIDCO will submit GAD showing vertical and
Horizontal clearances pending superstructure structural drawing in week time.
Draft Agreement submitted for legal check on 19.01.2015. After legal vetting of Agreement same
will be sent to BB Divn for execution with CIDCO. After execution of agreement and receipt of GAD
permission for work will be processed.
GAD submitted to Mumbai division on 30.01.15 and is under approval.
Draft Agreement has been sent to CIDCO on 23.01.15 for signature is yet to be returned duly
signed. Same will be returned by 20.2.15 or earlier. Work can start within two days, thereafter.
Draft agreement is yet to be received from CIDCO.
PDC 24.2.2015.
Page 5 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
PDC shifted to 03.03.2015 on 24.02.2015 as MD
/CIDCO‟s approval is pending. Expected by 15.3.2015.
GAD approved by Mumbai division and DFCCIL is
received in HQs on 23.02.15 and after scrutiny GAD returned to CIDCO for following
modifications: 1. Pier no.292 and 293 across existing Railway
tracks have been proposed as single piers. It
would be advisable to provide at least two piers for stability.
2. The vertical clearance over railway tracks is 13.76 m which is quite high. Further, 11.0 m
height of girder will result in approx. 25m high space unusable for Railways. The overall height
can be reduced by designing semi through girder.
3. Single truss girder has been proposed for both the tracks. Separate girders for two tracks should
be planned to facilitate ease of maintenance. PDC for CIDCO to react and sort out above issues
– 15.3.2015 Clarification by CIDCO to CBE vide letter dated 17.03.15 @ pier configuration. MOD is signed on 19.03.15. Agreement signed by CIDCO & CR on 20.03.2015.
Authority to start work given during today‟s meeting (07.04.15) in writing. Permission for
starting work in Rly area at 2 locations granted by
Division on 07.04.15 vide L.No. BB/W/3521/Metro Rail/DB. 1) Pier No.P-290 next to NH4 for highway
span. 2) Depot approach via duct. Station No. 10 - Permission to construct has been
granted on 21.04.15.
Preliminary presentation with CRS on 12.5.15 along with forest officers of S. No.13
No Rep as on 26.5.15.
13 CR GoM / CIDCO
b) Land acquisition for Nerul / Belapur-Seawoods – Uran Rly
project. (Ch: 8000 to Ch.11000)
This matter is under process with the office of Collector, Raigad and the Forest department.
The matter is under process with the office of Collector, Raigad and the Forest Dept.
TDC Dec 2014.
CIDCO is chasing actively. PDC of Dec. 14 will be honoured.
a) CIDCO is following up with concerned Land
Acquisition Authority of GoM for Navi Mumbai /
Raigad for expediting acquisition of the private land.
b) CIDCO is also following up for transfer of Forest Land. The matter involves multiple Govt
Departments. Expected PDC will be given in next meeting.
One meeting has been held by CIDCO PDC is not
possible now. It will be given by 28.2.15. Forest land will be handed over early. Private land
will be treated separately on priority.
Page 6 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
No change as on 24.03.2015, 07.04.2015 and
21.4.15. Still no PDC is possible by CIDCO. CIDCO hopes to solve the problem by 15.05.15.
No Rep as on 26.5.15.
15 CR
CIDCO
GM
Acquisition of land for DFCCIL alignment
through Panvel.
The issuance of MoM of the meeting held on 04th
July, 2014 in presence of C.S., GoM by PS (UD-i) office GoM is expected anytime as discussed
during Empowerment Committee meeting on 26.09.14.
Meeting called by Additional Secretary (Transport) on 28.04.15.
Re-alignment of DFC being relooked into
after meeting of Additional CS, DFC and CIDCO.
In the meeting on 28.04.15 under chairmanship of ACS(Transport)GoM – it
was decided that CIDCO will complete
scrutiny of the proposal in 10 days & discuss with DFCCIL, if there is a problem at any
location. Feedback awaited.
No Rep as on 26.5.15.
17
*
CR
GoM/CIDCO
CAO / C
ROB‟s in lieu of 13 nos. of Level
Crossings have been sanctioned by Railway Board on cost sharing basis in
connection with DFCCIL alignment.
Sanction of State Government for sharing 50% of the cost is awaited.
6 GADs submitted to CIDCO
(One pertains to MMRDA )
(LC 9 does not pertain to CIDCO area) (LC 6 near Bomali village needs to be
clarified whether the approach road pertains to PWD or CIDCO)
There are no guidelines regarding cost sharing. It
was decided to technically finalize the GAD drawings of these ROBs without waiting for clarity
on cost sharing.
DFCCIL to get the appropriate letter issued from Board, on cost sharing.
TDC for approval of GADs 30/10/14 (with 4 lane modification). Meeting fixed by CAO/C on
29.10.14. 3 Drawings will be approved by
CIDCO by 14/11/14. Rest 3 by 31/12/14. In the last meeting between CIDCO & C. Rly. held
on 13.11.2014, the nodal drawing of three locations LC 10, LC 20 & LC 23 were given to C.
Rly. to super impose the GAD of the ROB / RUB for checking the junction arrangement details.
PDC 5/1/15. There is delay of 15 days on both
PDCs due to feedback from DFC. Progress held up for want of revised Board circular
on cost sharing.
PDC 10.3.15 for Board Circular.
Meanwhile 4 GADs submitted by CR to CIDCO
and 2 GADs submitted to MMRDA on
Sept.2013 are still pending for approval. PDC - 30.03.2015 by CIDCO.
PDC - 30.03.2015 by MMRDA for LC No. 6 & 9.
No change as on 10.3.15 and 24.03.2015. Railway to study for RUBs at maximum possible sites. PDC
of 30.3.2015 will be honoured by CIDCO &
MMRDA New PDC of 22.04.2015 for MMRDA and CIDCO
Page 7 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
fixed on 07.04.2015.
Meeting called by Additional Secretary (Transport) on 28.04.15.
All six crossings of CIDCO will be RUBs. For
remaining seven, discussions are on by GoM.
DFCCIL: 20 LC in Maharashtra (13CR+7WR) against
which ROBs/RUBs are yet to be sanctioned
by State Govt./Local bodies. Issue of cost sharing was discussed in
meeting between Ch.Secy GoM & MD/DFFCILon 28.03.15.
Ch.Secy GoM directed to submit the cost of each ROB along with location details for
initiating process of sanction by
corporation/Road authority. Details of 17 ROBs costing 650.28 crores
have been submitted to Secretary (PWD) GoM on 24.04.15. (out of these 17 LCs, only
One LC no. 23 pertains to CIDCO)
For remaining 3 LCs which are in CIDCO territory, option of providing ROBs/RUBs is
under discussion between CR & CIDCO.
Follow up meeting was held with ACS (Transport) on 28.04.15 & advised DFCCIL to
submit GAD of these ROBs. Accordingly GAD
for 10 ROBs has been submitted on 15.05.15 in first phase.
GoM & CIDCO is requested to expedite the process for cost sharing.
No Rep as on 26.5.15.
Page 8 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
31 CIDCO
CR
DRM
Taking over of maintenance of 14 nos. of
suburban railway stations by the railways on or before 31st March 2015.
&
Finalizing the pending maintenance agreement between Central Railway and
CIDCO for the maintenance period beyond 2008.
CR has not taken over maintenance from CIDCO
as yet. As such we cannot charge w.e.f. 2008. We will charge w.e.f 2015 after we take over. We can
take over after CIDCO does one time clearance of
arrears / deficiencies and clarifies the separation of utilities.
Agreement for 2008-2015 will also have to be signed.
DRM / BB, Central Railway to be the single point
for co-ordinating and decision in the matter. He will hold detailed meeting with CE ( Spl. Proj) /
CIDCO in DRM office on 8/10/14 at 15:00 hrs. DRM / BB held meeting on 17.10.14. Next meeting
planned on 29.10.14 and site visits on 5.11.2014. CIDCO:
The maintenance agreement between CR &
CIDCO has not been formalised w.e.f. 2008. CIDCO has already communicated the draft of the
maintenance agreement in 2011-12. Now since it is decided that Railways shall take over
maintenance of the stations w.e.f. 01.04.2015, the
maintenance agreement should be finalised by Railways considering 2008-2015.
CIDCO & Railways jointly should finalize the issues pertaining to the outstanding dues, if any, on
either side, the cost of repairs to be shared & as also the utilities sharing / separation.
JUINAGAR will be taken over by Railways first. JA
grade meetings over. SA grade meetings to be done and issue finalized by 15.3.15.
New PDC -30.4.2015. Site Insp. of Juinagar Station done on 5.03.15. Letter regarding details for Shops and Stations area sent to CE (SP)CIDCO on 20.3.2015. Details awaited.
Some details of agreement done with
Shopkeepers are not available with CIDCO. It was decided on 7.04.2015 to repair the
agreement in such a way that share of maintenance charges, if not borne by shops
shall be borne by CIDCO in future.
Meeting will be conducted with CE CIDCO by Mumbai Division.
No Rep as on 26.5.15.
Page 9 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
42 CIDCO
CR
DRM
For re-locating the Assistant
Commissioner of Police, harbour Division‟s Office at the ground level unit
of the Vashi Railway Station Building
(south side), the keys of these offices have to be handed over to CIDCO for
completing the handing over process. Currently, the keys to these premises are
kept in Station Master‟s office.
The said premises are in possession of Central
Railway since 1992 and are being used for various purposes. Further all the station building in Navi
Mumbai will be under control of Central Railway
from 01.04.2015, so it will be appropriate that the railways take a view on this issue.
TDC: 15.10.14. CIDCO informed that these premises should have
lock up and even room for the Hon‟ble Judge also.
To be discussed in 08/10/14 meeting. CIDCO informed that these premises have lock up
and room for the Hon‟ble Judge. This premise has to function as mandated. Meeting rescheduled for
17.10.2014. Railway has planned a safety training centre for
Motormen & ASMs..
Two rooms out of five are likely to be encroached. Subject to be finalized by
15.03.2015 along with item. No.31. Linked with Sr. No.31.
New PDC – 30.4.2015.
No Rep as on 26.5.15.
48 CIDCO CR
DRM
Due to site constraint, CIDCO requires 1200 square meter railway land (CH 77
kms) along Panvel Uran railway line near
Bhangarpada falling under village Dapoli, Tal -Panvel for laying the storm
water drain in Pushpak Nagar which is part and parcel of Navi Mumbai
International Airport Project.
DEN (LM) CSTM through letter dtd 16/5/2014 informed CIDCO that land shall be leased to
CIDCO for 35 years.
CIDCO to submit its proposal to Railways as explained in the meeting.
PDC for CIDCO 30/10/14. Submitted on 8/10/14. Copy again given on
11/11/14.
DRM BB : Proposal is under divisional approval. XEN CIDCO to liaise with BB Division.
a)Proposal for leasing of 1200 m2 land is under divisional approval.
b)Proposal for exchange of land is not received
from CIDCO. No change as on 10.3.15. CIDCO advised to
send lease proposal as per ready reckoner rates.
Proposal for transfer of land to be dealt on normal leasing basis
No Rep as on 26.5.15.
49 CIDCO
CR
CAO / C
The final approval for two ROBs taken up
for construction at MSEB Sub-station and Uran Station on Nerul-Uran Railway Line
are awaited from Railway.
Both ROBs are under scrutiny of Design office and
for some clarifications, concerned designer of that bridge is required at design office of headquarters
office of CR. Old PDC was 15/10/14. C.Rly requested for priority.
MSEB was indicated by CIDCO as priority 1 PDC for MSEB 31/10/14.
PDC for URAN 07/11/14.
Both progresses are on schedule. Designer required again in CAO(C)„s office for
minor clarifications. One approval of MSEB done on 24/11/14. Second consultants to visit CAO ( C )
Page 10 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
for URAN.
Design to be finalized by 15.3.15. No change as on 10.3.15.
Consultant visited on 11.3.2015.
URAN design received from Consultant on 6.04.2015. Now CAO/C will approve by 30.4.2015.
Design finalized by CAO/C on 18.04.15.
For ROB of MSEB, CIDCO will give revised design because of gas pipelines. No Rep as on 26.5.15.
90 CIDCO CR
Civil works of Phase-I at new Seawoods Darave Railway Station was completed in
Feb‟2015 & C.Rly were requested to take necessary action towards diversion of
Rail Operations from Old station to
Phase-I of New station to facilitate its commissioning as well as taking up the
construction of Phase-II.
CIDCO is yet to get the confirmation and schedule from CR. This item may be considered on top
priority to enable further works by CIDCO.
CAO/C indicated that OHE issues are
pending. CIDCO wanted the diversion of trains from old station to new station so
that old station can be dismantled. This point shall also be covered by CIDCO in their
presentation on 12.5.15. No Rep as on 26.5.15.
Page 11 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
16
*
CR
MbPT/ MMRDA
CAO/C
Construction of Wadala- Kurla dedicated
Goods Line (on deposit terms) is pending for want of removal of hutments and
rehabilitation. Resettlement of the
project affected persons to be done by MMRDA / MbPT.
237 allotments done out of 1680 encroachments.
150 shifted out of 237. SPARC (NGO) coordinates. PDC Dec ‟14 - given by MMRDA but progress on
ground is not commensurate.
Fresh allotments are held up due to MMRDA. New shifting held up for wants of repairs to tenement
by MMRDA. (Civil Engineering Dept). Dy CE MbPT: Demolition of the hutments vacated
by the slum dwellers and construction of the
compound wall along the safety zone is in progress.
Demolition of the huts of the PAPs who have been allotted the tenements but not shifted from the
project site is scheduled on 10.11.2014. Fresh allotment of tenements held up for want of
repairs to the tenements.
CAO/C: Work is held up. MbPT absent on 16/12/14.
445 allotments done. 220 shifted. 680 tenements repaired. 800 tenements scrutinized.
No further progress till 10.2.15.
Now the same 445 shelters are being allotted to hutment owners of MAP-3 from Wadala end.
Commercial encroachments as seen during joint site visit, should also be planned by MbPT/MMRDA
for resettlement at the earliest. No change on 10.3.15 and 24.3.2015.
70 allotments of commercial sites also done.
Railways requested MbPT to advise MMRDA to allotments for hutments in the vicinity of
Shanmukhanand RUB as there is a long lead item and its tender is waiting for finalization.
483 allotments done now. Shifted only 220.
600 allotted and 330 shifted as on 26.5.15.
Earthwork contract awarded by Railways. Work will start within a fortnight.
MbPT has requested for changes of alignment near Raoli Bridge so that 400
PAPs can be saved. Sketch discussed during meeting on 26.05.2015. Rlys to examine the
proposal by 02.06.2015.
Page 12 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
25 MbPT
CR
GM
Taking over of Port Railway by C.Rly and
Exchange of Haji Bunder land of Railways with Wadala land of MbPT.
Agreement sent to MbPT on 08.09.2014.
MbPT is waiting for Rani Jadhav Committee report. C.Rly cannot introduce 12 car services on harbour
line without this agreement of MbPT. Detailed
meeting with MbPT office postponed to 10/10/14 at 17:00 hrs.
ROB meeting was requested by MbPT on 14/10/14, which can be held today itself.
MbPT vide its letter dated 27.10.2014 has
forwarded its comments on the Central Railway‟s letter dated 08.09.2014 wherein certain terms and
conditions have been stipulated for taking over Port‟s railway operations. MbPT Absent on
16/12/14. This point added in the agenda of Port Trust
meeting planned for 7/1/15.
Meeting planned for 13.1.2015. Meeting planned for 19.1.2015. Meeting postponed again. Meeting
with Shri Parmar held by GM/CR on 20.02.2015. No change on 10.3.15 and 24.3.2015 and
subsequently on 26.05.15
Page 13 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
6 MCGM
CR
CBE
Carnac Road Over Bridge & Hancock
ROB: - Rebuilding of Carnac Road over bridge at KMs. 0/1-2 & Hancock Road
over bridge at KMs. 2/6-7.
MCGM has agreed for dismantling of existing ROBs
by Railways at their cost. Estimate for demolition of existing bridge submitted to MCGM on
30.05.2014 but acceptance is still awaited.
Dismantling scheme of existing ROB has been submitted on 08.08.2014. MCGM was to approve
this by 5/10/14. CAO (C) CSTM will execute the work of demolition.
It was decided to process for CRS sanction
simultaneously for dismantling MCGM submitted the GAD & TAD to Railway for
approval on 14.08.2014 for the new bridges to be constructed.
GAD and TAD returned to MCGM with observation vide letter no. W.294.Rehab.Genl. dated
20.08.2014 regarding launching.
Revised GAD and TAD was awaited from MCGM by 15/10/14. Today MCGM clarified that they need
approved plan of 5th and 6th line. MCGM was requested by Railways to delink
dismantling from the new bridge in view of public
safety. Central Railway was to give approved plan of 5th
and 6th line plan by 20/10/14. Plan given on 16.10.14. PDC for MCGM 15.11.14.
Scrap will be removed by Rlys a.s cost of scrap has been subtracted from estimate.
Utilities planning in interim to be detailed by MCGM
by 5/12/14. Rs.2.6 Cr received from MCGM on 27.11.14.
Utility shifting – JJ hospital pipe of 300 mm dia. and 9 cables of BEST , 3 cables of MTNL be taken
along with 900 mm. dia. pipe of MCGM pipe bridge
2M away. Abandoned pipe of 600 mm dia. to be thrown.
For shifting of utility services on pipeline bridge needs strengthening before shifting which is being
advised to Construction Dept. Pipe and cables will
be provided by user dept. of MCGM. PDC for strengthening of pipe bridge and
dismantling – CBE:
Tender for dismantling of 2 ROBs opened on 06.01.15 and under finalization with CAO/C.
PDC for finalization 10.3.15. Meeting with CAO(C) & CE/Br. of MCGM held on 23.02.15 & BMC is requested to shift utilities by BMC itself & intimate date for starting dismantling. Shri A.R.Patil (9869022185) of BMC has been nominated for planning the utility shifting of Carnac ROB first. He will take up Hancock ROB after that. Meeting with CE/Br MCGM of utilities on 17.03.15. In meeting BMC, CE agreed to explore scope of diverting all utilities either by new utility bridge or by adjusting it on proposed ROB. Schematic plan is being developed by BMC in coordination with BEST, MTNL, and Hydraulic Deptt.
Page 14 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
It was decided to close the traffic on both the
bridges w.e.f 15.4.2015. Necessary notices in newspapers to be given by traffic Police of BMC.
Meeting with consultant Shri S.N. Bobe of MCGM to
be held in GM‟s chamber to decide the modus operandi of accommodating the utilities on
8.04.2015 or 9.4.2015, CBE & CAO/C will be present. A meeting with CRS will also be held
before preliminary TAD is made.
CRS meeting conducted on 21.04.15 at 1500 hrs. Demolition starts from 01.10.15 and finishes on
31.12.15 for first bridge and from 01.02.16 to 31.05.16 for the second bridge. MCGM will submit
the utility shifting plans for both the bridges by 31.05.15.
MCGM is planning shifting of utilities with
consultant Shri Bhobe. MCGM on 26.5.15 indicated that they have
held a meeting with all departments of utilities and not drawn any minutes. MCGM
wanted Railways to provide solution which
is not possible. Details like weight/meter and length of utilities also not given by
MCGM. Water supply and Electric supply of JJ Hospital may be jeopardized if bridge has
to be stopped and dismantled.
7 MCGM
CR
CBE
Currey Road ROB & Tilak ROB: -
Proposed strengthening work of Currey road and Tilak ROB at kms. 6/2-3 and
Tilak ROB at kms. 9/5-6.
Estimate amounting for Currey Road ROB
Rs.2,50,91,702/- and for Tilak ROB Rs.2,35,70,677/- vide letter No. B.W. 3512.
Estimate. ROB.Gen.DB. dated 30.06.2014
submitted to MCGM. Not received as per MCGM. To be given again. Acceptance of estimate
awaited from MCGM TDC 22/10/14. Confirmed today, to be behind
schedule. Revised target 7.11.14. Target Revised again to 26/11/14. Rs 5 Crore will
be deposited by 28/11/14.
Rs 2.5 Crs received for Currey Road on 15/12. PDC for Tilak 22/12/14.
Tilak Bridge money (2.5Cr) received on 25/12/14. Tender for strengthening of 2 ROBs is being
invited. NIT will be issued by 30.1.2015.
CBE: Tender for strengthening of 2 ROBs is beings invited. NIT will be issued by 20.02.15.
CBE: NIT for strengthening of 2 ROBs will be issued by 15.03.15. Fund deposited by MCGM for both ROBs. Tender schedule under finance vetting. Tender is being
invited by Dy.CE/C/DR. No change as on 10.3.15.
Tender schedule still under vetting of FA&CAO (Cons) as on 06.04.15.
NIT issued, Tender opening on 19.05.15.
Page 15 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
No representative of MCGM and no
discussions on 5.5.15
MCGM advised on 26.5.15 that utilities of
Currey Road and Tilak may also be planned for shifting as during strengthening the
bridge will be lifted also and disturb the utilities. In view of no progress on Sr. No. 6
& 7, City Police may have to close traffic on
all four ROBS simultaneously.
8 CR
MCGM
GM
Issue of Occupation Certificate for “E”
building at Railway Officer‟s Flats at Nirmal Park, Byculla. Three Meetings
already held on the issue with MCGM at
the level of GM and MCGM commissioner.
5% land for amenities was earmarked along the
station road and as BEST service station. MCGM postponed the targets from 05/10/14 to
30/10/14. Now Railways will be forced to have a
relook on rules. Status: issue is taken up with BEST by MCGM. BEST remarks received.
Case being processed by BMC. No discussions on 10.3.15, 24.03.2015 &
07.04.2015. No representative of MCGM and no discussions on
5.5.15
Concerned Officer of MCGM to act or comment on GoM’s minutes dated 27.4.15
not present.
9 CR
MCGM
GM
Approval of layout for proposed
construction of Railway Staff Quarters on replacement account at Gunpowder road
railway colony near Dockyard station.
MCGM has submitted a comprehensive report with
Ch Eng (DP) / MC. Under process with MCGM. TDC was 30/9/14. No progress by MCGM, will be
taken up after elections. Status: Approval of layout will be issued by
30/11/14. Letter is yet to be issued. No discussions on 10.3.15, 24.03.2015 &
07.4.2015.
No representative of MCGM and no discussions on 5.5.15 and 26.5.15.
27 WR
MCGM
Land Acquisition 550 sq. m at Vile Parle
(South) on BMC road in connection with 6th line work between Mumbai Central to
Borivali. – Correspondences have been
made with MCGM authorities on 25.02.14, 04.04.14, 28.04.14 &
26.06.14.
Joint inspection by W.Rly and MCGM official held
on 24/9/14. Land required is not encroaching any road. It is
not infringing with any future plans. Can be
acquired by W.Rly. Detailed plan submitted on 6/10/14 to Ex. Eng /
Traffic. MCGM representative agreed to request Ex Engg
(Tfc) to expedite. On 26/11/14. MCGM has asked
WR to submit details of owners. PDC 7/1/2015.
Page 16 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
Local society members objected to survey & a
meeting fixed with MCGM on 5/1/15 but postponed. Issue resolved without meeting. Total
station survey now to be done by RITES by
5.2.2015. Survey completed on 9.2.15.Land required is now
319.sq m. Since the land is from the footpath of the BMC road, BMC is planning to widen the road
by demolishing 16 buildings for which RITES
survey is done. Discussions with Exec. Engg/Traffic Shri Patel held
with DY.CE. PDC for deciding the demolition as per DP – 28.02.2015.
WRly to approach city survey department. They will provide the name of owner, if it is private
land, BMC has no objection to handover the land
in principle as they can widen the road on the other side.
Shri Shende (9892924769)of MCGM & Shri Sanjay Tyagi of WR to approach City Survey
department jointly as they had asked for some
BMC plans. It was decided that this is BMC land. Now BMC will
advise the cost of land to Railways after clearance of DP department, so that Railways can pay.
Concerned Officer not present. Mr.Shende refused to discuss.
29 WR
MCGM
Completion of approaches of ROB‟s at
Jogeshwari, so that Level crossings can be closed and Oshiwara station can be
commissioned.
a) Construction of Road Over Bridge in lieu of LC 26 & 27.
b) Construction of Road over Bridge in lieu of LC 24 & 25.
MCGM will complete ROB approaches by May ‟15.
Interior progress on schedule as per WRly. Approach held up on east side for 80m . Out of
500 meter due to encroachment.
PDC by MCGM will be given in next meeting. West side encroachment removed. East side
encroachers gone to court. MCGM requested to do out of court settlement for east side at the
earliest. Issue resolved out of court. PDC‟s stated above will be honoured. (May 2015).
No change as on 10.3.15, 24.03.2015 &
07.04.2015. Target of May 15 shifted to July 15 by CBE for
Jogeshwari south and for Jogeshwari north target will be Dec.15.
No representative of MCGM and no discussions on
5.5.15. Both targets will be honoured as per MCGM
on 26.5.15.
Page 17 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
50
(a)
50
(b)
MCGM
CR
DRM
Widening of Nanepada Nallah from
Railway culvert to Jai Hind colony. MCGM has already paid Rs.3,43,43,524/-
towards Way Leave Charges of railway
land vide Receipt No MR 063195 dated 24/12/2013 for grant of NOC to carry out
the construction of nallah work in railway premises. Matter pertains to Divisional
Engineer (Land) C.Rly.
Widening of Nanepada Nallah ( below the track )
Item 50 to 56 given by Storm Water Department,
who is not present in the meeting. To be discussed in next meeting of 14/10/14.
The drawing has been returned with remarks on
13/10/14. Meeting held on 20.10.14. Site inspection with
MCGM planned for next week. Site inspection done on 14/11/14 with Se DEN
(South).
PDC for approval by DRM – 05/12/14. DRM BB: GAD for work under Railway Area being
finalized. BOX is not feasible. Pipe crossing will be planned
with 1.8 m dia as done in Kurla upstream. NOC also requested by MCGM, after above is settled.
Drawing approval to be done by 8/1/15. HQ PDC
25/1/15. PDC of 08.1.15 postponed to 22.1.15
HQ PDC now stands at 15.2.15. Proposal with zonal HQ (CE(G)) since 17.02.2015. Original GAD duly signed by division & proposal vetted by finance also sent to HQ on 17.02.15.
Since the money was deposited by BMC in 2013, they requested that 2013 rates to be used. Same
was agreed to. Proposal with CE(G) since 17.02.15
SWD should start the work at the earliest
Proposal duly vetted by finance being sent to Rly.Bd for post facto sanction. Work started by
MCGM. MCGM indicated that old contractor will not
do this work. New tender will be floated. PDC 30.6.15
Railway has submitted plans to MCGM using five
1.8m dia pipes vide Sr. DEN south‟s letter no. BB.3512.BMC.NEW/BR/DB dated 24.12.14. PDC
for approval by MCGM 15.05.15. New tender will be floated by BMC by
30.6.15.
Consultant (M/s MWH) has recommended to MCGM, the width to be increased from
6m to 16m. Railway clarified that the C-S area of 16m x 1.5 m (depth) BOX can be met
with by multiple pipe of 1.8m dia as suggested by Railways and that this WORK
HAS TO BE DONE BY RAILWAYs ONLY.
MCGM will not be permitted to do this work.
Page 18 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
51 MCGM
CR
DRM
Work of widening of Somaiya Nallah
from Vidyavihar station (east) to Tansa pipeline is proposed to be undertaken in
the fair season starting from OCT 2014.
NOC for the work is required from C.Rly to carry out the work. Matter is being
pursued with Sr Divn. Engg.(South) C.Rly .
Photo copy of proposal given by MCGM again on
11/11/14. Site inspection planned on 21/11/14 with Sr DEN (South). Joint inspection done. DRM
will communicate way lease charges by 10/12/14.
DRM BB: Existing Somaiya Nallah is 8m wide. During Joint Inspection, MCGM requested to widen
Nallah by 2m width and 7m wide service road all along the Nallah. MCGM is requested to submit
GAD incorporating this requirement. GAD was
awaited from MCGM five copies deposited again by MCGM on 16/12/14.
Revised PDC 15/1/15. Received on 16.1.15. Hutments on this land will
be decided by MCGM only for settlement, if applicable.
Railways will not be able to spare land for service
Road if it is made wider than 3 metres. GAD duly signed by BOs is under revision at OSD level. Proposal was sent to Finance for vetting of leasing amount Rs.34.61 Cr. on 12.02.15. Finance asked feasibility report from all BO which is awaited from Sr.DSTE & Sr.DOM. PDC 24.3.2015. Certificate that the hutments on the land being proposed to be transferred will be rehabilitated by
MCGM under PAP awaited. Reply of MCGM
regarding certificate is still pending. SWD department, who has to give this certificate
was not present on 07.4.2015. Shri Vhatkar should
be pursued by OSD (services). Matter being chased with CE CWD Mr. Vhatkar,
who will call for a meeting before 30.04.15. Meeting not held by Shri Vhatkar till 5.5.15.
Meeting not held by Shri Vhatkar till 26.5.15
also.
53 MCGM
WR
Proposed work of widening and draining
of V.H.Desai Nallah parallel to W.Rly Dahisar (west) from Dahisar Sub way to
creek.
NOC for the work is required from WRly for which site visit and co-ordinations
between agencies is required so that Way Leave Charges can be paid to carry
out the work.
PDC 11/1/15. Feasibility Okayed. On 28/10
Proposal to be submitted by MCGM. PDC 05/12/14. Letter given by WR again on
16/12. Further PDC for money deposit for MCGM –
7/1/15. Revised PDC 25/1/15. Concerned MCGM engineer not present.
Concerned MCGM engineer not present on 10.2.15. Again not present on 24.2.2015. Cost of
project to be given by MCGM so that WRly can advise the supervision charges. Mr
Khamkar(8879329216) is the concerned engineer
– Not present on 10.3.15 also. To be pursued on phone.
Cost of project will be given by MCGM by 10.4.2015 after detailed soil investigation.
No change on 7.4.2015. WR to pursue with MCGM.
MCGM assured that estimate will be submitted by 30.04.15.
Page 19 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
Estimate of Rs. 20 Crs submitted last week.
Railways to indicate the supervision charges. MCGM to proceed with tendering.
MCGM on 26.5.15 is revising the Rs. 20 Cr. Estimate to include Avdhoot Nagar Nallah
also.
60 CR
MCGM
CAO / C
Kurla Subway:
New Subway for providing East to West
connectivity on Kalyan end of Kurla station has been constructed by Railways
in Oct 2005. Subway could not be commissioned so far due to non-
completion of exit and entry works on
the approaches.
CE(Bridges),MCGM vide their letter No.
Ch.E/5060/Bridges dated 31.12.2013 has
confirmed that MCGM will execute the part work of approaches which is falling in MCGM limit. On
confirmation of MCGM, CR has finalized Railway portion (East approach) tender. Railway work will
start by 03.03.2015.West approach to be done by
MCGM. Tender to be floated by MCGM after administrative
approval. It was wrongly recorded by MCGM as floated in previous meeting. PDC for MCGM for
tender schedule finalization by 30.04.2015. No change as on 10.3.15, 24.03.2015 &
07.4.2015. PDC of 30.04.2015 by MCGM will be
honoured. East approach will be done by Rlys by 15.06.15
and West approach work will start in Oct.‟15 after tender invitation in first week of May ‟15.
No representative of MCGM and no discussions on
5.5.15. PDC of Oct.’15 will be honoured as indicated
by MCGM on 26.5.15. Completion period is one year.
64 MCGM
CR
Construction of FOB across Harbour
Railway line at Govandi station near
Ankur cinema in M/East ward. Rs. 2,00,23,139/- paid on 28.03.2013.
PDC 30/6/15.
No representative of MCGM and no
discussions on 5.5.15
65 MCGM
CR
Construction of FOB across Harbour
Railway line at Govandi station from Kumud Vidyalaya to Tata Nagar in
M/East ward.
Rs. 2,49,79,290/- paid on 28.03.2013.
PDC 30/6/15
No representative of MCGM and no discussions on 5.5.15
66 MCGM CR
Construction of FOB across Harbour Railway line at Mankhurd station in
M/East ward.
PDC 31/8/15 No representative of MCGM and no
discussions on 5.5.15
Page 20 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
Rs. 3,11,72,881/- paid on 28.03.2013.
67 MCGM
CR
Construction of FOB across Harbour
Railway line at Kurla from Brahmanwadi Kurla (West) to Kurla (East) end of
platform No.9 in L ward.
Rs. 1,60,000/- paid on 16.05.2000. Rs. 1,10,00,000/- paid on 01.12.2006.
Rs. 30,00,000/- paid on 22.11.2007. Rs. 34,95,140/- paid on 25.03.2008.
Rs. 2,45,90,263/- paid on 28.03.2013. (Total .. Rs. 4.22 Crores)
PDC 30/11/15
No representative of MCGM and no
discussions on 5.5.15
80 CR MCGM/GoM
Permission for cutting/relocating of the trees to facilitate construction of Wadala-
Kurla Dedicated Goods Line for Mumbai Port Trust.
166 nos. of trees are to be cut/ relocated. The proposal for cutting of the trees was
submitted to Dy. Supdtt of Gardens, ”E” ward, Byculla of MCGM on 25.02.2012 and thereafter the
matter has been followed up a number of times.
Joint inspection of the site has been done with MCGM officials.
Permission of cutting /relocating of trees is still awaited from MCGM, although a period of 2 ½
years has already elapsed and the project of new line is held up.
Photographs to be attached by CAO/C. Reference
of 25.2.12 also required. Joint inspection done on 19.03.2015 with Garden
Supdt., Mr Hire. Permission by Tree Authority / Garden Suptd.
awaited.
No representative of MCGM and no
discussions on 05.5.15 and 26.5.15.
81 WR
MCGM
Providing covering on MCGM Nallah no.
64 (Krishna Nagri Nallah) of MCGM
passing under platform no. 7 & 8 at Borivali station.
MCGM is requested to take action for its immediate cleaning and providing
covering of the Nallah to avoid
inconvenience to public commuting to and from Borivali.
Western Railway to submit MAP.
MCGM indicated that NOC from adjoining society
will be required which may not be true. To be pursued with Mr. Khamkar (8879329216) –
Not present on 10.3.2015 and 7.4.2015 Under process by MCGM.
WR to pursue and send Officers to MCGM
headquarters with Shri Dilip Bhoir. Shri Bhoir ( 9987148657 ) is yet to decide whether
this Nallah will be covered or not. Drawings and details to be given by WR to
Shri Dusane.
Drawing givcen by WR to Shri Dusane on
05.5.15. MCGM to arrange covering of Nallah as per above drawing.
Page 21 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
82 CR MCGM/GoM
Permission for cutting/relocating of the
trees to facilitate construction of Pit Lines at Wadi Bunder.
Permission for cutting of 10 nos. of trees is
awaited since 31.12.2014, in connection with the work of construction of maintenance of Pit Lines at
Wadi Bunder. Inspection by officials of Dy.Supdtt
of Gardens, MCGM done in Feb‟15. Reminder letter no. DR/DRG/Pit Line/WB dt.
11.03.15 sent by Dy. CE(C) Dadar. Due to delay in permission for cutting of trees, the important work
of construction of Pit Line getting delayed.
Joint Meeting done with Garden Supdt. on 19.03.2015.
Permission awaited from Tree Authority. Inspection scheduled before 30.04.15 by Garden
Suptd.
No representative of MCGM and no
discussions on 5.5.15 and 26.5.15.
84 CR MCGM
CBE
Repairs of 14 Nos. ROB & re-building of 9 Nos. ROBs at sub-urban area on
Mumbai division: List of 14 Nos. R.O.B for repairs:
1.CSTM - PNVL (HB) – Wadala Km.9/10-11, 2. CSTM-KYN–Ghatkopar (KYN end) Km.19/18-20/1, 3. CSTM-KYN–KJRD Km.24/5-6, 4. CSTM-PNVL (HB) – Chembur-1 Km.17/6-7, 5. CSTM-PNVL(HB) – Chembur-2 Km.17/9-10, 6. CSTM – PNVL (HB) – Govandi Km. 19/2-03, 7. CSTM-KYN – GC ROB (BB end) Km.18/15-16, 8.CSTM-PNVL (HB)–Mankhurd Km. 21/2-03, 9.CSTM-KYN – Mulund Km.30/19-31/1, 10.CSTM-KYN – Tilak Hospital Km. 11/5-06, 11.CSTM-PNVL(HB)–Koliwada Km.11/12-13, 12. CSTM-PNVL(HB) – Chunabhatti Km
12/28-13/1, 13.CSTM-KYN – Curry Road Km. 6/2-3, 14. CSTM-KYN – Tilak ROB Km.9/5-6.
List of 9 Nos. ROB for re-building:
1. CSTM-KYN (Carnac) Km.0/1-2, 2. CSTM-KYN(Hancock)Km.2/16-17,
3.CSTM-KYN(Olivent)Km.3/7-8,
4.CSTM-KYN(TramByculla) Km.3/17-18, 5.CSTM-KYN(Garden)Km.4/5-7,
6.CSTM-KYN(Arthur)Km.5/5-7, 7.CSTM-KYN(Carol(CR+WR Portion)
Km.7/9-10,
8.CSTM-KYN(Sion)Km.12/11-12, 9.CSTM-KYN(Nahur) Km.28/6-7
All ROB on Mumbai division have been inspected and has been noticed that 14 Nos. of ROB have to
be repaired and 9 Nos. of ROB have to be rebuild.
Repairing of 2 ROBs i.e. Tilak ROB & Curry Road
ROB, already MCGM deposited an amount of Rs. 4.85 Cr. with Railway.
Repair work of remaining of 12 Nos. of ROBs has
been proposed to be carried out and ROB wise
estimate have been prepared with total cost of Rs. 1.47 Cr.
Rebuilding of 2 ROBs i.e. Hancock & Carnac are
already proposed and in process.
Dismantling cost of two ROBs already deposited by
MCGM with Railway. Remaining 7 Nos. of ROBs which have outlived
their codal life and on condition basis, required to rebuild. The estimated cost of rebuilding of these
bridges is Rs.172.49 Cr.
Sanction for rebuilding of 7 ROB may be arranged
by MCGM. In this connection matter referred to Chief
Engineer (Bridges) MCGM, by Divisional
Engineer/CSTM vide letter No.BB/W/3521/ROB/Genl/DB dt.26.02.2015.
Matter to be pursued with Shri Shrinivas Addl.Mun.Comm./Eastern suburbs by
OSD(services). Meeting not held. Hoped by 12.5.15.
No progress on 26.5.15.. MCGM Commissioner should attend meeting
Page 22 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
himself or send a technical Officer with
proper authority.
85 CR MCGM
CBE
Repairs to 18 Nos. Public FOB & re building of 4 Nos. of Public FOB at
suburban area of Mumbai division.
Structural audit of all Public FOBs on Mumbai suburban area has been carried out thoroughly by
the field officials of Railway. 4 Nos. of FOBs are need to be replaced on
condition basis. The detail estimate cost of
Rs.10.63 Cr. already been intimated to Chief Engineer (Bridges) MCGM on 12.1.15 & letter dt.
30.03.2015. Remaining 18 Nos. public FOBs need repair work
at cost of Rs. 5.92 Cr. conveyed to Chief Engineer
(Bridges) MCGM vide letter dt.29.1.15 & letter dt.30.03.2015.
In this connection, Municipal Commissioner, MCGM have been advised by Chief Bridge
Engineer/Central Railway vide letter No.W.294.BR.FOB.Maintenance dt.19.1.2015.
Amount yet to be deposited by MCGM.
Matter to be pursued with Shri Shrinivas Addl.Mun.Comm/ Eastern suburbs by OSD(services). Meeting not held yet. It is hoped that meeting will be held by 12.5.15.
No progress on 26.5.15. MCGM
Commissioner should attend meeting himself or send a technical Officer with
proper authority.
86 CR
MCGM
CE/C/MTP
Construction of ROB at Vikhroli is held
up for want of action to be taken by
MCGM on the following items;
a. Construction of 60 m wide D.P. Road on East side of Vikhroli, for which an
assurance was given by MCGM to
Hon‟ble High Court, Mumbai‟s order dt. 10.03.2010 and 31.03.2010 in
PIL No. 134 of 2009. b. Relocation of Police Chowky on
Vikhroli East to maintain the
existing 17 feet width of the access road (running parallel to track) from
main Pheroj Shah Godrej Road during construction .
c. Taking up construction of the approaches of the proposed ROB by
The matter has already been referred to Municipal
Commissioner, MCGM vide this office letter No.
EW/221/PL/25 dt. 24.02.2015 followed by reminder letter dt. 02.04.2015
Approach tenders will be allotted by MCGM
30.09.15
No representative of MCGM and no
discussions on 5.5.15 and on 26.5.15.
Page 23 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
MCGM which will facilitate launching
of girders of railway span. d. Removal of encroachments, falling
on the alignment for approaches of
the ROB and D.P. Road.
87 CR MCGM
Currey Road – New FOB to be constructed at CSTM end.
Location of landing on west side in MCGM area to be finalized.
Since MCGM is not giving permission of any
other option we should complete the work by landing the FOB at proposed location.
91 WR
MCGM
Culvert No 53 & 54 near Malad
Station. Railway has proposed widening as both sides of the Nallah
have been widened
Remarks of MCGM shall be given by
15.10.15.
Estimate should be given by WR by 02.6.15.
92 MCGM CR
Mukhyadhyapak Nallah and Dharavi Nallah- For widening Rs. 6 Cr paid
in 2008
Central Railway to give position in next meeting.
C.Rly failed to comment this case in their
records. MCGM requested to give details of money
paid. Site visit also to be done by S/Shri V.L.Kamble,Dy.Ch.Eng.(SWD)City, Shri Y.P.
Junnarkar,A.E.(SWD)MCGM&Y.P.Singh(Rlys)
on 27.5.15 As requested by MCGM.
93 MCGM CR
0Chunabhatti drain was damaged by Railways. Railways have paid
Rs.55 lakhs for upside work to MCGM.
The work has to be done by MCGM . MCGM can complete the work and raise bills on
Railways which will be honoured.
Page 24 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
11 CR
TMC
CAO /C
For construction of ROB at level crossing
no. 29-C at diva station, consent of TMC for sharing 50 % of the cost of the ROB
and approval of the GAD are held up.
Encroachments on the approach road are the main
cause of delay. TMC decided to do a survey and come up with revised plan of action by 15.11.14.
Board meeting of Dec ‟14 is likely to clear this
project. None attended from TMC on 6/1/15. Even GAD is yet to be approved by TMC. TMC not
present on 20.1.15. TMC attended on 10.2.15. Plan for new alignment
submitted with CAO/C. East side landing of ROB
has been shown to be on the proposed platforms of line No.5 & 6. To be rectified by TMC. PDC
03.03.2015. Rough sketch made on 10/3/15 during meeting
given by TMC on 10/3/15 to DRM/BB to cross check whether proposed landing is now interfering
with Railway land / Buildings. Rough sketch returned to TMC for incorporating Railways observations. TMC has been intimated that proposed alignment is interfering with railway land vide letter dated 13.03.15.
Discussed in A.S. (Transport)„s meeting on 23.04.15.
TMC will give final plan of DIVA ROB by
19.5.15 No. rep on 26.5.15
59 CR
TMC
CAO /C
Construction of KHAREGAON ROB in lieu
of LC No. 28/C between Thane-Kalwa on
cost sharing basis (50:50) between CR & TMC, sanctioned in the year 2012-13.
Approach land is with Court receiver.
The work in Railway portion is in progress in full
swing but the work on approaches is yet to be
started by TMC. This is likely to result into delay in commissioning of the ROB and consequently in
closing the LC gate. Joint letter to be written to Court receiver. Draft by
TMC given on 26/12/14. Rly will write to collector
as desired by TMC. TMC will now request court with the help of collector. TMC absent on 6/1/15.
TMC absent on 20.1.15 also. TMC attended on 10.2.15. No further progress on land issue. Copy of
letter written by Railways to be given to TMC by Secretary. Letter to collector issued on 24.02.2015.
Copy given to TMC. TMC to pursue the
matter with Court and Collector office. All the 3 piers in Railway area completed.
Girder fabrication started. Approaches to be made by TMC – Land under dispute.
No development. Land acquisition held up in
Collector office. Shri Malegaonkar requested to intervene.
No. rep on 26.5.15
88 CR TMC
Approach Road to Kalva Station on west side
Only elevated Road is possible. Scheme submitted to TMC almost two months back.
Final drawing will be submitted by TMC on 19.5.15. Funds will be managed separately.
No. rep on 26.5.15
Page 25 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
12 CR
KDMC
CAO /C
ROB at level crossing no 47-B between
Shahad- Ambivali station has been completed in Railway portion but work
on the approaches by KDMC is at stand
still.
Contractor of KMDC is not progressing the work.
Due to problem of land acquisition. 12 out of 16 foundation works started, remaining 4
foundations, one will be started by Dec.14.
(One NRC pipeline to be shifted) work of three foundations also started. June 15 requested as
final date. Land dispute of 2 piers will be solved by KDMC by
3/1/2015. KDMC is negotiating with a builder (Mr
Gadda) who is having one of the two POA of the land lady. Expected PDC 31/1/15. FIR lodged by
land owner. Progress to be reviewed in next meeting. Approved GAD of 38C (Thakurli gate)
submitted by KDMC on 16/12/14. Present on 24.02.2015 and 10.3.15.
KDMC has no solution but to wait for
litigation to conclude.
68 KDMC
CR
Construction of 24.00 m. Wide Railway
parallel D.P. Road from Mhasoba Nagar Thakurli to Patripool,Kalyan
Benefits:-This road connects Kalyan -
Dombivli parallel to railway line reduces road length by 3.0 Km.
Useful for Railway passengers.
Railway Land required at a) Mhasoba
Nagar Thakurli East total lenght 60.00
Mt and b) Kachora Gaon total length
85.00 Mt .
Inform to KDMC by Rlys. vide L.No.
BB/W/6001/LM/KDMC-Road/THK-KYN/449/DB dated 22/12/2014 to clarify
the proposal.
Feasibility to be studied by OSD (services)
for sparing ( 60 + 85 ) x 24 sq. meters.
None present on 24.02.2015 and 10.3.15.
Proposal needs modification, feasibility of sparing additional land and cost being
worked out.
Cost will be advised to KDMC on 25.04.15.
Rs.24 Cr advised to KDMC. KDMC expressed
inability to pay on 26.5.15
69 KDMC
CR
15.00 Meter wide DP road near Mahila
Samiti School at Thakurli East. Railway has demanded Rs 14.07 Crs
towards lease charges of 3510 Sq.mt
which comes out to be (Rs 40,095 per Sq.mt) the rates are commercial rates.
It is requested to correct the lease charges as per the open land rate based
on State ready reckoner.
(Draft Agreement submitted to
Commissioner KDMC on 5/3/2012 for signing is still awaited)
OSD / Services to study the ROB drawing of
KDMC. None present on 24.02.2015 and 10.3.15.
Proposal for flyover submitted as per commercial rates of ready reckoner.
KDMC will hold meeting with OSD(S) on 24.04.15 to decide the rates at 1100 hrs.
Alignment to be changed as suggested by Railways.
Page 26 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
73 KDMC
CR/
CAO/C
ROB at Level Crossing gate no 38-C
between Thakurli and Kalyan. Detail construction estimate is sanction by
Central Railway on 20/11/2013 for Rs.
1392.7 Lakhs Since work is on cost sharing. To join this ROB to Railway
parallel road the Elevated road is proposed and GAD is approved.
It is requested to give required Railway
land without any value charges. KDMC has submitted the agreement for the
said work to Dy CE(Const) GC on Dt 25.11.2014 for approval and sign.It is
requested to accept the agreement and execute it on Railways part so as to
deposit Rs. 242.63 lakhs to Railway as
KDMC share.
(The work executed by CAO/C agreement signed &
copy of same send to KDMC on 31.12.14)
One water pipe line of KDMC on Thakurli
East is coming in the way of foundation. KDMC have to shift it early.
None present on 24.02.2015 and 10.3.15.
Revised Tenders being invited by KDMC due to no response.
No representative of KDMC & no discussions
on 05.05.15.
Tender invited. To be finalized by July end.
76 KDMC
CR
ROB at Level Crossing NO.51-A between
Ambivali and Titwala station. KDMC has submitted GAD by vide letter
No.KDMC/CE/18, 21/05/2014 to Sr. DEN [N/E] CSTM. GAD approval requested.
(GAD approved and sent to HQ on 31.12.14) OSD BB : Remarks from HQ received on 03.02.15 & sent to KDMC on 05.03.15.
None present on 24.02.2015 and 10.3.15. KDMC has been asked to revise drawing as per HQ remarks vide letter dated 05.03.15.
PDC 07.05.15.
No representative of KDMC & no discussions on 05.05.15.
Corrected GAD Submitted to CAO/C on 20.5.15.
77 KDMC
CR
Construction of Skywalk under SATIS
Kalyan East Since Elevated booking office is included
in Phase II work and which is under
tendering process it is not possible to construct elevated booking structure
immediately. Due to this work of Phase I is prolonged. Hence it is requested to
dismantle the existing booking shed and
SBI ATM to carry further foundation at two location. KDMC is willing to construct
Temporary booking office on 5.00 wide span as done by railway on west side.
Sr No 68 to 77 to be discussed by KDMC with
OSD services in a detailed meeting at 1600 hrs on 20.01.15.
None present on 24.02.2015 and 10.3.15.
Tender for overhead booking office under finalizing by KDMC.
Permission to connect sky walk to FOB will be given after acceptance letter of Booking
office is issued. To be done on the same day.
No representative of KDMC & no discussions on 05.05.15.
Acceptation letter of Booking office will be
issued by 05.6.15
Page 27 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
19 CR
GoM
DRM
NAGOTHANE-ROHA (160KMPH)
LAND ENCROACHMENT & Land acquisitions
GoM clarified on 23.09.14 that this encroachment
will have to be removed by Railways only. GoM will, however, provide police bandobast. To be
done after elections.
Planned in next 10 days. CAO ( C) to fence & put Cess material on the same day. Meanwhile a copy
of wrongly drawn minutes was seen. These will be cancelled and as when encroachments are
removed, track will be slewed to increase the
speed. STAY obtained by encroachers to be vacated by
CAO/C. Court has given stay order against elimination
of structure till final decision of court. Now we
will avoid the encroachments by using
different alignment. It was decided on 07.4.2015 that this work will be done under
police protection for which DC (Raigad) may be requested.
20 CR
GoM
GM
Payment of MAHAGENCO: An
outstanding of `84.34 Crs on net
demurrage and other charges is pending with MAHAGENCO for payment to
Central Railway.
GoM is requested to offset the electricity bills of
Central Railway by the amount of agreed upon
demurrage. Issue is pending for last 18 months. GoM indicated that MAHAGENCO officers visit CS
every Thursday in 2nd half. CCM/CR to ask for slot on 20/11/14. Meeting cancelled by CS. New date
awaited. To be fixed after new set of officers
settle down. Agenda for next meeting with Transport Secretary to finalized by CAO/C.
21 CR GoM
GM
a) Return of the land taken over by Collector, Solapur without Railway‟s
consent near Solapur Station. (101 crore.)
GoM has advised CR to prefer an appeal with Divl. Commissioner, Pune in the matter.
DRM/SUR advised to file an appeal. Previous Chief Secretary had agreed to a proposal
that transactions between CR and GoM shall be
debited and Credited as per the then value of land in a Register of Running accounts.
20/11/14 fixed for Meeting with CS. Meeting cancelled by CS. New meeting date awaited.
Not present on 10.3.15. This issue will be raised with Transport
Secretary.
Meeting done on 23.4.15. This item will be discussed in the next meeting of Addl Chief
Secy Transport.
b) Allotment of Land at Pune in lieu of land already handed over between
Latur-Harangul in Latur District. (14 crore)
C) Relinquishment of land at Belapur-
Shevgaon in Ahmednagar district. (18 crore)
D) Balance payment regarding Land handed over to PMC, Pune for
widening of road. (1.29 crore)
22 CR
GoM
GM
Levy of Octroi /LT to m/s IOCL for HSD
oil at Miraj.
Miraj Municipality is the only authority in
Maharashtra levying the tax for last 3 years. This money has to be refunded.
COS / C.Rly to press for arrears.
Not present on 10.3.15.
Page 28 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
24 GoM
CR
CAO /C
SANCTION OF EIGHT PROJECTS:
i. WADSA–DESAIGANJ-GADCHIROLI
NEW LINE.
ii.GADCHANDUR-ADILABAD
NEW LINE.
iii. PUNE-NASIK - NEW LINE.
iv. KARAD-CHIPLUN - NEW LINE.
v.MANMAD-DHULE-INDORE-NEW LINE
vi.NAGPUR-NAGBHID
GAUGE CONVERSION.
Hon‟ble CM has written to Hon‟ble MR requesting
to expedite sanction of pending projects.
i. Revised estimate of Rs 469 Cr has been checked
by PWD/Nagpur. Rs 10 Crs will be release shortly. Part estimate under sanction with
Railway Board. FLS and Geo- technical exploration has been completed.
Hon‟ble CM requested Hon‟ble MR to expedite
sanction of revised estimates for the project. Rs. 10 crores released on 05.02.15. SECR has revised the estimate to Rs. 403 cr not yet sanctioned by Railway Board
ii. Survey report submitted to Rly
Board on 03.05.2013 at a cost of 48.4 crs. ROR 8.35% with 50% sharing with GoM.
Status: Project not sanctioned yet.
iii. Survey report submitted to Rly Board on
12.03.2010 at projected cost of 1899.6 crs with ROR less than (-)2.84%. Revised ROR with 50%
cost sharing by GoM is 4.11%, sent to Rly Board on 28.02.12.
Status: Project not sanctioned yet.
iv. Survey Report submitted to Rly. Board on 29.01.2010 at projected cost of 928.1 crs with
ROR (-) 4.37%. Revised project cost with 50% share of GoM with ROR (-) 3.17%. KRCL is
likely to do this project.
Proposal for participating in the project is under consideration of Maharashtra Maritime Board.
Project sanctioned in Budget by 20.5.15
v. Updated Report submitted to Rly Board in 2004
with revised cost of Rs. 2257 crs and ROR 9.52%. Status: Project not sanctioned yet.
vi. Project sanctioned in 2013-14 at a cost of 401 crs. Final location survey and estimate preparation
has been started. Board have stipulated that no expenditure is to be
incurred by SECR without Boards approval.
Hon‟ble MR has been requested by Hon‟ble CM to expedite pending approval.
Page 29 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
vii.Ahmednagar–Beed-Parli-
Vaijnath
viii.Wardha - Nanded
vii.Rs. 20 crores released on 19.1.2015 and 10 Cr
released on 31.3.2015 and Rs. 100 Crs released by Railways on 31.3.2015 for land
acquisition. Paid to DC/Bheed. Another Rs.125 Crs
earmarked by Railways. There are 31 cases of land acquisition due to
change of alignment to be reviewed by CAO/C GoM has released Rs. 208.75 Cr till 31.03.15
viii.Fund utilization certificate to be given to GoM
for further release of funds by 28.2.15. Rs. 5 Cr released by GoM on 30.3.2015. Rs
35 Crs earmarked by Railways in 2015-16. Matching funds to be arranged by GoM.
26 WR PS(Forest)
GoM, Collector
Mumbai Suburban,
District Collector/
Suburban, Commssioner
Konkan
Land Acquisition at 4 locations (Total 1178 sqm) i.e. Vile Parle (South) &
(North), Malad (West) and Borivali
(South) in connection with 6th line work between Mumbai Central to Borivali. –
Application for Land acquisition submitted on 15.10.2012 and 25% of
Estimated cost of land has been deposited on 18.02.14 and 14.03.14.
OSD (Rlys) has been asked to coordinate with collector (suburban) to expedite land acquisition
cases.
Action to be taken after elections. Documents given to OSD (Rlys) on 17.10.14
Rs 48 lakhs deposited with GoM in March ‟14. Sec IV notification for land acquisition by Dec ‟14.
Meeting held with DM (Suburban) on 25/11/14. DM (Sub) advised that this acquisition will be done
under new rates with fresh social impacts study to
be done after WR deposits charges for the same. Collector requested to exempt social impact study
under section 9, section 40 of new act on 6.1.2014.
Shri Malegaonkar given a copy of reference
made to collector for facilitating the permission.
Not present on 10.3.15.
Shri Malegaonkar requested to arrange
exemption from social impact study.
40 CR GoM
DRM
Notices have been served on Igatpuri
Municipal Corporation and Manas Resort
to explain the permission granted for
construction and whether they have
resulted in the hill slope being unstable.
The foundation of the Resort‟s rear
building has been exposed during the
landslide on 30/7/14 The scheme
submitted by Manas Resort for repairs is
under scrutiny.
Meanwhile GoM will check the authorized existence of the rear building and the swimming
pool
NOCs of Manas resort have been withdrawn by Igatpuri corporation OSD(services) to organize
clear indication to all authorities that the construction done in 2010 onwards is dangerous
and unsafe for travelling public.
DRM BB: Manas Resorts has submitted the proposal to carry all protection outside Railway
boundary to ensure safety of passengers. Protection plan has to be cleared by CRS.
Plan submitted by Manas Resort in end of Dec.2014.Division checking by 30.1.2015.
OSD BB: Plan with HQ, who have further send it for proof checking at COEP, Pune. Meanwhile drain is cleared & loose earth is removed in railway boundary
Not present on 10.3.15.
Page 30 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
83 CR Sec(Forest),
Revenue & Forest Dept, OSD & Jt
Sec (Rlys), Home (Transport) Dept
of GoM,
CR Dy. Conservator
of Forest (Territorial),
Shahapur and OSD & Jt Sec (Rlys) GoM,
Delay in land acquisition for 3rd line
between Kalyan-Kasara.
a) Proposal for acquisition of land
in 38 villages (Kalyan & Shahapura Taluka) were submitted to District
Collector, Thane during June 2014 to December 2014. Land acquisition still to
be initiated. Matter has been taken up by
CAO/C with Secretary (Forest), Revenue & Forest Dept.GoM with copy to OSD &
Joint Secretary (Rlys, Home Dept. to exempt the Social Impact Assessment
study and to expedite the land acquisition process. Due to delay in land
acquisition, the important project is
getting delayed.
b) In the mean while, forest land
(Govt land) may be transferred to Railways. The matter has been taken up
with Dy. Conservator of Forest (Territorial), Shahapur vide letter no.
DyCe/C/GC/41/LA dt. 11.03.15 by Dy CE/C/GC.
Railway contracts for major bridges awarded. Earth work is likely to start in
August 2015.
Land acquisition proposal will go to Nagpur
for transfer of forest land.
94 DFCCIL
GoM
Transfer of Government Land Approximately 60.82 Ha of Government Land
in Palghar, Thane & Raigad district in 52
villages is required for the DFC project. Out of these, approval of GoM is given for 0.64
Ha of land in 3 villages for all other villages the proposals are pending at various stages
and needs to be cleared as early as possible.
Meeting held with CPM/DFC on 28.4.15.
Target details for land acquisition have been fixed.
Page 31 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
33 MRVC
GoM/TMC
CE / G
Commercial Development of
Railway Land at Thane, Mulund & Bhandup
Approval from the Govt. of
Maharashtra for Mulund
Additional survey by TMC as directed by PS/UDD.
Under process with GoM.
New meeting of committee made by CS on this subject is expected to be held by last week of
October.
Now last week of November ‟14 TMC finished their work of clearance.
Now pending with GoM. For change of land use and grant of FSI of
3 (PS of UD1) MRVC to hold a meeting with
UD1. No change as on 10.3.15 & 7.4.2015.
Proposal still with PS(UD-I). MRVC to pursue.
34 MRVC GoM
Redevelopment of 20 suburban Stations alongwith station area development –
Mumbai Central, Lower Parel, Dadar (W), Bandra, Andheri, Goregaon, Borivali,
Mira Road, Bhayander, Virar on Western Line & Dadar (C), Kurla, Ghatkopar,
Mulund, Thane, Dombivali, Kalyan,
Shahad on Central Line and Wadala Road, Chembur on Harbour line.
This Project needs about Rs. 2000 cr. to seamlessly transfer commuters between Railways,
Metro and BEST. Most of the Railways rooms will have to go to First floor air space. GoM has to
foot the bill. Presentations made by MRVC to CR on 26.09.14. Details to be finalized and
presented to the new Govt. by Nov. ‟14.
PDC 7/1/15 by MRVC. Sent to Board by MRVC for approval as part of MUTP III.
No change as on 10.3.15 & 07.4.2015.
35 MRVC GoM, MMRDA, MCGM,TMC,
CR,WR, LOCAL MUNICIPAL
BODIES.
Proposed mid-section trespass control works at 20 locations on CR/WR/Harbour
line – finalization of study by J. J. School of Architecture.
44 Locations earmarked. We can do 20 immediately provided GoM shares the cost like
they are sharing on existing 12 stations. Presentation on sites on CR made on 26.09.14.
Detailed proposal will be examined by CR and
thereafter by the new Govt. PDC 7/1/15 by MRVC.
Sent to Board by MRVC for approval as part of MUTP III.
No change as on 10.3.15 & 07.4.2015.
Page 32 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
36
& 57
MRVC
CR
CSTE & DRM
Running of 12 car on Harbour line
MRVC is executing the infrastructure works. PDC:
Dec.‟14 – Wadala. Jan.‟15 – CSTM. CR will have to arrange for measurement of
coupler forces (1 in 37) & for new stabling
yards for EMUs. CSTM block will be for 3 days to extend platform
no. 1 & 2. (CR has to arrange rakes by AC-DC conversion)
About 1100 crores required by CR for rolling
stock. No change as on 10.3.15 & 07.4.2015.
37 MRVC CR
CAO /C
5th & 6th line between CSTM-Kurla. 1st phase Kurla-Parel.
Detailed estimate for 5th and 6th line sanctioned. Tenders for works will be invited shortly.
Resettlement to be done expeditiously by MMRDA. For 642 hutments between (10/22 to 12/10) & 47
hutments at Parel.
(To be coordinated by MRVC) Partial list of structure handed over to MMRDA on 30.09.14.
Complete list will be made by SPARC by October 2014.
Papers submitted to Distt Collector. Point to be discussed separately as decided by CM
on 3/12/14.
Presentation (CSTM–Sandhurst) submitted to CM office. This was discussed on 08/1/15 between
Hon‟ble CM & Hon‟ble MR. SPARC report on R&R pending with MRVC.
PDC 15.3.15 for MRVC.
PDC shifted to 30.3.2015 & now to 30.4.2015.
PDC shifted to 30.6.15.
38 MRVC
GoM, MMRDA, CIDCO
MUTP III Proposal
Quadrupling of Virar-Dahanu Road,
Doubling of Panvel-Karjat,
New suburban corridor between Airoli-Kalwa on Trans-Harbour Link,Virar-Vasai-
Panvel New Suburban Corridor, Extension of Harbour line from Goregaon
to Borivali, 5th & 6th line between
Borivali-Virar, 3rd & 4th line between Kalyan-Kasara, 3rd & 4th line between
Kalyan-Karjat, Capacity enhancement & augmentation work, Fast elevated
corridor between CST-Kurla-Panvel, Elevated corridor between Oval Maidan-
Virar.
With Ministry of Railways.
Part detail estimate costing 38.85cr sanctioned
vide letter NO.2013/W1/CR/Kalyan-Kasara dt.
16.01.2014. Full detail estimate under preparation Pending with Railway Board since 15/11/13.
C.Rly to clear these projects.
MRVC has sent these to Board without C.Rly
comments, as per normal procedure.
No change as on 10.3.15 & 07.4.2015.
Page 33 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
63 MBMC
WR
Construction 10M wide of subway for
pedestrians and light vehicles at Bhayandar station at Km 43/5A–6A
below platform and running tracks by
trenchless technology.
MBMC deposited Rs.9 lakhs in June 2006 and work
started in May 2015 after CRS & other approvals. 75% work has been completed till June 2014 and
further work stopped by WR for „Non-payment of
codal charges‟ of Rs.16.83 Cr. MBMC requested WR in Sept.2014 for permission
to resume work and assured payments due after getting approval from General Body meeting.
Mira Bhayandar Municipal official Absent on 20.01.2015. 3 Crore being paid today. Rest
will be paid in two installments on June ’15 & Dec ’15.
Meetings held with WR during Jan‟15, and as per letter dated 15.01.2015, WR permitted MBMC to
commence work.
MBMC expresses gratitude for cooperation and help.
None present from MBMC on 24.02.2015 and 21.04.15.
No representative of MBMC & no discussions on 05.05.15 & 26.05.15.
Page 35 of 47
ITEM CLOSED:
Sr
No Proposing Agency
Name of Work Status of Work
Pending
with Nodal Agency
3 MMRDA
CR
Mumbai Monorail Project revised GAD for
obligatory span crossing railway track at Currey Road railway station.
Revised GAD approved on 05.08.2014.
GAD now under C.R.S. approval. During CRS inspection on 08.09.2014,
modification to GAD has been suggested to
Monorail Authorities (Mr. Murthy) regarding infringements. Revised GAD received in division
sent to CRS on 24.09.2014. CRS sanction received and conveyed to MMRDA.
ITEM CLOSED.
Item reopened on 10.03.15 Launching scheme to be submitted to CRS on 30.3.15.
Launching scheme given on 12.3.2015, approved by division and HQ and submitted to
CRS Meeting with CRS planned by MMRDA on
08.04.2015.
Sanction of CRS received on 17.4.2015. ITEM CLOSED
4 MMRDA
CR
DRM/BB
Mumbai Monorail Project obligatory span
crossing railway track crossing Wadala railway yard.
Compliance to CRS observation dated
13.02,2014 submitted to CRS on 16/9/14. Case pending with CRS.
DRM/BB to give fresh application to CRS. Presentation in CRS office fixed today at 1600
hrs.
Revised GAD approved by HQ.(25.11.14) During presentation CRS, wanted revised launching
scheme from MMRDA. PDC 01/01/2015. Revised PDC 15/1/15 (MMRDA decided to discus
with CRS) Presentation was done on 13.01.15 with CRS.
Revised launching scheme as advised by CRS is
awaited from MMRDA. This is being submitted to Division on date.
Revised launching scheme submitted to Mumbai division on 19.01.15 and is under divisional
approval.
Approval by Headquarters by 28.02.15
Launching scheme was discussed during meeting on 24.2.2015 to finalized details
of winches and terminology used on drawings by the consultant.
CBE: TAD approved by HQ on 24.02.15.
CRS sanction application submitted to CRS on 02.03.15.
MMRDA has asked a dated from CRS for presentation.
CRS sanction received on 04.03.15
ITEM CLOSED.
Page 36 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending
with Nodal Agency
10 CR
MCGM, GoM
GM
Permission for cutting / transplanting of
62 nos. trees for EMU Carshed at Kurla. Development of maintenance facility for
15 car rakes is held up.
Under process with Municipal secretary.
TDC 5/10/14 New TDC 15/10/14. Next meeting of committee after election will
clear this. Work sanctioned. Letter likely to be issued in a week. Letter issued on last week of
November.
CAO/C: Money has been deposited by Railways for tree cutting.
Now trees can be cut under supervision of Superintendent of Gardens / Byculla.
ITEM CLOSED.
13 CR GoM/CIDCO
CAO /C
a) Releasing of funds for cost sharing of railway projects
Thane-Turbhe-Nerul / Vashi and Nerul/Belapur-Seawood-Uran.
The fund utilization statement for Nerul-Belapur-Uran corridor upto August 2014 was asked for
release of further funds. The fund utilization statement for Nerul-Belapur-
Uran corridor up to August 2014 was given on
15.09.2014 and the process for release of funds is in progress.
C.Rly will give forecast of fund utilization up to
March 2015 also by 30.9.14 to enable CIDCO to release funds, regularly every month, as
discussed.
CIDCO informed Railways that they will have to submit the proper reconciliation of the funds
duly certified by their Accounts Department to enable Advance Payments made by CIDCO.
TDC for release of funds (24 crores) 10/10/14.
Cheque of 24 Crores received on 14/10/14. Funds for Seawood – Uran have to be
sanctioned by 31/12/14 to avoid break in progress.
Rs. 72 Crore deposited by CIDCO ON 25.11.14. ITEM CLOSED
c) Approval for revised estimate for
Belapur-Panvel railway project.
Revised cost of Rs. 438 Crores
CIDCO will convey the terms and the approvals
in the week commencing 30/9/14. Letter issued by CIDCO to Railways on
24.09.2014. Proposal sent to Railway Board on
10.10.14. Board sanction expected by 31/12/14.
CAO (C) is pursuing with Board. Estimate was put up to MR. Since estimates also
will now not go upto MR, revised processing
methodology in Board will be known by 10.3.15. This is likely to be delayed till 30.3.2015 now.
No change as on 24.03.2015 & 07.4.2015.
Estimate sanctioned on last week of April 15 by Railway Board.
ITEM CLOSED ON 05.05.15.
Page 37 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending
with Nodal Agency
14 CR
GoM/CIDCO
GM
Approval for sharing of 2/3rd cost of
project and making required land available to railways for Panvel coaching
complex.
Presentation was given to CIDCO on 04.07.14 as
desired. A meeting with Chief Secretary & CIDCO was also held in July. Draft minutes of
the meetings received from CIDCO. GoM signature still pending.
It was decided with CS this presentation of
PANVEL will now have to be repeated again- Transport Secretary will chair the meetings, may
be after UMTA Core meeting on 02.03.2015 as indicated on 24.02.2015. Still pending with
Transport Secretary as on 10.3.2015. Transport Secretary has, however held an internal
meeting.
Meeting with Railways planned on 23.04.15.
ITEM CLOSED ON 05.05.15.
18 CR GoM
GM
` 5 crs out of ` 10.36 crs has been
released. The remaining funds shall also
be transferred to Central Railway so that developmental works for Kumbh Mela at
Nasik can be completed without any delay.
Release of funds expected by 15.10.14. Any further delay beyond this will entail in discharge
of tenders. ITEM CLOSED.
23 CR
GoM
CAO / C
Approval for permission of mining the
moorum & stone at Daund-Gulbarga doubling project.
ITEM CLOSED.
28 WR MCGM,
BEST, JT
COMMISSIONER POLICE (TRAFFIC)
Construction of Flyover to facilitate
smooth flow of traffic between Bandra
and Bandra Terminus. – MCGM has agreed to hand over 296 sqm of land
near water mains for widening of Existing Road on payment of easement
charges. However, there are
encroachments and license vendors on this land. MCGM is requested to hand
over Encumbrance free land early for widening of road.
BEST officials have inspected the site and agreed with planning of Railways. Traffic police
have agreed to provide additional deployment during construction of ramp. MCGM was asked
to expedite early handing over of encumbrance free land for widening of road.
TDC for hand over of 296 sqm land – 17/10/14.
Assistant commissioner (H ward) MCGM is to be requested for handing over of land. A cheque of
Rs 90 lakhs ready with WR. MCGM to remove licensees presently occupying the land.
MCGM representative assured that this will be
done after elections with the help of police. MCGM: Action was proposed to be taken on
08.10.14 but due to elections, postponed to 10.11.2014.
According to the availability of police protection,
removal of encroachment at Gate no.18 Bandra (east) is proposed on 10.11.14. Concerned
officers of water department (MCGM) and Railways informed.
Work likely to be done today. Encroachment removed on 11/11/14. 90.45
lakhs deposited on 1/12/14 . Permission
received from MCGM on 11/12/14. ITEM CLOSED
Page 38 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending
with Nodal Agency
30 WR
CR
DRM/BB
Handing over of 2731Sqm land at Curry
Road depot from Central Railways to Western Railways in connection 6th line
work between Mumbai Central to Borivali.
Joint inspection was carried out on 19/9/14 and
there was agreement for transfer of land. DRM / BB:
The revised drawings to be submitted by WR and transfer will be ensured after consulting
CAO (C) regarding requirements of 5th and 6th
lines and Parel Terminus.
This issue will be decided by CRS on common drawing to be made by CAO (C) by 30/11/14.
WR has given an prima facie acceptable plan on 4/12/14. PDC for CR 7/1/15.
CR agreed that WR can take the narrow strip of road as shown on drawing after reconstructing
the CR structure at nearby locations along with new boundary wall.
ITEM CLOSED.
32 MRVC
CR,MbPT, CIDCO,
MMRDA
CAO / C &
DRM
Fast elevated corridor between
CST-Panvel:
Alignment through BPT
Navi Mumbai Area
Land Acquisition & Resettlement &
Rehabilitation.
Meeting of CIDCO , MMRDA , MRVC,
C.Rly as ordered by CM.
20% of land required (air space) is from MbPT.
70% will be air space of C.Rly. Details with alignment particulars
(between Reay Road & Wadala) to be given to
MbPT & MCGM again.
CIDCO has certain issues: The alignment shown in the Navi Mumbai area
needs to be resolved since it infringes on existing structures.
At Seawood station, the MRVC has proposed
Fast Track Corridor at grade passing through the Seawood Station. The clearance from Central
Railway is required since one platform of Nerul-Uran corridor will be reduced to single discharge
facility. This decision is required urgently as phase –II construction of the new Seawood
Railway Station will commence shortly and
accordingly the GAD and the design may have to be revised for certain column and beams.
Land requirement put up by MRVC to the south of Kharghar Railway Station is also to be
decided.
The location of the platforms in Panvel Terminus for Fast Track Corridor is also to be decided.
Detailed inspection was held by MRVC on
31/10/14 with CAO (C). Concept plan submitted
on 07/11/14. DRM/BB to comment on this along with CE / Plg.
It was decided to merge the two lines of the fast corridor & two line of harbor on the same
alignment from CSTM to Sandhurst road for the making of station
between Hon‟ble Minister for Railways and
Hon‟ble Chief Minister. It was also decided to include two roads along
with four railway lines for effective disaster
Page 39 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending
with Nodal Agency
management.
A meeting may be called by Chief Secretary on 12.2.15.
Meeting held on 13.02.2015. CIDCO to respond on the proposal made on
13.02.2015
PDC – 30.2.2015. ITEM CLOSED in view of no interest by
State Govt.
41 CIDCO
CR
DRM
Whether there is a Railway requirement
for the triangular plot between Thane-
Turbhe & Mankhurd-Belapur Line near
Juinagar Station.
During meeting with CIDCO on 19.09.2014,
Railways have asked them to provide
dimensions of the land plan. Area plan was discussed on 23.09.14. Since the
length is about 350 meters, Stabling lines can be made. To be accepted by C.Rly formally.
CIDCO will communicate the terms and
conditions. The said piece of land has been marked for
25KV substation. CIDCO has been advised accordingly. C.Rly will try to accommodate few
stabling lines also. CIDCO:
The Railways informed that the said piece of
land has been marked for 25 KV sub-station. CIDCO stated that this triangular piece of land
belongs to CIDCO and the terms & conditions for use of this land for Railway purposes will be
conveyed to Railways.
Railway to provide the exact net area of the triangular plot after deducting the Railway
reservation of the three tracks corridors on the periphery of the plot. Thereafter, CIDCO will
communicate the terms & conditions for providing the CIDCO land of the triangular plot
to Railways.
ITEM will be CLOSED after area of the plot is decided by Railways.
Area calculated as 15500 sq.m. by Railways. Letter to be given to CIDCO PDC 2/1/2015.
Letter No. BB.W.6001.LM.Genl.22.DB
dated 06.01.2015 given to CIDCO. ITEM CLOSED on 24.02.2015.
43 CIDCO CR
There is demand for providing escalators at Nerul-Uran Railway Stations
Commuter Sub-ways. Necessary provision need to be provided by
Railways in the structures being constructed by Railways.
Escalators are not to be provided in any subway as per Railway policy.
(Usually subways are not provided with
escalators since number of steps required to be climbed is substantially less as compared to a
FOB).
ITEM CLOSED.
Page 40 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending
with Nodal Agency
44 CIDCO
CR
CAO /C
The details of the surcharges have not
been provided to CIDCO till date and it is an Audit issue with CIDCO.
CIDCO needs details of more micro level. This is to be provided at the
earliest.
Central Railway regularly makes payment by
third week of following month to CIDCO. The information is also regularly conveyed to CIDCO.
Copies of the latest acknowledged communications and its confirmation are
available on record.
Information of surcharges paid from the year 1992-93 onwards is also available on records.
This is also a Court matter (PIL for stopping surcharge) with CIDCO. Railways assured to
provide the details in next meeting. New PDC 14/10/14. To be coordinated by CAO
(C ).
CIDCO conveyed that there is audit query in regard to the absence of the details regarding
collection of the surcharge. These details are to be provided by the Railways urgently.
Details given on 29/10/14 upto the minutest
level. CCM & FA&CAO may be able to give further
details. A/c departments of CIDCO & Central Railway to
sit together & decide. ITEM CLOSED.
45 CIDCO
CR
GM
The revenue from the rakes plying on
the Cost Sharing Projects of Mankhurd – Belapur - Panvel & Thane – Turbhe -
Vashi / Nerul -Panvel are not received
from Railways.
C.Rly agrees to share „Revenue Expenses‟ with
CIDCO as per the agreement between CIDCO and Railways.
This revenue to be passed to CIDCO shall be in
line with the agreed terms. This will be Revenue minus the operating
expenses. ITEM CLOSED.
46 CIDCO
CR
DRM
The Railways have not filled the form of
application for obtaining HT connection at the New Seawood Railway station in
the name of Railways which is to be submitted to MSEDCL.
The issue was discussed during the meeting
held on 18.09.2013. MOU for taking up all the buildings for maintenance by Railways in
Seawood-Uran projects is to be formalized between CIDCO and Central Railway.
CIDCO advised to start with two temporary
electricity and water connections so that in due course, one set can be earmarked for railways
stations and hand over to railways This item may be discussed with CIDCO officials
in next meeting scheduled on 17.10.2014.
The maintenance agreement between CIDCO & Railways for Seawood-Uran project should be
finalised now since the diversion to the new Seawood station shall take place shortly.
Draft agreement will be given to CIDCO by 20/1/15.
Draft agreement given. Railways will take
electricity connection only on the day of taking over of station.
ITEM CLOSED.
Page 41 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending
with Nodal Agency
47 MMRDA
WR
Sparing of Railway Land:
a) At Mumbai Central Station:
Metro station is proposed at Mumbai Central Station, opposite to the long
distance terminal on Dr.Nair Marg. The
station will be fully underground with entry / exit structures and ancillary
building being the only structure at ground level. For the construction of the
proposed station entry / exit structures and ancillary facilities, some land is
required in Railway premises.
i. Land for Entry / Exit point and ancillary structure
ii. Land for temporary use during construction period
iii. Land below ground for proposed
sub-ways for passenger connectivity.
b) At Grant Road Station: 1. Land for Entry / Exit points on
permanent basis. Approx. 400 sq. mtrs.
2. Interchange facilities at Mumbai
Central, Churchgate, Mahalaxmi and Grant Road stations.
3. Crossing of Metro alignment with WR tacks at Mahalaxmi & Mahim
stations. (Harbour and WR).
c) Space for Metro III.
PCE/WR
one reference was received vide MMRDA‟s letter dated 06.09.2013 which was examined
and considering the adequate depth of the proposed tunnels below the railway track and
structures, prima facie the proposal appears to
be feasible. The permission will be subject to drafting necessary agreement and submission
of charges as per Railway Board‟s extant policy.
(Mahalaxmi opening may not be possible. A deck over BMC road with lift may be planned )
i. Approximately 400 sq. mtrs. Proposal submitted to Divisional Railway manager,
WR, Mumbai Central vide Letter No.MMRC/ML-3-CBS/WR/LA/2014 dated 15th
September 2014.
ii. Proposal has been submitted to DRM, WR, Mumbai Central Dn. Vide letter No. T&C/ML3
CBS/WR/LA/2014/99 dated 20th February 2014 for Mumbai Central, Churchgate and
Mahalaxmi stations. Proposal has been submitted to DRM, WR vide letter
No.MMRC/ML3-CBS/WR/LA/2014 dated 15th
September 2014 for Grant Road Station. iii. Proposal has been submitted to WR Rly. HQ,
vide letter No. MRTS/ML3/WR Crossing dated 04th February 2014.
MMRDA arranged a presentation on Metro III by
their consultants on 23/9/14 which was found very useful by all members. It was assured by
railway that whatever land will be required for few years to lower TBMs will be made available
at rates as applied for Chennai Metro by S.Rly, without any delay. Google map of sites required
for Metro 3 were handed over to W.Rly on
14/10/14. Joint inspection at all four stations has been completed on 16.10.14 by BCT division
along with MMRDA officials. Based on joint inspection MMRDA has been given clearance to
prepare final drawing duly indicating exact
dimensions vide letter no. W.220/2/737 dated 20.10.14. Copy again given in the meeting to
Advisor (Civil) MMRDA.
WR confirmed that Google Maps received on 19/10/14 and detailed inspection done on
20/10/14. Tech clearance given on 20/10/14. Now MMRDA to submit details by 02/12/14.
Fresh PDC 17/12/14.
Another PDC 15/1/15. MMRDA requested repeatedly to give
photographs of land parcels to be handed over to contractors of 7 segments within 28 days of
finalization of contracts (May end). These photographs can be taken from a high rise
building after positioning four men with flags at
Page 42 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending
with Nodal Agency
corners of the plot and at corners of the problem
area. PDC for above photographs - 03.02.15 (during
next meeting). PDC Revised by MMRDA to today afternoon
i.e 10.2.15.
Five photographs shown on 24.2.2015 for two sites of Western Railway at Mumbai
Central station. Both the sites will be spared by Western Railway, in principle.
MMRDA can propose the sites as per 5 photographs submitted on 24.2.2015.
ITEM CLOSED ON 24.02.2015.
52 MCGM
CR
DRM
Work of Kurla Carshed Nallah at Kurla
(East) near Kranti Nagar was undertaken by CR in last fair season, which was
stopped during monsoon. Addl Municipal
Commissioner (Eastern Suburb) vide letter dated 20.05.14 and 07.07.14 had
requested GM/CR to give suitable instructions to concerned staff for
restarting the work immediately. However, same is not still started on
site.
The same may be instructed to be started early.
Meeting between Sr.DEN/S and
Director/Project/SWD is scheduled on 14.10.2014.
Laying of three pipes (1800mm dia.) out of five
pipes under Yard/Main line completed. In order to complete the widening project in all respect,
four additional works yet to be planned. Therefore, MCGM has to deposit additional funds
of Rs.9,53,58,685/- for completion of balance work and same has been intimated to MCGM
Vide Mumbai division Sr DEN/S/BB letter
no.BB/W/3512/BMC/CLA-nallah/DB dated 24.09.2014. Further, way leave charges of Rs.
3.0Cr has been deposited so far, balance Rs. 6.40 Cr. yet to be deposited by MCGM. Same
has been advised vide above letter. To complete
balance work above funds may deposited with Railway at earliest. Pending approval of AMC for
RE . PDC – Feb 2015. Leftover work of connectivity is being started
and shall be completed by 28.02.15. GAD given by MCGM ON 16.1.15. Approved by Division
30.1.2015. Approved by HQ 10.2.15.
This is Nallah widening by 8 m from the existing 6 to 7m to 14 to 15 m. MCGM to start the
encroachment removal and submit photographs by 03.2.15 in next meeting of before and after
condition of removal of encroachments.
Funds will be available in mid March 2015. West side connection is completed. East side works are in progress & likely to be completed by 31.05.15. Nallah widening work is also in progress. Likely to be completed by 15.04.15. MCGM has yet to deposit balance fund.
PDC 30.03.2015. Work is in progress likely to be complete by 31.05.15. MCGM has deposited Rs. 9,53,58,685/- against balance work and Rs. 6.40 Cr against value charges on 01.04.15.
Tender will be floated by 01.6.2015 by Sr. DEN
(south) No change as on 21.4.15. ITEM CLOSED ON 05.05.15.
Page 43 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending
with Nodal Agency
54 MCGM
CR
DRM
MCGM has made payments for the work
of improvement and augmentation of culvert capacity in Railway area for SWD
system at 10 locations in city and eastern suburbs in the following
locations.
i. Dhobighat Nallah – Sion.
ii. Swadeshi Mills Kms 14/2-3. iii. LBS Marg Kurla kms 14/5-6
iv. LBS Marg Kurla kms 14/7-8 v. Chunabhatti Station kms
13/3-4.
vi. Wadala Harbour kms 9/61.
vii. Kurla Railway Colony Nallah from Carshed culvert to Tilak
nagar Station.
viii. Culvert at Nanepada, kms 29/6-7.
ix. Currey Road kms 5/11-12.
x. Chinchpokli kms 5/1-2.
The works at above locations are yet to
be carried out by CR.
MCGM:
Proposed augmentation: i. Box Culvert 2 M x 1 M
ii. Box Culvert 2 M x 1 M iii. Box Culvert 2 M x 1 M
iv. Box Culvert 2 M x 1 M
v. Box Culvert 2x2 M x 1 M For items i. to v above, Rs. 6 Cr deposited on
26.03.2008. vi. Box Culvert 1.80 M x 1.20 M
Rs. 27.11 lakh deposited on 20.03.2003.
vii. For Culvert and Nallah augmentation –
Rs. 12,62,72,125/- deposited on 18.03.2009.
viii. For Culvert augmentation - Rs. 1,75, 96,
987/- deposited on 28.03.2003.
ix. For Pipe culver 1.20 M dia. – Rs. 33,880/- deposited on 01.02.1996.
x. For Pipe 2 x 0.90 M.dia – Rs. 2,31,270/- deposited on 23.04.1996.
CBE: i) & ii) Contract awarded. Segmental box are
ready at Bhandup depot.
Iii) Work completed under Main lines. Work under HB lines balance.
Iv) Contract awarded. Segmental box are ready at Bhandup depot.
V) Details of connectivity of this culvert to
creek/ other Nallah system needs to be furnished by MCGM.
vi) Work partially completed. Segmental box are ready at site. For further work,
Downstream side to be augmented by MCGM. vii)The work for widening of Nallah near Railway
colony and LTT area has been completed except
encroachment location at Savale nagar. viii), ix) & x) Feasibility of augmentation of
culvert below Rly. tracks may be furnished after joint inspection with Rly site Engineer.
DRM clarified that 2 or 3 out of 10 items ( Sr No
i & iii ) will be completed in this season during April 2015.
DRM BB: Work of the Dhobhighat and LBS Marg at km 14/5-6 cannot be planned unless DIVA
gate is closed with a ROB.
ITEM CLOSED ON 24.02.2015.
Page 44 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending
with Nodal Agency
55 MCGM
CR
DRM
Reconnection of SWD line at
Chunabhatti Railway Station by CR. (platform no. 1) since damaged and
blocked by CR while carrying out the work of foundation for FOB in 2013.
Several letters written to restore the
damaged SWD. Unfortunately as per CR, existing SWD to be diverted by MCGM
outside Railway land.
This pertains to Construction Organization,
Sr.DEN/S/BB Vide letter on 11.04.2014, construction org. has been advised to restore
the Pipe drain which has been damaged by Construction org. Dy CE (C) DR during the work.
Storm water drainage was damaged during
foundation work of FOB. MCGM has to divert the drain in the BMC area. Railway will pay from
deposit work of Wadala – Kurla. Drg will be ready by 10/12/14 by DRM. This drawing is not required as pipe is available under the platform. The Scheme is being developed to be discussed on 3.2.2014 with photographs. Photographs seen. Apparently the site of Rs.66 lakhs work estimated by BMC is outside Railway Boundary. To be inspected jointly by 15.2.15.Inspection
done the work is O/S Railway Boundary. Rs. 66
lakhs to be paid by Railways will be paid by
15.03.2015. No change as on 10.3.15. Rs. 55.13 lakhs deposited to MCGM on 23.03.15 vide Cheque No. 688619 SWD department will start the work. Tender is being invited by Shri Vhatkar.
ITEM CLOSED. 56 MCGM
CR
DRM
1. The work consists of laying 1.60
M.dia. pipe under steel casing of 2.50
M.dia. MCGM has made payment of Rs. 58,40,408/- on 13.01.2001 to CR. The
work was reported to have been completed by CR in the year 2007.
Now, MCGM has taken up work of
laying 1.60 M.dia pipe below the MbPT Railway track on downstream side of
the said work. A Trial pit was for the said work when
it is observed that the Railway
authorities have laid only the steel casing pipe below harbour Railway
track and the 1.60 M. dia pipe is not laid inside the casing pipes.
CR to expedite the work of laying 1.60 M.dia RCC pipe inside the casing pipe
for the portion below Harbour Railway
track to enable MCGM to lay the downstream side pipe line with proper
connectivity. 2. Further, on upstream side the
newly laid drain has to be connected to
the existing drain for which excavation will be required in the Railway land at
km 7/17-18 near Railway track. CR is requested to grant permission for the
same.
DRM / BB:
MCGM may give a firm proposal along with the
execution schedule. CBE:
1) The work of Casing pipe under Railway track has already been completed in 2007. MCGM is
to carry out the work of laying RCC pipe through
the Casing pipe. 2) No proposal received for extension of drain
on up stream side at km 7/17-18. On receipt of proposal matter will be examined by Railway.
Casing pipe to be examined by MCGM and point recast if there is any problem.
ITEM CLOSED as casing work is over.
Page 45 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending
with Nodal Agency
57 MRVC
CR/WR
GM
Running of 15 car on WR and CR:
MRVC has carried out study on the WR and CR through RITES. The report has
been submitted to WR and CR. The same will be made to CR on the date to
be mutually decided.
Presentation planned on 20/10/14.Presentation
made. RITES reports to be modified as per
discussion with of Railways.3 rakes of 12 car
each requested every year w.e.f 2015-16. For
next year for this 360 coaches , 1080 crores
required for Rolling stock.ITEM CLOSED.
58 MRVC CR/WR
GM
Concept Plan: New Suburban link between Wadala to Ballard Estate
through MbPT. MRVC has prepared the concept plan for
new suburban link between Wadala to Ballard Estate through MbPT. This will
enhance the capacity between South
Mumbai to Panvel and South Mumbai to Andheri/Goregaon and thus enable direct
connection with Central, Western & Navi Mumbai area. The concept plan has
been submitted to Mrs. Jadhav,
Chairperson of MbPT Land Redevelopment Committee on
10.10.2014.
Joint meeting of MD/MRVC & GM/CR with Mrs Jadhav to be organized on 16/10/14.
The meeting held on 14/11/14. & 19/11
ITEM CLOSED.
61 MRVC
MbPT
Chief Engg.
MRVC has requested MbPT to give the
permission to ply vehicles carrying P-way
and construction material on Reynold Road in Tejasnagar colony near Vadala
Road station. The same needs to be granted.
MbPT Absent on 16/12/14.
Permission given ITEM CLOSED.
62 MRVC TMC
Urgent permission is requested from TMC to cut gulmohar trees on platform 1
on Diva station which are coming in way
of new FOB. Tree authority committed has already inspected the site on 26-06-
2014.
TMC indicated PDC of 15/01/15.
TMC Absent on 20/1/15.
ITEM CLOSED.
70 KDMC
CR
Construction of Gutter Foothpath on
Murbad Road opp. Breakmans Chawl
Kalyan (W) in Railway Land During widening of Murbad road about
20 years back the gutter and foot path was constructed opp. to old Breakmans
Chawl. The gutter is about 3.00 mt
inside the Railway land for 10.00M length. Now KDMC has taken up road
concretization work. Recently Railway provided barbed wire fencing, So work of
gutter is pending and unhygienic condition are created. Railway should
give NOC to construct gutter at its old
alignment to avoid bottleneck in road.
Work completed.
ITEM CLOSED.
71 KDMC
CR
Proposal for Improvement of Traffic
Circulation area on Kalyan East.
Proposal submitted to Railway vide Letter No. KDMC/Commissioner/486
Dt.28/06/2013. It is requested to issue NOC to KDMC.
(Proposal is not available in Division)
None present on 24.02.2015 and 10.3.15.
Proposal not acceptable in present format. ITEM CLOSED. Reframe as SATIS on first
floor.
Page 46 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending
with Nodal Agency
72 KDMC
CR
Permission for crossing Railway Lines at
3 location in Dombivali for laying rising Main DI Pipe, under JNNURM scheme.
KDMC has deposited Rs 2.52 Cr to
Railway for the Crossing of Tracks. As
KDMC doing work by HDD method, It is
requested to give permission at the
earliest.
(Pending with KDMC due to methodology details
for CRS sanction, letter to KDMC) None present on 24.02.2015 and 10.3.15.
Three – 800 mm casting pipe pushing work. Awaiting CRS sanction.
CRS permission arranged on 18.04.15
ITEM CLOSED.
74 KDMC
CR
ROB at Level crossing No 47-B between Shahad -Ambivali Station has been
completed in Railway portion but work on approaches by KDMC is delayed.
Due to problem of Land acquisition
KDMC could not complete the approaches. Substructures work
completed in available front and land acquisition is in process.
Railway has spend excess amount on
ROB on this level crossing.
None present on 24.02.2015 and 10.3.15.
ITEM CLOSED (money paid to KDMC after reconciliation)
75 KDMC
CR/
CAO/C
ROB at Level Crossing Gate 1-A between Vitthalwadi and Kalyan.
Work is completed settlement of accounts is requested. KDMC has
submitted the completion cost of the
project to Dy-Chief Engineer [C]GC and requested to release balance amount of
Rs.383.50 lakhs by wide letter KDMC / CE/434, Dated 20/03/2014.
KDMC has spent excess amount on
this ROB. Therefore reconciliation of above item no 74 & 75 are under
process
None present on 24.02.2015 and 10.3.15.
ITEM CLOSED (money paid to KDMC after
reconciliation)
78 CR KDMC
Tree cutting permission (181 nos.) for construction of 12th Battalion RPSF
Complex at Thakurli is pending since long as a result work is held up.
Tree committee meeting to be held by KDMC by 15/2/15.
None present on 24.02.2015 and 10.3.15. PDC for KDMC 7.5.15.
No representative of KDMC & no discussions on 05.05.15.
KDMC refused to permit tree cutting. Railways agreed to transplant the trees.
ITEM CLOSED ON 26.05.15.
79 MRVC/CR GoM, TMC
Encroachments on Railway land at km 38/6 - 16 local line at Retibunder and
Rana Nagar between Kalwa and Mumbra.
For 5th and 6th line between Thane Diva, BSES survey was carried out in 2012 to identify the
hutments in safety Zone at Reti bunder and Rana Nagar ( km 38/6-16) between Kalwa and
Mumbra,
As per the survey, 98 Project Affected Persons
were required to be rehabilitated at Retibunder. Accordingly, the proposal for rehabilitation of
these was processed by MMRDA. However, it has been observed that about 160 nos. new
unauthorized hutments have come up recently
Page 47 of 47
Sr No
Proposing Agency
Name of Work Status of Work
Pending
with Nodal Agency
due to which R&R work cannot be taken up.
Similarly at Rananagar, 26 Project Affected
Persons/Shops were identified which were to be rehabilitated and the proposal for rehabilitation
was processed by MMRDA. However, it has been
observed that about 40 nos. new unauthorized hutments have come up inside the Anand Patil
Workshop recently which is hampering the R&R work.
The ongoing works at Thane-Diva will be held up
and suffer if these unauthorized hutments
/encroachments are not removed. It is requested that these encroachments may please be
removed early. Second round of demolition to be planned by
Mumbai division in March 15. Thereafter MRVC
to secure land by dumping sleepers or rails
No change as on 10.3.15. Demolition program has been issued by MRVC as on 20.03.15 but could not be carried out due to non-availability of city police.
New date for demolition 28.04.15. Demolition completed on 28.4.15
ITEM CLOSED ON 05.05.15